Congratulations on the purchase of your boiler. Here at Thermo-Dynamics Boiler Com-
pany we pride ourselves on the design and construction of our product. Our intent is to furnish
you with a high quality appliance that will provide you and your family with years of trouble
free service.
In order to maintain peak performance of your boiler, it is recommended that the burn-
er/boiler be serviced annually, preferably prior to the onset of the winter heating season.
Servicing of your appliance must be performed by a qualified heating technician. You should
utilize a qualified heating technician familiar with your installation to manage your boiler and
perform periodic maintenance. Proper care and maintenance of your boiler will allow you to
enjoy the benefits of your new purchase as well as extend its long useful life.
In the event that your serviceman encounters difficulty with the boiler, he/she shall con-
tact the distributor from which the product was purchased. The distributor shall, in turn, contact
the Thermo-Dynamics sales representative for your area. By adhering to this protocol, Thermo-
Dynamics wishes to provide you with responsive and unparalleled service. We realize the
importance that our product means to you and your family and our goal is to get your boiler up
and running as quickly as possible.
Thank you for purchasing the Thermo-Dynamics boiler. Again, it is our intent to provide
you with a high quality trouble free product that will be part of your family for many years to
come. Please consider Thermo-Dynamics Boiler Company in the future for all of your home
heating needs.
TDX Series
Boiler Installation and Operating Manual
Contents
SubjectPage
Read This First2
Specifications4
Installation4
Operational Sequence7
Start-Up8
Appendices
Troubleshooting GuideA14
DimensionsB16
Piping DiagramsC17
Wiring DiagramsD18
Installer/Serviceman LabelsE20
Burner Service Set Up Records22
Installation and Service Check ListBack Cover
Read This First
1. Installer must be a trained, experienced technician and should read all instructions before installation.
2. Inspect the boiler, jacket and all components to be sure damage has not occurred
in shipment. If damage is evident a claim must be filed with the freight carrier who
transported the boiler from the factory to the distributor where it was purchased.
Do not install the boiler. Contact your distributor.
3. Disconnect power supply before connecting wiring.
4. Refer to local codes for oil burning equipment, for recommended installation practice. You will need to be familiar with NFPA International Standard 31, “Standard
for the Installation of Oil Burning Equipment”.
5. A complete heat loss calculation is necessary to choose the proper size unit to
install. The boiler should be sized to within 25% of the actual heat loss of the
structure. Over sizing will result in short cycling and inefficient operation.
6. When moving the boiler, do not push against the jacket or burner. Damage will
result.
7. If the boiler is vented to a chimney, be certain the chimney is clean and free of
obstructions. The chimney must be masonry with tile lining or metal insulated
with a stainless steel surface. The Chimney must be properly sized. Draft
requirements are essential for safe and proper operation of the boiler.
8. If the boiler is connected to a venting device, make sure that it is listed by a
recognized testing service. Follow the venting device manufacturer’s installation
instructions. Verify that the venting device installation complies with the recommendations of the manufacturer and local and state codes.
9. Conduct a thorough checkout when installation is complete. Check for indications
of leaks and make sure that no material is left adjacent to the boiler.
10. The use of low sulfur No. 2 heating oil is highly recommended.
11.The following definitions apply to potential hazards noted in this manual.
3
DANGER: Indicates a hazardous situation which if not avoided will result in death
or serious injury.
WARNING: Indicates a hazardous situation which if not avoided could result in
death or serious injury.
CAUTION: Indicates a hazardous situation which if not avoided, may result in a
minor injury. It may also warn against unsafe practices that may result in minor
njury or damage to equipment.
NOTICE: Indicates that special attention to information is required. Not related
to personal injury or property damage.
12. Modifications, substitutions or removal of equipment supplied or specified may
result in property damage, personal injury or loss of life.
1) Place the boiler on a level floor, preferably raised and as close to the chimney as possible.
Refer to the installers label to determine if the boiler may be installed on combustible flooring or
if non-combustible flooring is required. The minimum clearances for installation are shown
below. Reduced clearance installations must follow NFPA-31 guidelines. If the boiler is a Knock
Down (not packaged for ease of installation), install the jacket in accordance with the directions
provided in the jacket package, prior to piping.
Standard Clearances
Front24”
Sides6”
Rear12”
Top18”
Chimney Connector18”
Floor Non-Combustible
2) Install the boiler piping. For location of piping refer to the Installation Drawing.
