Unitronics electric UM2B User Manual

Read this manual before using the equipment.
Keep this manual with the equipment.
(Recovery voltage Meter)
User manual
TABLE OF CONTENTS
- 1 -
TABLE OF CONTENTS
PROLOGUE _____________________________________________________________ 3 SYMBOLS _______________________________________________________________ 4 GUARANTEE ____________________________________________________________ 5
1.- INTRODUCTION ______________________________________________________ 6
2.- DESCRIPTION OF MEASURING METHOD _______________________________ 8
2.1.- Philosophy of the method ________________________________________________ 8
2.2.- Test characteristics _____________________________________________________ 9
2.3.- System behavior and important parameters during measurement ______________ 9
2.4.- ETPRA. Data interpretation _____________________________________________ 13
3.- UM2B EQUIPMENT___________________________________________________ 14
3.1.- Description of the product ______________________________________________ 14
3.2.- System elements _______________________________________________________ 15
3.3.- Physical description of equipment ________________________________________ 19
4.- PREPARATIONS BEFORE TO USE _____________________________________ 21
4.1.- Precautions in the area of installation _____________________________________ 22
4.2.- Equipment connection __________________________________________________ 23
4.3.- Disconnection of equipment _____________________________________________ 26
5.- SOFTWARE DESCRIPTION ____________________________________________ 27
5.1.- Introduction __________________________________________________________ 27
5.2.- Hardware dongle. Configuration menu ____________________________________ 29
5.3.- Test performance ______________________________________________________ 31
5.3.1.- Test identification _______________________________________________________ 33
5.3.2.- Transformer technical data ________________________________________________ 38
5.3.3.- Configuration of measurement _____________________________________________ 42
5.3.4.- Connection ____________________________________________________________ 44
5.3.5.- Measurements _________________________________________________________ 46
5.4.- Test analysis __________________________________________________________ 52
5.4.1.- Select test file __________________________________________________________ 53
5.4.2.- Transformer technical data ________________________________________________ 55
5.4.3.- Recovery voltage _______________________________________________________ 57
5.4.4.- Peak time _____________________________________________________________ 59
5.4.5.- Insulation resistance _____________________________________________________ 60
TABLE OF CONTENTS
- 2 -
5.5.- Test duplication assistant _______________________________________________ 62
5.6.- Remarks page _________________________________________________________ 63
5.7.- Reports printing _______________________________________________________ 64
5.8.- About … _____________________________________________________________ 70
5.9.- Exiting _______________________________________________________________ 71
6.- EQUIPMENT MAINTENANCE _________________________________________ 73
6.1.- Cleaning of equipment _________________________________________________ 74
6.2.- Care of cables _________________________________________________________ 75
6.3.- Check of high voltage cables _____________________________________________ 76
6.4.- Replacing fuse ________________________________________________________ 78
6.5.- Storage and transport __________________________________________________ 79
7.- TROUBLESHOOTING _________________________________________________ 80
8.- TECHNICAL SUPPORT________________________________________________ 83
8.1- Return for calibration/repair _____________________________________________ 83
8.2.- Ordering spares _______________________________________________________ 86
8.3.- Observations __________________________________________________________ 86
8.4.- Authorized representatives and technical services ___________________________ 89
9.- SPECIFICATIONS ____________________________________________________ 90
9.1.- Electrical. ____________________________________________________________ 90
9.2.- Technical characteristics: _______________________________________________ 91
9.3.- Measurement Scales. ___________________________________________________ 91
9.4.- Minimum control PC requirements _______________________________________ 92
9.5.- Additional specifications ________________________________________________ 92
APPENDIX A.- “CE” CONFORMITY DECLARATION ________________________ 93 APPENDIX B.- CONTROL SOFTWARE INSTALLATION ______________________ 94 APPENDIX C.- OTHER UNITRONICS EQUIPMENT _________________________ 95
C.1.- Available applications __________________________________________________ 96
APPENDIX D.- GLOSSARY ______________________________________________ 101
PROLOGUE
- 3 -
PROLOGUE
This instructions manual contains all the information required to start-up and maintain the UM2B metering system. The objective is to provide all the information required for a correct operation.
