TR MA DE Rev003
STÜBBE GmbH & Co. KG Hollwieser Straße 5 32602 Vlotho Germany Phone: +49 (0) 5733-799-0 Fax: +49 (0) 5733-799-5000 E-mail: contact@stue bb e.com Internet: w ww.stuebbe.com
Subject to technical modifications.
Read carefully before use. Save for future use.
Table of contents
Table of contents
1 About this document ............................... 4
1.1 Target groups .................... ............. 4
1.2 Other applicable documents ................ 4
1.3 Warnings and symbols ..... .................. 5
2 Safety ............................... .................. 6
2.1 Intended use ................................ .. 6
2.2 General safety instructions ................ .. 6
2.2.1 Product safety ................................ 6
2.2.2 Obligations of the operating company . .. .. . 6
2.2.3 Obligations of personnel ..................... 7
2.3 Specific hazards . ............................. 7
2.3.1 Hazardous pumped liquids ........... ....... 7
3 Layout and function ...................... .......... 8
3.1 Marking ............. .......................... 8
3.1.1 Name plate ...................... ............. 8
3.2 Description .... ................................ 8
3.3 Assembly ........................... .......... 8
4 Transport, storage and disposal ........... ....... 9
4.1 Transport ...................................... 9
4.1.1 Unpacking and inspection on delivery . .... . 9
4.1.2 Lifting ....................... .................. 9
4.2 Storage ............................. .......... 10
4.3 Disposal ................................... .... 10
5 Setup and connection .............................. 11
5.1 Preparing for installation ........ ............. 11
5.1.1 Check operating conditions ................. 11
5.1.2 Preparing the installation site .. ............. 11
5.1.3 Surface preparation .......................... 11
5.2 Setting up .............................. ....... 11
5.3 Planning pipelines .......................... .. 11
5.3.1 Specifying supports and flan ge
connections .............. ..................... 11
5.3.2 Specifying nominal widths ................... 12
5.3.3 Designing pipelines .......................... 12
5.3.4 Optimizing changes of cross section and
direction ....... ................................ 12
5.3.5 Providing safety and control devices
(recommended) .............................. 12
5.4 Connecting the pipes ........................ 12
5.4.1 Keeping the piping clean .. .................. 12
5.4.2 Installing the pressure pipe ................ .. 12
5.4.3 Inspection for stress-free pipe
connections .............. ..................... 12
5.5 Electrical connec
5.5.1 Connecting the motor ........................ 13
5.5.2 Check direction of rotation ................... 13
5.6 Performing the hydrostatic test .............. 13
6Operation............................... ............. 14
6.1 Preparing for commi
tion .........................
ssioning .............. ..
13
14
6.1.1 Check downtimes ........................ .... 14
6.1.2 Filling and bleeding ................... ....... 14
6.2 Commissioning ........................... .... 14
6.2.1 Switching on .................................. 14
6.2.2 Switching off .. ................................ 14
6.3 Shutting down the pump .............. ....... 15
6.4 Restoring the pump to service .............. 15
6.5 Operating the stand-by pump ............... 15
7 Maintenance ............................... .......... 16
7.1 Inspections ......... .......................... 16
7.2 Servicing ...................................... 16
7.2.1 Maintenance in accordance with maintenance
schedule .................................. .... 16
7.2.2 Cleaning the pump ........................... 16
7.3 Dismounting ..................... ............. 17
7.3.1 Preparations for dismounting ................ 17
7.3.2 Dismounting hydraulic system .. . .. .. . .. .. . . 17
7.3.3 Dismounting coupling and intermediate
ring ............................................ 18
7.3.4 Dismounting V-rings ..................... .... 18
7.3.5 Dismounting shaft bearing ................... 18
7.4 Replacement parts and return .... .......... 18
7.5 Installing ...... ................................ 19
8 Troubleshooting ............... ..................... 20
9 Appendix ........................................... .. 22
9.1 Replacement parts ........................... 22
9.1.1 Part numbers and design ations .. . .. .. . . . .. . 22
9.1.2 Drawing ETL 20-100 to 65-200 ............. 23
9.1.3 Drawing ETL 80-200 ............ ............. 24
9.2 Technical specifications ...................... 25
9.2.1 Ambient conditions .................... ....... 25
9.2.2 Flange tightening torques ......... .......... 25
9.2.3 Sole plate tightening torques . . . . .. .. . . . .. .. . 25
9.2.4 Tightening torques of casing screws . .. . . . .. 25
9.2.5 Switching frequency ............ ............. 25
9.2.6 Volumetric flow of liq uid medium - minimum
flow rate ....... ................................ 25
9.2.7 Sound pressure level ........................ 26
9.2.8 Installation dimensions and filling
heights ...................... .................. 28
9.3 Maintenance schedule ....................... 29
9.4 Lubrication ....... ............................. 30
9.4.1 Lubricating points ............. ............... 30
9.4.2 Lubricant .................... .................. 30
9.5 Declaration of conformity in accordance with
EC machinery directive ............... ....... 31
2 ETL BA-2018.08.22 EN 300 106
Table of contents
List of figures
Fig. 1 Name plate (example) ....................... 8
Fig. 2 Assembly ....... .............................. 8
Fig. 4 Replacement parts ETL 20-100 to
65-200 .......... .............................. 23
Fig. 5 Replacement parts ETL 80-200 ............. 24
Fig. 6 Installation dimensions and filling
heights ..................... ................... 28
Fig. 7 Lubricating points ............................ 30
List of tables
Tab. 1 Other application documents, purpose and
where found ............................. ..... 4
Tab. 2 Warnings and symbols .................. ..... 5
Tab.3 Measurestobetakenifthepumpisshut
down .......................... ................ 15
Tab. 4 Measures depending on the behavior of the
pumped liquid ............. ................... 15
Tab. 5 Fault/number assignment ...... ............. 20
Tab. 6 Troubleshooting list .......................... 21
Tab. 7 Designation of components according to part
numbers ..... ................................. 22
Tab. 8 Ambient conditions ... ........................ 25
Tab. 9 Flange tightening torques ................... 25
Tab. 10 Sole plate tightening torques ................ 25
Tab. 11 Tightening torques of casing screws . .. .. .. . 25
Tab. 12 Switching frequency ......... ................ 25
Tab. 13 Volumetric flow of liquid medium ............ 25
Tab. 14 Noise level for 2-pole motors
0.25 kW to 1.5 kW ........................... 26
Tab. 15 Noise level for 2-pole motors
2.2 kW to 45 kW ................... ........... 26
Tab. 16 Noise level for 4-pole motors
0.18 kW to 1.5 kW ........................... 26
Tab. 17 Noise level for 4-pole motors
2.2 kW to 11 kW .............................. 27
Tab. 18 Installation dimensions (minimum
dimensions) .. ................................. 28
Tab. 19 Maintenance schedule ............ ........... 29
Tab. 20 Lubricant ...................................... 30
Tab. 21 Lubricant quantities ....................... ... 30
300 106 BA-2018.08.22 EN ETL 3
About this document

