The actual balancing of any indoor unit is preset by the dials
in the control valves on every warm and cold valve kit. See
controls document and technical sheet for settings.
It is advised to install ball valves and water flow measuring
valves at main sections on both flow and the return pipes
in order to shut off sections of the hydraulic system for later
changes of the system and local repairs and verifying correct
water flow.
Once the proper system operation is established, the definite appropriate operating conditions such as flow rates and
pressure drops should be recorded for future reference.
During commissioning, poor operating conditions may
exist due to incorrect system pressures, resulting in noticeable water noise or undesired valve operation or lack of
flow. Once the total system is correct, these conditions will
not exist on properly designed systems. If any noticeable
water noise or undesired valve operation persist, recheck
the system for air that may not have been properly vented
during start-up.
8.4 Air balancing
In particular if the unit is connected to external grilles, TripleAqua strongly recommend to install the original 3PL and
3PD plenum boxes. Plenums can be installed on the suction
and on the discharge side. Please take good notice not to
exceed the maximum external pressure drops as is indicated
in the technical specs and the fan graphs.
If plenum boxes are used, TripleAqua strongly recommend
to use all round spigots. If some spigots are blocked, proper
operation and performance cannot be guaranteed.
Especially if the external duct runs are unequal, additional air
dampers should be considered at the shortest duct runs.
Suggested external nominal external pressure is 30-50 Pa.
8.5 Equipment start-up checklist
Receiving and inspection
• Unit plenums, controllers and structural support
is complete and correct
• Unit received undamaged (e.g., dents and paint)
• Goods have been received complete as ordered
• Unit arrangement, models, options and handing
is correct
Handling and installation
• All electrical service is provided according to the
regulations
• Mounting grommets/isolators are used if critical
installation applies.
• Unit mounted level and square (condensate drainage)
• All screws are checked
• Good access is provided for unit and accessories
• A proper condensate trap avoiding odours
• Suitable overcurrent external fuse protection is provided
• Proper service switch// power plug or means to
disconnect is provided
• Proper piping of cold and warm and return piping to unit
• All services to unit in code compliance
• Unit protected from dirt and other objects
Cooling/heating connections
• Protect cold valve package components against
condensation
• Both valve packages are in good order and shape
• Connect field piping to unit
• Pressure test unit piping for leaks
• Pressure test field piping for leaks
• Install drain lines and traps, as required
• Insulate cold piping, as required and warm piping
as preferred
Ductwork connections
• Flexible duct connections at unit as smooth as possible
• Ducting is not bended obstructing proper air flow
• Proper supply and return grille type and size
• Control fresh outside air for freeze protection
avoiding frost on the coil
• Insulate all supply ductwork
• Adjust max fan speed setting as required during
air system balancing
Unit start-up
• Flush water systems
• Vent water systems
• All isolation valves are open
• Check for water leaks
• Vent air from coil if needed
• All unit panels and filters in place
• Check ductwork and units for air leaks
• Balance air systems if required
• Record final settings for future reference
• Check ductwork and piping for any vibration
• Check dampers for proper operation
• Verify proper cooling operation
• Verify proper heating operation
• Test the condensate line by adding water into
the drain tray
• Set unit to desired position for operation
8 Commisioning
40