2 What’s Included 7
3 Installation 9
3.1 Receiving, Unpacking, andRemovingtheDCERackfromthePallet 9
3.2 Loading Equipment 9
3.3 Operating Door Handle 9
3.4 Reversing the door handle 9
3.5 Door Removal and Attachment 11
3.6 Field-reversible Front and Rear Doors 12
3.7 Side Panel Removal 13
3.8 Top Panel Mounting 13
3.9 Top Panel Mounting for the E426112DR 14
3.10 Bottom Panel Mounting for the E426112DR 15
3.11 Casters and Leveling Feet 16
3.11.1 Leveling Feet Adjustment 20
3.12 Mounting Rail Adjustment 20
3.13 PDU/Cable-management Brackets 22
4 Optional Accessories 23
4.1 Vertical Cable Manager Kit: E846015 23
4.2 Horizontal Front-to-rear Cable Manager: E11015/E12015 25
4.3 Front-to-rear Cable Trough: E811015/E812015 25
4.4 Adjustable Ladder-rack Bracket: ELRB016 26
4.5 Overhead cable trough: E6016/7016/8016 28
4.6 Exhaust Chimney: E1832014/E3246014 29
4.7 Vertical-airflow Baffle with Brush Kit for800-mmWRack:E48801/E428014/E458014 29
4.8 Vertical Airflow Baffle with Brush Kit for700-mmWRack:E487014/E427014/E457014 31
4.9 Vertical-airflow Baffle withBrushKitandVerticalCableManager 32
4.10 Switch Kit for Side-to-side Cisco Switch for1000-mmWRack:E7009014/E7018014 33
4.11 Switch Kit for Side-to-side Cisco Switch for800-mmWRack:E650304/E6506014/E9513014/E6513014 36
4.12 Baying Gasket Kit: E4013 38
4.13 Baying Kit: E9013 39
Vertiv | DCE Installer/User Guide | 3
Page 4
Vertiv | DCE Installer/User Guide | 4
Page 5
1 IMPORTANT SAFETY INSTRUCTIONS
Save These Instructions
This manual is provided to prevent service personnel from committing an act that results in the risk of fire, electric shock, or injury to persons. Only trained service personnel should receive, unpack, and assemble the DCE Racks. In addition, only trained service personnel should install equipment in racks.
Improper handling and use of the DCE Rack could result in equipment damage, serious injury, or possible death.
WARNING: Only trained service personnel should be used to remove the rack from the pallet. Also, be sure you have a sufficient number of service personnel. Do not attempt to move racks by yourself.
WARNING: All wiring and electrical circuits must be in compliance with National and Local electric codes. Only ITE (Information Technology Equipment) bearing the safety compliance mark of a NRTL should be installed inside the DCE Rack. NRTL compliance marks include UL®, C-UL®, CSA®, ETL®, TUV®, and CE.
WARNING: Be sure to read and follow all individual manufacturer equipment manuals for safety and installation instructions.
WARNING: Proper spacing is required when installing electrical equipment to avoid electrical shock. Maintain minimum spacing between the accessories and components and the computer rack assembly for safe operation of the equipment when installed in accordance with the National Electric Code ANSI/NFPA 70-1999.
Vertiv | DCE Installer/User Guide | 5
Page 6
This page intentionally left blank.
Vertiv | DCE Installer/User Guide | 6
Page 7
2 WHAT’S INCLUDED
DCE unit (assembled)
Keys as needed (depending on configuration)
(50) M6 cage nuts (3/8” square) and M6 screws
Baying hardware
Edge grommet
This Installer/User Guide
This manual applies to the following pre-configured and applicable configured DCE racks:
PART NO. RU W (MM) D (MM)
E24611 24 600 1100
E42611 42 600 1100
E42612 42 600 1200
E426112DR 42 600 1100
E42711 42 700 1100
E42712 42 700 1200
E42811 42 800 1100
E42812 42 800 1200
E42112 42 1000 1200
E45611 45 600 1100
E45612 45 600 1200
E45711 45 700 1100
E45712 45 700 1200
E45811 45 800 1100
E45812 45 800 1200
E45112 45 1000 1200
E48611 48 600 1100
E48612 48 600 1200
E48711 48 700 1100
E48712 48 700 1200
E48811 48 800 1100
E48812 48 800 1200
E48112 48 1000 1200
DCE static weight capacity: 3000 lbs.
