Thomas & Betts 164FT Installation Manual

Page 1
IS---0376
IS---164FT
January 2010
Page 1 of 3
Installation & Operating Instructions
164FT
FEED--THRU/GROUNDING DEVICE
CONTENTS: Feed--thru Body Complete with Mounting Hardware, Lubricant, Operating Instructions.
before operating connectors.
The feed--thru can be used for the following functions: A) A junction point, B) A grounding point. To use the feed--thru as a junction point, follow steps 1 to 7. To use the feed--thru as a grounding point, follow steps 1 to 5 and 8 to 9. A yellow band provides indication of full elbow seating. This product is identified by a yellow ID washer attached to the eyebolt.
DANGER
All apparatus must be de--energized during installation or removal of part(s) except for test point caps and indicators that can be installed and operated energized.
After installation loadbreak products can be operated energized per operating instructions. All deadbreak connectors must be de--energized before operating.
All apparatus must be installed and operated in accordance with individual user, local, and national work rules. These instructions do not attempt to provide for every possible contingency.
Do not touch or move energized products.
“Loadbreak connectors must be operated with a full insulated “hotstick” type live -- line tool.” Consult the company’s safe work practices for the required live--line tool length.
FOR MORE INFORMATION ON PARTS, INSTALLATION RATINGS AND COMPATIBILITY, CALL THE NEAREST ELASTIMOLD OFFICE.
Excess distortion of the assembled product may result in its failure.
Inspect parts for damage, rating and compatibility with mating parts.
This product should be installed only by competent personnel trained in good safety practices involving high voltage electrical equipment. These instructions are not intended as a substitute for adequate training or experience in such safety practices.
Failure to follow these instructions will result in damage to the product and serious or fatal injury.
If this product is supplied with a protective shipping cover(s), remove this shipping cover(s) and replace with the appropriate HV insulated cap(s) or connector(s) before submerging or energizing the circuit.
IMPORTANT
1. Check contents of package to ensure they are complete and undamaged.
2. Check all components to ensure proper fit with cable and/or mating products.
STEP 1
Grounding -- Insert ground lead into the grounding lug provided on themounting hardware and tighten lug. Ground lead should be No. 14 copper wire or equivalent. Connect the opposite end of the lead to ground, leaving enough slack to operate with a hotstick.
Yellow ID Washer
Ground Lug
No. 14 Copper Wire
To Ground
3. Read entire installation instructions before starting.
4. Have all required tools at hand and maintain cleanliness throughout the procedure.
STEP 2
Remove the protective caps from the bushings of the feed--thru. PROTECTIVE CAPS MUST NOT BE ON THE BUSHINGS OF THE FEED--THRU WHEN THE FEED--THRU IS BEING USED. When the feed--thru is not in use, the protective caps should be placed on the bushings of the feed--thru to protect them from dirt and other contaminants. Clean the bushing surfaces and lubricate them with the lubricant supplied. DO NOT SUBSTITUTE. Other lubricants may be harmful to this product and its mating product(s).
Clean & Lubricate
IS---0376 IS---164FT
January 2010 Printed in U.S.A.
Clean & Lubricate
8155 T&B Boulevard, Memphis, Tennessee 38125 (800) 888-- 0211 Fax: (800) 888--0690
Page 2
IS---0376
January 2010 Page 2 of 3
STEP 3
Attach feed--thru eye firmly to hotstick.
Eye
Hotstick
Using a hotstick, slide feed--thru onto parking stand. Unlock hotstick and back off, to allow space for eyebolt to be tightened. Tighten eyebolt by rotating hotstick clockwise until snug. DO NOT OVERTIGHTEN. Release hotstick.
Eye
Hotstick
Parking
Strand
To Ground
SIDE VIEWFRONT VIEW
Parking
Stand
STEP 4
STEP 5
Remove one loadbreak elbow from its apparatus loadbreak bushing following the applicable loadbreak operating instructions (IS--165/166LR). Using a hotstick, firmly attached to the elbow, insert the probe tip into one feed--thru until the first slight resistance is felt. Immediately push the elbow home with a fast, firm straight motion which will engage the internal lock on the mating interfaces.
Hotstick
Elbow
FOR JUNCTION POINT APPLICATION FOLLOW STEPS 6 AND 7
STEP 6
Remove second loadbreak elbow, following the applicable loadbreak operating instructions (IS--165/166LR). Using a hotstick, firmly attachedto the elbow, insert the probe tip into the remaining feed--thru until the first slight resistance is felt. Immediately push the elbow home with a fast, firm straight motion which will engage the internal lock on the mating interfaces.
Page 3
IS---0376
1.2
.
January 2010
Page 3 of 3
STEP 7
When it is desired to re--connect the elbow(s) to the apparatus bushing(s), first make certain no faults exist on the system. To return the loadbreak elbow to the apparatus bushing, reverse the operational sequence, following the applicable loadbreak--loadmake operating instructions.
FOR GROUNDING POINT APPLICATION FOLLOW STEPS 8 TO 9
IMPORTANT: Do not insert grounding elbow into Feed--Thru unless circuit has been tested “De--Energized”.
STEP 8
Ensure that the system is de--energized with either of the following procedures.
1. Check the capacitive test point on the loadbreak elbow for voltage, with an appropriate voltage detection device.
CAUTION: The voltage test point is a capacitance device; it is notdirectly connected to the conductor. It requires the
use of specially designed instruments. Do not use conventional voltage measuring requirements; NO INDICATION WILL BE OBTAINED.
2. Remove existing elbow or insulated cap from the bushing with a hotstick following the applicable loadbreak operating instructions (IS--165/166LR, IS--273/274LR or IS--375/376LR). Firmly tighten a hotstick to the 370TR test rod operating eye. Insert the test rod into the bushing. Using a meter capable of direct reading the system voltage, check the test rod disc for voltage. Remove test rod.
IMPORTANT: If voltage is indicated by either of the two preceding procedures, do not proceed without De--energizing
the system.
IMPORTANT: The hotstick eye and disc of the test rod are not insulated; be careful to keep them clear from ground until
tested ”de--energized”.
Operating
Eye
Hotstick
Test Rod
Test
Point
STEP 9
Install ground elbow into the second plug of the feed--thru, following the grounding elbow operating instructions (IS--160/370GLR).
Disc
370TR
Test Rod
STEP 10
Complete assembly of an insulatedcap or elbow isindicated by no portion of the yellow band being visible when viewed from the side