DANGER: Boilers with tankless coils must be piped in accordance with the piping diagram
including installation of a tempering or mixing valve. Domestic hot water temperatures exceeding 125°F will cause severe burns instantly or death by scalding.
WARNING: Relief valve discharges and drain valve piping must be piped to a safe place of
discharge.
NOTICE: TDX Series Boilers are provided with a built-in air scoop feature. This feature allows
quiet, air free operation of the hot water system by eliminating air pockets without installation of
air scoops. The supply line tapping in the top of the boiler extends approximately 1 inch below
the top of the boiler, allowing only air-free water to enter the heating system supply. Any air
trapped in the top of the boiler is purged through the 3/4” vent tapping. The 3/4" vent tapping
should be connected to an automatic float vent, a manual vent or piped to a conventional
expansion tank.
5
3) Packaged boilers are shipped with the burner, aquastat and circulator installed and wired
at the factory. See the Basic Wiring Diagram for wiring schematic. See component manufacturer’s manual for wiring instructions.
4) An expansion tank, not provided, must be matched to the system and installed in accordance with the manufacturer’s instructions. Do not undersize the expansion tank. An
automatic feed and pressure reducing valve, not provided, should be installed in the
water inlet line to keep the entire system from falling below the pressure setting of the
valve ( about 12 psi) See the feed valve suppliers instructions for maximum allowed
water supply pressure and requirements for pressure reducers. For piping and wiring of
other system components see the manufacturer’s installation manuals.
5 The tank-less water heater may be piped as shown in the Installation Drawing. A mixing
valve (tempering valve), not supplied, must be used to reduce the water temperature at
kitchen or bathroom taps. High temperature water for a dishwasher may be obtained by
piping as shown in the Installation Drawing. The nuts that secure the tank-less coil
flange should be tightened before the boiler is filled with water, after initial firing and once
a year during the annual maintenance.
CAUTION: Deterioration due to coil gasket leaks will void the warranty.
6) a. Chimney Vent Aplications. Connect boiler flue outlet to chimney using galvanized
smoke pipe. The flue pipe should be pitched upward at least 1/4” per foot of run. Refer
to the boiler specifications for proper size flue pipe for your model boiler. Use only
elbows and straight sections. Tees may be used in a straight section in conjunction with
a barometric draft regulator however they must not be used for a 90° turn. Each joint
should be securely fastened with sheet metal screws. The flue pipe must not be inserted
beyond the inside wall of the chimney. Install barometric draft regulator in the horizontal
or vertical section of the flue pipe. The draft regulator should be installed in accordance
with the manufacturer’s instructions. Set the draft to in the stack as specified in the boiler
specifications and on the Installer/Serviceman Label on the boiler jacket. The flue gas exit
of the venting system should be at designed with clearances in accordance with NFPA
31. A chimney must be at least 3 feet above the highest point where it passes through
the roof and at least 2 feet higher than any portion of a building within 10 feet of the venting system. The horizontal length of a chimney connector should not exceed 10 feet
unless a draft booster is used. Where the possibility of down drafts exist, install a listed
vent cap.
b. Direct Vent Applications. Follow the instructions provided with the Double Wall Direct
Vent Kit for installation, operation and maintenance.
CAUTION: External vent surfaces are hot.
NOTICE: Use only the venting system components supplied with the kit.
NOTICE: Surface discoloration of the building may occur due to improper burner/boiler
adjustmet. Thermo-Dynamics will not accept any liability for such discoloration.
7) The boiler room must be well ventilated to allow sufficient make-up air to support combustion. Lack of adequate combustion air may result in erratic operation of the burner,
noisy combustion or fuel odors. Remember your need for outside air will be greatly
6
increased if you have a vented dryer in the basement or other venting fans in the home.
Boilers located in confined spaces shall be provided with two permanent openings, one
near the top and one near the bottom of the enclosure. Each opening shall have a free
area of not less than one square inch per 1000 BTU per hour input rating of the boiler,
freely communicating with interior areas having adequate infiltration from the outside.
8) Fill boiler and system with water. Be sure entire system has been purged of air and the
desired pressure is obtained. Leak-check the boiler and piping system by turning off the
make-up water supply and observing the boiler pressure gage. A loss of pressure indicates a system leak that must be repaired prior to operating the boiler.
9) Remove the nozzle line assembly and check that the correct nozzle is installed for the
desired firing rate. Check that burner settings are correct for the nozzle that is installed.