IMPORTANT: Read the entire instructions manual before starting up the UM2B unit.
The information contained in this manual is considered to be as accurate as possible. In any case, UNITRONICS will accept no responsibility for direct or indirect damage arising as a result of misinterpretation, inaccuracies or omissions therein.
SYMBOLS
- 4 -
SYMBOLS
DANGER: This symbol indicates a highly dangerous procedure that
might cause serious damage to the equipment or to persons, or even death, if not correctly performed.
ATTENTION: This symbol indicates a dangerous procedure that might cause serious damage to the equipment or to persons if the appropriate precautions are not taken.
UNITRONICS, S.A.U. is an ISO9001 certified company.
The equipment meets the requirements of the EU Directives.
UM2B. Recovery Voltage Meter User Manual
June 2008 (Fifth Edition) UM2B User Manual V3_0CE.doc
Copyright 2008, UNITRONICS. URL: http://www.unitronics-electric.com All rights reserved. The reproduction of any part of this manual is prohibited without authorization. The contents of this manual may be changed without prior notice.
GUARANTEE
- 5 -
GUARANTEE
All equipment produced by UNITRONICS has a standard warranty period of 12 months as from the date of delivery to the customer.
The warranty is against defects in materials and workmanship. UNITRONICS‟ obligation shall be to repair or replace defective products within the warranty period. The warranty covers the equipment. It does not cover accessories such as cables, etc.
In order to benefit from this warranty, the purchaser should inform UNITRONICS or his closest representative (see section 8) of the defect prior to the completion of the warranty period.
This warranty does not cover any defect, fault or damage caused by misuse or inadequate maintenance by the purchaser, nor non-authorized modifications or use outside the specifications. Neither does it cover faults caused by natural disasters, including fire, flood, earthquake, etc.
Any opening of the equipment, modification, repair or attempt to repair performed without authorization shall invalidate this warranty, which shall automatically be left void.
This warranty is effective only for the original purchaser of the product and is not transferable in the event of resale.
Warranty extensions and maintenance contracts are available for both the hardware and software. Please ask for information from the commercial department of your nearest representative (see section 8).
1.- INTRODUCTION
- 6 -
1.- INTRODUCTION
This unit has been especially developed to facilitate the measurement of recovery voltage in dielectrics. This measurement is especially significant in the case of transformer dielectrics, where the equipment provides an interpretation of the possible degree of humidity in the insulation and its evolution with time. In paper-oil dielectrics, the quality of the insulation is influenced to a large degree by it‟s humidity content. In any case, the unit is capable of evaluating the status of dielectrics of all types, both in rotating machines and in transformers, cables and other devices.
Gaining insight into the status of transformers is a complex problem. For this reason, different techniques have been developed, allowing in-depth studies to be performed on the different parts into which transformers may be divided.
One of the methods used consists of measuring the recovery voltage of transformers, this allowing problems such as the following to be detected:
degradation of solid dielectric degradation of liquid dielectric contamination of the insulation
Almost all these methods have a peculiarity: the absolute values of the parameters measured are not usually sufficiently indicative for the results to be evaluated. Rather, it is their evolution that provides the best information on the status of the winding, as a result of which it is particularly useful for the results to be memorized and incorporated into databases for correlation.
This leads to the definition of a predictive maintenance policy consisting of the scheduling, at a suitable frequency, of a series of routine and easily performed tests that provide sufficient information on the evolution of the assembly through the analysis of certain parameters. When these analyses detect rapidly evolving situations, or when average values considered to be potentially hazardous are reached, other more complex testing techniques will be applied, which may imply the unavailability of the machine for long periods or even some risk for the integrity of the winding.
The objective of this type of maintenance is to gain accurate insight into the actual status of the equipment or component and, depending on its condition, to determine what course of action would be most appropriate: continue normal operation, impose certain limitations, undertake service or repairs or, finally, undertake replacement. In other words, the aim is not only to limit unnecessary actuations but also to complete the information available on the actual status of the equipment, such that suitable decisions may be taken.
