If you encounter any installation or operational issues with your product, check the pertinent section of
this manual to see if the issue can be resolved by following outlined procedures. For additional assistance,
visit https://www.VertivCo.com/en-us/support/
4.4 Equipment Layout, Repositioning, Removal and Installation14
4.4.1 Installing the Edge Guard14
4.4.2 Positioning and Attaching Front-andRear-Mount19-in.EIARails15
4.4.3 Removing and Reversing Doors17
4.4.4 Removing and Replacing Side Panels18
4.5 Mounting Power Distribution Units19
4.5.1 Installing a Full-height PDU/Cable-Management Bracket19
4.6 Baying the DCF Cabinets20
5 Periodic Maintenance21
Vertiv | DCF Installer/User Guide |3
Page 4
Vertiv | DCF Installer/User Guide |4
Page 5
1 IMPORTANT SAFETY INSTRUCTIONS
Save These Instructions
This manual contains important instructions that must be closely followed during installation of this unit
to maintain compliance with agency listings. Read all safety and operating instructions. Adhere to all
warnings on the unit and in this manual. Follow all operating and user instructions.
WARNING: Risk of handling heavy unit. Can cause equipment damage, injury or death. Read all
instruction before beginning.
WARNING: Risk of top-heavy unit falling over. Improper handling can cause equipment damage, injury
or death. Only properly trained and qualified personnel wearing appropriate safety headgear, gloves,
shoes and glasses should attempt to move, lift, remove packaging from or prepare unit for installation.
Read all instructions before attempting to move, lift, remove packaging from or preparing unit for
installation.
This product is designed for commercial / industrial use only. This product is not intended for use with life
support or other U.S. FDA designated “critical” devices. Maximum loads must not exceed those specified in
this manual. The maximum load rating for the DCF is found in the DCF quide specficiation SL-11392. Do
not exceed the static load rating.
Install and operate in a clean environment, free from moisture, flammable liquids, gases and corrosive
substances. The DCF must be installed on a flat, level surface for proper assembly and operation.
Ensure that the DCF has proper ventilation. Never block or insert objects into the ventilation holes or
other openings. Maintain minimum clearances as specified in this manual.
Provide the minimum spacing between the accessories/components and the housing that shall be
maintained for safe operation of the equipment when installed in accordance with the National Electric
Code, ANSI/NFPA 70.As appropriate, all wiring and equipment should be installed in accordance with
NFPA 70, “National Electrical Code,” and the applicable sections of ANSI C2, “National Electrical Safety
Code."
We recommend that casters only be used to move empty cabinets.
Vertiv | DCF Installer/User Guide |5
Page 6
This page intentionally left blank.
Vertiv | DCF Installer/User Guide |6
Page 7
2 INTRODUCTION
The highly versatile DCF Optimized Rack System provides an organized, secure, controlled environment
in a single system for sensitive electronic equipment.
The DCF Optimized Rack System is available in two heights—42U and 48U (78.1in. and 88.6in; 1985mm
and 2251mm). These cabinet heights are available in the following widths and depths:
Height, width, anddepth dimensions are independent.
Depth with door is measured from t he f ront door frame to the rear door frame.
HEIGHTWIDTHDEPTH
FRAME
ONLY
WITH LEVE LING
FEET
WITH
CASTERS
WITH AND WITHOUT SIDE
PANEL S
WITHOUT
DOORS
WITH
DOORS
Assembly instructions in this manual cover the various configurations of the DCF Optimized Rack System,
either a single rack for simple equipment organization or a suite of DCF Optimized Rack System racks.
Vertiv | DCF Installer/User Guide |7
Page 8
This page intentionally left blank.
Vertiv | DCF Installer/User Guide |8
Page 9
3 MAJOR COMPONENTS
DCF Optimized Rack System will have all of the components addressed in this section. All components are
finished with a textured powder coat, color is RAL 7021.
3.1 Frame
The DCF Optimized Rack System is constructed of hot and cold rolled steel. Frame is light weight and
strong with a 3000 lb static load rating.
3.1.1 Adjustable Rails
The DCF Optimized Rack System ships with 2 sets of 19-in. (EIA310-E) compliant rails. The 19-in. rails have
U marking labels on both sides of the rails. Front and rear mount rails are installed in the DCF at 29.13in.
(740mm).
