THIS MANUAL IS SUPPLIED AS AN INTEGRAL AND ESSENTIAL PART OF THE PRODUCT AND MUST BE DELIVERED TO THE
USER.
INFORMATION INCLUDED IN THIS SECTION ARE DEDICATED BOTH TO THE USER AND TO PERSONNEL FOLLOWING PRODUCT INSTALLATION AND MAINTENANCE.
THE USER WILL FIND FURTHER INFORMATION ABOUT OPERATING AND USE RESTRICTIONS, IN THE SECOND SECTION
OF THIS MANUAL. WE HIGHLY RECOMMEND TO READ IT.
CAREFULLY KEEP THIS MANUAL FOR FUTURE REFERENCE..
1)GENERAL INTRODUCTION
zThe equipment must be installed in compliance with the regulations
in force, following the manufacturer’s instructions, by qualified personnel.
zQualified personnel means those having technical knowledge in the
field of components for civil or industrial heating systems, sanitary
hot water generation and particularly service centres authorised by
the manufacturer.
zImproper installation may cause injury to people and animals, or
damage to property, for which the manufacturer cannot be held liable.
zRemove all packaging material and inspect the equipment for inte-
grity.
In case of any doubt, do not use the unit - contact the supplier.
The packaging materials (wooden crate, nails, fastening devices, plastic
bags, foamed polystyrene, etc), should not be left within the reach of children, as they may prove harmful.
zBefore any cleaning or servicing operation, disconnect the unit from
the mains by turning the master switch OFF, and/or through the cut-
out devices that are provided.
zMake sure that inlet or exhaust grilles are unobstructed.
zIn case of breakdown and/or defective unit operation, disconnect the
unit. Make no attempt to repair the unit or take any direct action.
Contact qualified personnel only.
Units shall be repaired exclusively by a servicing centre, duly authorised
by the manufacturer, with original spare parts.
Failure to comply with the above instructions is likely to impair the unit’s
safety.
To ensure equipment efficiency and proper operation, it is essential that
maintenance operations are performed by qualified personnel at regular
intervals, following the manufacturer’s instructions.
zWhen a decision is made to discontinue the use of the equipment,
those parts likely to constitute sources of danger shall be made har-
mless.
zIn case the equipment is to be sold or transferred to another user, or
in case the original user should move and leave the unit behind,
make sure that these instructions accompany the equipment at all
times so that they can be consulted by the new owner and/or the
installer.
zFor all the units that have been modified or have options fitted then
original accessory equipment only shall be used.
zThis unit shall be employed exclusively for the use for which it is
meant. Any other use shall be considered as improper and, there-
fore, dangerous.
The manufacturer shall not be held liable, by agreement or otherwise, for
damages resulting from improper installation, use and failure to comply
with the instructions supplied by the manufacturer.
2)SPECIAL INSTRUCTIONS FOR BURNERS
zThe burner should be installed in a suitable room, with ventilation
openings complying with the requirements of the regulations in force,
and sufficient for good combustion.
zOnly burners designed according to the regulations in force should
be used.
zThis burner should be employed exclusively for the use for which it
was designed.
zBefore connecting the burner, make sure that the unit rating is the
same as delivery mains (electricity, gas oil, or other fuel).
zObserve caution with hot burner components. These are, usually,
near to the flame and the fuel pre-heating system, they become hot
during the unit operation and will remain hot for some time after the
burner has stopped.
When the decision is made to discontinue the use of the burner, the user
shall have qualified personnel carry out the following operations:
aRemove the power supply by disconnecting the power cord from the
mains.
b) Disconnect the fuel supply by means of the hand-operated shut-off
valve and remove the control handwheels from their spindles.
Special warnings
zMake sure that the burner has, on installation, been firmly secured to
the appliance, so that the flame is generated inside the appliance
firebox.
zBefore the burner is started and, thereafter, at least once a year,
have qualified personnel perform the following operations:
aset the burner fuel flow rate depending on the heat input of the
appliance;
bset the flow rate of the combustion-supporting air to obtain a combu-
stion efficiency level at least equal to the lower level required by the
regulations in force;
ccheck the unit operation for proper combustion, to avoid any harmful
or polluting unburnt gases in excess of the limits permitted by the
regulations in force;
dmake sure that control and safety devices are operating properly;
emake sure that exhaust ducts intended to discharge the products of
combustion are operating properly;
fon completion of setting and adjustment operations, make sure that
all mechanical locking devices of controls have been duly tightened;
gmake sure that a copy of the burner use and maintenance instruc-
tions is available in the boiler room.
zIn case of repeated burner shut-downs, do not continue re-setting
the unit manually. Contact qualified personnel to take care of such
defects.
zThe unit shall be operated and serviced by qualified personnel only,
in compliance with the regulations in force.
3)GENERAL INSTRUCTIONS DEPENDING ON FUEL USED
3a) ELECTRICAL CONNECTION
zFor safety reasons the unit must be efficiently earthed and installed
as required by current safety regulations.
zIt is vital that all saftey requirements are met. In case of any doubt,
ask for an accurate inspection of electrics by qualified personnel,
since the manufacturer cannot be held liable for damages that may
be caused by failure to correctly earth the equipment.
zQualified personnel must inspect the system to make sure that it is
adequate to take the maximum power used by the equipment shown
on the equipment rating plate. In particular, make sure that the
system cable cross section is adequate for the power absorbed by
the unit.
zNo adaptors, multiple outlet sockets and/or extension cables are per-
mitted to connect the unit to the electric mains.
zAn omnipolar switch shall be provided for connection to mains, as
required by the current safety regulations.
zThe use of any power-operated component implies observance of a
few basic rules, for example:
- do not touch the unit with wet or damp parts of the body and/or with
bare feet;
- do not pull electric cables;
- do not leave the equipment exposed to weather (rain, sun, etc.)
unless expressly required to do so;
- do not allow children or inexperienced persons to use equipment;
zThe unit input cable shall not be replaced by the user.
In case of damage to the cable, switch off the unit and contact qualified
personnel to replace.
When the unit is out of use for some time the electric switch supplying all
the power-driven components in the system (i.e. pumps, burner, etc.)
2
Page 3
should be switched off.
3b) FIRING WITH GAS, LIGHT OIL OR OTHER FUELS
GENERAL
zThe burner shall be installed by qualified personnel and in com-
pliance with regulations and provisions in force; wrong installation
can cause injuries to people and animals, or damage to property, for
which the manufacturer cannot be held liable.
zBefore installation, it is recommended that all the fuel supply system
pipes be carefully cleaned inside, to remove foreign matter that might
impair the burner operation.
zBefore the burner is commissioned, qualified personnel should ins-
pect the following:
athe fuel supply system, for proper sealing;
bthe fuel flow rate, to make sure that it has been set based on the
firing rate required of the burner;
cthe burner firing system, to make sure that it is supplied for the desi-
gned fuel type;
dthe fuel supply pressure, to make sure that it is included in the range
shown on the rating plate;
ethe fuel supply system, to make sure that the system dimensions are
adequate to the burner firing rate, and that the system is equipped
with all the safety and control devices required by the regulations in
force.
zWhen the burner is to remain idle for some time, the fuel supply tap
or taps should be closed.
SPECIAL INSTRUCTIONS FOR USING GAS
Have qualified personnel inspect the installation to ensure that:
athe gas delivery line and train are in compliance with the regulations
and provisions in force;
ball gas connections are tight;
cthe boiler room ventilation openings are such that they ensure the air
supply flow required by the current regulations, and in any case are
sufficient for proper combustion.
zDo not use gas pipes to earth electrical equipment.
zNever leave the burner connected when not in use. Always shut the
gas valve off.
zIn case of prolonged absence of the user, the main gas delivery
valve to the burner should be shut off.
Precautions if you can smell gas
ado not operate electric switches, the telephone, or any other item
likely to generate sparks;
bimmediately open doors and windows to create an air flow to purge
the room;
cclose the gas valves;
dcontact qualified personnel.
zDo not obstruct the ventilation openings of the room where gas
appliances are installed, to avoid dangerous conditions such as the
development of toxic or explosive mixtures.
DIRECTIVES AND STANDARDS
Gas burners
European directives:
- Directive 90/396/CEE - Gas Appliances;
- Directive 2006/95/EC on low voltage;
- Directive 2004/108/CEE on electromagnetic compatibility
Harmonised standards :
-UNI EN 676 (Gas Burners;
-CEI EN 60335-1(Household and similar electrical appliances - Safety.
Part 1: General requirements;
- EN 50165 (Electrical equipment of non-electric appliances for household and similar purposes. Safety requirements.
Light oil burners
European directives:
- Directive 2006/95/EC on low voltage;
- Directive 2004/108/CEE on electromagnetic compatibility
Harmonised standards :
-CEI EN 60335-1(Household and similar electrical appliances - Safety.
Part 1: General requirements;
- EN 50165 (Electrical equipment of non-electric appliances for household and similar purposes. Safety requirements.
National standards :
-UNI 7824: Monobloc nebulizer burners for liquid fuels. Characteristics
and test methods
Heavy oil burners
European directives:
- Directive 2006/95/EC on low voltage;
- Directive 2004/108/CEE on electromagnetic compatibility
Harmonised standards :
-CEI EN 60335-1 Household and similar electrical appliances - SafetyPart
1: General requirements;
- EN 50165 Electrical equipment of non-electric appliances for household
and similar purposes. Safety requirements.
National standards :
-UNI 7824: Monobloc nebulizer burners for liquid fuels. Characteristics
and test methods
Gas - Light oil burners
European directives:
- Directive 90/396/CEE Gas Appliances;
- Directive 2006/95/EC on low voltage;
- Directive 2004/108/CEE on electromagnetic compatibility
Harmonised standards :
-UNI EN 676 Gas Burners
-CEI EN 60335-1(Household and similar electrical appliances - Safety.
Part 1: General requirements;
- EN 50165 Electrical equipment of non-electric appliances for household
and similar purposes. Safety requirements.
National standards :
-UNI 7824: Monobloc nebulizer burners for liquid fuels. Characteristics
and test methods
Gas - Heavy oil burners
European directives:
- Directive 90/396/CEE - Gas Appliances;
- Directive 2006/95/EC on low voltage;
- Directive 2004/108/CEE on electromagnetic compatibility
Harmonised standards :
-UNI EN 676 (Gas Burners;
-CEI EN 60335-1(Household and similar electrical appliances - Safety.
Part 1: General requirements;
- EN 50165 Electrical equipment of non-electric appliances for household
and similar purposes. Safety requirements.
National standards :
-UNI 7824: Monobloc nebulizer burners for liquid fuels. Characteristics
and test methods
3
Page 4
C.I.B. UNIGAS - M039219CA
PART I: INSTALLATION MANUAL
GENERAL FEATURES
This series of industrial burners is designed for all those applications that require big-sized air fans or air-flue heat exchangers to be
installed in sound-proof areas to reduce noise. They can be provided with built-in or separate-mounted control panel (console or wallmounted).
Burner
Gas train
Pumping unit
Fan
Electric panel
Note: the picture shows one of the possible installations. Fan, electrical panel and pumping unit can be placed according to the customer needs.