See the Installer/Serviceman Label.
10) Connect burner to fuel supply. Refer to fuel unit manufacturer literature for piping, connections, lift and tank installation. If such information is unavailable use the following guide lines.
FUEL UNITS/FUEL LINES
Fuel supply “level with” or “above” burner: A single stage fuel unit connected to the fuel
supply with a single supply line is the most common type of installation for these conditions.
Manual venting of the fuel unit is usually required on initial start-up. Failure to vent air could
result in an air lock/oil starvation condition. (One pipe)
Fuel supply below the level of burner:
Use a single stage fuel unit in lift conditions of up to
10 ft., and a two stage fuel unit when the lift exceeds 10 ft. Both conditions require the use of
a return line which purges the fuel unit of air returning it to the fuel tank. The “by-pass” plug
must be inserted into the fuel unit when installing a return line. (Two pipe)
Fuel line installation:
Continuous lengths of heavy wall copper tubing are recommended
and should be installed under the floor when possible. Always use flare fittings. Always install
fittings in accessible locations. Never use teflon tape on any fuel fitting. Use of teflon will void
any warranty. Fuel lines should not run against the appliance or the ceiling joists.
Fuel line valve and filter:
Install two high quality shutoff valves in accessible locations on
the oil supply line. Locate one close to the tank and the other close to the burner ahead of the
filter. Some filters come with built-in shutoff valves. Install a generous capacity filter inside the
building between the fuel tank shutoff valve and the burner locating both the filter and the
valve close to the burner for ease of servicing.
CAUTION: All oil feed lines to burners must be air tight. Use only flare fittings when assembling oil lines since the slightest air leak, caused by loose fittings, bad gaskets or any other
reason, can cause a foaming oil stream which will cause any of the following conditions:
a) Intermittent firing, causing safety shutdown
b) Poor starts
c) Smokey starts
d) Continual sooting of boiler and burner parts including the cad cell
e) Reduced firing rate, inefficient operation and erratic fire pattern
f) A dangerous combustion condition, allowing the firebox to fill with a lean mixture (too
much air in the oil stream) which could cause a delay in ignition of the fuel mixture until
the danger point has been reached.
7
Suction Vacuum Test. A fuel pump suction vacuum test should be performed. See the fuel
pump manufacturers literature for details. The suction vacuum must be limited to ensure that
there is adequate pump lift. This problem becomes proportionately larger with underground
tanks. If the following procedures are followed, burner related problems will be minimized:
a) Connect vacuum gauge to fuel pump. Suction vacuum must not exceed 10 inches of mer-
cury for single stage pumps and 15 inches for two stage pumps. It is preferable to stay
below these limitations.
b) When the suction line is tight and properly installed the pump will hold its vacuum for a
minimum of 60 minutes after shutdown.
c) Installation of a check valve in the suction line of a two pipe system is advisable under all
circumstances. Be sure the check valve fittings are airtight.
11) Connect the electric supply to the boiler as indicated on the wiring diagram. The wiring
must be instal
led in accordance with the National Electrical Code and any other state and
local codes and the following requirements.
a) Internal wiring is completed at the factory on packaged boilers. External wiring must
conform with the National Electric Code and local codes.
b) Field connections should be protected with a 15 amp fuse.
c) A separate, fused disconnect switch should be installed and located near the unit so
that power can be shut-off for servicing, unless already equipped.
d) Install the room thermostat (not provided) on an inside wall away from cold drafts,
windows or heat from fireplaces, appliances or sunlight. Set the heat anticipator in
accordance with the manufacturer’s instructions. Connect the thermostat leads to the
“TT” terminals on the circulator control.
C. Operational Sequence
1) TDX-WC equipped with tankless coil are equipped with a combination aquastat control
which has high and low limits to be set at 180° F and 160° F respectively by the installer.
These settings are nominal and may be adjusted for the particular installation conditions.
A 20° F difference between high and low limit is recommended. The control prioritizes
domestic hot water heating as explained below.
a) When room temperature falls below thermostat setting, thermostat calls for heat start
ing the burner and circulating pump. The burner and pump continue to operate until
room heating requirements are satisfied (thermostat setting is reached), or until boiler
water temperature reaches the high limit control temperature setting. If the high limit
control temperature setting is reached, the burner shuts off and the circulating pump
continues to operate until the room heating requirements are satisfied. If the thermostat continues to call for heat after the boiler water temperature has dropped to
approximately 10 degrees below the temperature setting of the high limit control, the
oil burner will start again and the circulating pump will continue to run.
b. The boiler water temperature is normally maintained at 160°F around the tankless coil
by the operating control so that an abundance of hot water is available. If the boiler
water temperature should fall approximately 10 °F below the operating control low
8
limit setting, the oil burner will be started again by the control (and the circulating
pump will be prevented from operating) until the operating control setting is satisfied.