1.- INTRODUCTION
- 7 -
Predictive maintenance is applied successfully and with the greatest frequency to major items of equipment subjected to complex ageing or degradation phenomenon and on which a large number of variables act. In most of these cases there is no formula available allowing the status of the equipment to be estimated, as a result of which tests are required to obtain the values of different significant parameters and, on the basis of these, to undertake interpretation.
Consequently, start-up goes hand in hand with the definition and performance of tests and the interpretation of their results. For the first, it is necessary to have in-depth knowledge of the equipment and techniques involved, while for the second there is a need for specialist technical personnel.
As a complement to the UM2B unit and it‟s associated software of Recovery Voltage measurement, it exists a software application for Insulation Resistance measurement. This application will allow us to carry out a quick evaluation of the machine insulation test without executing Recovery Voltage software.
3.- UM2B EQUIPMENT
- 8 -
2.- DESCRIPTION OF MEASURING METHOD
2.1.- Philosophy of the method
The UM2B is an automatic system designed to determine the recovery voltage of transformers. It is designed to be a predictive maintenance system, for which it meets the following requirements:
Automatic measuring system. In order to avoid errors due to acquisition times,
manipulation and corrections caused by the ambient conditions and the conditions of the machine at the moment of measurement.
Repeatability of the measures. The system warranties that the readings obtained
over time have been acquired in the same way and under the same degree of accuracy and tolerance. This will allow the evolution of the readings to be studied.
Automatic and organized storage of results. This allows the information obtained
to be handled in a very simple manner.
Updateable system. The system has been developed such that whatever new
software development might arise, it may be implemented with the same hardware elements.
Acquisition of key parameters. The system automatically calculates certain
parameters and graphics for the diagnosis of machine status.
Non-destructive testing. If suitably handled, there is no risk of damage to the
winding during testing.
3.- UM2B EQUIPMENT
- 9 -
2.2.- Test characteristics
The test to be used should be performed, with a view to the following:
The tests should be easy to perform, allowing for performance by suitably trained
personnel from the facility, without the need for specialists.
The tests should not imply any risk for the equipment to be tested.
The tests should not imply excessive unavailability (and if possible none).
The data and results obtained should offer at least some information allowing the
operator performing the test to make an immediate interpretation.
The set of data obtained should allow for storage on data-processing media, such
that they be simple to transmit for in-depth study by specialists, who will obtain the maximum information from the data acquired and take the appropriate decisions through comparative studies with other cases.
2.3.- System behavior and important parameters during measurement
3.- UM2B EQUIPMENT
- 10 -
The UM2B unit is designed to output a direct current voltage of up to 2 kV to the element to be tested, carry out the loading and discharge intervals on the dielectric as described for the specific test and, finally, measure the voltage and current.
The unit will examine the status of the dielectric of the equipment being tested, as shown electrically in figure 2.1. The different elements in this figure are as follows:
- Cg, Geometric capacity of the equipment being tested. This will be determined by
the physical characteristics of the armatures of the equivalent condenser, surface,
properties of intermediate dielectric and separation between armors.
- Ra, Insulation resistance. In measuring, this is related to the final leakage current
following the transitory loading period of the dielectric.
- Rpx and Cpx are the electrical elements used to describe the recovery voltage
characteristic. In an equivalent circuit there will be a multitude of such elements, in
order to reflect the distributed nature of this behavior.
The test to be performed aims to determine the equivalent time constants Rp/Cp, the measure and evolution of which are determining factors as regards the current and future status of the dielectric. The test consists of inserting over a time T a previously established voltage of up to 2 kV. Following this time, a short-circuit is performed on the sample for a time T/2, and finally the evolution of the recovery voltage appearing is recorded. This process (cycle) is repeated for multiples of T, and the maximum recovery voltages associated with each interval or cycle are used to graph a curve on which would be shown in a T time axis of application and maximum tension in the other axis. Above the mentioned dots a fitting curve is drawn. Then, each time constants Rp/Cp should appear as a maximum on the graph.
