Stratco DUTCH GABLE Assembly Instructions Manual

DUTCH GABLE
FREESTANDING CARPORT
STRATCO OUTBACK ASSEMBLY INSTRUCTIONS.
®
Your complete guide to building a
FREESTANDING Outback DUTCH GABLE CARPORT
BEFORE YOU START
BARGE CAP
The barge cap covers the area where the deck finishes at portal frame
RIDGE KNUCKLE
Slots inside the gable rafters to form connection at the ridge
HIP PLATE
Connects purlins to the hip rafter.
EAVES KNUCKLE
Slots inside gable rafter and column to form connection at eaves.
COLUMNS AND RAFTERS
Pre cut 120 outback beam make up rafters and columns
PURLINS
Purlins provide support for cladding
PARTS DESCRIPTION
RIDGE CAP
HIP FLASHING
This flashing covers the roof sheets at the gable ridge.
Covers the roof sheet ends along the hip rafter.
INFILL PANELS
Sufficient number of sheets are provided, from which the required dutch gable infill panels can be cut.
HEX HEAD SELF DRILLING SCREWS
Screw types vary depending upon the connection, ensure correct screws are used
10x16
12x20
14x95
BOLTS AND RIVETS
Bolt types vary depending upon the connection, ensure the correct fixings are used
VERANDAHS PATIOS CARPORTS PERGOLAS
K
UTBA
®
PANEL STRIPS
Panel strips attach to the infill panel where applicable
WEATHER STRIP
Weather strip supports infill panel and covers the sheet ends at the collar tie
FOOTING KNUCKLE
Slots inside column to form an in ground footing connection
FOOTING PLATE
Slots inside column to form on concrete footing connection.
68 mm PURLIN BRACKET
This bracket fastens end purlin supports in place and front purlins to end purlin supports
COMPONENT LAYOUT
7
8
9
10
6
5
4
3
2
1
Hip Flashing
End Frame
Portal Frame
Purlins
Eaves Purlin Connection
120 Beam-Beam Connection
11
Hip Plate Connection
Seated Connection
Ridge Knuckle
Eaves Knuckle
Roof Cladding
Collar Tie
Ridge Connection
Footing Connection
Barge Cap
Footing Plate
Footing Knuckle
OR
Infill Panel
Weather Strip
Panel Strips
End Purlin Support
15 20
21
16
17
18
19
14
13
12
19
20
1
18
16
17
12
9
13
10
5
8
4
7
3
14
2
6
21
11
15
Figure 1
2
OUTSIDE
OF COLUMNS
OUTSIDE OF COLUMNS
OVERALL W
IDTH
OVERALL W
IDTH
END FRAME
SPACING
END FRAME
SPACING
FRAME CENTRES
FRAME CENTRES
45°
END
FRAME
INTERNAL
PORTAL
PORTAL
FRAME
FRAME
INTERNAL
OVERALL LENGTH
OVERALL LENGTH
OUTSIDE OF COLUMNS
OUTSIDE OF COLUMNS
COLLAR TIECOLLAR TIE
SINGLE CARPORT
HIP RAFTER
45°
INTERNAL
PORTAL
FRAME
FRONT PURLINFRONT PURLIN
C
O
LLA
R
TIE
COLLAR TIE
DOUBLE CARPORT
HIP RAFTER
DUTCH GABLE PLAN VIEW
END
FRAME
END
PURLIN
SUPPORT
CONSTRUCTION
MARKING OUT CARPORT POSITION
A) IN GROUND FOOTING
Note: These column locations are very critical, as the roof sheet lengths are governed by these dimensions.
Place stakes at the carport column locations using the appropriate dimensions from the drawings supplied.
Therefore ensure the end frame spacing and the width of the carport are exactly as specified in the drawings.
Tie string lines between the stakes to ensure the footings are in line. Check the dimensions and diagonals for squareness.
The end frame spacing, gives the centreline spacing between the rectangular end portal frame and the internal gable portal frame. Where more than two internal portal frames are required, space at the dimensions specified on the drawings supplied.
Dig holes to the required size as stipulated by your Council Application Form. Place bricks in the bottom of the holes to give a solid base onto which the footing knuckles can be positioned.
If bolting columns onto existing concrete slab check to ensure concrete dimensions are as specified by your Council. Stratco does not take any responsibility for concrete failure.