Each DCF rack leaves the factory with 2 full-height rack pdu/cable-management brackets installed. The
brackets are installed in the rear of the rack, flush against the frame, one bracket installed on each side of
rack.
3.1.3 Casters
DCF Optimized Rack System ships standard with 4 swivel, non-locking casters installed.
Figure 3.1 Caster plate
3.2 Enclosure
Exterior components of the DCF Optimized Rack System are finished in textured powder coat, color RAL
7021.
Vertiv | DCF Installer/User Guide |9
Page 10
3.2.1 Doors
All doors for the DCF are framed from sheet metal and have hexagonal perforations leaving 75% open for
airflow and efficient cooling. All doors have a single-point latch system and come standard with lock. The
DCF rack ships with a single, contoured, perforated front door and split-perforated rear doors designed for
easy access. All doors can easily be removed and the single, contoured front door is designed for
reversibility (left/right) hinging in the field. (See "Removing and Reversing Doors" on page17.)
Each door opens to 135 degrees.
Table 3.1 Door dimensions, single door
DOOR DIMENS IONS, IN (MM)
FRAME SIZE
HEIGHTWIDTH
PART NUMBER
78.1 x 23.6 (2000 x 600)
42U
78.1 x 31.5 (2000 x 800)31 (768)Part#546053G2L
83.4 x 23.6 (2100 x 600)
48U
83.4 x 31.5 (2100 x 800)31 (768)Part#546053G4L
76 (1931.5)
87 (2198.2)
23 (586)Part#546053G1L
23 (586)Part#546053G3L
Table 3.2 Door dimensions, split doors
DOOR DIMENS IONS, IN (MM)
FRAME SIZE
HEIGHTWIDTH EACH DOOR
78.1 x 23.6 (2000 x 600)
42U
78.1 x 31.5 (2000 x 800)15.5 (384)Part#546054G2L
83.4 x 23.6 (2100 x 600)
48U
83.4 x 31.5 (2100 x 800)15.5 (384)Part#546054G4L
76 (1931.5)
87 (2198.2)
11.5 (293)Part#546054G1L
11.5 (293)Part#546054G3L
PART NUMBER
3.2.2 Side Panels
Side panels for the DCF Optimized Rack System are a split side panel design constructed of sheet metal.
Each side panel section comes with a lock for security which is installed in the center top of each panel.
Two keys ship with the side panels; the side panel keys are the same keys that are used for the doors.
Table 3.3 Side-panel sizes and part numbers
RACK HEIGHT, IN (MM)RACK DEPTH, IN (MM)SIDE PANEL PART NUMBERS
43.3 (1100)546055G1L
78.1 (2000)
88.6 (2250)
47.2 (1200)546055G2L
43.3 (1100)546055G3L
47.3 (1200)546055G4L
Vertiv | DCF Installer/User Guide |10
Page 11
3.2.3 Top Cover
All DCF racks ship with a top cover constructed of sheet metal. The top cover has cut-outs for fan
mounting, cabling, and cage-nut installation for mounting DCF accessories.
Figure 3.2 Top cover for 1100-mm and 1200-mm deep rack
ITEMDESCRIPTION
1Cable-entry holes, 4 holes include edge guards and removable grommets.
2Fan/Cable-access hole, s tandard
3.3 Mounting Hardware and Tools
Hardware to install accessories ships with the DCF rack.
•1 bag of 50 M6 cage nuts
•50 M6x12 pan-head screws
•50 nylon washers
•1 cage-nut insertion tool
•1 #13/14 wrench
•1 L Key with a T30Torx head and Phillips head
•9ft of black edge guard
•1 baying kit
Vertiv | DCF Installer/User Guide |11
Page 12
This page intentionally left blank.
Vertiv | DCF Installer/User Guide |12
Page 13
4 INSTALLATION
4.1 Inspection
Upon receiving a DCF Optimized Rack System, examine the packaging for any signs of mishandling or
damage. If any damage is noted, notify your local Vertiv™ representative and your carrier immediately.
4.2 Required Setup equipment
The DCF ships with the tools necessary to adjust supplied components:
•cage-nut tool
•13/14-mm wrench
•combination T30 Torx L-key with Phillips head
The following tools are also required to set up a DCF:
•pallet jack or forklift
•utility knife or scissors
•14-mm socket and ratchet or 14-mm wrench
4.3 Unloading the DCF Rack
Before unloading, note the weight of the model (see Specifications.