How to choose the burner
To check if the burner is suitable for the boiler to which it must be installled, the following parameters are needed:
zfuel
zfurnace input, in kW or kcal/h (kW = kcal/h / 860);
zboiler type;
zcombustione head type (reverse flame or three phase)’
ztemperature or pressure of the thermal carrier fluid
zComburent air temperature
zAir duct positioning
zPressure in the combustion chamber
zElevation (altitude) of burner installation
zGas train (only for gas burners)
zPumping unit (only for light-oil or heavy-oil burners)
zAir fan
zBilt-in or separated control panel
zbackpressure (data are available on the boiler’s ID plate or in the user’s manual).
Burners provided with built-in control panel are designed for IP40 index of protection. For other values of IP, please contact the CIB
UNIGAS Technical Dpt.
See the diagram in Fig. 2, as to find the burners that better suite the power range requested in the exmple (9600kW). Once the models
are founded out, the choice regards technical and economical features. Technical features can be summarised in a higher modulation
ratio (fewer start-ups, less consumption, fewer swigings in the generator temperature and pressure values.
Checking the proper gas train size
To check the proper gas train size, it is necessary to the available gas pressure value upstream the burner’s gas valve. Then subtract
the backpressure. The result is called p
the x-axis, as far as intercepitng the network pressure curve, according to the installed gas train (DN65, in the example). From the interception point, draw an horizontal line as far as matching, on the y-axis, the value of pressure necessary to get the requested furnace
input. This value must be lower or equal to the p
gas. Draw a vertical line matching the furnace input value (600kW, in the example), quoted on
gas value, calculated before.
Tipo / Type P6 0
M-...50 (Multibloc DUNGSMB-DLE 420 B01)M-...65 (Filtro /Filter DN65+ SIEMENS VGD40.065 +SKP1x+SKP2x)
25
20
15
10
pressure (mbar)
5
rete / Minimum inlet gas
Minima pressione gas in
0
100200300400500600700800900
Potenza / Output (kW)
Rp 2" (50)
DN65
Fig. 2
5
Page 6
C.I.B. UNIGAS - M039219CA
BURNER SPECIFICATIONS
Burner model identification
Burners are identified by burner type and model. Burner model identification is described as follows.
Type HTP91A Model MG. PR. S. *. A. 1. 80
(1) (2) (3) (4) (5) (6) (7) (8)
(1) BURNER TYPEHTP91A
(2) FUELM - Natural gas G - Light oil
(3) OPERATIONPR - Progressive MD - Fully modulating
(4) BLAST TUBES - Standard
(5) DESTINATION COUNTRY* - see data plate
(6) BURNER VERSIONA - Standard Y - Special
(7) EQUIPMENT 1 = 2 valves + gas proving system
8 = 2 valves + gas proving system + maximum pressure switch
(8) GAS CONNECTION 50 = Rp2
65 = DN65
80 = DN80 100 = DN100
Technical specifications
Note: the Output values are referred to comburent air temperature lower than 50°C.
BURNER TYPEHTP90AHTP91AHTP92AHTP93A
Outputmin - max kW320-2300480 - 2670
Fuel
Natural gas - Light oil
480 - 3050550 - 4100
Gas category(see next paragraph)
Gas rate
min.-max. (Stm
3
/h)
34 - 24351 - 28351 - 32358 - 434
Gas pressure(see Note 2)
Oil viscosity
Oil density
Light oil rate
Power supply
Total power consumption
Total power consumption
Protection
Operation
Gas train 50Ø Valves /Connection
Gas train 65ØValves / Connection
cSt @ 40°C2 - 7.4
3
kg/m
min.-max. kg/h
27 - 19440 - 22540 - 25746 - 345
0.84
230V 3~ / 400V 3N~ 50Hz
kW0.55
kW1.05
1.11.11.1
1.61.61.6
IP40
Progressive - Fully modulating
2” / Rp 2
2”
1/2
/ DN65
Gas train 80ØValves / Connection3” / DN80
Gas train 100ØValves / Connection4” / DN100
Operating temperature°C
Storage Temperature°C
Working service*
-10 ÷ +50
-20 ÷ +60
Intermittent
6
Page 7
C.I.B. UNIGAS - M039219CA
BURNER TYPEHTP512AHTP515AHTP520AHTP525A
Outputmin - max kW600-4500770 - 5200
Fuel
Natural gas - Light oil
1000 - 64002000 - 9750
Gas category(see next paragraph)
Gas rate
min.-max. (Stm
3
/h)
63 - 47681 - 550106 - 677212 - 1032
Gas pressure(see Note 2)
Oil viscosity
Oil density
Oil rate
Power supply
Pump motor
Total power consumption
Protection
Operation
Gas train 50ØValves / Connection
Gas train 65ØValves / Connection
cSt @ 40°C2 - 7.4
kg/m
3
0.84
min.-max. (kg/h)50 - 37965 - 43884 - 539168 - 821
230V 3~ / 400V 3N~ 50Hz400V 3N~ 50Hz
kW1.1
kW1.6
1.51.54
22 4.5
IP40
Progressive - Fully modulating
2” / Rp 2
/ DN65
2”
1/2
Gas train 80ØValves / Connection3” / DN80
Gas train 100ØValves /Connection4” / DN100
Operating temperature°C
Storage Temperature°C
Working service*
-10 ÷ +50
-20 ÷ +60
Intermittent
-
Note1:
Note2:Maximum gas pressure = 360mbar (with Dungs MBC gas valves).
all gas flow rates are referred to Stm
rific value H
= 500mbar (with Siemens VGD gas valves / Dungs MBC gas valves)
Minimum gas pressure = see gas curves.
= 34.02 MJ/Stm3).
i
3
/h (1013 mbar absolute pressure, 15 °C temperature) and are valid for G20 gas (net calo-
* NOTE ON THE BURNER WORKING SERVICE: for safety reasons, one controlled shutdown must be performed every 24 hours of
continuous operation.
NOTE: Choosing the nozzle for light oil, consider Hi equal to 10200 kcal/kg.
Country and usefulness gas categories
GAS
CATEGORY
I
2H
I
2E
I
2E( R ) B
I
2L
I
2ELL
I
2Er
AT ES GR SEFIIE HU IS NO CZ DK GB ITPT CY EE LV SI MT SK BG LT RO TR CH
DN = gas valves size.
* It is recommended to fit a counterflange between burner and boiler. As an alternative, make a smaller hole H, but greather than Y and fit the blast tube from the internal side of boiler
NOTE: the overall dimensions are referred to burners provided with Siemens VGD valves.
C.I.B. UNIGAS - M039219CA
Page 10
Performance Curves
HTP520A
HTP515A
HTP512A
HTP93A
HTP92A
C.I.B. UNIGAS - M039219CA
Output diagram (air temperature = 15°C)
HTP525A
HTP91A
HTP90A
0200040006000800010000120001400016000
Burner performance range
Campo di scelta bruciatore
To get the input in kcal/h, multiply value in kW by 860.
Data are referred to standard conditions: 1013mbar, 15°C.
The burners are despatched in wooden crates. Their dimensions are:
9xA series: 1740mm x 1270mm x 1010mm (LW x PH x HD)
5xxA series:
1burner with gas train detached;
1gasket to be inserted between the burner and the boiler;
2 flexible oil pipes;
1 oil filter;
1envelope containing this manual
Packing cases of this type are affected by humidity and are not suitable for stacking.
To get rid of the burner’s packing, follow the procedures laid down by current laws on disposal of
materials.
1740mm x 1420mm x 110mm (LW x PH x HD)
H
P
L
Handling the burner
ATTENTION! The lhandling operations must be carried out by specialised and
trained personnel. If these operations are not carried out correctly, the residual risk for the burner to overturn and fall down still persists.
To move the burner, use means suitable to support its weight (see paragraph
“Technical specifications”).
The burner is provided with eyebolts, for handling operations.
Eyebolts
Fitting the burner to the boiler
To install the burner into the boiler, proceed as follows:
1make a hole on the closing door of the combustion chamber as described on paragraph “Overall dimensions”)
2place the burner to the boiler: lift it up and handle it according to the procedure described on paragraph “Handling the burner”;
3place the 4 stud bolts (5) on the hole of the boiler’s door, according to the burner’s drilling plate described on paragraph “Overall
dimensions”;
4fasten the 4 stud bolts;
5place the gasket on the burner flange;
6install the burner into the boiler;
7fix the burner to the stud bolts, by means of the fixing nuts, according to the next picture.
8After fitting the burner to the boiler, ensure that the gap between the blast tube and the refractory lining is sealed with appropriate
insulating material (ceramic fibre cord or refractory cement).
Pay attention when designing the air duct: dimensioning must be performed according to the flow rate, the temperature, the distance
between the fan and the burner and according to the fan features as well.
ATTENTION! The bellows unit provided is made of canvas and is provided with blocking spacers to avoid breaking it during
installation: first place the bellows unit between flanges, then remove the spacers. Canvas has to be stretched after the installation, but not stressed.
12
Page 13
C.I.B. UNIGAS - M039219CA
Matching the burner to the boiler
The burners described in this manual have been tested with combustion chambers that comply with EN676 regulation and whose
dimensions are described in the diagram . In case the burner must be coupled with boilers with a combustion chamber smaller in diameter or shorter than those described in the diagram, please contact the supplier, to verify that a correct matching is possible, with respect of the application involved. To correctly match the burner to the boiler verify the necessary input and the pressure in combustion
chamber are included in the burner performance curve; otherwise the choice of the burner must be revised consulting the burner manufacturer. To choose the blast tube lenght follow the instructions of the boiler manufacturer. In absence of these consider the following:
z Cast-iron boilers, three pass flue boilers (with the first pass in the rear part): the blast tube must protrude no more than 100 mm into
the combustion chamber.
z Pressurised boilers with flame reversal: in this case the blast tube must penetrate at least 50 - 100 mm into combustion chamber in
respect to the tube bundle plate.
The length of the blast tubes does not always allow this requirement to be met, and thus it may be necessary to use a suitablyspacer to move the burner backwards or to design a blast tube tha suites the utilisation (please, contact the manifacturer).
Key
a) Heat output in kW
b) Lenght of the flame tube in meters
c) Flame tube firing intensity in MW/m
3
d) Combustion chamber diameter (m)
Fig. 3 - Firing intensity, diameter and lenght of the test flame tube as a function of the heat
input in kW.
sized
Fig. 3
Gas train connections
The diagrams show the components of the gas trai included in the delivery and which must be fitted by the installer.The diagrams are in
compliance with the current laws.
ATTENTION: BEFORE EXECUTING THE CONNECTIONS TO THE GAS PIPE NETWORK, BE SURE THAT THE
MANUAL CUTOFF VALVES ARE CLOSED.
