Swegon TBLZ-3-50 Instruction For The Installation

GB.TBLZ350.170214
Instructions for the Installation of the type TBLZ-3-50 Zone Control Box (X zone) GOLD
1. General
The zone control box consists of two IQlogic+ modules and one transformer (230 VAC/24 VAC) mounted inside a metallic enclosure. Necessary wiring terminals are provided for connection to external components. The metallic enclosure has cable gland screw caps for cable entry. See also the separate guide to the Xzone functions.
2. Range of Application
Sometimes more than one temperature zone is required in a ventilation system. Different temperature needs in vari­ous parts of a building may be due to the perimeter wall of the building facing north or south, diverse operations conducted inside or other reasons, for instance. The func­tion is designed for one extra temperature zone, max.
3. Installation
Secure the zone control box to a wall, the air handling unit or the like by means of four screws.
4. Technical Data
Supply voltage 230 V AC or 400 V AC,
max. 10 A
CE-approved to EN 61000-6-2,
EN 61000-6-3
Enclosure class IP 65
Ambient temperature at relative humidity
Relay contacts 2 A/AC3, 5 A/AC1
Weight 8 kg
Dimensions (Width x Height x Depth)
Fuse protection 2-pin connector, 0.25 A, C
Transformer 24 V AC/24 VA
-40 °C – +55 °C 10 – 95%
300 x 400 x 120 mm
characteristic
We reserve the right to alter specifications.
www.swegon.com 1
5. Function
GB.TBLZ350.170214
5.1 Xzone heating (wiring terminals 101-114)
IQlogic+module 1 is used for the extra heating control zone function (function selector switch 1 is set to Position A).
The function can be enabled in the hand-held micro termi­nal of the GOLD unit or via a communication interface.
The module controls an electric air heater or an air heater for hot water.
Connect the 0-10 VDC control signal of electric air heater or valve actuator to the IQlogic connector.
Connect the conductors from the pump, if fitted, to Termi­nals 101 and 102.
Connect the pump alarm, if required, to Terminals 103 and 104.
Connect the freeze guard sensor of the air heater for water to the IQlogic
-module with an RJ 45 connector.
Connect the conductors from the supply air temperature sensor (TBLZ-1-30) to wiring terminals 113 and 114.
See 6. Electrical connections on the next page.
module with an RJ 45
5.2 Xzone cooling (wiring terminals 115-132)
IQlogic+module 2 is used for the extra cooling control zone function (function selector switch 2 is set to Position B). Always use this module for extract air control/room air control even if the room is not being cooled. However, there’s no need to enable the cooling function in the hand-held micro terminal of the GOLD unit.
The function can be enabled in the hand-held micro termi­nal of the GOLD unit or via a communication interface.
The module controls a DX air cooler or an air cooler for chilled water.
Connect the 0-10 VDC control signal of valve actuator to the IQlogic
Connect the Cooling step 1/Pump 1 connectors (relay output) to Terminals 115 and 116.
Connect the Cooling step 2/Pump 2 connectors (relay output) to Terminals 117 and 118.
Connect the Cooling step 1/Pump 1 Alarm conductors to Terminals 119 and 120.
Connect the Cooling step 2/Pump 2 Alarm conductors to Terminals 121 and 122.
Connect the temperature sensor in the extract air duct (TBLZ-1-30), if required, to Terminals 131 and 132.
Connect room sensor, TBLZ-24-2 (1-4 sensors), if required, to the IQlogic installation instructions.
See Section 6. Electric connections appear on the next page.
module with an RJ 45 connector.
module with RJ45 contact, see separate
2 www.swegon.com
We reserve the right to alter specifications.
Loading...
+ 4 hidden pages