CAUTION: Use at least two people when moving the unit.
1. Using a pallet jack or forklift, move the DCF on its pallet to the installation location.
2. Cut the shrink wrap and remove all packaging.
3. Use a 14-mm socket or a 14-mm wrench to remove the 4 lag bolts that secure the 2 anchor
brackets to the shipping pallet, one in the front and one at the rear of the rack. Each bracket is
secured by four bolts.
•If the brackets will be used to anchor the rack to the floor, leave them attached to the
rack. If not, removed them.
4. Use a pallet jack or forklift to raise the DCF off the shipping pallet.
5. Slide the shipping pallet out from under the rack.
Vertiv | DCF Installer/User Guide |13
Page 14
6. Position the DCF in the installation location using the forklift, with 2 or more people carrying it,
or by rolling the rack on its casters.
•If using the casters to move the rack, raise the leveling feet before moving.
7. Position the rack and do one of the following:
•Lower the leveling feet
•Bolt the rack to the floor with the shipping/anchoring brackets.
Figure 4.1 Removing rack from shipping pallet
ITEMDESCRIPTION
1Anchor bracket
2Bolt-holefor securing anchor bracket to rack (2 typical)
3Lag-bolt holes for securing anchor bracket to pallet and/or floor
4.4 Equipment Layout, Repositioning, Removal and Installation
To keep the unit’s center of gravity as low as possible, install equipment from the bottom up, starting with
the heavier units. Leave any unused space at the top of the rack.
CAUTION: After equipment is installed, the DCF Optimized Rack System may have a high center of
gravity. Avoid tipping the unit when it is being moved.
4.4.1 Installing the Edge Guard
1. Press edge guard to the top-cover cut outs by pressing along the edge of the cut out opening
as shown in the following figure.
Vertiv | DCF Installer/User Guide |14
Page 15
2. Trim excess edge guard with a pair of scissors after the edge guard after completely applied
around the opening.
3. Repeat steps 1 and 2 for remaining cut outs.
Figure 4.2 Applying the edge guard
4.4.2 Positioning and Attaching Front-andRear-Mount19-in.EIARails
Front- and rear-mount, 19-in., EIA rails are installed in 600-mm wide racks at the factory at 29.13in.
(740mm). They attach to the cabinet frame at the top and bottom, in the center to the support member
using M6x12 Torx-head screw into a rail-adjustment bracket.
In 800-mm wide racks, 19-in. EIA rails are attached using node brackets. The node brackets attach to the
top and bottom of the DCF frame and in the center to the support member. The EIA rails move as a unit if
they need to be repositioned.
To position the EIA rails on 600-mm cabinets:
1. Determine the installation location of the EIA rails.
2. Loosen the M6x12 screws in the rail-adjustment brackets, securing the 19" EIA rails to the frame
member as shown in the following figure.
NOTE: Rails in both the 600- and 800-mm wide racks are attached at the top, center and bottom.
3. Slide the rail-adjustment brackets up or down, depending on their orientation in the rack.
4. Slide the EIA rail to the desired position, making sure to keep it square. The frame member and
support have small holes spaced on 6.35-mm centers to help properly position the rails.
NOTE: The front and rear 19-in. EIA rails must be kept at a 90-degree angle to the upper and lower
frame members. The left- and right-front vertical rails must be the same distance from the front of the
rack. The left- and right-rear vertical rails must be the same distance from the rear of the rack. If these
conditions are not met, equipment and optional features will be difficult to install.
Vertiv | DCF Installer/User Guide |15
Page 16
5. Hold the rail in position, then and the M6x12 screws into the rail-adjustment brackets.
6. Repeat steps 2 to 5 for the corresponding rail.
Figure 4.3 19-in. EIA rail positioning in 600-mm racks
ITEMDESCRIPTION
1Face of EIA rail
2Rail-adjustment screw
3Frame-member holes
4Frame member
To position EIA rails on 800-mm cabinets:
1. Determine the installation location of the EIA rails.
2. At the top, bottom, and center-support member, loosen the 2 screws that secure the nodeadjustment brackets to the bottom frame member, then slide the bracket down.