Figure 2.1: Dielectric equivalent circuit.
When a high voltage generator DC voltage is applied to a dielectric, the current
across the insulation shows the following behavior, as plotted in figure 2-2.
3.- UM2B EQUIPMENT
- 11 -
Figure 2-2: Description of the test procedure.
1) Application of H.V. voltage to the sample. The current starts with a high value that
gradually decays with time and finally remains stable. The low initial insulation resistance is caused in part by the high initial loading current of the associated condenser Cg. This capacitive current rapidly decays to a low value as the insulation is charged. Furthermore, the low initial insulation resistance is caused by another phenomenon, which is the dielectric absorption current, Rp/Cp. This current also decreases with time, albeit more gradually, until it reaches an insignificant value. The final leakage current does not change with the time of voltage application, and is a fundamental parameter for judging the insulation, this is Ra. The insulation resistance varies directly with the thickness of the insulation, and inversely with the area tested.
2) Short-circuiting of the sample. At this moment the current is initiated with a high
value in inverse direction to the period before corresponding to the rapid discharge of Cg, while Ra does not actuate due to the short-circuit having a lower resistance.
There will be a weak current associated with the discharge of the Cp‟s across the Rp‟s, but the most likely thing will be that if the short does not last too long, these
Cp‟s will maintain part of their charge.
3) The short-circuit is removed and the measurement performed. During this phase,
and with the Cp‟s remaining charged, if the voltage is recorded at the terminals of the sample, the Cp‟s will be observed to charge the capacitor Cg across the Rp, and
finally both will discharge via Ra. This gives a curve with a maximum that, as commented before, is the one registered for every cycle.
3.- UM2B EQUIPMENT
- 12 -
For the measurement to be performed under optimum conditions, there are certain
details that should be taken into account:
Conditions of the surfaces. Any dust accumulating on the surface of the sample tested may alter insulation resistance measurements if there is associated humidity, for example in the case of rainfall.
Temperature. The resistance of insulating materials changes with temperature. Consequently, the result of a test will be comparable to that of another only if both are performed at the same temperature. For this purpose, it is habitual to refer tests to certain reference temperatures, with the appropriate correction parameters, in order to allow for comparison. It is of interest that the tested machine has his temperature stabilized (let settle after switched off from service) and his temperature be measured from the inside with appropriate accuracy. Temperature has a large influence in dielectric evaluation as insulation resistance is directly related to temperature variations. To figure out, each 10ºC of thermal increment for the same increment to the same dielectric, his resistance is halved.
Test voltage. Insulation measurements will be performed at test voltage values agree with the working voltage of the machines to be tested, in order not to cause degradation to their insulations.
Previous charge effect. A factor that affects insulation and dielectric absorption measurements is the preliminary presence of a previous charge in the insulation. This charge may come from the normal operation of a generator with its neutral not grounded or from previous insulation resistance measurements. A lot of time may be saved if the generator winding is grounded until such time as the test is to be performed. The duration of this grounding should be around four times the charge period of the previous test.
Measuring cables. In view of the weak currents involved in the measurement and its special characteristics, it is important to take into account the following as regards the cables:
Do not tread on cables or knock or move them during testing.
Locate the cables extended, without bending or folding, as close as possible and in
parallel throughout their entire length.
Should be in perfect condition and checked for use.
3.- UM2B EQUIPMENT
- 13 -
2.4.- ETPRA. Data interpretation
It follows interesting details if you have available the Insulation Resistance
Measurement Software (ETPRA).
From the exam of the circuit of figure 2-1, it states that to discharge Cg, you only
need to short-circuit the dielectric terminals, but to discharge Cpx, it will be required a time proportional to the time constant Rpx*Cpx. This means to say that if a transformer has not been phase-grounded the required time to discharge that Cpx, it will exist some residual charge that make hard to compare consecutive test of Insulation Resistance performed in the dielectric.