The operating control has an adjustable low limit differential setting. The low limit differential setting determines how high the boiler temperature must rise before the
burner turns off and or the circulator comes on if the thermostat calls for heat. The
differential is measured from 10°F below the low limit. See control manufacturer’s
literature included in the data package for detailed wiring, operating and safety
instructions.
c) Adjusting the low limit differential to higher values will provide priority to heating
domestic hot water over a greater range of boiler temperature. (Maximum of approximately 25°F differential measured from 10°F below the low limit setting.)
2) TDX boilers that do not have a tankless coil
and are equipped with a high limit
aquastat must be used with bypass control which should be set at 180°F by the installer.
This setting is nominal and may be adjusted for the particular installation conditions.
a) When room temperature falls below thermostat setting, thermostat calls for heat start-
ing the burner and circulating pump. The burner and pump continue to operate until
room heating requirements are satisfied (thermostat setting is reached), or until boiler
water temperature reaches the high limit control temperature setting. If the high limit
control temperature setting is reached, the burner shuts off and the circulating pump
continues to operate until the room heating requirements are satisfied. If the thermostat continues to call for heat after the boiler water temperature has dropped to
approximately 15 degrees below the temperature setting of the high limit control, the
oil burner will start again and the circulating pump will continue to run.
b) The boiler water temperature need not be maintained at a160°F low limit setting since
there is no domestic hot water load to protect. See control manufacturers literature
included in the data package for detailed wiring, operating and safety instructions.
c) Boilers without Tankless Coils may be equipped with a combination aquastat that has
a high and low limit setting. The high limit control is set at 180°F and the low limit is
set based on the application. If the boiler is used with an indirect hot water heater for
domestic hot water, the low limit is set at 160°F to support the operation of the indi
rect hot water heater. If the an indirect hot water heater is not used, the low limit may
be set between 120°F and 140°F to provide protection against condensation in the
boiler. The settings are nominal and many be adjusted for the particular installation
conditions.
3) A cadmium sulfide flame scanner (cad cell) and relay are provided with the oil burner. The
cad cell will stop the oil burner within a predetermined number of seconds if the fuel fails
to ignite or if the flame goes out during operation. The oil burner will remain off until the
red reset button on the relay has been pushed. Reset must never be pressed more than
once during a single flame failure.
D. Start-Up and Check-Out Procedure
CAUTION : Only a trained, experienced serviceman should attempt the checkout
procedure outlined below. You should read to the burner manual provided with this
manual for specific instructions and set points.
9
1) Confirm that electrical power to the boiler is off. The fuel tank must be filled with No.
2 heating oil. Low Sulfur fuel is preferred.
2) Check electrode settings, nozzle size and air setting. Electrode settings are shown in
the burner manual provided along with this manual. Burner settings are listed on the
Service Man’s Label attached to the boiler and on the Specifications provided along
with this manual.
3) Set thermostats substantially above room temperature.
4) Open all shut-off valves in the fuel supply line to the burner.
5) Install pressure gauge in the port provided on the fuel pump. Attach a length of 1/4”
O.D. clear plastic tubing to the end of the bleed plug.
6) Turn on power to the boiler. If burner does not start immediately reset manual overload
switches and control. See control manual for reset instructions.
7) On one pipe systems bleed the fuel pump as soon as burner motor starts. To bleed the
pump, loosen plug while holding an empty container under the tubing installed in step 6
to catch all of the expelled fuel. Bleed for at least 15 seconds after the fuel stream is free
of all air. If air is still evident in the bleed line you must check the oil lines, all fittings, filters and any other connections for tightness. Kinks in the fuel lines will create undue high
vacuum therefore they must be eliminated. When you are sure all air has been eliminated
then close the bleed valve. Ignition should be instantaneous following the closing of this
valve. If it is not, proceed to the trouble shooting guide to determine why the fuel did not
ignite.