1 About this document

This manual:
is part of the e qui pment
applies to all series referred to
describes safe and proper operation during all operating phases

1.1 Target groups

Operating company
Responsibilities: – A lways keep this manual accessible where the device
is used on the system.
– Ensure that employees read and observe this docu-
ment, particularly the safe ty instructions and warnings, and the docume nts which also apply.
– Observe any additional country-specific rules and reg-
ulations that relate to the system.
Qualified personnel, fitter
Mechanics qua lification: – Qualified employees with additional training fo r fitting
therespectivepipework
Electrical qualification: – Qualified electrician
Transport qualification: – Qualified transport specialist
Responsibility: – Read, observe and follow this manual and the other
applicable documents, especially all safety instructions and warnings.

1.2 Other applicable documents

Document/purpose/ Where found
Installation drawing
Dimensions when installed, fitting dimensions, etc.
Resistance lists
Resistance of materials used to chemicals
www.stuebbe.com/pdf_resistance/
300051.pdf
CE decl aration of conformity
Conformity with standards
Data sheet (300 134)
Technical specifications, operating conditions, dimensions
www.stuebbe.com/
pdf_datasheets/300134.pdf
Spare parts list
Ordering spare parts
Sectional drawing
Sectional drawing, part numbers, component designations
Supplier documentation
Technical documentation for parts supplied by subcontractors
Tab. 1 Other application documents, purpose
and where found
Documentation included
(9.5 Declara­tion of conform­ity in accorda­ncewithECm­achinery directi-
ve, Page 31).
Documentation included
Documentation included
Documentation included
4 ETL BA-2018.08.22 EN 300 106

1.3 Warnings and symbols

About this document
Symbol
1., 2., ... Multiple-step instructions
Tab. 2 Warnings and symbols
Meaning
Immediate acute risk
Death, serious bodily harm
Potentially acute risk
Death, serious bodily harm
Potentially hazardous situation
Minor injury
Potentially hazardous situation
Material damage Safety warning sign
Take note of all information highlighted by the safety warning sign and follow the instru ctions to avoid injury or death.
Instruction
Precondition Cross reference Information, notes
300 106 BA-2018.08.22 EN ETL 5
Safety

2 Safety

The manufacturer accepts no liability for damage caused by disre garding any of the documentation.