Mark the position of the columns as shown in Figure 4. using the appropriate dimensions from the drawings supplied.
Therefore ensure the end frame spacing and the width of the carport are exactly as specified in the drawings supplied.
B) ON CONCRETE FOOTING
Note: These column locations are very critical, as the roof sheet lengths are governed by these dimensions.
3
OUTSIDE OF COLUMNS
O
U
TS
ID
E
O
F
C
O
LU
M
N
S
HOLE POSITIONS
DIAGONALS
STRING LINESTRING LINE
FRAME SPACINGFRAME SPACING
FRAME SPACINGFRAME SPACING
END FRAME
SPACING
END FRAME
SPACING
END FRAME
SPACING
END FRAME
SPACING
The end frame spacing, gives the centreline spacing between the rectangular end portal frame and the internal gable portal frame. Where more than two internal portal frames are required, space at the frame spacing dimensions specified on thedrawings supplied.
Place the footing plate in the appropriate locations as specified on the drawings supplied. The orientation of the base plate is such thatthe smaller dimension runs alongthe width as shownin Figure 4.
Mark the position of the holes through the existing holes in the footing plate. Remove the footing plate and drill into concrete using the values given in Table 1.
Use chemical anchors (for size refer to Table 1) together with the appropriate anchor capsules and install according to the manufacturers recommendations.
Leave the Stud Bolt undisturbed for the minimum time specified by the manufacturer for the resin to cure. Curing times are dependent on the concrete temperature at the time of installation.
Footing plates are not fixed until portal frames have
been assembled.
NOTE: Do not drill completely through slab, as chemical anchors require a solid base to bear against.
Note:
ASSEMBLE PORTAL FRAMES
Place the three knuckle connections inside portal frame members, using a hammer to tap in position (a block of timber should be used whenever hammering to avoid damaging paintwork).
Knuckles are colour coded as follows,
ensure that the correct knuckle is used for each connection.
° ° °
Important note:
22 Ridge Knuckle - Green 22 Eaves Knuckle - Red 30 Eaves and Ridge Knuckle - Yellow
FRAME SPACINGFRAME SPACING
4
OUTSIDE OF COLUMNSOUTSIDE OF COLUMNS
END FRAME
SPACING
END FRAME
SPACING
END FRAME
SPACING
END FRAME
SPACING
O
U
T
S
ID
E
O
F
C
O
LU
M
N
S
OUTSIDE
OF COLUMNS
CARPORT
CARPORTS < 5000mm WIDE
IN W41 WIND SPEED
CARPORTS 5000mm WIDE
IN W41 WIND SPEED
³
CHEMICAL ANCHOR
SIZE (mm)
9512M10x130
11514M12x160
HOLE DIAMETER
(mm)
HOLE DEPTH
(mm)
TABLE 1
Join all frame members; first insert eaves knuckle into column to rafter joint, next the footing knuckle/base plate into the column base, and then finally the ridge knuckle into the two halves of the frame at the ridge (refer to figure 5 for knuckle locations).
Use a hammer at the eaves knuckle to join the two sides together as shown in Figure 5. If knuckles are difficult to insert apply a lubricant or grease.
5
HAMMER
BLOCK OF
WOOD
COLUMN/RAFTER JOINT
(EAVES CONNECTION)
COLUMN BASE
(FOOTING CONNECTION)
RAFTER/RAFTER JOINT
(RIDGE CONNECTION)
2 (12 X 20 HEX HEAD SELF DRILLING SCREWS) BOTH
SIDES OF RAFTER AND
COLUMN
2 (12 X 20 HEX
HEAD SELF DRILLING
SCREWS) THROUGH
OUTSIDE OF COLUMN
2 (12 X 20 HEX HEAD
SELF DRILLING SCREWS) THROUGH
TOP OF EAVES PURLIN CONNECTION
AND RAFTER
7
RAFTER
COLUMN
EAVES PURLIN
CONNECTION
BRACKET
EAVES
CONNECTION
ASSEMBLE END FRAMES
Pre-drill a 10 mm diameter hole 34 mm down from the topof the column through the centre of the double flange side (eaves purlin will bolt onto here) as shown in Figure 9.