8) Be sure the fuel pump discharge pressure is adjusted to the pressure listed on the
Installer/ Service Man Label. If it is not, refer to the burner manufacturer’s instruction
sheet for pressure adjustment procedure.
FINAL ADJUSTMENTS OF THE BURNER MUST BE MADE USING PROPER COMBUS
TION TEST EQUIPMENT. Combustion test equipment required for proper burner adjustment:
a) CO
Analyzer
2
b) Draft Gauge
c) Oil Pressure Gauge 0-200 PSI
d) Stack Thermometer
e) Smoke Test Gun
f) Vacuum Gauge 0-30 in. of Hg
Notice: Read the burner manufacturer’s instructions supplied with this manual to set combustion. The burner instructions contain special instructions that may apply to the model
supplied with your boiler including how special features may affect the set-up procedure.
-
10
9) Burner Adjustments. Allow the burner to operate steadily for 5 to15 minutes. Check
burner settings shown on the Installer/Service Man Label and make the following adjustments.
a) Punch or drill a 1/4” hole in the flue pipe between the boiler and the barometric draft
regulator. All test readings should be taken from this point.
b) Take a draft reading from the flue pipe sampling hole. Adjust the draft in the stack,
using the barometric draft regulator, to the value shown on the Installer/Serviceman
Label. In tall chimneys a second draft regulator may be required in the flue pipe to
regulate draft under high draft conditions.
c) Remove the draft port plug over the fire and take a draft reading from the draft port.
Compare the readings with those on the INSTALLER/SERVICEMAN label. Refer to
the trouble shooting procedure if the draft over the fire reading is not correct.
Reinstall the draft port plug after all readings have been taken.
d) Follow the burner manufacturer’s instructions to adjust the air supply until a trace of
smoke is recorded. At the trace of smoke level, measure the CO
. This is the refer-
2
ence point for all further adjustments.
e) Increase the air supply to reduce the CO
about 1-1/2% to 2% from the reference
2
point. A zero smoke reading should result. If this adjustment can not be obtained,
refer to the Trouble Shooting section of this manual.
f.) When combustion is set, follow the burner manufacturer’s instructions to lock or
tighten adjustment mechanisms as required.
10) Check operation of the cad cell relay by removing one cad cell wire from external terminal during the flame cycle. The relay should cut the burner off in approximately 15 sec.
11) Direct Vent Applications. The burner control for direct vent applications is provided with a
post-purge feature to keep the burner fan operating after the flame is off. The post purge
cycle time is 120 seconds. See the burner manufacturer’s operating instructions for more
information on the post purge settings.
E. Servicing the Boiler/Burner Unit:
1) Burner Components: If replacement of burner parts is necessary, always use parts
recommended by the manufacturer. Specify part number and description when ordering.
2) Electrode settings are important for reliable ignition of the fuel. Check to be sure the
settings are in accordance with the instructions provided in the burner manual.
3) Nozzles: The nozzle specifications listed in the manual are the result of years of exhaustive engineering testing. Use extreme care in handling nozzles to avoid scratches or dirt
that could cause leaks or affect the fuel spray pattern.
CAUTION: Any nozzle replacement should be of the exact type as listed in the
specifications.
11
4) Fan and blower housing should be kept clean of dirt and lint. If heating unit is located
near an unvented dryer, special care must be taken so that lint does not clog the burner
air inlets.
5) Replace the fuel filter cartridge annually.
6) Check all water connections and plugs for evidence of leaks. Check for leaks by shutting
the make-up water supply valve. If boiler pressure decreases, it is evidence of a leak
which must be repaired.
7) Cleaning the Boiler: Cleaning should be done only by a trained, experienced serviceman.
DANGER: Before cleaning turn off all power to the boiler. Failure to turn off power could
result in firing the boiler when it is open.
a) Remove the burner cover by lifting up to disengage the fasteners and out to remove
the cover. Remove the boiler front cover and rear cover by lifting up and out.
b) Disconnect the control wires from the aquastat control to the burner.
c) Remove the brass nuts that secure the hinged burner door and carefully open the
door.
d) Remove the rear cover on the flue box.
e) Remove baffles from the units and clean them. Brush all tubes and the furnace tube
with a #2 soft flue brush. Use a boiler vacuum to collect any residue.
f)Inspect the burner head. Remove any accumulation on the burner. Inspect and
follow burner manufacturer’s recommendations for cleaning and maintenance.
g) Check all refractory and gaskets for resilience and continuity. Replace damaged
parts prior to re-assembling the unit.
h) Reassemble the boiler.
