Preparation In cold weather,all glazing should be completed and the building heated to a minimum of 55 °F (13 °C) before
gypsum base or lath and plaster installation. The temperature of the building must be maintained in uniform range above 55 °F for an adequate period prior to application of plaster, while plastering is being done, and until plaster is dry. Heat should be well distributed in all areas, with deflection or protective screens used to prevent concentrated or irregular heat on the plaster surfaces.
Ventilation and air circulation should be provided to properly dry the plaster subsequent to plaster applications and proper set. This can be accomplished by keeping windows open sufficiently to provide air circulation in glazed buildings; in enclosed areas lacking normal ventilation, provisions must be made to mechanically remove moisture-laden air.
If glazed sashes are not in place and the building is subject to hot, dry winds or temperature differentials from day to night of 20 °F (11 °C) or more, openings must be screened with cheesecloth or similar material.
Application Mixing STRUCTO-LITE Brand Gypsum Plaster contains mill-mixed aggregate, so it is mixed with water only on the jobsite.
Conventional
Mix basecoat plaster by hand or in a mechanical mixer to a uniform consistency.
Plaster
Applying Apply the basecoat plaster by hand or machine in one or two coats. Unit masonry surfaces that exhibit high suction Basecoat
shall be moderately wetted immediately before plastering.
For two-coat work over gypsum lath and masonry, apply the S
TRUCTO-LITE Brand Gypsum Plaster basecoat (first
coat) with sufficient material and pressure to form a good bond to the base and to cover well; then double back to bring the plaster out to grounds. Straighten to a true surface with a rod and darby without the use of addition­al water and leave rough to receive the finish (second) coat.
For three-coat work, apply the S
TRUCTO-LITE Brand Gypsum Plaster scratch (first) coat with sufficient material
and pressure to form good full keys on metal lath, and good bond on other bases, and then cross-rake.Apply brown (second) coat after scratch (first) coat has set firm and hard. Bring out to grounds and straighten to a true surface with a rod and darby without the use of additional water. Leave the brown coat rough to receive the finish (third) coat.
STRUCTO
-LITE
®
Brand
Gypsum Plaster
Application Tips
Manufactured by United States Gypsum Company 125 South Franklin Street Chicago, IL 60606
800 USG.4YOU (874-4968) www.usg.com
P848/2-04 ©2004, United States Gypsum Company Printed in U.S.A.
Trademarks
The following are trademarks of United States Gypsum Company or a related company: S
TRUCTO-LITE, USG.
Note
Products described here may not be available in all geo­graphic markets. Consult your U.S. Gypsum Company sales office or representative for information.
Notice
We shall not be liable for inci­dental or consequential dam­ages, directly or indirectly sus­tained, nor for any loss caused by application of these goods not in accordance with current printed instructions or for other than their intended use. Our lia­bility is expressly limited to replacement of defective goods. Any claim shall be deemed waived unless made in writing to us within thirty (30) days from the date it was or reasonably should have been discovered.
SAFETY FIRST!
Follow good safety practices. Read material safety data sheets and related literature on products before specification and/or installation.