Attach end wall beam-column connection 30 mm down from the top inside face of column, using two 10 x 16 hex head self drilling screws.
Double flange must always be on the outside of the
frame.
Slip end rafter over connection and fasten with four coloured 10 x 16 hex head self drilling screws as in Figure
9.
Note:
EAVES AND RIDGE CONNECTION
FOOTING CONNECTION
Screw together eaves and ridge connections, using two 12 x 20 hex head self drilling screws both sides of each member and two 12 x 20 hex head self drilling screws through the top (double flange side) of each member. Pilot holes indicate screw locations as shown in figures 6 and 7.
Make sure that the two ends are flush at the connection, leaving no gaps.
An eaves purlin connection bracket is attached as partof the eaves connection to both sides of the portal frame using two 12 x 20 hex head self drilling screws as detailed infigure 7 (pre drillfor ease of fastening).
For all footing connections, bolt together through pre drilled holes using M10 cup head bolts as shown in figure 8. Ensure that the bolt heads are all on the same side of the frame.
Mark the purlin centres on the top of the portal frames.
Important Note:
6
2 (12 X 20 HEX HEAD SELF
DRILLING SCREWS) THROUGH
TOP OF BOTH RAFTERS
2 (12 X 20 HEX HEAD SELF
DRILLING SCREWS) EACH SIDE
OF BOTH RAFTERS
RAFTER
RAFTER
RIDGE
CONNECTION
COLUMN
COLUMN SHOULD NOT COME INTO CONTACT WITH CONCRETE OR SOIL
8
FOOTING
CONNECTION
2 (M10 CUP HEAD
BOLTS) THROUGH
PRE DRILLED HOLES
9
30 mm30 mm
END FRAME RAFTER
END FRAME
COLUMN
END FRAME
COLUMN
FASTEN WITH 2 (10x16 HEX
HEAD SELF DRILLING SCREWS
ON EACH SIDE
DOUBLE FLANGE
DOUBLE FLANGE
34 mm34 mm
10 mm DIA
HOLE
10 mm DIA
HOLE
ERECT END FRAMES
A) IN GROUND FOOTING
Stand the end portal frame in the appropriate footing location and temporarily brace in position with clamps and struts (see Figure11).
Bolt the eaves purlins to the sides of the end frame columns using the 1.0 x 3/8 hex bolts provided, so that the purlins are level with the top of the column as shown inFigure 12.
Raise the other end frame and secure to eaves purlins. Ensure the ends of the purlins are flush with the outside faces of the end frames and the diagonal distances between the end frames are equal.
Check column base is at the ground surface, and the clear opening between columns is correct. Finally and most importantly check thatthe columns are vertical.
The concrete should be finished slightly raised towards the column, ensuring water runs away from the column, see Figure 11.
If concrete or soil is in permanent contact with the colorbond columns, corrosion will result in the base of the coloured column. Refer to the "Selection, Use and Maintenance of Stratco Steel Products" brochure for complete details ofmaintenance requirements.
Select the end rectangular portal frames. Place the footing plates in position and bolt securely.
Concrete the footings and leave overnight tocure.
Note:
Important Note:
B) ON CONCRETE FOOTING
11
BRACES
BRICK
FOOTING
KNUCKLE
END FRAME
FINISH CONCRETE SLIGHTLY RAISED
TOWARDS COLUMN
CLAMP
PRE-DRILL PURLINS
Note: All purlins are supplied to suit the individual Heritage
designs, It is important you refer to your plan and check purlin lengths before cutting.
For extra long carports where you need to join two purlins, make sure they are joined over a portal frame and that the top lap faces the same way for both purlins to achieve a neat joint.
Cut the eaves purlins to correct length. Pre-drill the eaves purlins with 10 mm diameter holes at the end portal frame locations. Only drill holes through the single side rib of the eaves purlin (see Figure 10).
34
34
DRILL THROUGH
SIDE RIB
10 mm
DIAMETER
HOLE
EAVES PURLIN
CUT AS SPECIFIED ON PLAN
34
34
DRILL THROUGH
DOUBLE FLANGE
14 x 95 SCREW
CUT AS SPECIFIED ON PLAN
ROOF PURLIN
10
ERECT PORTAL FRAMES
Now stand the internal portal frames in position, so that the eaves purlins rest on the eaves connection brackets Fasten the eaves purlin to the eaves connection through the underside of the bracket using two coloured 10 x 16 hex head self drilling screws .
