Steamist SMP-12, SMP-15 Electrical Installation Instructions

Page 1
Electrical Installation Instructions
®
®
C
US
Steambath Generators Models: SMP-12 and SMP-15
Important: Locate Publication No. 199 “Steam Bath Important Safety Instructions”. This publication includes a Warning label that the contractor must install on the wall near the entrance to the steam room in a highly visible location. This label and its additional safety information are packaged with the generator in the envelope containing the installation
!
instructions. If it is lost or missing contact Steamist (201-933-0700) for a replacement Publication No. 199. This publica­tion along with all documents must be left with the owner.
NOTE: A “TSC series control is required to operate the "SMC" generator.
The Steamist “SMP” Generator operates with only “TSC” series controls mounted inside and an optional TSX control located outside the steamroom. It’s small enough in size to be tucked away using very little space in a vanity, closet, or basement, but large enough to provide steam for most residential baths.
The Steamist “SMP” Steambath Generator comes factory assembled, carefully wired and tested.
1. Pre-Installation
a) Proper electrical supply (208 or 240 Volt): See rating
label on Steam Generator and Chart on page 4. Determine proper size of wire, voltage, amperage, and phase for the Steam Generator. 90°C copper wire is required for generator connection.
b) In-line fuse/circuit breaker required: Fuse/circuit breaker
to be installed must be sized in accordance with chart on back page. Do NOT install a GFI (Ground Fault Interrupter) to this equipment (per article 210-8 in the National Electric Code).
c) Route power supply cable to the location where the
Steam Generator will be installed (before walls are closed).
2. Electrical Rough-in
a) Route appropriate power cable to the location the Steam
Generator will be installed. If receptacle is desired, mount the box for the receptacle near the location of the Steam Generator.
NOTE: The plug and receptacle require a rating of no
less than 250V and proper amperage. Refer to chart on page 4 for amperage rating.
After the walls are complete, the Steam Generator and
Control can be wired.
3. Steam Generator Electrical Installation
WARNING: All power to the Steam Generator must be
turned off.
a) Remove the two screws holding the electrical access
cover and remove cover.
b) Locate the supply line knockout. Mount proper strain
relief into knockout hole.
c) Strip back power cable’s outer insulation jacket
eight inches and insert into Steam Generator. Strip back insulation ½" from the three (3) incom­ing wires (two power and one ground).
d) Insert ground wire into grounding lug located
on the right side of the electrical compartment and secure.
CAUTION: Be sure the ground wire does not come in contact with a live electrical part.
e) Locate the terminal/fuse block in the upper portion
of the electrical compartment. Insert power wires into the power lugs on the front of the terminal/fuse block and secure.
4. Optional Auto Drain Valve Connection
a) Open knockout for Auto Drain Valve conduit
connection.
b) Route flexible conduit from valve to knockout and
secure.
c) Connect two wires from valve to the auto DRAIN
connection J11 on the printed circuit board (see Figure 2).
Figure 1 - Steam Generator
Knockouts for Control Cable
Water Inlet
⅜" Compression
Knockouts for
Electrical Supply Line
Install Upright
and Level
Relief Valve
Optional Auto
Drain Valve
Model AD-900
Fitting
Outlet
¾" Safety
IMPORTANT: The warranty of this product is voided if it is used in a commercial application or for anything other than a residential steambath installation. All electrical connections must be performed by a licensed electrician in accordance with Local and National Electric Codes.
04/18
- 1 -
Pub. No. 231-B
Page 2
Checklist
Electrical Installation Instructions
Models: SMP-12 and SMP-15
Before starting, insure that the conditions of the following checklist have been met:
The proper size Steam Generator has been selected by using the sizing page in the “Full Line Brochure,” “Pricing Guide,” or “The Generator Sizing Guide” in the Residen­tial Systems/Steambath Product Information section of the Steamist website - www.steamist.com.
CAUTION: An improperly sized Steam Generator will NOT produce the amount of steam necessary to reach selected temperature.
The proper voltage Steam Generator has been selected (i.e., 208V or 240V). A 208V Generator operating on 240V will damage the heating element, and a 240V Generator operating on 208V will result in a 25% loss of power.
The Steam Generator is installed in an upright position.
The proper sized 90°C copper wire and circuit breaker have been used.
The circuit breaker is NOT a GFI (Ground Fault Interrupter) type.
The Steam Generator is properly grounded.
The circuit breaker or disconnect switch is on.
Water supply is open to the Steam Generator.
Modular Jacks (Plug control cable into any connector)
Water
Level Probe
Test button
PC Board
Troubleshooting LED’s
Optional Auto
Drain Connection
04/18
- 2 -
Pub. No. 231-B
Page 3
Figure 4 - Typical Installation
The Electrical Instructions must be given to the homeowner for future use.
NOTE: Unit must be wired with 90°C
copper wire in a suitable raceway, or, if local codes allow, provide twist lock plug on a 90°C copper wire cord from genera­tor to a 250V 2-pole, 3-wire grounding receptacle (amperage rating as required).
TSX Auxilary Outside
Control
Electrical Installation Instructions
Models: TSG-12 and TSG-15
Models: SMP-12 and SMP-15
TSC Series Control
Control MUST be installed inside
the Steam room.
Inside Installation
IM
9:31
2
112
SHOWER
STOP
1
2
Control Cable
STEAMSHOWERSTEAM
Route from
Control to Steam
Generator in a
Control should be mounted four
feet from the floor. Select a
location convenient to the
bather but not in a direct line of
Shower or Body Sprays and not
directly above the Steamhead.
¾" conduit.
IMPORTANT: Run the Control Cable through a ¾" conduit. Remove protective cap when making the final connection to Control.
04/18
- 3 -
Pub. No. 231-B
Page 4
Electrical Installation Instructions
Figure 5 - Wiring Diagram
Plug control cable into any connector
J5
H2O HI SEN
J6
H2O LO SEN
SW2
TEST
J9
J10
J12
TEST
S1
1 2 3 4
5 6 7 8
OPTIONS
COM FAIL
SYS OK
SYS FAIL
DS10
WTR1
DRAIN
0.8A 250VAC
DS2
DS3
F3
DS1
DS11
DS13
STEAMIST, INC. ASSEMBLY NO. 007-3427
J1
FILL1
J2
J11
DRAIN
RH1_L1
DS4 DS7 DS8
RH2_L1
RH3_L1
F1 F2
0.5A 250VAC
RH1_L2
RH2_L2
RH3_L2
0.5A 250VAC
Models: SMP-12 and SMP-15
DS9
DS5 DS6
EARTH
J7
EARTH
J8
WHITE
GRAY
Specification Chart
Model
No.
SMP-12
SMP-15
Max. Cu. Ft.
For Area Up To
550
675
Water
Solenoid
Valve
BLUE
BLUE
Optional
Auto Drain
Valve
KW Volt Phase Amps
12
15
240 208 240 208
1 1 1 1
50 58 63 72
GRAY
WHITE
Breaker
Size
60
70 80
90
Water
Level
Probe
TANK
Heating
Elements
90°C copper wire is required for generator connection. Installation shall be in accordance with appli­cable electrical codes.
GN
East Coast Office: 25 E. Union Ave., East Rutherford, NJ 07073 • Tel: 800-577-6478 • Fax: 201-933-0746
®
West Coast Office: Tel: 800-355-6478 • Fax: 661-940-1617
04/18
- 4 -
Pub. No. 231-B