Vertiv | DCF Installer/User Guide |16
Page 17
3. Slide the rails to their new location.
NOTE: The rails will bind if they are not kept at a right angle to the frame.
3Node bracket attached at the center depth support
4.4.3 Removing and Reversing Doors
DCF doors are removable for convenience when installing or maintaining equipment. The front door is also
reversible, so the single door may be opened in a more convenient direction if the rack is near a wall or
other equipment.
To remove a door:
Doors are supported by two hinges and held in place by gravity. They can be lifted off and reinstalled
without tools.
NOTE: Doors are easier to remove if they are open at a 90° angle to the DCF cabinet.
To reverse the front door:
NOTE: The door handle cannot be reversed.
1. Lift the door off the DCF, the loosen and remove screws from both the top and bottom hinges,
shown in the following figure.
2. Remove the hinges and place them on the opposite side of the frame in the slots provided.
3. Reinsert and tighten the screws.
4. Remove the hardware from the door catch and install the catch on the opposite side of the
frame.
5. Flip the door.
The hinge pin assemblies are now at the bottom of the hinge-pin attachment point.
6. Remove the hardware, flip the hinge pin and reinsert it in the hinge-pin attachment point.
Vertiv | DCF Installer/User Guide |17
Page 18
7. Reattach the hinge pin with hardware.
8. Hang the door on the newly positioned hinges.
Figure 4.5 Removing hinges and reversing the door
ITEMDESCRIPTION
1Frame
2Torx screws holding hinge to frame
3Door hinge
4Screw holes for Torx screws when changing direction door opens.
5Hinge location for reversed door
4.4.4 Removing and Replacing Side Panels
The DCF uses dual split-side panels fashioned from sheet metal. The lower panel hangs on a frame
member and the upper panel hangs on the rack frame. Each panel is secured with a lock making the
panels simple to remove and replace when installing equipment and performing maintenance .
To remove a side panel:
1. To remove a panel, insert the key in the side-panel lock and turn clockwise to unlock it.
2. Lift the panel up and away from the rack, and set it aside.
3. Repeat steps or other panels being removed.
To replace a side panel:
1. Insert the bottom of the panel into the cut-outs.
2. Move the top of the panel toward the rack.
3. Turn the key counterclockwise to lock the panel in place.
4. Repeat steps for other panels being replaced.
Vertiv | DCF Installer/User Guide |18
Page 19
4.5 Mounting Power Distribution Units
Power distribution units may be mounted on the rails or attached to mounting brackets in the DCF. The
following are the PDU options:
4.5.1 Installing a Full-height PDU/Cable-Management Bracket
The top and bottom of the 4-in. wide brackets are identical for use on either side of the cabinet.
To install a full-height bracket:
1. Position the full-height bracket for installation with the inside bottom flange of the PDU resting
on the flange of the frame member at the top and bottom. See the flange in the following figure.
2. Hold the PDU bracket in place, then insert and tighten the screws.
Figure 4.6 Full-height bracket end
ITEMDESCRIPTION
1Bracket flange
2Bracket clips
To reposition a full-height bracket:
1. Loosen the screws in the top and bottom PDU hanging bracket.
2. Slide the bracket along the frame member to the desired location and tighten the screws.
To remove a full-height bracket:
1. Loosen the screws in the top and bottom PDU hanging bracket.
2. Lift the bracket up until the hanging bracket clears the frame member and remove the
bracket from the cabinet.
Vertiv | DCF Installer/User Guide |19
Page 20
4.6 Baying the DCF Cabinets
Two or more DCF cabinets of the same height can be bayed with the supplied baying brackets. The
brackets have three holes:
•The single hole connects to the cabinet
•The outer hole centers the cabinets at 24in.(609.6mm)
•The center hole puts the cabinets on metric centers.
Connecting the racks is easier if the are in their final installation position before baying.
Figure 4.7 Baying brackets
ITEMDESCRIPTION
1Cabinet-connection hole
2Hole f or metric centers
3Hole f or 24-in. centers
Vertiv | DCF Installer/User Guide |20
Page 21
5 PERIODIC MAINTENANCE
The DCF Optimized Rack System cabinet requires no special maintenance. It should be cleaned
periodically, more frequently if the air in the vicinity is not filtered for particulates.
Dust should be cleaned from installed equipment according to the manufacturer’s recommendations.
Clean the interior of the cabinet with a dry cloth.