3.22020/06/22Add SNOW-1810U installation and picture setting
3.32020/08/07Add test pattern function
3.42020/08/21Adjust Power consumption info and Table of contents + Appendix
3.52020/09/04Add the luminance function of the operation for the mixed connections
3.62020/11/02Modify dehumidification mode
3.72020/11/16Add Network IP Setting by USB
3.82020/11/27Update LSM guide
3.92020/12/01Update Picture Option
4.02020/12/02Update Dehumidification Guide
4.12020/12/14Update Ventilation Guide
4.22020/12/28AC placement guide to prevent condensation
1
LED R&D Lab(VD)
This contents must be noticed to customer.
Please print this page and hand it to user.
Dehumidification guidance – during installation
When moist gets into LED package because of high humidity, ‘Line defect’ can
be caused by electrical short inside of LED Package.
For keeping the best quality of products during installation, please refer to the
below cautions.
- If the condition meets one of the below cases at least, dehumidification MUST be
processed. Do not play any contents on the screen before dehumidification finishes.
∙ Case when vacuum packaging is already unsealed before unpacking products.
∙ Case when environment condition is worse than Samsung working condition (0°C~40°C/10~80%RH).
∙ Case when it elapses longer than 7 days after unpacking them, even though the environment condition
satisfies Samsung working condition (0°C~40°C/10~80%RH).
∙ Case when production date on the label elapses more than 6 months, even though vacuum packaging is
sealed.
∙ Case when volatile chemicals such as oil paint, solvent are used in same place of installation.
(You can refer to Product Information and Precautions for Installation part in detail.)
- If the screen needs dehumidification on installation, MUST follow the directions of next page.
This contents must be noticed to customer.
Please print this page and hand it to user.
Dehumidification guidance – during installation
How to install the screen in the case that dehumidification is necessary
※ Before finishing the directions explained in next pages, never play other contents or use them.
※ If the installation site has higher humidity, it is highly recommended to use dehumidifier.
(If A/C turned off after working hour, it may make humidity higher and cause line defects.)
※ Chilled air from A/C should never touch LED surface directly.
※ If thermo-hygrometer is equipped on the site while the screen is installed, it is useful to analyze
the cause of line defects.
1.Play a specific pattern of LSM program without any cabinets.
(This pattern should be used. If other pattern is used, it can cause line defects.)
① Select S-Box and Test Pattern
② Set darker gray pattern among various patterns.
2.Inspect cabinets with darker solid patterns(W/R/G/B) and turn off cabinets.
(It should take less than 30 seconds to show each solid patter and you can refer to
Screen check’ category in detail.)
‘Process of
This contents must be noticed to customer.
Please print this page and hand it to user.
Dehumidification guidance – during installation
How to install the screen in the case that dehumidification is necessary.
3. While installing cabinets, S-Box should play only this pattern.
• Check S-Box shows the pattern through monitor connected to S-Box service port.
• After installing each cabinet, check whether the pattern is shown in it.
• OCM cable connection can be checked through this.
• Before turning off S-Box, turn off the cabinets, first.
• After being sure S-Box plays this pattern, turn on the cabinets.
4. After completing installation of cabinets, start 24hr dehumidification process.
5. After finishing 24hr dehumidification process, do edge correction and module calibration.
This information should be noticed to customer.
Please print this page and hand it to user.
Dehumidification guidance – during operation
•Electrical short in package is possible to happen during products are working.
•For keeping quality of products during installation, please refer below cautions.
–If one of below case meet during operation, MUST do dehumidification process.
Case when environment condition is exceed operation condition.
Case when products are not working more than 1 month, even though environment condition is under
operation condition.
–When environment condition is exceed operation condition, products are out of warranty.
Please check environment condition.
–Even products are operating, if the installed place have extra construction such as interior
modification, MUST do dehumidification following installation condition.
–It is possible to happen dew condensation on surface of products, even though working on
operating condition. When happening dew condensation, MUST operate after cleaning the dew
condensation & dehumidification.
This information should be noticed to customer.
Please print this page and hand it to user.
Dew condensation due to overcooling
Even though meet with Samsung recommended operation
condition, dew condensation is possible to happen when
surface of products is colder than environment temperature or
hot & humid air blow to cooled surface of products.
(cf : Principle of happening dew on surface of glass which have ice)
Case when dew condensation is happen on products, it is
possible to be the root of defect. In this case, it is possible to
be out of warranty.
This information should be noticed to customer.
Please print this page and hand it to user.
