1. Safety information
Safe operation of the unit can only be guaranteed if it is properly installed,
commissioned and maintained by a qualified person (see Section 1.10) in compliance
with the operating instructions. General installation and safety instructions for
pipeline and plant construction, as well as the proper use of tools and safety
equipment must also be complied with.
1.1 Intended use
Referring to these Installation and Maintenance Instructions, name-plate and
Technical Information Sheet, check that the product is suitable for the intended
use / application.
The products listed below comply with the requirements of the Pressure Equipment
Directive (PED) and carry the mark. The products fall within the following
Pressure Equipment Directive categories:
Product
Group 2
Gases
Flash vessel, FV6 and FV8 Category 2
Flash vessel, FV12, FV15 and FV18 Category 3
i) The products have been specifically designed for use with steam which is in
Group 2 of the above mentioned Pressure Equipment Directive. The products’
use on other fluids may be possible but, if this is contemplated, Spirax Sarco
should be contacted to confirm the suitability of the products for the application
being considered.
ii) Check material suitability, pressure and temperature and their maximum and
minimum values. If the maximum operating limits of the product are lower than
those of the system in which it is being fitted, or if malfunction of the product
could result in a dangerous overpressure or over temperature occurrence,
ensure a safety device is included in the system to prevent such over-limit
situations.
iii) Determine the correct installation situation and direction of fluid flow.
iv) Spirax Sarco products are not intended to withstand external stresses that may
be induced by any system to which they are fitted. It is the responsibility of the
installer to consider these stresses and take adequate precautions to minimise
them.
v) Remove transit protection covers from all connections before installation.
1.2 Access
Ensure safe access and if necessary a safe working platform (suitably guarded)
before attempting to work on the product. Arrange suitable lifting gear if required.