The drawings supplied define the positioning of the internal portal frames relative to the end frames and as mentioned these are very critical.
(see Figure 18)
Note:
12
END FRAME RAFTEREND FRAME RAFTER
END FRAME
COLUMN
END FRAME
COLUMN
END FRAMEEND FRAME
INTERNAL PORTAL
RAFTER
INTERNAL PORTAL
RAFTER
ENSURE THE TOP
OF THE EAVES PURLIN
IS LEVEL WITH THE TOP
OF THE END FRAME
EAVES PURLIN
1.0x3/8
HEX HEAD
BOLT
Screw the four seated hip rafter connections to the top inside corners of the structure, level with the top of the eaves purlin. Fix with two 10 x 16 hex head self drilling screws, see Figure 14.
Lift hip rafter onto seated connection ensuring double thickness flange is at the top. The hip rafter angles away from the rectangular end frame at 45° and is screwed onto the internal gable frame as shown in figure 14.
Cut hip rafters to length and pre-drill with one large 14 x 95 hex head self drilling screw at the end, ensuring double thickness flange is at the top. Position hip rafter on the seated hip connection and fasten underside with two coloured 10 x 16 hex head self drilling screws.
Screw the remaining end onto the top of the internal portal frame. Do not over tighten, preventing crushing of the hip rafter.
Note:This 45° angle is critical in ensuring correct shape of the Dutch Gable and therefore the sheet lengths.
P2
C.L.
P1
C.L.
P1
C.L.
RIDGE
P2 = INTERNAL SPAN
P2 = INTERNAL SPAN
P1 = END SPANP1 = END SPAN
C.L. = CENTRELINEC.L. = CENTRELINE
110
13
P1
C.L.
P1
C.L.
RIDGE
P1 = END SPAN
P1 = END SPAN
C.L. = CENTRELINEC.L. = CENTRELINE
110
CHECK FRAMES
ROOF STRUCTURE
Now that the portal frames are in place, check the dimensions between portals are correct, and all portals are in line and vertical. Most importantly check the diagonal measurements are equal.
Pre-drill the roof purlins with 14 x 95 hex head self drilling screws at the internal portal locations, through the double flange first. Fasten one of these roof purlins at the ridge as shown in Figure 13. Check roof diagonals to ensure sloping roof area is square.
Refer to Figure 2
EAVES PURLINEAVES PURLIN
END WALL
RAFTER
END WALL
RAFTER
END WALL
COLUMN
END WALL
COLUMN
14
SEATED HIP
CONNECTION
IN CORNER
14X95 SCREW
HIP
RAFTER
COLLAR TIE
14X95 SCREWS
FRONT PURLIN
HIP RAFTER CONNECTION PLATE
FIX WITH 10X16 SCREWS
Single Size Carport
Note:
Double Size Carport
Attach remaining roofpurlins as shown inFigure 13.
Only 3 purlins for single carport, one purlin at eaves, one at ridge and one intermediate. Quantities may vary depending on roof cover and carport width.
Fasten the remaining roof purlins at the ridge location and 900 mm further down the rafter on each side. Position a purlin (first roof purlin - see Figure 15) 900 mm up the rafter from the eaves purlin (double flange on top).
Measure and cut a 45° mitre at the ends to fit flush against the hip rafter. Pre-drill with 14 x 95 self drilling screw at the internal rafter locationsand fasten in place.
Fix hip rafter connection plate to the underside of the hip rafter/side purlin joint using 10 x 16 hex head self drilling screws in the holes provided. Where end purlin supports are not required, locate front purlin on exposed connection plate, measure and cut a 45° mitre to fit flush with hip rafter. Screw in place (see Figures 14 and 15).
15
HIP
RAFTER
FIRST ROOF
PURLIN
FRONT PURLIN
HIP RAFTER
CONNECTION PLATE
FIX WITH 10X16 SCREWS
END PURLIN SUPPORTS
(IF REQUIRED)
COLLAR TIE
END PURLIN SUPPORTS
The collar tie spans horizontally across the outside of the internal gable portal frames. It aligns with the top of the hip rafters, so that the front roof sheets can run continuously over the rectangularend rafter, front purlin and the collartie.