2.1 Intended use

Only use the pump with suitable media (resistance lists).
Do not use pump for combustible or explosive fluids.
Adhere to the operating limits and size-dependent mini­mum flow rates.
Avoid cavitation: – Open the suction-side fitting and do not use it to regu-
late the flow.
– Do not open the pressure-side fitting beyond the
agreed operating point.
Avoid overheating: – Do not operate the pump while the pressure-side fitting
is closed.
– Note mi nimum flow (Data sheet).
Avoid damage to the motor: – Do not open the pressure-side fitting beyond the
agreed operating point.
– Note the maximum permissible number of times the
motor can be switched on per hour (manufacturer's specifications).
Consult with the manufacturer regarding any other use of the device.
If pumps are delivered without motors, then final assembly as a pump assembly must take place in a ccordance with the provisions of the Machinery Directive 2006/42/EC.
Use the pump only as part of a large system/tool.
Prevention of obvious misuse (examples)
Observe pump limits of use regarding temperature, pres­sure, flow and speed (data sheet).
The power consumption of the pump increases as the spe cific gravity of the pumped fluid increases. Adher permissible specific gravity in order to elimin sibility that the pump, coupling and motor bec loaded (data sheet). A lower specific gravity is permis systems accordingly.
When conveying fluids containing solids, observe the limit values for proportions of solid particles and particle size (Data sheet, technical description).
When using auxiliary plant systems: – Ensure c ompatibility of the operating medium with the
product medium.
– Ensure constant supply of the relevant operating
medium.
Pumps used wi used for foo ing wate
th water as the pumped liquid must not be
dstuffs or drinking water. Use for food or drink-
r only if specified in the data sheet.
sible. Adapt the auxiliary
etothe
ate the pos-
ome over-
The type of installation should be selected only in accor­dance with these operating instructions. For example, the following are not allow ed: – Hanging base plate pumps in the pipe – Overhead installation – Installation in the immediate vicinity of extreme heat or
cold sources
– Installation too close to a wall

2.2 General safety instructions

Observe the following regul ations before carrying out any work.

2.2.1 Product safety

The pump has been built according to state-of-the-art technol­ogy and the recognized technical safety regulations. Never­theless, operation of the pump can still put the life and health of the user or third parties at risk or damage the pump or other property.
Operate the pu m p only if it is in perfect technical condition and use it only as intended, staying aware of safety and risks, and in adherence to the instructions in this manual.
Keep this manual and all other applicable documen ts com­plete, legible and accessible to personnel at all t imes.
Refrain from any pro cedures and actions that would pose a risk t o p ersonnel or third parties.
In the event of any safety-relevant faults, shut down the pump immediately and have the fault corrected by appro­priate personnel.
In addition to the entire documentation for the product, comply with statutory or other safety and accident-preven­tion regulations and the applicable standards and guide­lines in the country where the pump is operated.
-

2.2.2 Obligations of the operating company

Safety-conscious working
Operate the pu m p only if it is in perfect technical condition and use it only as intended, staying aware of safety and risks, and in adherence to the instructions in this manual.
Ensure that the following safety aspects are observed and monitored: – Intended use – S tatutory or other safety and accident-prevention reg-
ulations
– Safety regulations governing the handling of haz-
ardous substances
– Applicable standards and guidelines in the country
where the pump is operated
– Applicable guidelines of the operator
Make personal protective equipment available.
6 ETL BA-2018.08.22 EN 300 106
Safety
Qualified personnel
Make sure all personnel tasked with work on the pump have read and understood this man ual and all other appli­cable documents, especially the safety, maintenance and repair informatio n, before they start any work.
Organize responsibilities, areas of competence and the supervision of personnel.
Ensure that all work is carried out by specia list technicians only: – Installation, repair and maintenance work – Transportation – Work on the electrical system
Make sure that trainee personnel only work on the pump under s upervision of specialist technicians.
Safety equipment
Provide the following safety equipment and verify its func­tionality: – For hot, cold and moving parts: pump safety guarding
provided by the customer
For pumps without capability to run dry: Dry run pro-
tection
For potential electrostatic charging: provide suitable
grounding
Warranty
Obtain the ma nufacturer's approval prior to carrying out any modifications, repairs or alterations during the warranty period.
Only use genuine parts or parts that have been approved by the manufacturer.
Following all work on the pump, refit safety devices in accordance with the instructions and bring into service.
Do not make any modifications to the device.

