Tektronix 4299-1 Installation Manual

Keithley Instruments
Model 4299-1 Single-Unit
1
Front rack-ear
2602-355
1
Rear rack-mount bracket
2602-334
1
Rack-mount extension arm
2602-335
1
Half-rack front panel
2602-363
6
Cage nut
FA-274
4
#8-32 × 3/8 in. Phillips pan-head screw
8-32×3/8PPH
2
#10-32 × 3/8 in. Phillips pan-head SEMS screw
10-32×3/8PPHSEM
6
#10-32 × 5/8 in. Phillips truss-head screw
10-32×5/8PHTRSH
28775 Aurora Road Cleveland, Ohio 44139 1-800-833-9200
tek.com/keithley
Rack-Mount Kit Installation Instructions

Introduction

The Model 4299-1 Single-Unit Rack-Mount Kit contains the hardware required to mount one half-rack instrument in a standard 48.3 cm (19 in.) rack. Typical installation is for one Series 2600A or 2600B System
®
SourceMeter

Parts list

Refer to the table below for a list of parts included in the kit.
Quantity Description Keithley part number
instrument.

Tools required

Medium (#2) Phillips screwdriver
3/8-inch wrench
Flat-bladed screwdriver or cage-nut installation tool

Installation overview

Review the Installation precautions (on page 2).
Select a location in the rack:
a. Clear as much space as possible around the selected rack location. b. Remove the cabinet side panels from the rack.
Prepare the instrument (on page 2
Install mounting hardware (on page 3).
Prepare the rack (on page 6).
Install the instrument (on page 7) in the rack.
PA-908 Rev. F April 2021
).
*PPA-908F*
1
Model 4299-1 Single-Unit Rack-Mount Kit Installation Instructions

Installation precautions

Observe the following safety precautions while installing instruments.
Turn off instrument power and unplug all cables before installing an instrument in a rack. Failure to remove power before installation may cause personal injury or death from electrical shock.
Heat sources should be mounted away from the instrument, cabling, and accessories, with sufficient space provided between the instrument and heat source for airflow and cooling.
To prevent damaging heat build-up and ensure specified performance, make sure there is adequate ventilation and airflow around the instrument to ensure proper cooling. Do not cover the ventilation holes on the sides or back of the instrument. The rear vents and both side vents must be unobstructed to properly dissipate heat.
Mount precision equipment as low as possible in the rack. Operating temperatures are cooler lower in the rack.

Prepare the instrument

To remove the handle, mounting ears, and rear feet:
1. Gently pull the handle (1) away from the sides of the instrument case and swing it up or down until the orientation arrows on the handles line up with the orientation arrows on the mounting ears, as shown in the following figure.
Figure 1: Rack-mount kit handle removal
2 PA-908 Rev. F April 2021
Model 4299-1 Single-Unit Rack-Mount Kit Installation Instructions
2. After you align the arrows (2), pull the ends of the handle (1) away from the case.
3. Remove the screw that secures each mounting ear (3).
4. Pull down and out to remove each ear.
Figure 2: Mounting ear removal
5. From the bottom of the instrument, pull out the rubber feet and remove the screws (4), see the following figure.
Figure 3: Instrument rubber feet removal
6. Store the handle, rubber feet, and hardware for future use.

Install mounting hardware

The instrument may be installed on the either side of the rack. Attach the half-rack front panel (2602-
363) to the side without the instrument.
PA-908 Rev. F April 2021 3