Prevent condensation due to A/C
Make sure that the cold air does not blow directly on the screen.
–When the cold air from A/C (air conditioner) blows directly onto the screen surface,
condensation may occur depending on the ambient humidity and temperature of
screen surface.
–If the A/C and screen are close, install a wind deflector as shown in the figure
below to prevent condensation.
Install the wind deflector toward the screen.
Guidance of latest firmware
• When install products, please update latest firmware on online
- You can download latest firmware from SLM site.
URL of SLM Page : https://www.secslm.com
After login Help Download Center에서 Download
Before you download firmware, you MUST check same firmware of model
(marked red letter in below) & upper number of version (marked blue in below).
Cabinet : Main - L-xxxMWWAC-nnnn.n xxx = Pan name, nnnn.n = version
FPGA - aabbd_ddddd aa = pixel pitch, bb = LED package type, d_ddddd= version
※ Installation with IER/IFR of same pitch is recommended.
11
LED R&D Lab(VD)
1. Product Information and Installation Precautions
◆ Frame Kits configuration (See page 22.)
Frame kitConfiguration
for installation
VG-LFR84FWL
VG-LFR53FWL
VG-LFR52SWL
VG-LFR51PWL
VG-LFR11SWL
8*4 (32 sets)
5*3 (15 sets)
5*2 (10 sets)
5*1 P (15 sets)PIVOT installation
1*1 (1 set)
Remarks
Narrow
◆ Cabinet information
※ Please refer to Appendix for information of IER-F / IFR-F Frame Kit
<5*3 Frame>
◆ SBB-SNOWJAU, SBB-SNOWJMU, SBB-SNOWRAF
(S-Box, I/G)
12
<S-Box><I/G>
(Interface Gender)
LED R&D Lab(VD)
1. Product Information and Installation Precautions
◆ Installation precautions (LED damage)
PrecautionsImages
[Be careful of external impact or dropping]
① After removing the Cover-Corner from the product prior to installation,
exercise caution to ensure that the LED surface is not exposed to physical
impact and the product is not dropped onto the floor.
② Do not place the product on a vibrating object. Make sure the LED surface
does not face down onto the floor.
③ Exercise caution to ensure that the corners of the LED module are not
damaged due to contact with external factors.
④ Make sure the number of loaded rows does not exceed 12.
[Be careful of LED damage due to static electricity]
▶ Do not touch the LED surface with bare hands without anti-static gloves.
[Be careful of LED damage due to metallic foreign material]
▶ Exercise caution to ensure that metallic foreign material is not attached to
the LED front.
▶ If metallic foreign material is attached, remove the module and use a
MODULE
Front
① ②
③ ④
Metallic
foreign
material
magnet to remove the foreign material.
13
LED R&D Lab(VD)
1. Product Information and Installation Precautions
◆ Heat protection guide
Requirements for indoor installation
-Applicable to use of SAMSUNG wall mount (compliant with ADA)
∙Gap between the product front and the wall: 99.5 mm
∙Gap between the product rear and the wall: 35.5 mm
-Entry of sunlight
∙If sunlight enters through glass windows or outer walls of the building,
contact Company HQ for assistance.
-Cold/warm air from HVAC system
∙Make sure cold or warm air (especially warm air) from an HVAC system
※ This page is written based on the Full white,
650 nit (back light 7) version
※ ADA: Americans with Disabilities Act
99.5 mm
Outdoor temperature
measurement position
wall
does not reach the product.
-Outdoor temperature measurement position
∙Center of the product or the inlet area
14
Outdoor temperature
measurement position
35.5 mm
LED R&D Lab(VD)
1. Product Information and Installation Precautions
Outdoor
air temp.
Fan flow rate depending on the number of installed cabinet rows
No. of rows
1 to 3
Rows
※ CFM = cubic feet per minute
4 Rows5 Rows6 Rows7 Rows8 Rows9 Rows10 Rows
※ Measurement based on one column
Below 25℃
Fan is not
necessary
25℃ to 30℃
※ Example) If outdoor air temperature is 30℃ and cabinets are
arranged in a 5x4 (horizontal x vertical) configuration,
what is the total CFM ?
→ 70 [CFM/column] x 5 [column]=350 [CFM]
Fan is not necessary
7080100110130145160
708090100
4 Rows
Total minimum flow rate 350 CFM
70 CFM70 CFM70 CFM70 CFM70 CFM
FAN
Outdoor air
temperature is
30℃
5 Columns
※ For installation under other conditions not covered in this guide, contact the Development Team.