The software developed for UM2B unit accounts for this effect and let you perform a discharge period previous to the test, that will make consecutive test easy to exactly compare. Anyway, in some case it could be appreciated slight differences between the insulation measurement performed with the Recovery Voltage software and the one performed with the Insulation Resistance software (ETPRA). This is due to that the Recovery Voltage measurement software uses one of the charging cycles longer than 10 minutes to measure insulation. In this software the discharge conditions of that Cpx have been restricted enough not to make the test last too long and give accurate results. This limit could offer slight measurement differences between both applications.
It is therefore recommendable to begin the test with the unit UM2B after having shorted the machine to test. If it had been made previous test, that short should last at least around four times the charge time of the last test.
3.- UM2B EQUIPMENT
- 14 -
3.- UM2B EQUIPMENT
3.1.- Description of the product
The UM2B unit has been especially designed to determine the recovery voltage of single and/or three-phase transformers and autotransformers of any type. It is based on the measurement of a series of simple parameters by means of a data acquisition system and a computer application for the performance of calculations.
Figure 3-1: Appearance of the measurement system.
Once the data have been obtained, enough information is available for diagnosis of the current status of the transformer, and for assessment of the trend curves. The advantages that characterize the UM2B method may be summarized as follows:
minimum risk for the machine.
reduced unavailability times.
simple performance.
high degree of test automation.
3.- UM2B EQUIPMENT
- 15 -
3.2.- System elements
The equipment may be fitted with the following elements and / or accessories:
NOTE: The XX nomenclature indicates different versions, depending on the characteristics of the equipment. Please consult with your sales person.
REF No
DESCRIPTION
UM2BXX
UM2B measuring equipment with serial number.
Figure 3-2: Measuring unit.
BEL00
Measuring equipment transport bag.
Figure 3-3: Transport bag.
3.- UM2B EQUIPMENT
- 16 -
CR00
Mains supply cable with ground terminal.
CRS23200
Shielded series cable with DB9 terminal connectors for communications between the PC and the unit. The cable must be shielded.
Figure 3-4: Serial cable.
M8AT0L
8-metre long high voltage shielded measuring cables with wide opening clip pincers at one end and high voltage connectors at the other. The polarity is indicated by the color of the clips and connectors: red for positive and black for negative. These must be shielded.
Figure 3-5: High voltage cables with power clips.
3.- UM2B EQUIPMENT
- 17 -
BCL00
Cable transport bag
Figure 3-6: Transport bag.
SOFUM2BRBWXXX
1CD with equipment control software.
UM2BMUXX
The present user manual.
RAFVDM00
Four power sockets protected against voltage surges, differential currents and overcurrent. This incorporates a voltmeter for direct verification of the supply voltage indicator of ground connection and terminals for ground connection.
Figure 3-7: Power Socket.
3.- UM2B EQUIPMENT
- 18 -
MM00
Rigid transport case with reinforced external protection and internal padded lining of high-density foam rubber.
Figure 3-8: Transport Case.
3.- UM2B EQUIPMENT
- 19 -
3.3.- Physical description of equipment
Figure 3-9 shows a drawing of the UM2B unit, the upper part corresponding to the front panel and the lower to the rear panel. The function of each element of the unit is described below.
Figure 3-9: Front and rear panel of the unit.
3.- UM2B EQUIPMENT
- 20 -
1
Test voltage indicator. This acts as a voltmeter, indicating the voltage being applied to the machine by means of 4 LED diodes.
2
Power unit connection indicator. This should light up when the power switch (4) is turned on.
3
Luminous indicator of communications with the PC.
4
Equipment connection switch. This is operated to connect the equipment to the electrical mains when the PC software so indicates.
5
Mains input connection. This includes a fuse-holder and a spare fuse.
6
Unit nameplate.
7
PC communications connector.
8
Connectors for high voltage cables running to equipment being tested.
The rest of the indicators / warnings appear on the computer screen and will be described in detail in chapter 5 (Software description).