Gas train - 1 - Gas train with valves group VGD 20/40 with built-in gas pressure governor + VPS504 gas proving system
10
MANUFACTURER
54
INSTALLER
1
6
78
2
3
Gas train - 2 (Rp2) - Gas train with valves group MBC 1200SE(2 valves + gas filter + pressure governor + pressure switch) +
VPS504 gas proving system
MANUFACTURER
18
54
1
INSTALLER
7
8
2
3
13
Page 14
C.I.B. UNIGAS - M039219CA
Gas train 3(DN65/80/100) - Gas train with valves group MBC 1900/3100/5000SE (2 valves + gas filter + pressure governor +
pressure switch) + VPS504 gas proving system
MANUFACTURER
INSTALLER
19
1
2
3
54
6
78
Gas train - 4 - Gas train with valves group VGD 20/40.. with built-in gas pressure governor + PGCP gas leakage pressure switch
MANUFACTURER
4
5
1
2
10
16
6
INSTALLER
7
8
Gas train - 5 (Rp2) - Gas train with valves group MBC 1200SE (2 valves + gas filter + pressure governor) + PGCP gas leakage pressure switch
MANUFACTURER
18
45
INSTALLER
1
2
16
78
Gas train - 6(DN65/80/100) - Gas train with valves group MBC 1900/3100/5000SE (2 valves + gas filter + pressure governor) + PGCP
gas leakage pressure switch
MANUFACTURER
19
1
2
16
45
6
INSTALLER
78
Keys
1 Burner
2 Butterfly valve
3 Gas proving system
4 Maximum gas pressure switch (option)
5 Minimum gas pressure switch
6 Gas filter
7 Bellow joint
8 Manual cutoff valve
10 VGD Valves group
16 PGCP gas leakage pressure switch
18 MBC Valves group (2” with built-in filter)
19 MBC Valves group (DN65/80/100)
14
Page 15
C.I.B. UNIGAS - M039219CA
Assembling the gas grain
To assemble the gas train, proceed as follows:
”direction” arrows for installation
1A
5
3
1E
1C
21D
1B
4
Fig. 4 - Example of gas train
To mount the gas train, proceed as follows:
1-a) in case of threaded joints: use proper seals according to the gas used;
1-b) in case of flanged joints: place a gasket (no. 1A..1E - Fig. 4) between the elements
NOTE: the bellow joint, the manual cock and the gaskets are not part of the standard supply.
Keys
1A..1EGasket
2Gas filter
3Gas valves group
4Bellow joint
5Manual cock
gas supply network
ATTENTION: once the gas train is mounted according to the diagram on Fig. 4, the gas proving test mus be performed,
according to the procedure set by the laws in force.
The procedures of installation fo the gas valves are showed in the next paragraphs, according to the gas train used:
zthreaded gas trains with Multibloc Dungs MBC..SE 1200 or Siemens VGD20..
zflanged gas trains with Multibloc Dungs MBC..SE 1900-3100-5000 or Siemens VGD40..
Siemens VGD20.. and VGD40.. gas valves - with SKP2.. (pressure governor)
Mounting
zWhen mounting the VGD.. double gas valve, two flanges are required (as for VGD20.. model, the flanges are threaded);
zto prevent cuttings from falling inside the valve, first fit the flanges to the piping and then clean the associated parts;
zinstall the valve;
zthe direction of gas flow must be in accordance with the direction of the arrow on the valve body;
zensure that the bolts on the flanges are properly tightened;
zensure that the connections with all components are tight;
zmake certain that the O-rings and gaskets between the flanges and the double gas valve are fitted.
z
Connect the reference gas pipe (TP in figure), to the gas pressure nipples placed on the gas pipe, downstream the gas valves: gas pres-
sure must be measured at a distance that must be at least 5 times the pipe size .
Leave the blowhole free (SA in figure). Should the spring fitted not permit satisfactory regulation, ask one of our service centres for a
suitable replacement.
15
Page 16
C.I.B. UNIGAS - M039219CA
WARNING: removing the four screws BS causes the device to be unserviceable!
Once the train is installed, connect electrically all its elements: gas valves group, pressure switches, gas proving system.
ATTENTION: once the gas train is mounted according to the diagram on Fig. 4, the gas proving test mus be performed,
according to the procedure set by the laws in force.
Hydraulic diagrams for light oil supplying circuits
NOTE: in plants where gravity or ring feed systems are provided, install an automatic interception device (see n. 4).
Installation diagram of light oil pipes
PLEASE READ CAREFULLY THE “WARNINGS” CHAPTER AT THE BEGINNING OF THIS MANUAL.
From tank
To tank
Fig. 14 - Double-pipe system
The burner is supplied with filter and flexible hoses, all the parts upstream the filter must be installed by the customer. As far as
the hoses connection, see the related paragraph..
Key
1Burner
2Flexible hoses (fitted)
3Light oil filter (fitted)
4Automatic interceptor (*)
5One-way valve (*)
6Gate valve
7Quick-closing gate-valve (outside the tank or boiler rooms)
(*) Only for installations with gravity, siphon or forced circulation feed systems. If the device installed
is a solenoid valve, a timer must be installed to
delay the valve closing.
The direct connection of the device without a timer
may cause pump breaks.
18
Page 19
C.I.B. UNIGAS - M039219CA
The pumps that are used can be installed both into single-pipe and double-pipe systems.
Single-pipe system: a single pipe drives the oil from the tank to the pump’s inlet. Then, from the pump, the pressurised oil is driven to
the nozzle: a part comes out from the nozzle while the othe part goes back to the pump. In this system, the by-pass pulg, if provided,
must be removed and the optional return port, on the pump’s body, must be sealed by steel plug and washer.
Double-pipe system: as for the single pipe system, a pipe that connects the tank to the pump’s inlet is used besides another pipe that
connects the pum’s return port to the tank, as well. The excess of oil goes back to the tank: this installation can be considered self-bleeding. If provided, the inside by-pass plug must be installed to avoid air and fuel passing through the pump.
Burners come out from the factory provided for double-stage systems. They can be suited for single-pipe system (recommended in the
case of gravity feed) as decribed before.To change from a 1-pipe system to a 2-pipe-system, insert the by-pass plug G (as for ccw-rotation- referring to the pump shaft).
Caution: Changing the direction of rotation, all connections on top and side are reversed.
pipeline length in meters.
Danfoss KSM..
Suntec TA
Suntec T
G
G
G
Bleed
Bleeding in two-pipe operation is automatic : it is assured by a bleed flat on the piston. In one-pipe operation, the plug of a pressure
gauge port must be loosened until the air is evacuated from the system.
About the use of fuel pumps
zMake sure that the by-pass plug is not used in a single pipe installation, because the fuel unit will not function properly and damage
to the pump and burner motor could result.
zDo not use fuel with additives to avoid the possible formation over time of compounds which may deposit between the gear teeth,
thus obstructing them.
zAfter filling the tank, wait before starting the burner. This will give any suspended impurities time to deposit on the bottom of the
tank, thus avoiding the possibility that they might be sucked into the pump.
zOn initial commissioning a "dry" operation is foreseen for a considerable length of time (for example, when there is a long suction
line to bleed). To avoid damages inject some lubrication oil into the vacuum inlet.
zCare must be taken when installing the pump not to force the pump shaft along its axis or laterally to avoid excessive wear on the
joint, noise and overloading the gears.
zPipes should not contain air pockets. Rapid attachment joint should therefore be avoided and threaded or mechanical seal junc-
tions preferred. Junction threads, elbow joints and couplings should be sealed with removable sg component. The number of junc-
tions should be kept to a minimum as they are a possible source of leakage.
zDo not use PTFE tape on the suction and return line pipes to avoid the possibility that particles enter circulation. These could depo-
sit on the pump filter or the nozzle, reducing efficiency. Always use O-Rings or mechanical seal (copper or aluminium gaskets) jun-
ctions if possible.
zAn external filter should always be installed in the suction line upstream of the fuel unit.
Light oil pumps
Suntec TA..
Oil viscosity4 - 450 cSt
Oil temperature0 - 140°C
Min. suction pressure- 0.45 barto avoid gasing
Max. suction pressure5 bar
Max. return pressure5 bar
Rotation speed3600 rpm max.
19
Page 20
C.I.B. UNIGAS - M039219CA
Danfoss KSM..
Oil viscosity2.5 ÷ 450 cSt
Oil temperature-10 ÷ 160 °C
Max. suction pressure4 bar
Min. suction pressure -0.45 bar to avoid gasing
Max. return pressure4 bar
Rotation speed3450 rpm max
Keys
1Pressure regulator
2Pressure/Vacuum gauge port to measure inlet pressure/vacuum
3Pressure gauge port
5Suction
7To the nozzle
8Return
Suntec T pump
Viscosity4 - 800 cSt
Oil temperature0 - 140 °C
Minimum suction pressure- 0.45 bar to prevent gasing
Maximum suction pressure5 bar
Rated speed3600 rpm max.
Key
1To pressure adjusting valve G3/4
2Pressure/vacuum gauge port to measure the inlet pressure/vacuum G1/4
3Pressure gauge port G1/4
4Inlet G3/4
Suntec TV Pressure governor
Pressure adjustment
Remove cap-nut 1 and the gasket 2, unscrew the lock nut 4. To increase pressure,
twist adjusting screw 3 clockwise.
To decrease the pressure, twist screw counterclockwise. Tight the lock nut 4, refit the
gasket 2 and the cap nut 1.
To connect the flexible light oil hoses to the pump, proceed as follows, according to the pump provided:
1remove the closing nuts A and R on the inlet and return connections of the pump;
2screw the rotating nut of the two flexible hoses on the pump being careful to avoid exchanging the inlet and return lines: see
the arrows marked on the pump that show the inlet and the return (see prevoius paragraph).
Suntec TA..Danfoss KSM..Suntec T
R
20
R
A
A
R
A
Page 21
C.I.B. UNIGAS - M039219CA
Electrical connections
Respect the basic safety rules. make sure of the connection to the earthing system. do not reverse the phase and
neutral connections. fit a differential thermal magnet switch adequate for connection to the mains.
ATTENTION: before executing the electrical connections, pay attention to turn the plant’s switch to OFF and be
sure that the burner’s main switch is in 0 position (OFF) too. Read carefully the chapter “WARNINGS”, and the
“Electrical connections” section.
NOTE: if the burner is provided with separate control panel, please refer to the wiring diagrams.
To execute the electrical connections, proceed as follows:
1remove the cover from the electrical board, unscrewing the fixing screws;
2 execute the electrical connections to the supply terminal board as shown in the following diagrams,
3check the direction of the fan motor (see next pargraph)
4 refit the panel cover.
WARNING: The burner is provided with an electrical bridge between terminals 6 and 7; when connecting the high/
low flame thermostat, remove this bridge before connecting the thermostat.
IMPORTANT: Connecting electrical supply wires to the burner teminal block MA, be sure that the ground wire is
longer than phase and neutral ones.
Connect the three-phase supply to terminals L1, L2, L3 and PE (ground); then shunt the phase and neutral wires (Fig. 17) for the auxiliaries on the printed circuit (N-terminal = neutral; L-terminal = phase)
Fig. 16: Power supply terminal board
Keys - Fig. 17
IG: main switch
KM1: fan motor’s contactor
M: fan motor
TV: fan motor thermal cutout
Fig. 17: Electric motor connection
21
Alimentazione ausiliari
Auxiliary relais power supply
Page 22
C.I.B. UNIGAS - M039219CA
Electrical wiring diagram for burners provided with printed circuit (standard configuration).
As far as connections, refer to the terminal block shown on Fig. 18.
Fig. 18: Terminal board for connections on printed circuit
1Connect the signal conductors from the boiler to the burner, as for the next elements (
Fig. 19 - Fig. 21)
:
ST: thermostat/pressure switch series
TAB: High/low flame thermostat
2Connect the signal conductors from the burner to the boiler, as for the next elements (
Fig. 19 - Fig. 21)
LB: Burner’s lockout signalling LED
LSPG: Gas proving system’ lockout signalling LED
3In case of modulating burners, the 5, 6 and 7 terminals, on the MA teminal block, are already connected to the regulating modula-
tor (mod. RWF40). A 4-pole plug coming out from the electrical panel is provided for the temperature and pressure probes connec-
tions (see Fig. 20).
