The Model 4299-2 Dual-Unit Rack-Mount Kit contains the hardware required to mount two half-rack instruments
in a standard 48.3 cm (19 in.) rack. Typical installation is for two Series 2600A or 2600B System SourceMeter
instruments or one Series 2600A or 2600B instrument with another half-rack instrument.
Parts list
Refer to the table below for a list of parts included in the kit.
Quantity Description Keithley part number
®
8 #10-32 × 5/8 in. Phillips truss-head screw 10-32×5/8PHTRSH
2 M4 × 12 mm Phillips flat-head screw M4×12MMPFH
Tools required
Medium (#2) Phillips screwdriver
3/8-inch wrench
Flat-bladed screwdriver or cage-nut installation tool
PA-909 Rev. J April 2021 *PPA-909J*1
Model 4299-2 Dual-Unit Rack-Mount Kit Installation Instructions
Installation overview
Review the Installation precautions (on page 2).
Select a location in the rack:
a. Clear as much space as possible around the selected rack location.
b. Remove the cabinet side panels from the rack.
Prepare the instrument (on page 3
Install mounting hardware (on page 4).
Prepare the rack (on page 7).
Install the instruments (on page 9) in the rack.
Installation precautions
Observe the following safety precautions while installing instruments.
Turn off instrument power and unplug all cables before installing an instrument in a rack.
Failure to remove power before installation may cause personal injury or death from
electrical shock.
).
Heat sources should be mounted away from the instrument, cabling, and accessories, with
sufficient space provided between the instrument and heat source for airflow and cooling.
To prevent damaging heat build-up and ensure specified performance, make sure there is adequate
ventilation and airflow around the instrument to ensure proper cooling. Do not cover the ventilation
holes on the sides or back of the instrument. The rear vents and both side vents must be
unobstructed to properly dissipate heat.
Mount precision equipment as low as possible in the rack. Operating temperatures are cooler lower
in the rack.
2 PA-909 Rev. J April 2021
Model 4299-2 Dual-Unit Rack-Mount Kit Installation Instructions
Prepare the instrument
To remove the handle, mounting ears, and rear feet:
1. Gently pull the handle (1) away from the sides of the instrument case and swing it up or down until the
orientation arrows on the handles line up with the orientation arrows on the mounting ears, as shown in the
following figure.
Figure 1: Rack-mount kit handle removal
2. After you align the arrows (2), pull the ends of the handle (1) away from the case.
3. Remove the screw that secures each mounting ear (3).
4. Pull down and out to remove each ear.
Figure 2: Mounting ear removal
5. From the bottom of the instrument, pull out the rubber feet and remove the screws (4), see the following
figure.
Figure 3: Instrument rubber feet removal
6. Store the handle, rubber feet, and hardware for future use.
PA-909 Rev. J April 2021 3
Model 4299-2 Dual-Unit Rack-Mount Kit Installation Instructions
Install mounting hardware
Install the mounting hardware on the opposite sides of each instrument, as shown in the following figures.
To install the mounting hardware on the instruments:
1. Place the instruments side-by-side, in the same position that they will be installed in the rack.
2. Secure one rear rack-mount bracket (2602-334) to each instrument on the selected side using two Phillips
pan-head SEMS screws (#10-32 × 3/8 PPHSEM).
If the two instruments are not the same length, do not use one of the rear rack-mount brackets. Refer
to Install the instruments (on page 9
detail. Additionally, save all unused parts for future use.
), "To install two instruments that are of unequal length" for more
Figure 4: Rear rack-mount bracket
4 PA-909 Rev. J April 2021
Loading...
+ 8 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.