DCE dynamic weight capacity: 2500 lbs.
Vertiv | DCE Installer/User Guide | 7
Page 8
This page intentionally left blank.
Vertiv | DCE Installer/User Guide | 8
Page 9
3 INSTALLATION
3.1 Receiving, Unpacking, andRemovingtheDCERackfromthePallet
Inspect and report any damage before receiving. Unpack the rack by carefully removing the corrugated carton and corners. Avoid damaging the rack when removing packaging.
WARNING: Only trained service personnel should be used to remove the rack from the pallet. Also, be sure you have a sufficient number of service personnel. Do not attempt to move racks by yourself.
WARNING: Be careful when moving racks before installation. Sudden stops and starts, excessive force, obstructed routes, and uneven floor surfaces may cause the rack to topple over.
3.2 Loading Equipment
WARNING: Only install equipment after the DCE Rack has been properly secured. Do not move the rack assembly while loaded.
Once in place at the desired/intended location, deploy the leveling feet for maximum stability.
Rated or maximum-load capacity for the DCE Rack is 3000 pounds on the floor or on leveling glides.
To maintain a uniform distribution of the mechanical load in the DCE Rack, load the heaviest equipment first, at the bottom of the DCE Rack and load the lighter units at the top.
3.3 Operating Door Handle
The door swing handles have been installed at the manufacturer. No additional assembly is required. To operate the swing handle, lift up at the bottom of the handle then swing the handle to the right to open. The handle must be kept in this position to close the door. Return the handle to the initial position and use the key provided to lock the handle. The lock on the side panels will accept the same key.
The swing handles and doors are reversible. See "Reversing the door handle" below.
3.4 Reversing the door handle
1. Remove the Phillips-head bolt from the swing-handle retainer on the inside of the door.
2. Tilt the handle outward and lift up to remove it from the door.
3. Remove the Phillips-head cam retaining bolt, rotate the cam 180° and re-install cam retaining bolt.
Vertiv | DCE Installer/User Guide | 9
Page 10
4. After reversing the door, reinstall the swing handle by sliding downward into door and tilting inward.
5. Re-install swing-handle retainer and Phillips head bolt.
Figure 3.1 Door handle components
ITEM DESCRIPTION
1 Phillips-head bolt
2 Phillips-head cam-retaining bolt
3 Cam
4 Retainer
Vertiv | DCE Installer/User Guide | 10
Page 11
3.5 Door Removal and Attachment
NOTE: Before removing doors, grounding wires must be disconnected.
1. Open the door beyond 90° then pull on the hinge pins.
2. Carefully pull the door away from the rack to detach the door.
3. To attach the door, align the hinges and slide hinge pins back into the hinge assembly.
Figure 3.2 Removing and Attaching door
Vertiv | DCE Installer/User Guide | 11
Page 12
3.6 Field-reversible Front and Rear Doors
The front and rear doors are installed right-hand hinged from the factory. To change to left-hand hinge, follow door-removal instructions, "Door Removal and Attachment" on the previous page, then remove the Torx screws that attach the hinges to the frame.
To re-install the hinges on the left side of the frame:
Use the former top-right hinge at the bottom left and the former bottom-right hinge at the top left with the open end of the hinge facing the outside of the rack.
Using a T30 screwdriver, remove and re-install the catch plate on the opposing side with the bend toward the inside of the rack.
Then rotate the door 180° and slide the hinge pins into the assembly.
When the door is reversed the handle must also be rotated 180°; see "Reversing the door handle" on page9.
Figure 3.3 Moving hinges to reverse doors
ITEM DESCRIPTION
1 M6 Torx screw
Vertiv | DCE Installer/User Guide | 12
Page 13
3.7 Side Panel Removal
NOTE: Before removing doors, grounding wires must be disconnected.
The side panels are secured to the rack frame with a keyed lock.
To remove the side panel:
Unlock the panel, tilt the top of the side panel out slightly and lift the side panel up a couple of inches until it is free as shown in the figure.