Note: the regulating modulator is provided according to the ordered probe
Fig. 19: Progressive burners
RWF40 >>>
Fig. 21: Fully modulating burners
Fig. 20: Probes connection
22
Page 23
C.I.B. UNIGAS - M039219CA
Electrical wiring diagram for burners with no printed circuit provided
If the burner is ordered without printed circuit, follow the next connections diagrams.
Fig. 22 - Progressive burners
Fig. 24 - Fully modulating burners
Probes connection by means of the 7-pins plug (Fig. 25) see Fig. 23 for connections.
Fig. 23 - Probes connection
Fig. 25
Rotation of fan motor
Once the electrical connection of the burner is executed, remember to check the rotation of the fan motor. The motor should rotate
according to the indication on the body. In the event of wrong rotation, reverse the three-phase supply and check again the rotation of
the motor.
NOTE: (except for motors with “star-delta” start up): burners are supplied for three-phase 400V supply, and in the case of
three-phase 230V supply it is necessary to modify the electrical connections into the terminal box of the electric motor and
replace the overload tripped relay.
23
Page 24
C.I.B. UNIGAS - M039219CA
Combustion head gas pressure curves depending on the flow rate
Curves are referred to pressure= 0mbar in the combustion head!
The curves referred to the gas pressure in the combustion head, depending on the gas flow rate, are referred to the burner properly
adjusted (percentage of residual O
limits). During this stage, the combustion head, the gas butterfly valve and the servocontrol are at the maximum opening. Refer to Fig.
26, showing the correct way to measure the gas pressure, considering the values of pressure in combustion chamber, surveyed by
means of the pressure gauge or taken from the boiler’s Technical specifications.
in the flues as shown in the “Recommended combustion values” table and CO in the standard
2
1
2
4
3
Fig. 26
Key
1Generator
2Pressure outlet on the combustion chamber
3Gas pressure outlet on the butterfly valve
4Differential pressure gauge
Measuring the gas pressure in the combustion head
In order to measure the pressure in the combustion head, insert the pressure gauge probes: one into the combustion chamber’s pressure outlet (Fig. 26-2) to get the pressure in the combustion chamber and the other one into the butterfly valve’s pressure outlet of the
burner (Fig. 26-3). On the basis of the measured differential pressure, it is possible to get the maximum flow rate: in the pressure - rate
curves (showed on the next paragraph), it is easy to find out the burner’s output in Stm
measured in the combustion head (quoted on the y axis). The data obtained must be considered when adjusting the gas flow rate.
NOTE: THE PRESSURE-RATE CURVES ARE GIVEN AS INFORMATION ONLY; FOR A PROPER SETTING OF THE GAS RATE,
PLEASE REFER TO THE GAS METER READING.
3
/h (quoted on the x axis) from the pressure
24
Page 25
C.I.B. UNIGAS - M039219CA
Pressure in combustion head - gas flow rate curves
1Gas filter
2Gas proving system
3Gas valves
4Adjusting cam
5Actuator
4
5
Gas Filter
The gas filters remove the dust particles that are present in the gas, and prevent the elements at risk (e.g.: burners, counters and regulators) from becoming rapidly blocked. The filter is normally installed upstream from all the control and on-off devices.
VPS504 Gas proving system
The VPS504 check the operation of the seal of the gas shut
off valves. This check is carried out as soon as the boiler
thermostat gives a start signal to the burner, creating, by
means of the diaphragm pump inside it, a pressure in the
test space of 20 mbar higher than the supply pressure.
When wishing to monitor the test, install a pressure gauge
ranged to that of the pressure supply point PA.
If the test cycle is satisfactory, after a few seconds the consent light LC (yellow) comes on. In the opposite case the
lockout light LB (red) comes on.
To restart it is necessary to reset the appliance by pressing
the illuminated pushbutton LB.
PA
Fig. 28
LC
LB
Actuators
Two actuator models can be provided:
zBerger STM30.. (see page 28) or
zSiemens SQL33.. (see page 29).
26
Page 27
C.I.B. UNIGAS - M039219CA
Air and gas flow rate adjustements
ATTENTION: before starting the burner up, be sure that the manual cutoff valves are open and check that the
pressure upstream the gas train complies the value quoted on paragraph “Technical specifications”. Be
sure that the mains switch is closed.
ATTENTION: During commissioning operations, do not let the burner operate with insufficient air flow (danger of formation of carbon monoxide); if this should happen, make the gas decrease slowly until the normal
combustion values are achieved.
WARNING: never loose the sealed screws! otherwise, the device warranty will be immediately invalidate!
IMPORTANT! the combustion air excess must be adjusted according to the in the following chart:
Recommended combustion parameters
Fuel
Recommended (%) CO
Recommended (%) O2
2
Natural gas9 ÷ 10 3 ÷ 4.8
Light oil 11.5 ÷ 13 2.9 ÷ 4.9
During the factory test, the gas butterfly valve, air damper in low flame and actuator are set to average values.
Adjustments - brief description
Adjust the air and gas flow rates at the maximum output (“high flame”) first, by means of the air damper and the adjusting cam respectively.
zCheck that the combustion parameters are in the suggested limits.
zCheck the flow rate measuring it on the counter or, if it was not possible, verifying the combustion head pressure by means of a dif-
ferential pressure gauge, as described on par. “Measuring the gas pressure in the combustion head” on page 24.
zThen, adjust the combustion values corresponding to the points between maximum and minimum: set the shape of the adjusting
cam foil. The adjusting cam sets the air/gas ratio in those points, regulating the opening-closing of the throttle gas valve.
zSet, now, the low flame output, acting on the low flame microswitch of the actuator in order to avoid the low flame output increasing
too much or that the flues temperature gets too low to cause condensation in the chimney.
To change the burner setting during the testing in the plant, follows the next procedure, according to the servocontrol model provided
(mod. Berger STM30.. or mod. Siemens SQL..).
Adjusting procedure
If the burner is provided with the DUNGS MBC..SE gas valves group, set the pressure regulator to 1/3 of its stroke, using a 2.5 allen
key.
Now, adjust the burner according to the actuator model provided.
The burner is factory-set wih the adjusting plate holes fully open, and the combustion head at its MAX position, so it is fit to work at the
maximum output.
To adjust the gas flow, partially close the holes, as follows:
1loosen the three V screws that fix the adjusting plate D;
2insert a screwdriver on the adjusting plate notches and let it move CW/CCW as to open/close the holes;
3once the adjustmet is performed, fasten the V screws.
CAUTION: perform these adjustments once the burner is turned off and cooled.
Pressure setting
27
Page 28
z
HTP91A - HTP92A - HTP93A
C.I.B. UNIGAS - M039219CA
V
open holes
D
zHTP512A - HTP515A - HTP520A - HTP525A
V
open holes
D
Now, adjust the burner according to the actuator model provided.
Settings by means of Berger STM30.. actuator
1set GAS fuel by means of the burner CM switch (it is placed on the burner control panel)
closed holes
closed holes
STM30.. actuator cams
MAN-AUTO
IHigh flame
IIStand-by and Ignition
IIILow flame
2check the fan motor rotation (see “Rotation of fan motor” on page 23).
3Before starting the burner up, drive the high flame actuator microswitch matching the low flame one (in order to let the burner ope-
rates at the lowest output) to safely achieve the high flame stage.
4Start the burner up by means of the thermostat series and wait until the pre-purge time comes to an end and that the burner starts
up;
5drive the burner to high flame stage, by means fo the thermostat TAB.
6Then move progressively the microswitch to higher values until it reaches the high flame position; always check the combustion
values and eventually adjusting the gas by means of the valves group stabiliser.
7Go on adjusting air and gas flow rates: check, continuosly, the flue gas analisys, as to avoid combustion with little air; dose the air
according to the gas flow rate change following the steps quoted below;
8acting on the pressure stabiliser of the valves group, adjust the gas flow rate in the high flame stage as to meet the values
requested by the boiler/utilisation:
- Siemens VGD valves group: remove cap T and act on the VR adjusting screw to increase or decrease the pressure and conse-
quently the gas rate; screwind VR the rate increases, unscrewing it decreases (see next figure).
- Dungs MBC..SE valves group: act on its pressure governor to increase or decrease the pressure and consequently the gas
9To adjust the air flow rate in the high flame stage, loose the RA nut and screw VRA as to get the desired air flow rate: moving
the rod TR towards the air damper shaft, the air damper opens and consequently the air flow rate increases, moving it far from the
shaft the air damper closes and the air flow rate decreases.
28
Page 29
C.I.B. UNIGAS - M039219CA
Note: once the procedure is perfomed, be sure that the blocking nut RA is fasten. Do not change the position of the air damper
rods.
TR
VRA
RA
10 the air and gas rate are now adjusted at the maximum power stage, go on with the point to point adjustement on the SV adjusting
cam as to reach the minimum output point.
11 as for the point-to-point regulation, move the gas low flame microswitch (cam III) a little lower than the maximum position (90°);
12 Set the TAB thermostat to the minimum in order that the actuator moves progressively towards the low flame position;
13 move cam III to the minimum to move the actuator towards the low flame until the two bearings find the adjusting screw that refers
to the lower position: screw V to increase the rate, unscrew to decrease.
14 Move again cam III towards the minimum to meet the next screw on the adjusting cam and repeat the previous step; go on this way
as to reach the desired low flame point.
15 If it is necessary to change the burner output in the low flame stage, move cam III: the low flame position must never match the
ignition position, that is why cam III must be set 20°-30° more than cam II.
16 Now adjust the pressure switches (see next par.).
Keys
GV gas valves group
ID1 air damper index
ID2 index
PA air pressure switch
SC actuator
SV adjusting cam
V adjusting screws
VF butterfly valve
SC
PA
ID1
SV
VF
GV
SV
V
ID2
Gas butterfly valve closedGas butterfly valve open
.Adjustment by the Siemens SQL33.. actuator
1set GAS fuel by means of the burner CM switch (it is placed on the burner control panel);
2check the fan motor rotation (see “Rotation of fan motor” on page 23).
3Start the burner up by means of the thermostat series and wait until the pre-purge time comes to an end and that the burner starts
up;
4the burner starts up with the actuator on the ignition position, set it to the MAN (manual mode), by the MAN/AUTO selector (ignition
position= read on the air damper index ID1 - see picture on previous page);
5disconnect the TAB thermostat removing the wire from the terminal no. 6 or by setting MAN on the RWF40 modulatore or by set-
ting 0 by means of the CMF switch (only for fully-modulating burners);
6set the actuator on the manual mode (MAN) by means of the MAN/AUTO switch (see next pictures).
7manually drive the adjusting cam SV to the high flame position and set the actuator to the AUTO mode (by the related switch - see
picture) to lock the adjusting cam.