15
Air vent area
LED R&D Lab(VD)
1. Product Information and Installation Precautions
• Requirements for using FAN
–Air vent: Should only be installed on the bottom
–Upper portion: Seal the entirety, except the fan outlets
Location of FAN
Shape of FAN unit
Seal the left and right sides
WALL
Seal the left and
right sides
Vent requirements
-Use vents with an opening rate of at least 70%
-Opening rate (%) =
B
d
c
. ℎ
Air vent area
16
A
LED R&D Lab(VD)
1. Product Information and Installation Precautions
Minimum spacing for wall mounting installation
Min condition : 30mm (set ~ ceiling)
Recommended condition : more than 500mm
Air vent area
Air ventarea
WALL
(more than 60%
of opening rate)
Min condition: 30mm (set ~ floor)
Recommended condition : more than 500mm
17
Air vent area
(more than 60%
of opening rate)
LED R&D Lab(VD)
1. Product Information and Installation Precautions
Minimum spacing for processed installation
Min condition : 0mm (set ~ ceiling)
Recommended condition : more than 500mm
Essential cond. : more than 30mm of 100% opening rate
WALL
Essential cond. : more than 30mm of 100% opening rate
Min condition: 0mm (set ~ floor)
Recommended condition : more than 500mm
Air vent area
Air vent area
18
LED R&D Lab(VD)
1. Product Information and Installation Precautions
Example of minimum spacing and FAN allocation for wall mounting installation
Min condition : 30mm (set ~ ceiling)
Recommended condition : more than 500mm
Other parts except for FAN
area should be sealed
left and right should be sealed
WALL
leftandrightsealing
Air vent area should be mesh type with
an opening rate of more than 60%.
Min condition: 30mm (set ~ floor)
Recommended condition : more than 500mm
19
LED R&D Lab(VD)
1. Product Information and Installation Precautions
Example of minimum spacing and fan allocation for recessed installation
Min condition: 0mm (set ~ ceiling)
Recommended condition : 500mm
Essential cond. : more than 30mm of 100% opening rate
Other parts except
for FAN area should
be sealed
WALL
Essential cond. : more than 30mm of 100% opening rate
Min condition: 0mm (set ~ floor)
Recommended condition : 500mm
left and right should be sealed.
※ Vent and interior finishing work will proceed after screen installation.
20
Air vent area
LED R&D Lab(VD)
1. Product Information and Installation Precautions
Example of minimum spacing and placement during rear exhaust
Ambient temperature on the back of
the wall should be less than 30 ℃.
Other parts except for
FAN should be sealed.
WALL
left and right should be sealed.
Essential cond. : more than 30mm of 100% opening rate.
21
Air vent area
LED R&D Lab(VD)
1. Product Information and Installation Precautions
◆ Preparation for installation
Electric screwdriver
Service JIG
(BH81-00001A)
Phillips (+)
※ Recommended sizes
Holder Magnet Tool
(Included in LED MODULE JIG)
screwdriver
22
LED MODULE JIG
(model name: CY-LJRNLS)
Pliers
Anti-static
gloves
LED R&D Lab(VD)
1. Product Information and Installation Precautions
◆ IER (IFR) Accessory configuration
Common
Quick Setup Guide
Extension Power CableOCM Cable
COVER PCB
(IER : 7ea / IER-F : 4ea)
Product Warranty Card
(Not provided in some regions)
Power Cord
regulation guide
PET Tape (W10*L540,1 EA)
Machine Screws
(IER : 7ea / IER-F : 13ea)
IER / IFR
(guide pin,2ea)
IER-F / IFR-F
COVER PCB (6ea)
BRACKET LINK (2ea)
STUD PEM
BRACKET ALIGN (1ea)
23
LED R&D Lab(VD)
2. Preparation for Cabinet Installation
◆ Preparation for installation
① Remove the tape on top of the package box and open the box. (See Fig.1.)
② Remove the Top–Cushion and open the shielding bag.
Hold the handles inside, take out the set, and then remove the PE bag. (See Fig.2.)
③ Check that the sliding bolts are properly fastened. (See Fig.3.)
■ IER
■ IER- F
Fig.1 Contents of the
package
BottomCushion
Box
LED
set
IB &
cable
TopCushio
n
IB & cable
Fig. 2 Opening the
Bottom-Cushion
Fig.3 Checking the bolts
package
SLIDING BOLT
handl
e
Handle Shape
SLIDING
BOLT
Box
Top-Cushion
LED set
24
LED R&D Lab(VD)
2. Preparation for Cabinet Installation
◆ Preparation for installation
④ Connect the power and check for a problem with the screen. (See Fig.4.)