4.- PREPARATIONS BEFORE TO USE
- 21 -
4.- PREPARATIONS BEFORE TO USE
The UM2B equipment is an automatic, high performance system especially designed for the assessment of transformer recovery voltage parameter. For performance of the measurement, the system provides high voltages (up to 2000 Volts d.c.) during testing, this possibly implying serious danger for the equipment operator if the system is handled incorrectly.
Consequently, IT IS CONSIDERED ESSENTIAL THAT THE OPERATOR IN CHARGE OF HANDLING AND MAINTAINING THE EQUIPMENT RECEIVE TECHNICAL TRAINING.
Likewise, all persons performing or witnessing a test should take the necessary safety precautions, in order to avoid any contact with the parts to be analyzed or forming part of the measurement system, remaining at some distance from them unless these parts are free from voltage and grounded.
Measurements performed using the UM2B system are carried out OFF-LINE. Consequently, prior to beginning the test, THE SYSTEM SHOULD BE VERIFIED TO BE FREE FROM VOLTAGE/LOAD.
If the equipment is damaged during the warranty period as a result of inappropriate use, without following the instructions described in this chapter, the repair may be excluded from the warranty.
4.- PREPARATIONS BEFORE TO USE
- 22 -
4.1.- Precautions in the area of installation
When this instrument is used to test high voltage machines, all the habitual safety procedures and standards applicable to this type of machines should be adhered to. Ensure in all cases that the equipment being tested is completely discharged and grounded before touching it.
For the safety of the equipment operators or any other worker in the area, as well as for the integrity of the system itself and to ensure that the measurement results are valid, a series of precautions should be taken at the test location. These may be summarized as follows:
Check that the surrounding area is appropriate (without rain or dust storms) and that
it is within the temperature / humidity margins specified for the operation (see
chapter 9: Specifications).
Check that the system supply voltage is within the specific operating limits (see chapter 9: Specifications) and that it is grounded. This ground should match with that of the equipment being tested. In case of doubt, the best thing is to run a thick plaited grounding cable from the system supply to the equipment tested.
Check that the equipment to be tested is free from its operating voltage or any
remnant voltage (it is most advisable for the machine to have been in a previous short
circuit state before the test).
Position the measuring unit and the control computer close to the equipment being
tested, as shown in Figure 4-1.
Isolate the test area by means of the necessary mechanical elements, as homologated
by the safety department of each company, such as cones, fencing, safety tapes of
different colors located at waist height, etc.
4.- PREPARATIONS BEFORE TO USE
- 23 -
4.2.- Equipment connection
In view of danger that this equipment misuse might entail, ALWAYS ADHERE TO THE SEQUENCE DESCRIBED BELOW.
For the performance of a test, the measuring unit and control computer should be located close to the equipment to be analyzed, as shown in Figure 4-1. To start up the equipment, carry out the following instructions in the order presented (the different elements of the panels in Figure 3-9 are referred to in brackets):
Figure 4-1: Disposition of the test elements.
- Connection of PC to UM2B. This connection is accomplished with the series cable, connected to the serial communications port of the PC.
4.- PREPARATIONS BEFORE TO USE
- 24 -
- Safety check. The equipment to be measured should be checked to ensure that it is duly isolated from the external connection lines and completely discharged.
- Connection of high voltage cables to UM2B.
The high voltage cables should first be connected to the unit (8). Next, choose measurement configuration to perform test. The phases of each winding (high/low) will be put on short circuit. The phases may be interconnected by means of bare copper wire if the distances are short and there is no risk of short-circuiting to ground; otherwise, a proper insulating cable should be used. Finally, connect positive / negative terminal according to software indications.
Never remove high voltage connectors during test.
Figure 4-2: Configuration of the test.
V max.: 2000 V dc I max.: 5 mA Installation: CAT II
For properly measuring, the cables must be completely stretched until the measurement point without creases, or anyway, that these have a radius not under 200 mm.
4.- PREPARATIONS BEFORE TO USE
- 25 -
While measuring, the cables must not be stepped, moved or hit, because the measurements could be altered, specially when measuring high­quality insulations, due to the piezoelectric effect of the cable and the weak measured currents. If it is possible, put these cables parallel and nearest between them to avoid interferences.