F.Changing the Burner Door Hinge Location.
The side that the hinge is located on may be changed as follows.
1) Turn power off to the burner.
DANGER: Failure to turn off power to the burner during maintenance may result in
serious injury or death.
2) Remove the burner cover by lifting it up, out and away from the burner. Remove the
front boiler cover by lifting up, out and away from the burner.
3) Disconnect the burner power cord.
12
4) Disconnect the fuel supply line to the burner.
5) Remove the burner from the burner flange and set the burner to the side.
6) Remove two brass nuts that hold the door bracket to the boiler. Remove two brass nuts
that hold the door bracket to the door. Remove the two brass nuts that hold the hinge
the door. Set the door to the side.
7)Remove the two brass nuts that hold the hinge to the boiler, move the hinge to the other
side and attach it to the boiler using two brass nuts. Do not tighten the nuts fully. The
thick side of the hinge is attached to the boiler. The hinge pin is on the outside.
8)Attach the door bracket to the door using two brass nuts. Swing the door to make sure
that it is free and that the door bracket fits over the boiler studs on the other side. Make
final adjustments and tighten all nuts.
9)Close the door and attach the bracket to the boiler using two brass nuts. Do not tighten
completely.
10) Install the burner. Remove the two nuts that hold the door flange to the boiler. Check that
the door swings free. Adjust as required. Install and tighten door flange nuts.
11. Attach fuel supply line and burner cord to burner.
Follow start-up procedure in this manual. Check for combustion gas leaks around the door
gasket and repair prior to operation.
13
14
15
16
Appendix C
Low Water Cutoff
if required, install low water
cutoff(s) in the piping
anywhere above the top of
the boiler. Install in
accordance with the
manufacturer's instructions.
Supply to heating
circuits
10
Bypass
Piping
11
2
4
3
1
5
Burner
TDX-LC
6
7
8
8
Return from heating
circuits
8
6
7
1
2
4
3
Return from heating
circuits
TDX-WC
8
Burner
5
Supply to heating
c
ircuits
Domestic
Hot Water
Coil
Hot Water Out
Dishwasher
Tempered Hot Water
Cold Water In
9
Legend
1. Circulator
2. Relief Valve
3. Expansion Tank Pressurized
4. Vent
5. Flow Check
6. Shut off valve
7. Auto Refill/Pressure reducing valve
8. Drain
9. Tempering Valve
10. Manual Bypass Valve
11. Optional Danfoss Bypass Valve
Piping Diagram
17
ELECTRICAL DIAGRAM FOR TDX SERIES
BOILERS TO CONNECT BURNER TO AQUASTAT
(APPLIES TO CARLIN CHIMNEY VENT AND CARLIN DIRECT VENT BURNERS)
ELECTRICAL DIAGRAM FOR TDX SERIES
BOILERS TO CONNECT BURNER TO AQUASTAT
(APPLIES TO BECKETT CHIMNEY VENT AND DIRECT VENT BURNERS)
18
ELECTRICAL DIAGRAM FOR TDX SERIES
BOILERS TO CONNECT BURNER TO AQUASTAT
(APPLIES TO RIELLO CHIMNEY VENT BURNERS)
ELECTRICAL DIAGRAM FOR TDX SERIES
BOILERS TO CONNECT BURNER TO AQUASTAT
(APPLIES TO RIELLO DIRECT VENT BURNERS)
19
Installer/Serviceman Labels
Appendix E
INSTALLER/SERVICEMAN
Model NumberTDX-WC 90 TDX-WC 100 TDX-WC 110 TDX-WC 125
Burner TypeBeckett Beckett Beckett
Burner ModelNXNXNX
Nozzle Type0.70 60°B0.75 60°B0.85 60°BN/A
Pump Pressure PSI175175175N/A
Head/Pin Position2.53.004.5N/A
Air BandN/AN/AN/AN/A
Air ShutterN/AN/AN/AN/A
Draft Over Fire+0.06"+0.08"+0.10"N/A
Draft In Stack-0.02"-0.02"-0.02"N/A
CO2Reading10-12%10-12%10-12%N/A
Smoke ReadingZEROZEROZERON/A
Above settings are approximate. Final adjustments to be made
with proper test equipment. Be sure all oil lines are air free and
the use of flare fittings is recommended. See installation/service manual for detailed information.