AUTO
SQL330.. actuator cams
BF = Low flame
MAN
BF
G
B = plastic cam
G = cam locking lever
B
8Go on adjusting air and gas flow rates: check, continuosly, the flue gas analisys, as to avoid combustion with little air; dose the air
according to the gas flow rate change following the steps quoted below;
9acting on the pressure stabiliser of the valves group, adjust the gas flow rate in the high flame stage as to meet the values
requested by the boiler/utilisation:
- Siemens VGD valves group: remove cap T and act on the VR adjusting screw to increase or decrease the pressure and conse-
quently the gas rate; screwind VR the rate increases, unscrewing it decreases (see next figure).
29
Page 30
C.I.B. UNIGAS - M039219CA
- Dungs MBC..SE valves group: act on its pressure governor to increase or decrease the pressure and consequently the gas
rate.:
10 To adjust the air flow rate in the high flame stage, loose the RA nut and screw VRA as to get the desired air flow rate: moving
the rod TR towards the air damper shaft, the air damper opens and consequently the air flow rate increases, moving it far from the
shaft the air damper closes and the air flow rate decreases.
Note: once the procedure is perfomed, be sure that the blocking nut RA is fasten. Do not change the position of the air damper
rods.
TR
VRA
RA
11 the air and gas rate are now adjusted at the maximum output, go on with the point to point adjustment on the SV adjusting cam as
to reach the minimum output point: gradually move the adjusting cam in order to adjust each of the V screws as to set the cam foil
shape as described on the next steps:
12 to change the SV position set the actuator on the manual mode (MAN), turn the adjusting cam SV and set again the actuator to the
AUTO mode to lock the adjusting cam;
SV
V
SC
SV
VF
PA
ID1
GV
13 act on the V screw that mathces the bearings referring to the adjusting cam position;
14 to adjust the next screw, set again the actuator mode to MAN, turn the adjusting cam and set the actuator to AUTO mode to lock
the adjusting cam on the next screw; adjust it and go on this way to adjust all the screws in order to set the cam foil shape, accor-
ding to the combustion values read.
15 Once the cam foil shape is defined, reconnect the TAB thermostat reconnecting the wire to the terminal no.6 or setting the RWF40
burner modulator to AUTO or the CMF switch to 3 (only for fully-modulating burner).
16 Turn the burner off, then start it up again.
17 Once the pre-purge time comes to end, drive the burner to the high flame stage by the TAB thermostat and check the combustion
values;
18 drive the burner to low flame, if necessary adjust the low flame size (ouput) by inserting a screwdriver on the slot F to move the BF
cam.
ID2
Keys
GV gas valves group
ID1 air damper index
ID2 index
PA air pressure switch
SC actuator
SV adjusting cam
V adjusting screws
VF butterfly valve
BF
F
19 The low flame position must never match the ignition position that is why cam BF must be set 20°- 30° more than the ignition posi-
tion (see ID1 index on previous pictures).
20 Now adjust the pressure switches (see next paragraph).
Fully modulating burners
To adjust the fully-modulating burners, use the CMF switch on the burner control panel (see next picture), instead of the TAB thermostat as described on the previous paragraphs about the progressive burners. Go on adjusting the burner as described before, paying
attention to use the CMF switch intead of TAB.
The CMF position sets the oprating stages: to drive the burner to the high-flame stage, set CMF=1; to drive it to the low-flame stage, set
CMF=2. To move the adjusting cam set CMF=1 or 2 and then CMF=0.
CMF = 0 stop at the current position
CMF = 1 high flame operation
CMF = 2 low flame operation
CMF = 3 automatic operation
30
Page 31
C.I.B. UNIGAS - M039219CA
Calibration of air and gas pressure switches
The air pressure switch locks the control box if the air pressure is not the one requested. If it
happens, unlock the burner by means of the control box unlock pushbutton, placed on the
VR
burner control panel.
The gas pressure switches check the pressure to avoid the burner operate when the pres-
sure value is not in the requested pressure range.
Calibration of air pressure switch
To calibrate the air pressure switch, proceed as follows:
zRemove the transparent plastic cap.
zOnce air and gas setting have been accomplished, startup the burner.
zDuring the pre-purge phase o the operation, turn slowly the adjusting ring nut VR in the clockwise direction until the burner lockout,
then read the value on the pressure switch scale and set it to a value reduced by 15%.
zRepeat the ignition cycle of the burner and check it runs properly.
zRefit the transparent plastic cover on the pressure switch.
Calibration of low gas pressure switch
As for the gas pressure switch calibration, proceed as follows:
zBe sure that the filter is clean.
zRemove the transparent plastic cap.
zWhile the burner is operating at the maximum output, test the gas pressure on the pressure port of the minimum gas pressure
switch.
zSlowly close the manual cutoff valve (placed upstream the pressure switch, see gas train installation diagram), until the detected
pressure is reduced by 50%. Pay attention that the CO value in the flue gas does not increase: if the CO values are higher than the
limits laid down by law, slowly open the cutoff valve as to get values lower than these limits.
zCheck that the burner is operating correctly.
zClockwise turn the pressure switch adjusting ring nut (as to increase the pressure value) until the burner stops.
zSlowly fully open the manual cutoff valve.
zRefit the transparent plastic cover on the pressure switch.
Adjusting the high gas pressure switch (when provided)
To calibrate the high pressure switch, proceed as follows:
1remove the plastic cover;
2measure the gas pressure in the network, when flame is off;
3by means of the adjusting ring nut VR, set the value read on step 2, increased by the 30%;
4replace the plastic cover.
PGCP Gas leakage pressure switch (witn SiemensLDU/Siemens LMV burner control)
zremove the pressure switch plastic cover;
zadjust the PGCP pressure switch to the same value set for the minimum gas pressure switch;
zreplace the plastic cover.
31
Page 32
C.I.B. UNIGAS - M039219CA
Adjusting light oil flow rate
The light oil flow rate can be adjusted choosing a by-pass nozzle that suits the boiler/utilisation output and setting the delivery and
return pressure values according to the ones quoted on the chart below and the diagram on Fig. 29-Fig. 30 (as far as reading the pres-
sure values, see next paragraphs).
NOZZLE
PRESSURE
bar
BERGONZO A32011 ÷ 136 (recommended)
FLUIDICS WR225
DELIVERY
RETURN
PRESSURE MAX.
bar
20
RETURN
PRESSURE MIN.
bar
7 (recommended)
Fig. 29
Example (Bergonzo): if a 220kg/h flow rate BERGONZO nozzle is provided, set the return pressure at 11bar, supply at 20bar on the
delivery to get a 220kg/h flow rate. If the return pressure needed is 5bar, instead, act on the V adjusting screw on the pressure gover-
nor (see chapter on page 32). The flow rate will then be about 95kg/h (see the example showed on the Bergonzo diagram-Fig. 29).
32
Page 33
FLOW RATE kg/h
DIMENSIONSMinMax
401340
501650
602060
702370
802680
903090
10033100
11538115
13043130
14548145
16053160
18059180
20066200
22574225
25082250
27591275
30099300
330109330
360119360
400132400
450148450
500165500
550181550
600198600
650214650
700231700
750250750
800267800
C.I.B. UNIGAS - M039219CA
Fig. 30
Example (Fluidics): as for over 100kg/h nozzles, the 80% of the nozzle flow rate can be obtained with a return pressure at about 18bar
(see Fig. 30).
Oil Flow Rate Settings by means of Berger STM30.. actuator
1Once the air and gas flow rates are adjusted, turn the burner off, switch it on again by turning the CM switch to the oil operation
(OIL, on the burner control panel).
2with the electrical panel open, prime the oil pump acting directly on the related CP contactor (see next picture): check the pump
motor rotation and keep pressing for some seconds until the oil circuit is charged;
CP
3bleed the air from the M pressure gauge port (Fig. 31) by loosing the cap without removing it, then release the contactor.
Suntec TA..Danfoss KSM..Suntec T..
M
VR
M
M
VR
VR
Fig. 31
4Before starting the burner up, drive the high flame actuator microswitch matching the low flame one (in order to let the burner ope-
rates at the lowest output) to achieve safely the high flame stage .
33
Page 34
C.I.B. UNIGAS - M039219CA
5record the high flame value set during the gas operation adjustments (see previous paragraphs);
6start the burner up by means of the thermostat series and wait until the pre-purge time comes to an end and that the bruner starts
up;
7drive the burner to high flame stage, by means fo the thermostat TAB.
8Then move progressively the microswitch to higher values until it reaches the high flame position; always check the combustion
values and eventually adjusting the oil pressure (see next step).
9the nozzle suplly pressureis already factory-set and must not be changed. Only if necessary, adjust the supply pressure as follows
(see related paragraph);insert a pressure gauge into the port shown on Fig. 32 and act on on the pump adjusting screw VR (see
Fig. 31 and page 20) as to get the nozzle pressure at 20 bar or 25bar (according to the nozzle model provided: Bergonzo or Flui-
dics nozzles - see page 32-33).
Pressure gauge port
PG
RP
V2
SV2
Fig. 32Fig. 33
10 in order to get the maximum oil flow rate, adjust the pressure (reading its value on the PG pressure gauge) without changing the air flow
rate set during the gas operation adjustments (see previous paragraph): checking always the combustion parameters, the adjustment is to
SV2
be performed by means of the
adjusting cam screw (see picture) when the cam has reached the high flame position.
11 as for the point-to-point regulation in order to set the cam foil shape, move the oil low flame microswitch (cam V) a little lower than
the maximum position (90°);
12 set the TAB thermostat to the minimum in order that the actuator moves progressively towards the low flame position;
13 move cam V(low flame) towards the minimum to move the actuator towards the low flame until the two bearings find the adjusting
screw that refers to a lower position: screw V2 to increase the rate, unscrew to decrease, in order to get the pressure as showed
on chart/diagram on “Adjusting light oil flow rate” on page 32, according to the requested rate.
14
Move again cam V towards the minimum to meet the next screw on the adjusting cam and repeat the previous step; go on this way
as to reach the desired low flame point.
15 The low flame position must never match the ignition position that is why cam V must be set 20°- 30° more than the ignition posi-
tion.
Turn the burner off; then start it up again. If the adjustment is not correct, repeat the previous steps.
Adjustment by the Siemens SQL33.. actuator
1Once the air and gas flow rates are adjusted, turn the burner off, switch the CM switch to the heavy oil operation (OIL, on the bur-
ner control panel (see page 37).
2with the electrical panel open, prime the oil pump acting directly on the related CP contactor (see next picture): check the pump
motor rotation and keep pressing for some seconds until the oil circuit is charged;
CP
3bleed the air from the M pressure gauge port (Fig. 31) by loosing the cap without removing it, then release the contactor.
4record the high flame value set during the gas operation adjustments (see prevoius paragraphs);
5Start the burner up by means of the thermostat series and wait unitl the pre-purge phase comes to end and that burner starts up;
6the burner starts up with the actuator on the ignition position, set it to the MAN (manual mode), by the MAN/AUTO selector (ignition
position= read on the air damper index ID1);
7disconnect the TAB thermostat removing the wire from the terminal no. 6 or by setting MAN on the RWF40 modulatore or by set-
ting 0 by means of the CMF switch (only for fully-modulating burners);
34
Page 35
C.I.B. UNIGAS - M039219CA
8manually drive the adjusting cam SV2 to the high flame position and set the actuator to the AUTO mode (by the related switch - see
picture) to lock the adjusting cam.
