USG RED TOP Gauging Plaster User Manual

Mixing Mix double-hydrate limes in a clean container or mechanical mixer.Add one bag of lime to 5-1/2 to 6 gal. of
water (21-23 liters) and mix until the putty is smooth. Mix with a portable drill mixer 2-1/2 to 3 min. at 450-600 rpm or with a paddle mixer for 12-20 min. at 50-75 rpm.
Mix single-hydrate limes in a clean container, using approximately 6 gal. (23 L) of water to each 50-lb. (22.7 kg) bag of lime. For a smooth, plastic putty, machine-mix to a soupy consistency, then pour it into a soaking box and hoe briskly. Let the mix soak for 16 hours and then screen the putty through 8-mesh hardware cloth before using.
To prepare finish plaster, mix R
ED TOP Brand Gauging Plaster in proper proportion by dry weight with lime. Over
Product Finish Texture Physical Gauging to Lime, Approx. Coverage
Properties to sand (dry wt.) per Ton (sq. yds.)
(1)
RED TOP Smooth trowel Standard 50 lbs. gauging 390 Gauging Plaster 100 lbs. lime and Lime Finish
RED TOP Float finish Standard 50 lbs. gauging 280 Gauging Plaster 100 lbs. lime Lime and 400 lbs. sand Sand Finish
1. 1/16thick.
Application Apply a tight scratch coat over the entire working area of the of the partially dry basecoat. Immediately double
back with material from the same batch and fill out to a true and even surface nominally 1/16 in. thick (no more than 1/8 in. thick). Allow the surface to become firm, then trowel well with water. Do final troweling after the finish has begun to set. Surface should be free from cat faces and other blemishes or irregularities.
R
ED TOP Brand Gauging Plaster and lime with sand may be used to produce a float finish; however, best results
are achieved by using R
ED TOP Brand Keenes Cement with lime and sand. For float finish coats, scratch plaster
in thoroughly and immediately double back to a true, even surface. Float using a sponge, cork, wood, carpet or rubber float to bring the aggregate to the surface to produce a finish of uniform texture free of slick spots, cat faces and other blemishes. Use water sparingly to prevent variations in texture and finished color.
RED
TOP
®
Brand
Gauging Plaster
Application Tips
Manufactured by United States Gypsum Company 125 South Franklin Street Chicago, IL 60606
800 USG.4YOU (874-4968) www.usg.com
P842/2-04 ©2004, United States Gypsum Company Printed in U.S.A.
Trademarks
The following trademarks used herein are owned by United States Gypsum or a related company: R
ED TOP.
Note
Products described here may not be available in all geographic markets. Consult your U.S. Gypsum Company sales office or representative for information.
Notice
We shall not be liable for inci­dental or consequential dam­ages, directly or indirectly sus­tained, nor for any loss caused by application of these goods not in accordance with current printed instructions or for other than their intended use. Our liability is expressly limited to replacement of defective goods. Any claim shall be deemed waived unless made in writing to us within thirty (30) days from the date it was or reasonably should have been discovered.
SAFETY FIRST!
Follow good safety practices. Read material safety data sheets and related literature on products before specification and/or installation.