To install the side panel:
Reverse the process and lock the panel. Make sure the slots on the side panel engage with the two tabs at the bottom of the frame.
3.8 Top Panel Mounting
The top panel of the rack is installed at the manufacturer.
To remove the top panel:
1. Remove the 6, M4 torx screws with a T15 screwdriver.
2. Lift the top panel out or off.
There are 3 top panel options for DCE Racks.
Figure 3.4 Removing the top panel and top-panel options
ITEM DESCRIPTION
1 Edge grommet on cut-outs
2 M4 Torx screw
Vertiv | DCE Installer/User Guide | 13
Page 14
3.9 Top Panel Mounting for the E426112DR
The top panel of the rack is installed at the manufacturer.
To remove the top panel:
1. Before removing the top panel, you must remove the trough in the top half of the cabinet:
Open or remove the back door of the cabinet to access the trough.
Remove the acorn nuts, washers, and carriage bolts from the bottom of the trough.
Pull the bottom of the trough toward the center of the cabinet to disengage the flange at the top of the trough from the top panel.
2. On the top panel, remove the 6, M6 flat-head Torx screws, and lift the top panel out or off.
To install the top panel:
1. Insert the top panel and fasten with 6, M6 FH Torx screws.
2. Reinstall the cable trough by inserting the flange in the top panel and securing the bottom with the carriage bolts, washers, and acorn nuts.
Figure 3.5 Removing the top panel of the E426112DR
ITEM DESCRIPTION
1 Carriage bolt (2 per trough)
2 Trough
3 Washer (2 per trough
4 Acorn nut (2 per trough)
5 Trough flange
6 M6 Flat-head Torx screws (6 per top)
7 Top cover
8 Front of rack
9 Trough in top compartment (side panels not shown for clarity)
Vertiv | DCE Installer/User Guide | 14
Page 15
3.10 Bottom Panel Mounting for the E426112DR
The bottom panel of the rack is installed at the manufacturer.
To remove the bottom panel:
1. Before removing the bottom panel, you must remove the trough in the bottom half of the cabinet:
Open or remove the back door of the cabinet to access the trough.
Remove the acorn nuts, washers, and carriage bolts from the top of the trough.
Pull the top of the trough toward the center of the cabinet to disengage the flange at the bottom of the trough from the bottom panel.
2. On the bottom panel, remove the 3, Flat-head screws that join the two halves of the panel.
3. Remove the 4 plastic covers to access and remove the 4 M8 Hex-head bolts that secure the bottom panel.
CAUTION: Risk of sharp edges. The edges of the cutouts are sharp. Be careful when removing the fasteners.
4. At the front of the rack, starting with the left panel, lift the center of the panel up and pull the panel out, then repeat for the right panel.
To install the bottom panel:
1. Insert right half, then the left half of the bottom panel, and secure with the 4 M8 Hex-head bolts.
2. Install the plastic covers on the 4 holes, and the 3, Flat-head screws to join the two halves of the panel
3. Reinstall the cable trough by inserting the flange in the bottom panel and securing the top with the carriage bolts, washers, and acorn nuts.
Figure 3.6 Removing the bottom panel of the E426112DR
ITEM DESCRIPTION
1 Flat washer (2 per trough)
2 Acorn nut (2 per trough)
3 Carriage bolt (2 per trough)_
4 Left-side half of bottom cover
5 M8 Hex-head bolt (2 per half of bottom cover)
Vertiv | DCE Installer/User Guide | 15
Page 16
ITEM DESCRIPTION
6 Cable pass-through cover
7 Right-side half of bottom cover
8 M6 Flat-head screw (3 per bottom)
9 Front of unit
3.11 Casters and Leveling Feet
CAUTION: When installing the casters and adjusting leveling feet, observe the following safety precautions:
To install casters, several people are required to tip the rack onto its side. The rack can be very heavy. Practice safe lifting techniques.
DO NOT lay the rack on its front or back, this may damage the door hinges.
Before tipping, remove the side panels to prevent damage to the locks and latches.
Removing doors and sides helps reduce the weight of the rack.