AUTO
MAN
AB
B
AB = High flame
BF1 = Low flame (gas)
G
BF2 = Low flame (oil)
B = plastic clamp
G = cam locking lever
SQL33.. actuator cams
AB
BF1
BF2
The nozzle supply pressureis already factory-set and must not be changed. Only if necessary, adjust the supply pressure as follows
(see related paragraph);insert a pressure gauge into the port shown on Fig. 34 and act on on the pump adjusting screw VR (see Fig.
31 and page 20) as to get the nozzle pressure at 20 bar or 25bar (according to the nozzle model provided: Bergonzo or Fluidics nozzles - see page 32-33).
Pressure gauge port
RP
PG
V2
SV2
Fig. 34Fig. 35
9in order to get the maximum oil flow rate, adjust the pressure (reading its value on the PG pressure gauge) without changing the air
flow rate set during the gas operation adjustments (see prevoius paragraph): checking always the combustion parameters, the
adjustment is to be performed by means of the SV2 adjusting cam screw (see picture) when the cam has reached the high flame
position.
10 once the air and oil flow rate have been adjusted at the maximum output, go on with the point to point adjustment on the SV2 adju-
sting cam as to reach the minimum output point: gradually move the adjusting cam in order to adjust each of the V2 screws as to
describe the cam foil shape.
11 to change the SV2 position set the actuator on the manual mode (MAN), turn the adjusting cam SV2 and set again the actuator to
the AUTO mode to lock the adjusting cam;
12 act on the V2 screw that mathces the bearings referring to the adjusting cam position;
13 to adjust the next screw, set again the actuator mode to MAN, turn the adjusting cam and set the actuator to AUTO mode to lock
the adjusting cam on the next screw; adjust it and go on this way to adjust all the screws in order to set the cam foil shape, accor-
ding to the combustion values read.
14 Once the cam foil shape is defined, reconnect the TAB thermostat reconnecting the wire to the terminal no.6 or setting the RWF40
burner modulator to AUTO or the CMF switch to 3 (only for fully-modulating burner).
15 Turn the burner off then start it up again.
16 Once the pre-purge time comes to end, drive the burner to the high flame stage by the TAB thermostat: check the combustion
values;
17 drive the burner to low flame, if necessary adjust the low flame size (output) by inserting a screwdriver on the slot F to move the
BF2 cam.
BF2
F
35
Page 36
C.I.B. UNIGAS - M039219CA
18 The low flame position must never match the ignition position that is why cam
BF2
must be set 20°- 30° more than the ignition position.
19 Turn the burner off; then start it up again. If the adjustment is not correct, repeat the previous steps.
As far as fully-modulating burners, see paragraph on page 30.
Light oil circuit
The fuel is pushed into the pump 1 to the nozzle 3 at the delivery pressure set by the pressure governor. The solenoid valve 2 set the
fuel immission into the combustion chamber. The part of fuel that is not burnt goes back to the tank through the return circuit. The fuel
amount to be burnt is adjusted by means of the burner actuator according to the adjustments set (see prevoius paragraph).
THE BURNER IS AN APPLIANCE DESIGNED AND CONSTRUCTED TO OPERATE ONLY AFTER BEING CORRECTLY CONNECTED TO A HEAT GENERATOR (E.G. BOILER, HOT AIR GENERATOR, FURNACE, ETC.), ANY OTHER USE IS TO BE CONSIDERED IMPROPER AND THEREFORE DANGEROUS.
THE USER MUST GUARANTEE THE CORRECT FITTING OF THE APPLIANCE, ENTRUSTING THE INSTALLATION OF IT TO
QUALIFIED PERSONNEL AND HAVING THE FIRST COMMISSIONING OF IT CARRIED OUT BY A SERVICE CENTRE AUTHORISED BY THE COMPANY MANUFACTURING THE BURNER.
A FUNDAMENTAL FACTOR IN THIS RESPECT IS THE ELECTRICAL CONNECTION TO THE GENERATOR’S CONTROL AND
SAFETY UNITS (CONTROL THERMOSTAT, SAFETY, ETC.) WHICH GUARANTEES CORRECT AND SAFE FUNCTIONING OF
THE BURNER.
THEREFORE, ANY OPERATION OF THE APPLIANCE MUST BE PREVENTED WHICH DEPARTS FROM THE INSTALLATION
OPERATIONS OR WHICH HAPPENS AFTER TOTAL OR PARTIAL TAMPERING WITH THESE (E.G. DISCONNECTION, EVEN
PARTIAL, OF THE ELECTRICAL LEADS, OPENING THE GENERATOR DOOR, DISMANTLING OF PART OF THE BURNER).
NEVER OPEN OR DISMANTLE ANY COMPONENT OF THE MACHINE.
OPERATE ONLY THE MAIN SWITCH, WHICH THROUGH ITS EASY ACCESSIBILITY AND RAPIDITY OF OPERATION ALSO
FUNCTIONS AS AN EMERGENCY SWITCH, AND ON THE RESET BUTTON.
IN THE EVENT OF REPEATED LOCKOUTS, DO NOT PERSIST WITH THE RESET BUTTON AND CONTACT QUALIFIED PERSONNEL WHO WILL PROCEED TO ELIMINATE THE MALFUNCTION.
WARNING: DURING NORMAL OPERATION THE PARTS OF THE BURNER NEAREST TO THE GENERATOR (COUPLING
FLANGE) CAN BECOME VERY HOT, AVOID TOUCHING THEM SO AS NOT TO GET BURNT.
OPERATION
ATTENTION: before starting the burner up, be sure that the manual cutoff valves are open and check that the
pressure upstream the gas train complies the value quoted on paragraph “Technical specifications”. Read carefully the “WARNINGS” chapter in this manual.
zChoose the typer of fuel by turning the A switch, on the burner control panel.
CAUTION: if the fuel chosen is light oil, be sure the cutoff valves on the feed and return pipes are open.
zCheck the control box is not locked (signalling light O, on); if so, reset it by means of the pushbutton C.
zCheck the series of thermostats and pressure switches turn the burner to on.
Gas operation
zCheck the gas feeding pressure is sufficient (signalling lamp G on).
z the gas proving system test begins; when the test is performed the proving system LED turns on. At the end of the test, the burner
staring cycle begins: in case of leakage in a valve, the gas proving system stops the burner and the lamp E turns on. Reset it, by
means of the reset pushbutton on the device, in burners with VPS504 (pushbutton LB in picture), or by the D pushbutton on the
burner panel if this one is fitted with LDU11 proving system.
LC
LB
VPS504
NOTE: if the burner is fitted with Dungs VPS504, the pre-purgue phase starts once the gas proving system is successfully performed.
Since the pre-purgue phase must be carried out with the maximum air rate, the control box drives the actuator opening and when the
maximum opening position is achieved, the pre-purge time counting starts.
zAt the end of the pre-purge time, the actuator drives the complete closing (ignition with gas position) and, as this is achieved the
ignition transformer is energised (LED L is on); the gas valves open.
zFew seconds after the valves opening, the transformer is de-energised and lamp L turns off.
37
Page 38
C.I.B. UNIGAS - M039219CA
z
The burner is now operating, meanwhile the actuator goes to the high flame position and, after some seconds, the two-stage operation begins; the burner is driven automatically to high flame or low flame, according to the plant requirements.
Operation in high or low flame is signalled by lamp N on the frontal panel.
Light oil operation
zThe fan motor starts and the pre-purge phase as well. Since the pre-purge phase must be carried out at the maximum air rate, the
control box drives the actuator opening and when the maximum opening position is reached, the pre-purge time counting starts.
zAt the end of the pre-purge time, the actuator is in the light oil ignition position: the ignition transformer is energised (lamp L on); the
light oil valves open. Few seconds after the valves opening, the transformer is de-energised and lamp L turns off.
zThe burner is now operating, meanwhile the actuator goes to the high flame position; after some seconds, the two-stage operation
begins; the burner is driven automatically to high flame or low flame, according to the plant requirements.
Operation in high or low flame is signalled by LED N on the burner control panel.
38
Page 39
C.I.B. UNIGAS - M039219CA
PART III: MAINTENANCE
At least once a year carry out the maintenance operations listed below. In the case of seasonal servicing, it is recommended to carry
out the maintenance at the end of each heating season; in the case of continuous operation the maintenance is carried out every 6
months.
WARNING: ALL OPERATIONS ON THE BURNER MUST BE CARRIED OUT WITH THE MAINS DISCONNECTED AND
THE FUEL MANAUL CUTOFF VALVES CLOSED!
ATTENTION: READ CAREFULLY THE “WARNINGS” CHAPTER AT THE BEGINNIG OF THIS MANUAL.
ROUTINE MAINTENANCE
zCheck and clean the gas filter cartridge, if necessary replace it (see next paragraghs);
zCheck and clean the fuel filter cartdrige, replace if necessary.
zCheck and clean the filter inside the light oil pump: filter must be thoroughly cleaned at least once in a season to ensure correct
working of the fuel unit. To remove the filter, unscrew the four screws on the cover. When reassemble, make sure that the filter is
mounted with the feet toward the pump body. If the gasket between cover and pump housing should be damaged, it must be replaced. An external filter should always be installed in the suction line upstream of the fuel unit.
zCheck the fuel hoses for possible leaks.
zRemove, check and clean the combustion head (see page 40);
zCheck ignition electrodes, clean, adjust and, if necessary, replace them (see page 41);
zCheck and carefully clean the UV detector, replace it if necessary; if in doubt, check the detection current, once the burner starts up
(see on page 41).
zRemove and clean the fuel nozzle (Important: cleaning must be performed using solvent, not metal tools!). At the end of
maintenance operations after the burner reassembly, light the flame and check its shape, replacing the nozzle whenever a questionable flame shape appears. Whenever the burner is used intensely, we recommend preventively replacing the nozzle at the start of
each heating season.
zClean and grease sliding and rotating parts.
ATTENTION: when servicing, if it was necessary to disassemble the gas train parts, remember to execute the gas proving
test, once the gas train is reassembled, according to the procedure imposed by the law in force.
Light oil filter maintenance
For correct and proper servicing, proceed as follows:
1cutoff the required pipe section;
2unscrew the filter cup;
3remove the filtering cartridge, wash it with gasoline; if necessary, replace it; check the tightening
O-rings and replace them if necessary;
4replace the cup and restore the pipe line.
Gas filter maintenance
ATTENTION: Before opening the filter, close the manual cutoff valve downstream the filter and bleed the gas; check that
inside the filter there is no pressurised gas.
To clean or remove the filter, proceed as follows:
1remove the cap unscrewing the fixing screws (A);
2remove the filtering cartridge (B), clean it using water and soap, blow it with compressed air(or replace it, if necessary)
3replace the cartridge in its proper position taking care to place it inbetween the guides as not to hamper the cap replacement;
4be sure to replace the Or ring into its place (C) and replace the cover fastening by the proper screws (A).
A
B
39
C
Page 40
C.I.B. UNIGAS - M039219CA
Inspection and replacement of theMULTIBLOC DUNGS MBC..SE filter (Threaded valves group)
Inspect the filter at least once a year.
zChange the filter, if pressure value between pressure connections 1 and 2 is grea-
ther than 10 mbar.
zChange the filter, if pressure value between pressure connections 1 and 2 is twice
as high compared to the last inspection.
1. Interrupt gas supply: close ball valve
2. Remove screws 1-2
3. Replace the filter insert 3
4. Screw in screws 1-2 without use force to fasten.
Fig. 40
5. Perform leakage and funcion test.
Space requirements for fitting filter, A: from 150 to 230 mm.
