Smoke detector installation TBLZ-2-49-a GOLD/COMPACT
Smoke detector TBLZ-1-49-a is used to measure smoke gases in ventilation ducts. It consists of an optical detector mounted in an adapter system in which both the tube and enclosure are designed for optimum airflow through the detector. The system meets all fire safety requirements at air speeds between 0.2m/s and 20m/s. The smoke detec­tor is used together with a control unit (installed in equip­ment cubicle ELQA or separate equipment cubicle for smoke function) for controlling fans, smoke and combus­tion gas dampers.
Accessories
Use an installation bracket when installing on circular or insulated ducts.
2. Function
When combustion gas is detected the LED on the detector lights red and the alarm signal is forwarded to the control unit. If the smoke detector becomes dirty, it becomes more sen­sitive and switches to alarm mode more slowly. To prevent false alarms if dirty, the detector is equipped with a service alarm (green LED). This indicates that the detector requires cleaning.
3. Technical Data
Detector type Optical Operating voltage 24VDC (from control unit) Power consumption: In-operation Max 0.04mA Service alarm ~ 13mA Combustion gas alarm ~ 50mA Ambient temperature -20°C to +50°C Humidity Max 99% rH Degree of protection IP54 Weight 800g
Dimensions
Venturi tube length of 600 mm or 1500 mm.
(All dimensions are given in mm)
4. Maintenance
When the smoke detector becomes dirty, it becomes more sensitive and may trigger the service alarm. This can be delayed by vacuuming the detector once a year.
Page 2
GB.TBLZ49.091201
We reserve the right to alter specifications without notice.
2
www.swegon.com
5. Installation and location
Position the smoke detector in the direction of flow, accord­ing to the arrow on the cover. The smoke detector is loca­tion-independent and can be installed on any side of the duct. In the event of large temperature differences, e.g. outside or in cold attics, the detector must be insulated from the surrounding air (due to the risk of condensation build-up in the detector housing). To ensure optimum combustion gas detection the smoke detector must be positioned so that the distance to the nearest interfering source in the duct (see example of inter­fering sources below), in the direction of airflow, is the same as 3 x the duct’s hydraulic diameter. Nearest location after an interfering source must be at least 5 x the duct’s hydraulic diameter.
d = D
Ø D
h
d =
h
2xHxB
H+B
H
B
Hydraulic diameter CIRCULAR DUCT
RECTANGULAR DUCT
MIN 3xd
h
MIN 5xd
h
GX
GX
MIN 3xd
h
MIN 5xd
h
GX
GX
MIN 3xd
h
MIN 5xd
h
GX
GX
MIN 3xd
h
MIN 5xd
h
GX
GX
MIN 3xd
h
MIN 5xd
h
GX
GX
MIN 5xd
h
GX
MIN 3xd
h
GX
MIN 5xd
h
GX
MIN 3xd
h
GX
GX
MIN 3xd
h
GX
GX
MIN 3xd
h
MIN 5xd
h
d = D
Ø D
h
d =
h
2xHxB
H+B
H
B
Examples of sources of disturbance
FAN
DAMPER
SILENCER
COIL
BEND
BRANCH
ADAPTER
EXTRACT AIR
SUPPLY AIR
AIR HANDLING UNIT
Page 3
GB.TBLZ49.091201
We reserve the right to alter specifications without notice.
www.swegon.com 3
• Open the cover above the junction hood by lifting the
catch.
• Insert the cable through any cable grommet.
When using another type of grommet, remove them premounted by first pressing through one side and then through the other (1-2).
• Connect wiring according to the wiring diagram in the
instructions for equipment cubicles.
1
2
Drill holes in the duct.
• Make holes without 38 mm installation bracket.
• Make holes with 51 mm installation bracket
(see point 9).
3
Do not cut this end!
• Measure the ventilation duct.
• Cut the tube.
• The tubes must cover at least 90% of the duct’s width.
Detectors with venturi tubes of 600 mm are intended for ducts with a max. duct width of 600 mm.
• Insert the end plug.
• Insert the seal onto the tube.
• Insert the tube into the bottom of the detector box.
• Lock the tube using the stop screw
4
• Install the tube and detector on the duct.
• Secure the detector box at 3 points at the markings of
the arrows.
Important! IMPORTANT! The direction arrows (see the shape of the detector’s base or the top of the housing) must point in the same direction as the air flow in the duct.
End plug
Stop screw
Seal
5
Flow indicator. The detector is equipped with an indicator, a red plastic tab, which, when the detector is correctly installed, swings out due to the air flow.
6
Electrical installation.
Important! If the indicator does not move, consider moving the detector or install a fan tube.
Flow indicator
Venturi tube with auxiliary fan
7
Performance checks. Check the detector using the smoke detector tester in spray form.
• Move the "test hole plug" to the
side and then quickly spray. In the event of a deployed alarm the LED lights red on the circuit board and the detector. In the event of a deployed service alarm the LED on the circuit board lights yellow and green on the detector.
• Reinstall the test hole plug.
Important! Do NOT drill holes for signs or similar in the plastic cover. This can cause leakage that seriously affects the function of the detector.
Page 4
GB.TBLZ49.091201
We reserve the right to alter specifications without notice.
4
www.swegon.com
Installation bracket TBLZ-1-53 for circular ducts or insulated flat ducts.
The duct diameter can be as small as 100 mm using the bracket.
• Check that the direction of the arrows is towards the direction of ow.
• Check that the plug for the test hole is properly installed.
• Check that the ow indicator shows ow (rocks).
• Full scale tests with smoke generator are recommended to check the function.
Troubleshooting.
The smoke detector deploys without any smoke present.
• The smoke detector is faulty, dirty or positioned so that
condensation can build up, see point 8. The detector insert must be replaced.
Only the control unit triggers an alarm.
• Check that the termination resistor is installed in the last
smoke detector.
• Check that the coil’s resistance is 2.2kΩ from the control unit.
• Check that the control unit is OK by installing the 2.2k
resistor in the smoke detector output on the control unit.
• Use a voltmeter to check that 21-24 VDC with the cor­rect polarity is in terminal 1 (-) and terminal 2 (+).
10
8
9
The installation bracket is supplied flat.
The installation bracket is easy to bend/shape so that it fits circular or flat ducts.
Secure the bracket’s legs to the duct.
Hole ø 51 mm.
Rubber seal
Circular duct. Insulated flat duct.
Rubber seal
Final checks
Installing different tubes in different duct widths.
Venturi tube 600 mm. Venturi tube 1200 mm.
Hole ø 38 mm
Hole ø 38 mm
Cut the venturi tube to the correct length
The Venturi tube must go through the entire duct.
Important! Hole ø 51 mm
Max. tube of 30 mm outside the duct.
For ducts less than 600 mm use ven­turi tube of 600 mm, standard. For ducts between 600 mm and 1400 mm, use venturi tube of 1500 mm.
Cut the tube to the correct length.
Insert the end plug.
Install the seal
Install rubber seal TET
26-35 as a bearing.