HF Series Generators
SPECIAL INSTRUCTIONS FOR CAPACITORS COMPACT GENERATORS
(WITH CAPACITOR CHARGER BOARD A3517--02)
The Installation process depends on Generator and System configuration. This document applies to installation of Capacitors Compact Generator.
Installation
THIS GENERATOR IS PERMANENTLY CONNECTED TO THE POWER LINE THROUGH A LINE PLUG. IT IS POWERED ON UNLESS THE SAFETY SWITCH INSTALLED IN THE ROOM ELECTRICAL CABINET IS OFF. WHEN THE UNIT IS POWERED, THE NEON (GREEN) LOCATED ON THE TRANSFORMER 6T2 IS ON.
KEEP THE PROTECTION COVERS IN PLACE ALL THE TIME, ONLY REMOVE THE COVERS TO PERFORM SERVICE OPERATIONS. INTERNAL PARTS (CAPACITOR OF HV INVERTER, STORAGE CAPACITORS MODULE, LINE FUSES, DC BUS FUSES, ETC.) CAN BE PERMANENTLY POWERED ON AND HAVE THE FULL VOLTAGE POTENTIAL OF THE CAPACITORS (APPROX. 800 VDC), ALTHOUGH THE UNIT IS DISCONNECTED FROM THE LINE OR THE CONTROL CONSOLE IS OFF. USE CAUTION WHEN WORKING IN THIS AREA.
1
HF Series Generators
Installation
SECTION 1 UNPACKING AND INSTALLATION
The generator is shipped in one box to facilitate transport and installation.
Upon receipt of the X-ray unit and associated equipment, inspect all shipping containers for signs of damage. If damage is found, notify the carrier or his agent immediately.
1.1 CAPACITORS POWERED COMPACT GENERATORS
1. Open the shipping box, then move away the Control Console, Interconnection Cables, Cabinet Cover and other furnished parts. Do not discard any packing material such as envelopes, boxes, bags until all parts are accounted for as listed on the packing list.
2. Remove the packing material from the pallet.
3. Remove the Generator Cabinet from the shipping pallet and place it near
4. When the equipment is unpacked, verify that all items on the customer
5. Check the part numbers / serial numbers of each component with its
Illustration 1-1 Capacitors Compact Generators
to its site in the room. At least two people are required for this operation.
order are present, and the hardware and internal wiring is secure.
identification labels, and inspect all pieces for visible damage. If any damaged parts are found, repair or order replacements to prevent unnecessary delay in installation.
2
HF Series Generators
Installation
6. Usually Generator Cabinet stands freestanding. Seismic areas and other conditions require to make firm the Generator Cabinet to the floor through the mounting holes on the bottom.
In some cases due to transport safety requirements, the HV Transformer is shipped out of the Generator Cabinet. Install the HV Transformer inside the Cabinet (upper area) and secure it with the respective anchors or plates, then connect the following cables from the Power Module to the corresponding terminals on the HV Transformer:
G P2-Shield (2 thin wires), P1 and P3. Take care to connect these
cables to the stud-brass terminals, use two wrenches to tighten the nuts and avoid twisting the studs.
G Ground wire to Ground stud.
G Connector J1.
THE HV TRANSFORMER HAS TO BE SECURED WITH ITS ANCHORS OR PLATES INSIDE THE CABINET. OTHERWISE P1, P2 AND P3 STUDS MAY BE IN CONTACT WITH THE CABINET FRAME AND PRODUCE A SHORT-CIRCUIT.
7. Control Console can be freestanding, wall supported or mounted on an optional Pedestal. Console is provided with a several mounting holes on the bottom for anchoring to the Pedestal or another support.
Console C PU Boards and AEC Control Board can be located inside the Console (standard) or inside the Generator Cabinet (for Serial communication).
8. When a Pedestal is used, secure the Pedestal to the floor through the anchoring holes on its base and place the cover base. Assemble the Console to the Pedestal through the mounting holes on the bottom of the Console.
9. When the Console is wall supported, secure the support to the wall and assemble the Console to the support through the mounting holes on the bottom of the Console.