To field-install casters
1. Tip the rack over and lay it on its side.
NOTE: Be sure to install swivel casters on the front and fixed casters on the rear of the rack.
2. Install the swivel casters on the front of the rack as shown in the following figure.
The longer side of the caster assembly features 2 holes.
Align the holes over the M8 pem studs located on the side of the frame.
Using a 13-mm socket, secure with M8 keps nut and tighten to 18 ft-lb.
3. The flange of the caster assembly aligns with a hole on the side of the frame. Secure with a M6 carriage bolt and nut and tighten to 7.5 ft-lb.
4. The shorter side of the caster assembly aligns with a hole on the front of the frame. Secure with a M8 Bolt and tighten to 18 ft-lb.
Vertiv | DCE Installer/User Guide | 16
Page 17
Figure 3.7 Installing swivel casters on front of rack
ITEM DESCRIPTION
1 Swivel caster assembly
2 M8 keps nut
3 M8 pem studs
4 Side of f rame
5 Leveling foot
6 Front of rack
7 M8 bolt
8 M6 nut
9 M6 carriage bolt
Vertiv | DCE Installer/User Guide | 17
Page 18
5. After the caster assemblies are installed, attach the support bar that connects the two casters as shown in the following figure.
Align the holes on the end of the support beam with the M8 pem studs on the caster assembly.
Using a 13-mm socket, secure with M8 keps nut and tighten to 18 ft-lb.
Figure 3.8 Attaching support bar between casters
ITEM DESCRIPTION
1 M8 pem studs
2 M8 keps nuts
6. Install the fixed casters on the rear of the rack as shown in the following figure.
Align the holes in the caster assembly over the M8 pem studs located on the side of the frame.
Secure with M8 keps nut and tighten to 18 ft-lb.
7. The flange of the caster assembly aligns with a hole on the side of the frame. Secure with a M6 carriage bolt and nut and tighten to 7.5 ft-lb.
Vertiv | DCE Installer/User Guide | 18
Page 19
8. Secure the caster assembly to the hole on the rear of the frame with a M8 Bolt and tighten to 18 ft-lb.
9. After the caster assemblies are installed, attach the support bar that connects the two casters.
Align the holes on the end of the support beam with the M8 pem studs on the caster assembly.
Using a 13-mm socket, secure with M8 keps nut and tighten to 18 ft-lb.
Figure 3.9 Installing fixed casters on rear of rack
ITEM DESCRIPTION
1 Fixed cast er assembly
2 Rear of rack
Vertiv | DCE Installer/User Guide | 19
Page 20
3.11.1 Leveling Feet Adjustment
Leveling feet are preinstalled at the factory. They are easily accessible in the front and rear of the rack frame.
To adjust the leveling feet from inside the rack, a 5/16 socket and refer to the following figure.
To adjust the leveling feet from beneath the rack use a 3/4 open-end wrench and refer to the figure.
Figure 3.10 Adjusting the leveling-feet
ITEM DESCRIPTION
1 Counter-clockwise rotation to adjust f eet up
2 Clockwise rotation to adjust feet down
3 Adjusting feet beneath rack
4 Adjusting feet from inside the rack
3.12 Mounting Rail Adjustment
Each rack has two pairs, 12 ga. steel, powder-coated vertical mounting rails installed with all standard frames at 19-in. EIA 310-E. Universal cage nut rails (M6) are standard. Rack Mount Units (RU) are marked on the front and rear of the rails for easy equipment mounting. Accessory Mounting Holes (AMH), rectangular cable pass-through holes, and vertical cable tie-down slots can be found on side of rails, shown in the following figure.
To adjust the rails:
CAUTION: Do not attempt to adjust rails once equipment has been loaded.
1. Rails are attached using an M6 carriage bolt and M6 keps nut. Loosen the top, bottom and middle bolts using a 10-mm drive socket.
2. Adjust the rails from any location from front to back.
Vertiv | DCE Installer/User Guide | 20
Page 21
3. If required by the application, engage the lock-rail feature by turning the locking tab around and inserting into the rail and into the slot on the horizontal support.
