Aztec Classic Electric Boilers
17
11. Servicing Instructions
To ensure reliable operation of your Aztec electric boiler, it is
recommended that you have your boiler serviced once a year.
The person(s), who services or carries out any remedial work, i.e.
electrical fault finding, must have suitable engineering
qualifications.
Isolate the mains supply before carrying out any service work.
1. Check all electrical connections on PCB and electric
elements to ensure they are secure and clean.
2. Check electrical insulation on wiring.
3. Ensure all air grilles are clean and free from obstructions.
4. Inspects seals around elements and also the heat
exchanger top and bottom flanges.
12. Parts Replacement
11.1 Casing Removal
IMPORTANT
Isolate the mains electrical supply to the boiler before carrying out
any maintenance work.
1. Isolate electrical supply to the boiler.
2. Remove 4 fixing screws securing front casing in position.
3. Slide top casing upwards this will allow front casing to slide
forward.
IMPORTANT: All electrical connections should be checked. Loose
connections can cause problems.
This boiler is fitted with a manual reset high limit thermostat. Before
replacing any part, ensure that the thermostat does not require resetting.
11.2 PCB Assembly Replacement
1. Ensure electrical supply is isolated to the boiler.
2. Remove the 4 fixing screws and washers (2 at top and 2 at
bottom), lift up the top-plate and carefully slide off the front
casing panel.
3. Disconnect the pump + call plug, the thermistor plug and the
high limit stat plug.
4. Disconnect all element cables apart from the rear element. N.B.
Take note of wiring arrangement before disconnecting.
5. Now remove the grey pipe insulation, it is now possible to
disconnect the remaining element.
6. With all elements disconnected, again taking note of wiring
arrangement, carefully disconnect and remove the element
cables from the PCB.
7. IMPORTANT: Care MUST be taken when handling the PCB.
8. For ease of access disconnect from the main terminal block
both the red + black cables and also the power input cables,
leaving the earth cable connected.
9. Free both the pump and call terminal blocks by removing the
terminal block fixing screws.
10. Finally remove the 4 fixing screws holding the PCB to the
bracket.
11.3 High Limit Thermostat Replacement
1. Ensure electrical supply is isolated to the boiler.
2. The high limit thermostat can be found fixed to top front
face of boiler.
3. Remove 2 terminal connectors from high limit thermostat,
loosen retaining straps and slide thermostat out from
behind.
4. IMPORTANT: When replacing the thermostat ensure a
heat sink compound is used between back of thermostat
and face of the boiler (See Fig. 21 for positioning).
5. Inspect retaining straps and replace where necessary.
11.4 Thermostat Replacement
1. Isolate the electrical supply to the boiler.
2. Thermistor is located fixed to the top front of the boiler
above the high limit thermostat.
3. Disconnect from the PCB and slide out from behind the
retaining strap.
4. IMPORTANT: When replacing the thermistor ensure a heat
sink compound is used between the thermistor and boiler
body (See Fig 21 for positioning).
5. Inspect retaining strap and replace where the necessary.
6. When replacing the front casing, ensure the thermostat
control shaft passes through the hole in the front control
panel.