Above settings are approximate. Final adjustments to be made
with proper test equipment. Be sure all oil lines are air free and
the use of flare fittings is recommended. See installation/service manual for detailed information.
See the label attached to your boiler for data specific to your boiler.
20
INSTALLER/SERVICEMAN
Model NumberTDX-WC 90 TDX-WC 100 TDX-WC 110 TDX-WC 125
Burner TypeCarlinCarlinCarlinCarlin
Burner ModelEZ-1 PROEZ-1 PROEZ-1 PROEX-1 PRO
Nozzle Type0.75 60°B0.85 60°B0.90 60°B1.00 60°B
Pump Pressure PSI150150150150
Head/Pin Position0.750.85-1.000.85-1.000.85-1.00
Air Band0.750.850.901.00
Air ShutterN/AN/AN/AN/A
Draft Over Fire+0.04"+0.07"+0.09"+0.12"
Draft In Stack-0.02"-0.02"-0.02"-0.02"
CO2Reading10-12%10-12%10-12%10-12%
Smoke ReadingZEROZEROZEROZERO
Above settings are approximate. Final adjustments to be made
with proper test equipment. Be sure all oil lines are air free and
the use of flare fittings is recommended. See installation/service manual for detailed information.
Model NumberTDX-WC 90 TDX-WC 100 TDX-WC 110 TDX-WC 125
Burner TypeCarlin*Carlin*Carlin*Carlin*
Burner ModelEZ-1 PROEZ-1 PROEZ-1 PROEX-1 PRO
Nozzle Type0.75 60°B0.85 60°B0.90 60°B1.00 60°B
Pump Pressure PSI150150150150
Head/Pin Position0.750.85-1.000.85-1.000.85-1.00
Air Band454065180
Air ShutterN/AN/AN/AN/A
Draft Over Fire+0.080"+0.115"+0.125"+0.140"
Draft In Stack+0.040"+0.055"+0.065"+0.075"
CO2Reading10-12%10-12%10-12%10-12%
Smoke ReadingZEROZEROZEROZERO
Above settings are approximate. Final adjustments to be made
with proper test equipment. Be sure all oil lines are air free and
the use of flare fittings is recommended. See installation/service manual for detailed information.
Model NumberTDX-WC 90 TDX-WC 100 TDX-WC 110 TDX-WC 125
Burner TypeCarlin*Carlin*Carlin*Carlin*
Burner ModelEZ-1 PROEZ-1 PROEZ-1 PROEX-1 PRO
Nozzle Type0.75 60°B0.85 60°B0.90 60°B1.00 60°B
Pump Pressure PSI150150150150
Head/Pin Position0.750.85-1.000.85-1.000.85-1.00
Air Band0.650.751.001.10
Air ShutterN/AN/AN/AN/A
Draft Over Fire+0.080"+0.115"+0.125"+0.140"
Draft In Stack+0.040"+0.055"+0.065"+0.075"
CO2Reading10-12%10-12%10-12%10-12%
Smoke ReadingZEROZEROZEROZERO
Above settings are approximate. Final adjustments to be made
with proper test equipment. Be sure all oil lines are air free and
the use of flare fittings is recommended. See installation/service manual for detailed information.
qBoiler level and in solid contact with floor?
qBoiler and burner wired per wiring diagram and National Electric Code? 120VAC wiring
Type_______ Size_______ AWG
qBurner sealed to boiler? Mounting nuts tight?
qSpace is large enough to provide required clearances?
qNFPA 31 Installation of Oil Burning Equipment followed?
qLocal, state and national codes, laws, regulations and ordinances followed?
Vent System
qExisting chimney and vent system inspected to NFPA 211 and in good condition?
qNew vent pipe installed and properly sealed?
qVent size checked against furnace manual and codes?
Burner Operation
qBurner Model: ____________________ Nozzle: _____ GPH _____ Deg. _____ Type _____
qBurner Pump Pressure: _________________
qFuel Filer and fuel lines installed and inspected as per burner manual?
qAir bled from oil piping? Piping checked for leaks?
qBurner started, adjusted and tested per burner manual?
Boiler Operation
qThermostat heat anticipator set per burner manual instructions?
qLimit control tested for proper operation?
qBoiler observed going through several operational cycles for proper operation?
Post Installation
qReviewed owners’ information in this manual with owner or maintenance personnel
and instructed to keep for future reference?
qInserted burner manual instructions with boiler manual for future use
MET-3381
1/08-250
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.