※ See page 12 for details on how to check for a screen problem.
⑤ Guide Pin (Accessory Enclosed) 2EA is assembled on top of the cabinet. (Excluding the capinet on the top row)
⑥Unfasten the screws (four screws in total) and remove the corner covers. (See Fig.5.)
※ IER / IFR
※ IER- F / IFR-F
Fig.4 Checking the screenFig.6 Removing the corner covers
Switch Button
Fig.5 Guide Pin Assembly
Guide
Pin
SCREW
Switch Button
25
SCREW
LED R&D Lab(VD)
2. Preparation for Cabinet Installation
◆ Note: Checking for a screen problem
⑥ Connect the power cord that came with the product and turn on the product.
Check that there is no LED damage and no problem is found on the screen.
Power In
Switch (Toggle)
Power out
※ Steps to perform in the event of White Pattern
-Apply power and press and hold the Switch for 5 seconds.
-When the factory info window appears, press the Switch once again.
- When the color screen appears, press the Switch repeatedly to check for malfunctioning LEDs.
(Each time the Switch is pressed, the LED color is switched in the following order:
white → blue → red → green.)
- To turn off the mode, press and hold the Switch for 5 seconds again.
26
LED R&D Lab(VD)
2. Preparation for Cabinet Installation
⑧ For cabinets placed on the edge, attach PET sheet before attaching PCB covers.
※ Attach PET sheet to all borders of the LED module (Fig.1), and attach PCB covers to the same outer sides where the
PET sheet has been attached (horizontally 5 points and vertically 4 points, as shown by the blue borders in Fig.2).
※ Attach PET sheet as shown in Fig.3. Make sure the area with no tape guides the LED module.
※ Attach PCB covers as shown in Fig.4.
No tape
0 to 0.5 mm
Fig.1 Attach PET sheet here
PET sheet
Fig.3
Fig.2 Borders requiring PET sheet and PCB covers
* Numeric figure: Quantity of PCB covers to attach
27
Fig.4
Fig.1 Attach PET sheet here
LED R&D Lab(VD)
3. Frame kit Components
① Check the configuration below in the frame kit.
※ Refer to the attached specifications for the IER-F/IFR-F installation.
No.Item
ⓐ
ⓑ
ⓒ
ⓓ
ⓔ
ⓕ
ⓖ
ASSY BRACKET SIDE
ASSY BRACKET MIDDLE
ASSY BRACKET CENTER
ASSY BRACKET JIG
JOINT V
ASSY ANCHOR SCREW
QUICK INSTALL GUIDE
ⓗ
ⓘ
Service JIG
Wrench
VG-
LFR84FWL
8X45X35X21X1PIVOT
22222
633-3
1 (+1)1 (+1)1 (+1)-1 (+1)
222-1
107727
502821414
11111
111--
11111
VG-
LFR53FWL
VG-
LFR52SWL
Qty (+spares)
VG-
LFR11SWL
VG-
LFR51PWL
a
e
JOINT V
b
d
f
M5,L65, Anchor screw
b
c
b
g
QSG
a
h
SERVICE JIG
WASHER (SLIDING BOLT)
ⓙ
ⓚ
ⓛ
Screen size for installation (mm)
BOLT – ETC
SCREW (M4)
1055--
----12
201414414
7680 X
2160
4800 X
1620
4800 X
1080
960 X
540
28
2700 X
2880
i
WRENCH
j
WASHER
k
BOLT-ETC
SCREW (M4)
LED R&D Lab(VD)
l
4. Frame Installation
② On the left end, place the ⓐBracket Side and fasten the screws to install the Bracket (Fig.3).
※ Fasten one screw first, and use a clinometer to vertically align the right edges and fasten screws into the other holes.
(See the next page for precautions when fastening screws.)
Fasten the screws in the order of screw 1 → screw 2 → screw 3. Fig.1
ⓐ Fix the Bracket Side, following the measurements shown in Fig.4.
25 mm or above
①
③
③
Screwing
hole
②
Fig.2 Screwing hole
Fig.1 Order of fastening the screws
a
b
d
b
Fig.3 Positions of
components to attach
c
b
a
12 mm or above
a
12 mm or above
Fig.4 Screw fastening position
based on screen
29
LED R&D Lab(VD)
Loading...
+ 93 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.