Figure 3.11 Rail features and hardware
ITEM DESCRIPTION
1 Vertical mounting rail
2 Lobster-claw holes
3 Cable pass-through cut-outs
4 Cable tie-down slots
5 Accessory mounting holes (AMH)
6 M6 carriage bolt
7 M6 keps nut
8 Locking t ab
9 Front-to-rear rack horizontal
10 Horizontal depth marking
Vertiv | DCE Installer/User Guide | 21
Page 22
3.13 PDU/Cable-management Brackets
PDU/Cable Management Brackets may be installed in each rear corner of the rack. Keyhole cutouts along the bar accept button-mounting of PDUs. The rectangular hole pattern accepts “D” rings, lobster claws, and a variety of other cable management.
Secure the brackets to the rack at the top, center, and bottom rack horizontally using the M6 keps nuts and screws as shown in the figure.
WARNING: When using power distribution units (PDUs), each PDU should be connected to a dedicated branch circuit that is rated for the continuous load of all the equipment connected. When not using a PDU, each piece of equipment should be connected to a dedicated branch circuit.
Figure 3.12 Installing PDU/cable-management racks
ITEM DESCRIPTION
1 Depth measurements
2 Key-hole cut-outs
3 Hole pattern for D rings, lobster claws , etc.
4 M6 keps nut
5 M6 screw
Vertiv | DCE Installer/User Guide | 22
Page 23
4 OPTIONAL ACCESSORIES
This section describes options that may be included with your DCE rack(s), and their installation.
4.1 Vertical Cable Manager Kit: E846015
Installation of Vertical Cable Manager kit requires the EIA rails to be recessed a total of 4.75 in. from the front of the rack.
When stalled in 700-mm and 800-mm wide racks, the vertical cable manger kit does not require AMH adapter brackets. When installed in in 600-mm wide racks, AMH adapter brackets are required.
To install adapter brackets and cable manager on a 600-mm rack:
1. Align the bent tabs to the cut-out pattern on the outside surface of the EIA rail, and insert them.
2. Install each adapter bracket with (14) panel fasteners.
Vertiv | DCE Installer/User Guide | 23
Page 24
3. Install each of the vertical cable managers using (4) flat-head M6 screws on the face of the adapter brackets, facing outward.
4. Mount the vertical cable manager directly to the AMH of the EIA rail.
NOTE: Vertical Cable Manager Kit can be installed with a Vertical Airflow Baffle with Brush Kit. See page "Vertical-airflow Baffle withBrushKitandVerticalCableManager" on page32.
Figure 4.1 Installing cable-management kit, including detail of AMH bracket installation
ITEM DESCRIPTION
1 AMH adapter bracket
2 Tabs for out-put pattern along EIA rail
3 Top-view of AMH adapter bracket
4 Vertical cable managerinstallation
5 7 RU vertical cable manager
6 AMH bracket
7 AMH bracket
8 Push f asteners f or AMH bracket
9 EIA rail
10 M6 Torx s crew
11 Vertical cable manager
12 Adapter bracket
13 Push f astener for AMH bracket
Vertiv | DCE Installer/User Guide | 24
Page 25
4.2 Horizontal Front-to-rear Cable Manager: E11015/E12015
The front-to-rear horizontal cable manager for 800 W units allows cabling to be managed from front to back of the DCE rack. The horizontal manager accepts lobster claw managers (part # 002185050), Velcro Strap Managers (part # 002185060), and has slots to accept cable ties.
The managers come in two depths for 1100-mm and 1200-mm racks.
The cable manager can be installed into the frame in 4 places, 2 in the middle and 2 in the bottom.
Refer to the figure to fasten the frame in the chosen location.
Figure 4.2 Installing horizontal, front-to-rear cable manager
ITEM DESCRIPTION
1 M6 Hex-head bolt
2 Hex nut
3 Mounting rail
4 Lacing bar
4.3 Front-to-rear Cable Trough: E811015/E812015
The 800-mm wide racks with depths of 1100mm and 1200mmhave the option for front-to-rear cable troughs. The troughs are adjustable with the movement of the mounting rails.
E811015: Adjustable from 20.188in. to 33.464in.
E812015: Adjustable from 22.188in. to 38.464in.