If the shell of the machine to be analyzed is grounded, a check should be
made to ensure that this is the same ground as the one of the PC supply and the measuring unit. To accomplish this, join these two points with a plaited cable of adequate cross-section. ALL THE GROUNDS USED IN TESTING SHOULD BE INTERCONNECTED.
- Connection of UM2B equipment to electrical mains. This connection is accomplished by running the power cable from (5) to a mains socket. The supply voltage should be checked to ensure that it is within the operating limits (see chapter 9: Specifications) and a check should made to ensure that the socket has an operative ground.
Once the different parts of the equipment have been connected, the PC should be switched on and the control software executed. Following this, it will be sufficient to follow the instructions as they appear on the PC screen. Consequently, the UM2B unit should be
turned on when this software so requires (4).
THE UM2B UNIT SHOULD NOT BE TURNED ON UNTIL THIS IS INDICATED BY THE CONTROL SOFTWARE.
WARNING: If the equipment is used outside manufacturer‟s
specifications, the security could be altered.
4.- PREPARATIONS BEFORE TO USE
- 26 -
4.3.- Disconnection of equipment
ATTENTION!: The cabling should be handled with great care, since
high voltage direct current is involved. There are moments during the test in which the equipment might be electrically charged at high voltage, and handling of the cabling or equipment after the test might be dangerous. Consequently, the habitual safety measures applied to high voltage installations should be taken into account.
Following performance of the test, the equipment itself will discharge the machine analyzed. Meanwhile, the computer will show a message indicating that this operation is being carried out. Consequently, the UM2B unit should be turned off when so indicated
by the control software, following the measurements.
In some transformers, discharging may take several minutes. Consequently, it is good safety practice to use rubber gloves when handling the connecting clips.
When requested by the program, the UM2B unit should be disconnected in accordance with the following steps:
- Switch off the UM2B unit.
- Remove the clips from the equipment being tested.
- Remove the cables from the UM2B. If high voltage connectors are
blocked, unblock them threading security screw that allows remove them.
5.- SOFTWARE DESCRIPTION
- 27 -
5.- SOFTWARE DESCRIPTION
5.1.- Introduction
Along with other units and their respective applications (see Appendix B) the UM2B constitutes a system for the testing and analysis of electrical machines. Consequently, all these applications will be launched from a common base application known as the Electrical Machine Testing and Analysis System” (Figure 5-1), which is located in the folder of the same name under Start Programs.
Figure 5-1: Test menu for power transformers.
This screen shows all the tests that may be performed on the different machines and / or components. If any of the options is shown disabled, it will be because the customer does not have the corresponding application, which he may acquire at any time (see chapter 8 and
appendix B). The UM2B unit is delivered with the application “Recovery Voltage” and it‟s
available another optional application “Insulation Resistance”.
5.- SOFTWARE DESCRIPTION
- 28 -
In this case, the tab entitled “POWER TRAFO” or “MEASURING TRAFO”, or the corresponding icon at the top of the screen should be selected. Then click on the icon corresponding to the UM2B and the Recovery Voltage program will be launched (Figure 5-
2) or the Insulation Resistance (ETPRA) if available. This last one will have the same menu to Figure 5-2 but without the icon‟s Recovery Voltage and Peak Time.
From this moment both applications: Recovery Voltage and Insulation Resistance will be described together because of their similarity, detailing when appear the differences or particularities that offer the Insulating Resistance software (ETPRA).
The main menu of the application offers basically two operating options:
- Test performance (Test).
- Analysis of results (Analysis).
Figure 5-2: Main menu of the UM2B test recovery voltage.
For performance of the test a series of data identifying the machine is required, this being provided by the operator.
Subsequently, it will be possible to carry out an analysis of the results based on the voltages measured and the performance of a series of calculations.
Also provided is a series of utilities, such as a file copy assistant or a notepad for test or analysis events.
Loading...
+ 79 hidden pages