Removing the combustion head
1Remove the top H.
2Remove the UV detector out of its housing: disconnect electrode cables and the light oil flexible hoses.
3Loosen the screws V holding the gas manifold G, loosen the two connectors E and remove the assembly as shown.
4Clean the combustion head by means of a vacuum cleaner; scrape off the scale by means of a metallic brush.
Note: to replace the combustion head, reverse the operations described above.
V
H
G
E
G
V
Removing the oil gun, replacing the nozzle and the electrodes
ATTENTION: avoid the electrodes to get in touch with metallic parts (blast tube, head, etc.), otherwise the boiler operation
would be compromised. Check the electrodes position after any intervention on the combustion head.
To remove the oil gun, proceed as follows:
1remove the combustion head as described on the prevoius paragraph;
2loosen the VL screw and remove the oil gun and the electrodes: check the oil gun, replace it if necessary;
3after removing the oil gun, unscrew the nozzle and replace it if necessary;
4in order to replace the electrodes, unscrew the VE fixing screws and remove them: place the new electrodes being careful to
observe the measures showed on pag.: reassemlbe following the reversed procedure.
Caution: adjust the nozzle position according to the air pipe, by means of the VU screw, ance the VL screw is fastened.
VU
VE
VL
40
Page 41
C.I.B. UNIGAS - M039219CA
Adjusting the electrodes position
Adjust the electrodes position, according to the quotes shown on the next picture.
TA
U
TG
E
Keys
Eelectrodes
TAair pipe
TGignition gas pipe
Unozzle
Fig. 41
Replacing the spring in the gas valve group
To replace the spring in the gas valve group,proceed as follows:
1Carefully twist the protection cap 1 and the O-ring 2.
2remove the “set value” spring 3 from housing 4.
3Replace spring 3.
4Carefully insert the new “set value” spring. Pay attention to mount properly. First insert the spring part with smaller diameter in the
housing.
5Place O-ring 2 in protective cap 1. Screw in the protective cap with the O-ring in it.
6Stick the adhesive label for spring identification on the type plate.
3
4
3
2
1
4
1
DUNGS MBC..SESKP Siemens actuator
Cleaning and replacing the detection photocell
The photocell working life is about 10000 working hours (about 1 year), at max 50°C after
which it must be replaced.
To clean/replace the detection photocell, proceed as follows:
1Disconnect the system from the electrical power supply.
2Shut off the fuel supply;
3remove the photocell from its slot (see next figure);
4clean the bulbe if dirty, taking care not to touch it with bare hands;
5if necessary, replace the bulb;
6replace the photocell into its slot.
1
41
Page 42
C.I.B. UNIGAS - M039219CA
Checking the detection current
To check the detection signal follow the scheme in Fig. 42 or Fig. 43. If the signal is less than the value indicated, check the position of
the detection electrode or detector, the electrical contacts and, if necessary, replace the electrode or the detector.
TERMINAL BOARD MC
µA DC
Fig. 42: Detection by electrode
27
Fig. 43: Detection by photocell QRA..
TERMINAL BOARD
Check of the detection current (with printed circuit)
To check the detection signal remove the bridge on “TEST ER” or “TEST UV”
and connect a micro ammeter when Fig. 44. If the signal is less than the
value indicated, check the position of the detection electrode or detector, the
electrical contacts (one ER terminal for the electrode, two FC terminals for the
UV probe - see pictureon the side) and, if necessary, replace the electrode or
the UV detector.
Control box
Siemens LFL1.3..
Siemens LFL1.3..
Minimum detection
signal
6µA (with electrode)
70µA (with UV detector)
ER
+ µA -
electrode
Control box
Siemens
LFL1.3..
Siemens
LFL1.3..
Fig. 44
- µA +
UV detector
Minimum detection
signal
6µA (with electrode)
70µA (with UV
detector)
FC
Seasonal stop
To stop the burner in the seasonal stop, proceed as follows:
1turn the burner’s main switch to 0 (Off position)
2disconnect the power mains
3close the fuel cock of the supply line
Burner disposal
In case of disposal, follow the instructions according to the laws in force in your country about the “Disposal of materials”.
42
Page 43
TROUBLESHOOTING
CAUSE
MAIN SWITCH OPEN
LACK OF GAS
MAXIMUM GAS PRESSURE SWITCH DEFECTIVE
THERMOSTATS/PRESSURE SWITCHES DEFECTIVES
OVERLOAD TRIPPED INTERVENTION
AUXILIARIES FUSE INTERRUPTED
DEFECTIVE CONTROL BOX
DEFECTIVE ACTUATOR
AIR PRESSURE SWITCH FAULT OR BAD SETTING
MINIMUM GAS PRESSURE SWIT C H D EFE CT I VE OR GAS
FILTER DIRTY
43
IGNITION TRANSFORMER FAULT
IGNITION ELECTRODES BAD POSITION
BUTTERFLY VALVE BAD SETTING
DEFECTIVE GAS GOVERNOR
GAS VALVE DEFECTIVE
BAD CONNECTION OR DEFECTIVE HIGH/LOW FLAME
THERMOSTAT OR PRESSURE SWITCH
ACTUATOR CAM WRONG SETTING
UV PROBE DIRTY OR DEFECTIVE
TROUBLE
THE BURNER
DOESN’TSTART
CONTINUE WITH PRE-
PURGE
DOESN’T START AND LOCK-
OUT
DOESN’T START AND
REPEATS THE CYCLE
STARTS AND REPEATS THE
CYCLE
STARTS AND LOCK-OUT
THE FLAME MONITOR
DEVICE DOESN’T
GIVECONSENT TO START
DOESEN’T SWITCH TO HIGH
FLAME
DOESEN’T RETURN IN LOW
FLAME
LOCK-OUT DURING
OPERATION
TTURNS OF AND REPEATS
CYCLE DURING OPERATION
z
zz
zz
zzz
z
z
zzzzz
zzz
C.I.B. UNIGAS - M039219CA
zzzz
zzzzz
z
z
zz
zzzz
z
zz
zzz
zzz
Page 44
C.I.B. UNIGAS - M039219CA
SPARE PARTS
DesriptionCode
HTP90AHTP91AHTP92AHTP93A
CONTROL BOX
IGNITION ELECTRODE2080292208029220802922080292
OIL FILTER 2090018209001820900182090018
GAS FILTER - Rp 22090019209001920901192090119
GAS FILTER - DN652090117209011720901172090117
GAS FILTER - DN802090117209011220901122090112
GAS FILTER - DN1002090112209011320901132090113
GASKET2110048211004821100482110048
AIR PRESSURE SWITCH2160065216006521600652160065
GAS PRESSURE SWITCH- DUNGS GW50 A52160076216007621600762160076
GAS PRESSURE SWITCH- DUNGS GW150 A52160077216007721600772160077
GAS PRESSURE SWITCH- DUNGS GW500 A62160087216008721600872160087
GAS PRESSURE SWITCH- DUNGS GW500 A52160089216008921600892160089
GAS PRESSURE SWITCH- ANTUNES DMG05021600A221600A221600A221600A2
GAS PRESSURE SWITCH- ANTUNES DMG15021600A321600A321600A321600A3
GAS PRESSURE SWITCH- ANTUNES DMG50021600A421600A421600A421600A4
GAS PRESSURE SWITCH- ANTUNES FCG50021600A721600A721600A721600A7
IGNITION TRANSFORMER
PUMP MOTOR
GAS VALVE GROUP - Rp2” - Siemens VGD20..2190171219017121901712190171
GAS VALVE GROUP - DN65 - Siemens VGD40..2190172219017221901722190172
GAS VALVE GROUP - DN80 - Siemens VGD40..2190169219016921901692190169
GAS VALVE GROUP - DN100 - Siemens VGD40..
GAS VALVE ACTUATOR SKP15
GAS VALVE ACTUATOR SKP25
GAS VALVE GROUP - Rp2” - Dungs MBC1200SE21903M521903M521903M521903M5
GAS VALVE GROUP - DN65 - Dungs MBC1900SE21903M621903M621903M621903M6
GAS VALVE GROUP - DN80 - Dungs MBC3100SE21903M721903M721903M721903M7
GAS VALVE GROUP - DN100 - Dungs MBC5000SE
GAS PROVING SYSTEM
GAS PROVING SYSTEM
CONTROL BOX2020448202044820204482020448
IGNITION ELECTRODE2080292208029220802922080292
OIL FILTER 2090018209001820900182090018
GAS FILTER - Rp 22090119209011920901192090119
GAS FILTER - DN652090117209011720901172090117
GAS FILTER - DN802090112209011220901122090112
GAS FILTER - DN1002090113209011320901132090113
GASKET2110047211004721100472110047
AIR PRESSURE SWITCH2160065216006521600652160065
GAS PRESSURE SWITCH- DUNGS GW50 A52160076216007621600762160076
GAS PRESSURE SWITCH- DUNGS GW150 A52160077216007721600772160077
GAS PRESSURE SWITCH- DUNGS GW500 A62160087216008721600872160087
GAS PRESSURE SWITCH- DUNGS GW500 A52160089216008921600892160089
GAS PRESSURE SWITCH- ANTUNES DMG05021600A221600A221600A221600A2
GAS PRESSURE SWITCH- ANTUNES DMG15021600A321600A321600A321600A3
GAS PRESSURE SWITCH- ANTUNES DMG50021600A421600A421600A421600A4
GAS PRESSURE SWITCH- ANTUNES FCG50021600A721600A721600A721600A7
IGNITION TRANSFORMER
PUMP MOTOR
2170302217030221703022170302
2180202218022321802232180219
GAS VALVE GROUP - Rp2” - Siemens VGD20..2190171219017121901712190171
GAS VALVE GROUP - DN65 - Siemens VGD40..2190172219017221901722190172
GAS VALVE GROUP - DN80 - Siemens VGD40..2190169219016921901692190169
GAS VALVE GROUP - DN100 - Siemens VGD40..
GAS VALVE ACTUATOR SKP15
GAS VALVE ACTUATOR SKP25
2190174219017421901742190174
2190181219018121901812190181
2190183219018321901832190183
GAS VALVE GROUP - Rp2” - Dungs MBC1200SE21903M521903M521903M521903M5
GAS VALVE GROUP - DN65 - Dungs MBC1900SE21903M621903M621903M621903M6
GAS VALVE GROUP - DN80 - Dungs MBC3100SE21903M721903M721903M721903M7
GAS VALVE GROUP - DN100 - Dungs MBC5000SE
OIL SOLENOID VALVE
GAS PROVING SYSTEM
Automatic programme in the event of interruption and indication of position when interrupted
By default, in the event of any kind of interruption, the flow of fuel is immediately interrupted. At the same time the programmer stops and this indicates the position at the time of the interruption.
A symbol on the indicator disc shows each time the type of stoppage:
No start-up (for example fault in the CLOSED signal for the
limit contact "Z" at terminal 8 or some other contact between
the terminals 12 and 4 or 4 and 5 is not closed).
Start-up suspended because of a fault in the OPEN signal
for the limit contact "A" at terminal 8.
P
Block due to absence of air pressure signal. From this
moment onwards any absence of air pressure will cause a
block.
Block due to malfunction of the flame detector circuit.