To install the cable trough:
1. Measure front-to-back distance between EIA rails from inside to inside mounting planes.
2. Loosen or remove (2) center screws to allow for adjustment and movement of inner and outer members.
3. Proceed to install trough into rack by finding the cut outs with (2) holes directly below cut-out.
4. From inside of rack and between rails, lift trough and engage tab through cut-out and drop into place
Vertiv | DCE Installer/User Guide | 25
Page 26
5. Repeat step 4 for the other end of the trough.
6. Proceed to install all screws, (2) front and (2) back through tab holes into EIA rail holes.
7. Install the (2) center screws to secure inner and outer trough members
Figure 4.3 Installing front-to-rear cable trough
ITEM DESCRIPTION
1 Center screws
2 Trough assembly
3 Screws for tab holes in EIA rail holes
4 Trough tab engaged in rail cutout
5 Screws for tab holes in EIA rail holes
6 Outer t rough assembly
7 Inner t rough assembly
8 Screws for tab holes in EIA rail holes
9 Center screws
4.4 Adjustable Ladder-rack Bracket: ELRB016
The adjustable ladder-rack and basket-tray support bracket allows most third-party ladder racks or trays to be installed on the top of DCE racks. The bracket accepts racks or trays of 12 in.,18in. and 24in. widths. Height can be adjusted to accommodate the difference in height between racks. There are many mounting holes in the top panel to accommodate the placement of the brackets. Two brackets are recommended per rack.
Vertiv | DCE Installer/User Guide | 26
Page 27
Figure 4.4 Ladder-rack bracket components
ITEM DESCRIPTION
1 Ladder rack, shown for reference only
2 J bolt
3 1/4-20 Hex nut
4 M6 Hex-head bolt
5 M6 cage nut
6 Square holes f or M6 cage nuts
7 5/16-18 Hex nut
8 5/16 flat washer
9 1/4-20 carriagebolt
10 Adjust top section to final height before tightening carriagebolts and hex nuts.
Vertiv | DCE Installer/User Guide | 27
Page 28
4.5 Overhead cable trough: E6016/7016/8016
The overhead troughs ship assembled, but not installed. The top of the DCE rack has a variety of mounting holes. Select the trough model based on rack width:
600-mm racks use DCE6016
700-mm racks use DCE7016
800-mm racks use DCE8016
To install the overhead cable trough:
1. Place the trough where you require cable routing.
2. Insert a cage nut into the appropriate square hole on the top panel, and secure the trough on top with M6 screws.
Figure 4.5 Installing overhead cable trough
ITEM DESCRIPTION
1 M6 cage nuts and screws
Vertiv | DCE Installer/User Guide | 28
Page 29
4.6 Exhaust Chimney: E1832014/E3246014
The chimney top panel includes and opening for an exhaust chimney. The chimney options are:
E1832014: Adjustable 18 in. to 32in. H; 18.75in. W x 14.3in. D
E3246014: Adjustable 32in. to 46in. H; 18.75in. W x 14.3in. D
To install the exhaust chimney:
1. Place the chimney on top of the opening in the top panel and secure it from inside the rack with four #10-32 x 1/2in. L screws.
2. Raise the outer section of the chimney so the rubber seal touches the ceiling. When the chimney is at the desired height, use a screwdriver to punch out the appropriate knockout along each side of the chimney.
3. Insert the chimney knob into the knockout to secure the chimney.
Figure 4.6 Installing the exhaust chimney
ITEM DESCRIPTION
1 Fully-extended c himney
2 Fully-compressed chimney
3 Knockouts for chimney knob
4.7 Vertical-airflow Baffle with Brush Kit for800-mmWRack:E48801/E428014/E458014
The vertical airflow baffle with brush kit is used to prevent air recirculation within the rack. It can be installed in 42, 45, and 48 RU racks that are 800-mm wide. The kit installs using the accessory mounting holes (AMH) along the rail.