2.3 Specific hazards

2.3.1 Hazardous pumped liquids

When handling hazardous fluids, observe the safety regu­lations for the handling of hazardous substances.
Use personal protective equipment when carryi ng out any work on the pump.
Collect leaking pumped liquid and residues in a safe man­ner and damage them in accordance with environmental regulations.

2.2.3 Obligations of personnel

All directions given on the pump must be followed (and kept legible), e.g. the arrow indicat ing the sense of rotation an d the markings for fluid connections.
Pump, coupling guard and components: – Do not step on them or use as a climbing aid – Do not use them to support boards, ramps or beams – Do not use them as a fixing point for winches or sup-
ports – Do not use them for storing paper or similar materials – Do not use the hot pump o r motor components as a
heating point – Do not de-ice the pump using gas burners or similar
tools
Do not remove the safety guarding for hot, cold or moving parts during operation.
Use personal protective equipment if necessary.
Only carry out work on the pump while it is not running.
Before all installation and maintenance work, disconnect the motor from the mai ns and secure it against being switched back on again.
Never reach into the suctio n or discharge flange.
300 106 BA-2018.08.22 EN ETL 7
Layout and function

3 Layout and function

3.1 Marking

3.1.1 Name plate

Hollwieser Str. 5 D-32602 Vlotho
Typ: Ser. NO.:
ID. NO.: Mat.: M. Seal:
8
Fig. 1 Name plate (example)
1Pumptype 2 Serial number 3 Ident. number 4 Housing / sealing material 5 Shaft seal information 6 Impeller diameter [mm] 7 Differential head 8Flow
Imp. Ø: Q:
m
3
/h
H:
m

3.3 Assembly

1 2
3 4 5 6
7
13
12
1
11
2
10
9
8 7

3.2 Description

Non self-priming, vertical centrifugal pump Useinopenorclosedunpressuredcontainersorpits/trenches.
Thepumpisdry-runningsafe.
6
5
Fig. 2 Assembly
1 V-ring seal 2 Discharge flange 3 Volute casing 4 Strainer (optional) 5Suctioncup 6Impeller 7Protectiontube 8Shaft 9 Immersion tube 10 Sole plate 11 Shaft bearing 12 Coupling 13 Motor
3 4
8 ETL BA-2018.08.22 EN 300 106

4 Transport, storage and disposal

Transport, storage and disposal

4.1 Transport

The user/owner is responsible for the transport of the pump.
Weight specifications (documents for the particular order)

4.1.1 Unpacking and insp ection on delivery

1. Unpack the pump/pump assembly upon delivery and inspect it for transport damage.
2. Check completeness and accuracy of delivery.
3. Ensure that the information on the name plate agrees with the order/design data.
4. Re port any transportation damage to the manufacturer immediately.
5. Dispose of packaging material according to local regula­tions.
Retain the transport frame for horizontal storage (recom­mended).

4.1.2 Lifting

DANGER
Death or limbs crushed as a result transported items falling over!
Use lifting gear appropriate for the total weight to be trans­ported.
Attach liftin g gear in accordance with the following dia­grams.
Never use the lifting eye of the motor as the attachment point for lifting the enti re pump (the lifting eye of the motor may be used for securing a pumpassemblywithahigh center of gravity against being knocked over).
Do not stand un der suspended loads.
1. Attach lifting gear in accordance with the above diagram.
2. Lift the pump/pump assembly appropriately.
300 106 BA-2018.08.22 EN ETL 9
Transport, storage and disposal

4.2 Storage

DANGER
Death or limbs crushed as a result of the pump overturn­ing!
For vertical storage: – Place pump on a horizontal underground and secure
against overturning.
NOTE
Material damage due to inappropriate storage!
Store the pump properly.
1. Sea l all openings with blind flanges, blind plugs or plastic covers.
2. Make sure the storage room meets the following condi­tions: –Dry – F rost-free – Vibration-free –UVprotected
3. Fo r horizontal storage: – Protect pump against sagging by means of proper sup-
port.
4. Rotate the pump shaft twice a month.
5. Make sure the shaft and bearing change their rotational position in the process.

4.3 Disposal

Plastic parts can be contaminated by poisonous or radioac­tive pumpe d liquids to such an extent that cleaning will be insufficient.
WARNING
Risk of poisoning and environmental damage by the pumped liquid or oil!
Use personal protective equipment when carrying out any work on the pu mp.
Prior to the disposal of the pump: – Collect and d amage any escaping pumped liquid or oil
in accordance with local regulations.
– Neutralize residues of pumped liquid in the pump. Remove plastic parts and damage them in accordance with
local regulations.
Dispose of the pump in accordance with local regulations.
10 ETL BA-2018.08.22 EN 300 106
Loading...
+ 21 hidden pages