Again pre-drill first through the double flange material with one large 14 x 95 hex head self drilling screw at each end, and fasten to side of gable rafters.
End purlin supports (68mm purlins) are only required if indicated in the drawings supplied. End purlin supports span between the collar tie and the end frame and are to be fastened in place using the 68mm purlin bracket before front purlin/s are screwed in place.
If only one end purlin support is required fasten one purlin bracket mid-span of collar tie and a second mid­span of the end frame (inline with the top of 120 end rafter) using two 10 x 16 hex head self drilling screws per bracket (Figure 16). If two end purlin supports are required fasten brackets at third points along both collar tie and end rafter (ie, 2 along collar tie and 2 along end rafter, Figure 17).
Measure, cut and mitre end purlin supports to fit flush between collar tie and end frame ensuring double flange is on top. When two end purlin supports are required legs on purlin brackets may need to be bent inward or outward slightly to accommodate angle between end purlin supports and frame.
Fasten end purlin supports in place using two 10 x 16 hex head self drilling screws per bracket per side of end purlin support. Cut (and mitre if necessary) front purlin/s to span between end purlin supports. 68mm purlin brackets are to be fastened to end purlin supports where they meet front purlin/s and front purlin/s are screwed in place.
This procedure applies to both ends of the Dutch
Gable unit.
Note :
CONCRETE REMAINING FOOTINGS (IN CONCRETE FOOTING)
GUTTER ASSEMBLY
Once the carport frame is complete concrete the remaining footings. Only concrete the galvanised tube footing stumps.
The concrete should be finished slightly raised towards the column, ensuring water runs away from the column, see figure 11.
If concrete or soil is in permanent contact with the colorbond columns, corrosion will result in the base of the colored column. Refer to the "Selection, Use and Maintenance of Stratco Steel Products" brochure for complete details ofmaintenance requirements.
(a) Measure and cut gutters to the appropriate length ( ie back length of gutter should equal outside frame dimensions + 30mm). Rivet and silicone seal.
(b) Notch hole in gutter and insert downpipe pop so that downpipe is in line with a portalcolumn.
If your column footings are in ground you would have installed your portal frames with a slight fall towards downpipe end. Ensure that the gutter is notched at the right end.
However if you are bolting the footings on to existing concrete slab, and there is a slight fall in the slab ensure that the downpipe is at the lower end of the slab to help the water run off). Fasten the pop in place using rivets and silicone seal.
(c) Cut 70 mm long metal strips from band supplied. Pop rivet these tags to the top of the eaves purlins and end frame rafters at 1200 mm centres. Rivet the back lip of the gutter to these tags, ensuring the back face of the gutter is held vertical as shown in Figure 18. Rivet and silicone seal.
Note:
Note:
Important Note:
16
COLLAR TIE
ONE END PURLIN SUPPORT
COLLAR TIE
END PURLIN
SUPPORT
END PURLIN
SUPPORT
FRONT
PURLIN
END FRAME
68mm PURLIN BRACKET
2 (10 X 16 HEX HEAD SELF
DRILLING SCREWS)
THROUGH BOTH SIDES
17
COLLAR TIE
TWO END PURLIN SUPPORTS
COLLAR TIE
END PURLIN
SUPPORT
END PURLIN
SUPPORTS
FRONT PURLIN
END FRAME
68mm PURLIN BRACKET
2 (10 X 16 HEX HEAD SELF
DRILLING SCREWS)
THROUGH BOTH SIDES
b) Cut triangular gable infill panels (from the rectangular panel provided ), to fit the vertical gable frames located at each end of the Dutch gable roof. Paint the panels to the desired colour before installing. Rest the panels on the weather strip flashing. Fasten panels onto adjoining rafters through the top groove using 12x 35 roofing screws spaced at 1000 mm centres.
c) Hip Capping: Attach the small lengths hip capping to cover hip rafter seams, and mitre to fit the gutter corner.
d) Front and Rear Barges: The front and rear barge caps are fixed to the crest of the CGI roof and front of the gable infill panel. Mitre flashing to overlap weather strip and hip cap so as to give a neat water tight finish at the Dutch gable junction. Silicone joint if necessary.
e) If ordered, fix decorative strips todutch gable infill panel.
f) Gable Spires (Finials): If decorative gable spires are desired, nail the spire bracket to the back of the wooden spire, and rivet in position at the top of the ridge.
g) Ridge Cap: The ridge flashing can now be attached. The ridge should finish flush with the end of the carport, overlapping the front and rear barge capping to provide a weather proof seal.