Vertiv | DCE Installer/User Guide | 29
Page 30
Figure 4.7 800-mm baffle components and grommet installation
ITEM DESCRIPTION
1 Top cross plate for first AMH on all racks
2 Tool-less rivets for 1/4-in. push holes
3 Brush grommet strips
4 RU break-off intervals on brush-strip mounting plate for 45 RU and 42 RU racks
5 Top view of brush grommet installed.
6 EIA rail
7 Brush grommet
8 Brush-strip mounting plate
Vertiv | DCE Installer/User Guide | 30
Page 31
4.8 Vertical Airflow Baffle with Brush Kit for700-mmWRack:E487014/E427014/E457014
The vertical airflow baffle with brush kit is used to prevent air recirculation within the rack. It can be installed in 42, 45, and 48 RU racks that are 700-mm wide. The kit installs using the accessory mounting holes (AMH) along the rail.
Figure 4.8 700-mm baffle components and grommet installation
ITEM DESCRIPTION
1 Top cross plate for first AMH on all racks
2 Tool-less rivets for 1/4-in. push holes
3 Brush grommet strips
4 RU break-off intervals on brush-strip mounting plate for 45 RU and 42 RU racks
5 Top view of brush grommet installed.
6 EIA rail
7 Brush grommet
8 Brush-strip mounting plate
Vertiv | DCE Installer/User Guide | 31
Page 32
4.9 Vertical-airflow Baffle withBrushKitandVerticalCableManager
The brush grommet rail kit and vertical cable manager can be installed together. To install the cable manager, the EIA rails must be recessed a total of 4.75in. from the front of the rack. When installing both options, place a vertical cable manager on top of the mounting plate of the vertical airflow baffle; align with the AMH. Insert a tool-less rivet through both the vertical cable manager and mounting plate.
Figure 4.9 Installing a baffle and cable manager together
ITEM DESCRIPTION
1 Tool-less rivets for 1/4-in. push holes
2 AMH along EIA rail
3 Vertical brush-mounting plate
Vertiv | DCE Installer/User Guide | 32
Page 33
4.10 Switch Kit for Side-to-side Cisco Switch for1000-mmWRack:E7009014/E7018014
The kit provides proper air flow for a side-to-side switch. The kit options are:
E7009014: Kit for 14 RMU Cisco switch
E7018014: Kit for 25 RMU Cisco switch
Each kit includes:
2-piece side air baffle
Top cross-plate/baffle
24 cover panels for EIA rails, with fasteners
Cable-management rail kit, with 12 finger managers and fasteners
The switch kit controls air flow for proper switch performance. The following figure shows how air should flow past the switch when the kit is installed.
NOTE: For clarity, the main rack is not shown in the figure.
Figure 4.10 Air-flow through the Switch Kit
ITEM DESCRIPTION
1 Cool-air intake
2 Hot-air exhaust
3 Left-rear EIA rail
4 Foam gasket
Vertiv | DCE Installer/User Guide | 33
Page 34
ITEM DESCRIPTION
5 Depth-adjustable interior bracket
6 Foam gasket
7 Right-rear EIA rail
8 Air-intake baffle
9 Right-front EIA rail
10 Foam gasket
11 Front of enclosure
12 Left-front EIA rail
13 Air-exhaust baffle
To install the baffle, finger cable managers, and cover plates:
1. Insert one side of the baffle through the front or rear of the rack, and set it on top of the bottom-gusset of the EIA rail.
2. Mate the side of the baffle to the side of the EIA rail, align the cutouts, and secure to the front and rear rails with the fasteners as shown in the following figure.
3. Repeat steps 1 and 2 for the second side of the baffle.
4. Install the brush strip onto flange of the depth-adjustable interior bracket.
5. Peel the backing from the foam gasket, and stick it in place on the top and bottom flanges of the baffle. You may need to cut the gasket to size.