Start-up interrupted because there is a fault in the MINMUM
signal for the auxiliary contact of the damper servo motor at
terminal 8.
1
Block due to absence of flame signal at the end of the 1st
safety period.
From this moment onwards any absence of a flame signal will cause a
block.
2
Blockdue to absence of flame signal at the end of the 2nd
safety period (flame signal of main burner).
Blockdue to absence of flame signal or air pressure during
operation.
Where a block stoppage occurs at any moment between switch on and
pre-ignition without registering any symbol, the cause is normally an
unscheduled flame signal.
a-bStart-up programme
b-b' For time variants:move the programmer on to the automatic stop
after the burner starts up (b' = position of the programmer during normal
burner operation).
b(b')-aPost-ventilation programme after a regulation stop.At the start-up
position "a" the programmer stops automatically.
.Safety time duration for mono-tube burners
..Safety time duration for twin-tube burners
The apparatus can be reset immediately after a block. After resetting (and
after the elimination of any problem causing the stoppage or after a power
failure) the programmer returns to its start-up position. In this event only
the terminals 7, 9, 10 and 11 are live in accordance with the monitoring
programme. Only after this the device programs a new startup.
Operation
The wiring system and also the control system of the programmer "P"
have already been given in this manual. The response signals required
for the active parts and the flame monitor circuit are shown by a hatching.
In the absence of these response signals the mechanism interrupts the
start-up programme; the exact time of the interruption can be identified
from the visual indicator and will cause a block if the safety code requires
it.
A consent to start-up by means of the thermostat or pressostat "R"
A-B start-up program
B-C normal burner operation
C regulation stop caused by "R"
C-D programmer returns to start-up position A.
During the regulation stop only terminals 11 and 12 are live and the dam-
per, through the limit contact "Z" of its servo-motor is in the CLOSED position.The flame detector circuit F is activated (terminals 22 and 23 or 23/4)
for the detector test and the paracitic light test.
Where the burners do not have dampers (or have an independent 00
damper control mechanism) there must be a bridge between terminals 6
and 8, otherwise the mechanism will not start up the burner.
For a burner to start up the following conditions must be met:
z Mechanism not blocked/reset.
z Damper closed.Limit contact switchZ must be in the CLOSED position
and allow current to flow between terminals 11 and 8.
z Any contacts checking that the fuel valve (bv...) is closed, or other con-
tacts with similar functions, must be closed between terminal 12 and
the air pressostat LP.
z The contact for the air pressostat LP must be in the off position (LP
test) so as to feed terminal 4.
z The gas pressostat contacts GP and the safety thermostat and pres-
sostat contacts W must also be closed.
Start-up program
A Start-up
(R closes the start-up control ring between terminals 4 and 5)
The programmer starts up.At the same time the ventilator motor is fed
through terminal 6 ( only for pre-ventilation) and, after t7, the ventilator
motor or the combustion gas exhaust fan is fed through terminal 7 (preventilation and post-ventilation).
At the end of t16, the command opening the damper passes through terminal 9; during the damper opening time the programmer does not move
since terminal 8, through which the programmer is fed, is dead.
Only once the damper is fully open and the limit contact switch A has
switched on, feeding terminal 8, does the programme proceed.
t1Pre-ventilation time with damper fully open (nominal air flow).
Shortly after the beginning of the pre-ventilation time, the air pressostat
should switch off the current between terminals 4 and 13;otherwisethe
apparatus would block (air pressure monitor).
At the same time the terminal 14 should be live since current feeding the
ignition transformer and the fuel valves passes through this circuit.
During pre-ventilation time the flame detector circuit is checked and in the
event of an operational defect the monitor brings about a block.
At the end of the pre-ventilation time the monitor automatically moves the
damper servo-motor, through terminal 10, to the flame ignition position
which is governed by the auxiliary contact "M".
During this period the programmer stops until terminal 8, is again activatedthrough contact "M".
After a few seconds the little programmer motor is directly fed by the
active part of the apparatus.
After this point terminal 8 plays no further part in the burner ignition process.
Mono-tube burner
t3Pre-ignition time waiting the response from the fuel valve at terminal 18.
t2Safety time (start up flame strenght); at the end of the safety time a
flame signal should appear at terminal 22 of the amplifier and it should
stay on until a regulation stop; if this does not happen the mechanism will
block.
t4 Interval; at the end of t4, terminal 19 is live.
t5Interval At the end of t5 terminal 20 is live.At the same time the
monitor outlets from 9 and 11 and terminal 8 into the active part of the
apparatus are kept galvanically separatedso as to protect the monitor
itself from recovery voltage through the capacity regulator circuit.
Twin-tube burners (**)
t3 Preignition time until the all clear to the pilot burner valve at
terminal 17.
t2 First safety time (pilot flame strenght); at the end of the safety time
a flame signal should appear at terminal 22 of the amplifier and it should
stay on, until a regulation stop; if it does not, the apparatus will block.
t4 Interval until the consent to the fuel valve at terminal 19, for the first
flame of the main burner.
Page 58
t9 2nd safety time; at the end of the second safety time the main burner should be lit by means of the pilot. At the end of this period, terminal
17 is dead and therefore the pilot burner will be out.
t5 Interval; at the end of t5 terminal 20 is live. At the same time the
monitor outlets from 9 to 11 and the terminal 8at the input of the active
part of the apparatus are galvanically separated so as to protect the apparatus itself from recovery voltage through the strenght regulator circuit.
When the strenght regulator LR at terminal 20 gives the consent,
the start-up programme for the apparatus comes to an end. Depending on
time variants, the programmer stops either immediately or at the end of a
set time, without effecting the position of the contacts.
BOperational position of the burner
B-C Burner operation (production of heat)
While the burner is working the strnght regulator controls the damper,
according to the demand for heat, by means of the positioning at nominal
load of the auxiliary contact "V" of the damper servocontrol.
CRegulation stop for operation of "R"
When there is a regulation stop the fuel valves immediately close. At the
same time the programmer starts to programme:
t6 Post-ventilation time (post-ventilation with the ventilator "G" at ter-
minal 7).Shortly after beginning of the post-ventilation time terminal 10
becomes live and moves the damper to the "MIN" position. The full closure of the damper only happens towards the end of the post-ventilation
time and is prompted by an automatic signal from terminal 11
t13Admissible post-ignition time
During this time the flame monitor circuit may still receive a flame signal
without the apparatus blocking.
D-A End of automatic programme
At the end of t6, at the point where the programmer and the automatic
contacts have reverted to the starter position, the detection probe test
restarts.
During an operational stop even an unscheduled flame signal lasting a
few seconds can cause a block because during this period an NTC in the
circuit acts as retarder.This means that brief unscheduled influences cannot cause a block.
(**) Times t3, t2 and t4 only apply only to safety devices in the series 01.
Specifications
Mains voltage 220V -15%...240V +10%
Frequency50Hz -6%...60Hz +6%
Absorbed capacity3.5 VA
Built-in fuseT6.3/250E slow action DIN41571 No.
451915070
External fusemax. 16A
Interference N-VDE0875
Flow permitted at terminal 1 5A (DIN 0660 AC3)
Flow permitted at control terminals
4A (DIN 0660 AC3)
Flow at monitor contacts:
input at terminals 4 & 5 1A, 250V
input at terminals 4 & 111A, 250V
input at terminals 4 & 14function of the load at terminals 16 and
19, min.1A, 250V
EmplacementAny
Protection IP40
Permitted ambient temp-20...+60° C
Min.temperature (trans/storage) -50° C
Weight:
apparatusapprox. 1,000g.
baseapprox. 165g.
Ionisation monitor
voltage in detector electrode
normal working330V ±10%
test380V ±10%
short circuit currentmax. 0,5 mA
Ionisation current, min.request 6 µA
max. permitted length for connecting cables
normal cable (laid separately**) 80m
armoured cable(high frequency) protection at terminal 22
140m
UV monitor
Voltage in UV detector
normal working330V ±10%
test380V ±10%
Detector current, min. request* 70µA
Max. detector current
normal working630 µA
test1300 µA
Max.length of connecting cable
normal cable (laid separately**) 100m
armoured cable (high frequency) protected at terminal 22
200m
Weight
QRA260 g
QRA10450 g.
*Connect up in parallel to the measuring device a condenser 100µF,
10...25V.
** The wire connecting up the detector electrode should not be in the
same sleeve as the other conductor wires.
Ignition spark monitor with QRE1 series 02 detector
Minimum detector current 30µA
Operating times
t7 initial delay for ventilator G2 2
t16 initial delay of air damper OPEN consent4
t11 opening time for damperany
t10 initial delay for air pressure monitor8
t1 pre-ventilation time with damper open36
t12 travel time for air damper to MIN positionany
t3 t3' pre-ignition timet34
t3't2 t2' safety time (1st safety time for burners with intermittent pilot
lightert22
t2't4 t4' interval between start of t2 and response to valve at terminal 19
t410
t4't9 2nd safety time for burners with intermittent pilot lighter 2
t5 interval between end of t4 and response at terminal 20 10
t20 interval before programmer cuts out after start-upduration of start-up60
t6 post-ventilation time (G2 only) 12
t13 permitted post-ignition time12
t16 initial delay from opening consent of the air damper
t20 interval until the automatic shut-off of the programming mechanism
after the burner start
Key
Alimit contact switch for damper OPEN position
AIblock remote signal
ARmain relay (working network) with contacts "ar"
ASMonitor fuse
BRblock relay with "br" contacts
BVfuel valve
EKreset button
FEdetector electrode of ionisation circuit
FRflame relay with "fr" contacts
Gventilator motor or burner motor
GPgas pressure switch
Hmain interruptor switch
Lblock stoppage LED
LKair damper
LPair pressostat
LRsafety regulator
Mauxiliary contact switch for damper "MIN" position
QRA UV detector
QRE ignition spark detector
Rthermostat or pressostat
Sfuse
SAdamper servo-motor
SMsynchronous programmer motor
Vflame signal amplifier
Vin case of servo-motor: auxiliary contact for response to fuel
valve with regard of damper position
Wsafety pressostat or thermostat
Zignition transformer
Zin case of servomotor: end of limit contact switch for damper
CLOSED position
ZBV pilot burner fuel valve
°for mono-tube burners
°°for twin-tube burners
Page 59
(1)input for raising QRA detector voltage to test level
(2)input for excitation of flame relay during flame detector test
circuit (contact XIV) and during safety time (contact IV)
(3)Do not press EK for more than 10 seconds
Programmer diagram
t1pre-ventilation time
t2safety time
*t2'1st safety time
t3pre-ignition time
*t3'pre-ignition time
t4interval for creating current between terminals 18 and 19
*t4'interval for creating current between terminals 17 and 19
t5interval for creating current between terminals 19 and 20
t6post-ventilation time
t7interval between startup consent and current created at
terminal 7
t8duration of start-up
*t92nd safety time
t10interval before air pressure monitoring begins
t11damper opening travel time
t12damper closure travel time
t13permissible post-combustion time
t16initial delay of damper OPEN response
t20interval before programmer automatically stops
* These times are valid with the use of a series 01 safety device for moni-
toring burners with intermittent pilot lighter.
Page 60
C.I.B. UNIGAS S.p.A.
Via L.Galvani, 9 - 35011 Campodarsego (PD) - ITALY