20
HIP FLASHINGHIP FLASHING
WEATHER
STRIP
WEATHER
STRIP
RIDGE CAPRIDGE CAP
BARGE CAPBARGE CAP
PANEL
STRIPS
PANEL
STRIPS
GABLE SPIRE WITHGABLE SPIRE WITH CONNECTION BRACKETCONNECTION BRACKET
INFILL
PANEL
INFILL
PANEL
FIX FLASHINGS AND INFILL PANELS
Refer to Figure 20 for all flashing positions. In general fasten all flashings using 3 mm pop rivets at approximately 600 mm centres. However when fixing flashings to the infill panels use split-tail rivets.
a) Dutch Gable Weather Strip: Position flashing along collar tie member with leading edge resting on top of roof sheets. Notch flashing to fit around gable rafters and fasten with pop rivets.
TYPE 12x35 ROOFING SCREWS (CREST FIX)TYPE 12x35 ROOFING SCREWS (CREST FIX)
**USE 5 SCREWS PER ROOF SHEET FOR EDGE**USE 5 SCREWS PER ROOF SHEET FOR EDGE
FIXING & 3 SCREWS PER ROOF SHEET FORFIXING & 3 SCREWS PER ROOF SHEET FOR
INTERNAL FIXING**
LAYING DIRECTIONLAYING DIRECTION
LAP
ALIGN WITH OUTER EDGE OF REAR PORTAL
ALIGN WITH OUTER EDGE OF
REAR PORTAL
19
ROOF SHEETING
Begin sheeting the internal framework of the carport roof with the large CGI sheets, allowing for a 40 mm overhang at the eaves into the gutter (see Figure 19). Always have the lap joint facing away from the prevailing wind direction on all carport roof faces. Lap final sheet to fit last span. Position, mark and cut triangular sheets for sides of Dutch gable roof section.
triangle offcuts are re-used on the opposite side of roof, so make sure the cuts are clean and accurate. Make sure offcuts are positioned correctly before laying the longer sheets, sothat capping direction can be determined.
Crest fix CGI sheeting with 12 x 35 Roofing Screws using 5 per sheet for end spans and 3 per sheet for internal spans. Work from one side of the structure to the other, marking and cutting triangular sheets as appropriate. Pan fix the triangular sheets to the hip rafter with 10 x 16 hex head self drilling screws.
Sheet the front and rear faces of the Dutch gable roof. Crest fix the sheets and triangular offcuts at the end rafter and front purlin locations. Pan fix with 10 x 16 hex head self drilling screws at collar tie and hip rafter locations.
Attach the gutter straps at 1200 mm centres by crest-fixing to roof sheets with 10 x 16 Screws. Construct two 85 mm downpipe offsets from the downpipe lengths supplied and attach to pops with rivets. Fasten the downpipes and straps to the adjoining column.
Note:
STEEL STRIP RIVETED AT
1200 MM INTERVALS TO
EAVES PURLIN AND GUTTER
18
RAFTER
EAVES
PURLIN
COLUMN
GUTTER
EAVES PURLIN CONNECTED
TO BRACKET USING 2 COLOURED
(10 x 16 HEX HEAD SELF
DRILLING SCREWS)
Issued: 29/08/2001
HELPFUL TIPS
MAINTENANCE
Leave plastic coating on members until they are about to be fastened to the structure. This will help prevent scratching of the colorbond finish.
Sweep the roof and clean gutters after the completion of work. Ensure any swarf andrivet stubs are removed as they can cause unsightly rust stains.
Leave bracing struts in position until structure is complete and concreted in. This stabilises the structure and holds it square during construction.
Double check all measurements and drilling locations before proceeding.
Regularly check framework for squareness and vertical alignment to make sure it hasn't moved during construction.
Regular washing or hosing of the inside and outside of your Stratco Heritage Outback will ensure it looks its best at all times. Refer to the "Selection, Use and Maintenance of Stratco Steel Products" brochure for complete details of maintenance requirements.