Figure 4.11 Fastening the baffle to the rail
ITEM DESCRIPTION
1 EIA rail gusset
2 M6 carriage bolt
Vertiv | DCE Installer/User Guide | 34
Page 35
ITEM DESCRIPTION
3 Baffle sect ion
4 Wing nut
5 Foam gasket
6. Refer to the following figure to install the top-plate/baffle and cable-management fingers (6 per rail) on the front of the rails
Figure 4.12 Installing top-plate and cable-management finger sections
ITEM DESCRIPTION
1 Top plate/baffle
2 #10 flat washer
3 10-32 PH pan-headscrew
4 Finger cable-management s ection
5 10-32 Keps nut
7. Install the cover plates as shown in the following figure (example of front shown), leaving the only the following openings uncovered for proper air intake and exhaust depending on baffle size:
6 openings on the right front and left rear of a 25 RU baffle
3 openings on the right front and left rear of a 14 RU baffle
Vertiv | DCE Installer/User Guide | 35
Page 36
Figure 4.13 Cover-panel installation and location of openings
ITEM DESCRIPTION
1 Cover plate
2 #10-32Torx screw, 4 per panel
3 Sections in EIA rail to leave open
4 Right-front EIA rail
4.11 Switch Kit for Side-to-side Cisco Switch for800-mmWRack:E650304/E6506014/E9513014/E6513014
The kit provides proper air flow for a side-to-side switch. The kit options are:
E6503014: Kit for 4 RU Cisco switch
E6506014: Kit for 11 RU Cisco switch
E9513014: Kit for 14 RU Cisco switch
E6513014: Kit for 19 RU Cisco switch
To install the baffles:
1. Make sure to orient the baffles for proper air flow as follows:
Place the left-side, exhaust baffle vertically in the rail with the closed face toward the front, and the open face toward the back.
Place the right-side, intake baffle with the open face toward the front and the closed face toward the back.
2. Assemble and adjust the baffles before mounting on the rail.
3. Peel the backing from the gasket, and stick it on the top and bottom flanges that make contact with the side of the equipment.
Vertiv | DCE Installer/User Guide | 36
Page 37
4. Install the baffle on the rails by inserting the "tabs" on each end of the baffle in to the 0.281-in. square hole pattern on the rail, as shown in the figure.
5. Use the carriage bolts and wing nuts in the square holes above and below each tab to secure the baffle to the rails.
Figure 4.14 Switch baffle installation for 800-mm rack
ITEM DESCRIPTION
1 Exhaust baffle
2 Gasket
3 Tab in square-hole patt ern on rail
4 Carriage bolt in square-holepattern on rail
5 Intake baff le
6 M6 wing nut
7 M6 carriage bolt
Vertiv | DCE Installer/User Guide | 37
Page 38
4.12 Baying Gasket Kit: E4013
NOTE: The kit is for 24-in. wide spacing only.
When baying racks together on 24-in. centers, use a Baying Gasket Kit to seal the gap between the racks to maintain proper hot-aisle/cold-aisle best practices. The gasket must be installed before baying racks.
To install the gasket:
1. Measure and cut gasket to length.
2. peel adhesive backing from the gasket, and place the gasket around side perimeter of one of the racks.
3. Position the racks next to each other with the gasket between them. The racks are ready for baying.
Figure 4.15 Baying gasket location
Vertiv | DCE Installer/User Guide | 38
Page 39
4.13 Baying Kit: E9013
To install the racks in a bay configuration:
1. Place racks in a row and open or remove doors for easy access to frame holes.
2. Decide spacing between rack centers, 24in. or 600mm, which determines the screw holes used in the bracket, see the following figure.
3. Install 2 brackets at front and 2 at rear per the rack's mating planes, as shown in the figure.
Figure 4.16 Installing baying brackets
ITEM DESCRIPTION
1 Baying bracket
2 M6 flat-head Torx screw
3 Screw hole for 24-in. c enters
4 Screw hole for 600-mm centers
Vertiv | DCE Installer/User Guide | 39
Page 40
This page intentionally left blank.
Vertiv | DCE Installer/User Guide | 40
Page 41
Page 42
VertivCo.com | Vertiv Headquarters, 1050 Dearborn Drive, Columbus, OH, 43085, USA
© 2017 Vertiv Co. All rights reserved. Vertivand the Vertiv logo are trademarks or registered trademarks of Vertiv Co. All other names and logos referred to are trade names, trademarks or registered trademarks of their respective owners. While every precaution has been taken to ensure accuracy and completeness herein, Vertiv Co. assumes no responsibility, and disclaims allliability, for damages resulting from use of this information or for anyerrors or omissions. Spec ifications are subject to change without notice.
SL-11992_REV2_4-17/590-1311-501B
Loading...