This manual describes the transport, installation and commissioning of SMA central inverters of the
following types:
• Sunny Central 200 (SC 200)
• Sunny Central 250 (SC 250) with the "Protection against chemically active substances" option
• Sunny Central 250 (SC 250)
• Sunny Central 250 (SC 250) with the "Protection against chemically active substances" option
• Sunny Central 250HE (SC 250HE) with the "High Efficiency" option
• Sunny Central 350 (SC 350)
1.2 Target Group
This manual is intended for installers and operators of photovoltaic systems equipped with Sunny
Centrals.
1.3 Additional Information
Keep all manuals for the Sunny Central and for the installed components together with the system
documentation. They must be accessible at all times.
You will find further information on the Sunny Central in the download area of www.SMA.de/en.
Among other things, the download area contains the following items:
• Sunny Central Installation Requirements
• Sunny Central Certificates
• Additional information on other options (e.g. GFDI)
Installation GuideSC20_25_35-IEN0945217
Page 8
Notes on this ManualSMA Solar Technology AG
1.4 Symbols Used
The following types of safety instructions and general information appear in this document as
described below:
DANGER!
DANGER indicates a hazardous situation which, if not avoided, will result in death or
serious injury.
WARNING!
WARNING indicates a hazardous situation which, if not avoided, could result in death or
serious injury.
CAUTION!
CAUTION indicates a hazardous situation which, if not avoided, could result in minor or
moderate injury.
NOTICE!
NOTICE indicates a situation that can result in property damage, if not avoided.
Information
Information provides tips that are valuable for the optimal installation and operation of
your product.
8SC20_25_35-IEN094521Installation Guide
Page 9
SMA Solar Technology AGSafety
2 Safety
2.1 Appropriate Usage
Sunny Central is a central inverter. It feeds solar energy converted via photovoltaics from solar
modules into a low- or medium-voltage grid.
Principle of a grid-connected solar power system with a Sunny Central
A Photovoltaic generatorB Sunny CentralC Low voltage or medium
voltage grid
Sunny Central 200 / 250 / 350
Sunny Central 200 / 250 / 350 contains a low voltage transformer and feeds i nto low volt age grids.
Sunny Central 250HE
Sunny Central 250HE is a high-efficiency central inverter without its own low-voltage transformer. The
Sunny Central 250HE feed into the medium-voltage grid via a shared medium-voltage transformer.
2.2 Safety Instructions
Faults that affect or limit the safety of the device must be rectified immediately. Unauthorized
modifications and spare parts not recommended by SMA Solar Technology may cause fire, material
damage and electrical shock. Unauthorized personnel must not have access to the devices.
Si gns mus t al way s be att ach ed i n pr omi nen t po siti ons . Da mag ed s igns mus t be rep lace d im med iat ely .
2.2.1 Personnel
Only qualified personnel may work on the Sunny Central. “Qualified” means that the personnel must
have been trained for the activity performed.
The personnel must be familiar with the content of the installation guide and user manual in order to
commission and / or operate the Sunny Central. In particular, the safety ins tructions must be followed.
Installation GuideSC20_25_35-IEN0945219
Page 10
SafetySMA Solar Technology AG
2.2.2 Installation
Observe the installation conditions for the Sunny Central (separate document). The describe what you
must bear in mind when installing the Sunny Central.
An electrical service room is ideal for installation of the Sunny Central, to achieve optimal noise and
fire protection.
The Sunny Central was designed for use in industrial environments in terms of the EMC thresholds
(EMC = Electromagnetic Compatibility).
Note the following points when installing the Sunny Central:
• The inlet and exhaust ventilation systems for the Sunny Central must be separate to any other
ventilation, in order to minimize smoke distribution in case of fire.
• A sufficient escape route must be guaranteed.
• The EMC specifications must be observed (see technical data).
Smoke detector
We recommend that you install smoke detectors in the service room to deactivate the
Sunny Central if smoke develops. Incorporate the smoke detector in the Emergency Stop
circuit.
2.2.3 Special Hazards of Photovoltaic Systems
Photovoltaic systems in particular have some special hazards. They are described below:
• An active power source is connected. Depending on the operating mode, there may be voltage
present from the photovoltaic generator and the Sunny Central. This is especially important to
note when disconnecting particular parts of the system
• As a result of the very high DC voltages, arcing may occur if fuses and plugs are used
incorrectly.
• The short circuit current of the photovoltaic generator is only slightly higher than the maximum
operating current and also depends on irradiation conditions. If a short-circuit occurs in the
system, the available fuses are not guaranteed to switch off.
• A highly complex generator array may be difficult to disconnect if a fault develops (e.g. short
circuit). We recommend additional external DC circuit breakers, which disconnect the inverter,
the main DC lines and the Sunny String-Monitors (DC switches are available as an option).
2.2.4 Working on the Sunny Central
Work may only be performed on the Sunny Central when it is disconnected. Observe the following
safety rules when working on the Sunny Central:
1. Disconnect
2. Ensure that the device cannot be reconnected
3. Ensure that no voltage is present in the system
4. Ground and short-circuit if necessary
10SC20_25_35-IEN094521Installation Guide
Page 11
SMA Solar Technology AGSafety
5. If necessary cover or protect against accidental contact with any voltage-carrying components.
The individual safety rules are listed in greater detail below:
Disconnection (in the event of team connection: both team members must be
disconnected)
If the Sunny Central is running with team connection, disconnect both the team leader and the team
device. The following list shows which sources of voltage must be be disconnected:
1. Grid voltage for grid feeding (AC main switch)
2. Gri d vo lta ge fo r th e su ppl y the sys tem 's p owe r su pply (if the system draws its power supply from
external sources)
3. DC voltage from the photovoltaic generator
– Unplug the DC fuses to disconnect the photovoltaic generator. The DC fuses of the two poles
are behind the protective covers. Remove the protective covers to pull the DC fuses. Never
remove both covers simultaneously. After removing the fuses on one pole, attach the covers
again.
– Pull the DC input fuses only when the load is off to prevent dangerous arcing. Use a clip-on
ammeter to measure whether the DC input is off-load. The DC input fuses may only be
re mov ed w ith per son al s afe ty e qui pme nt a nd a fus e gr ip. The re a re t hre e wa ys t o di sco nne ct
the DC voltage from the photovoltaic generator:
– Pull the internal DC input fuse
– Pull the external DC input fuse (if a Sunny Main Box is used)
– Via an external circuit breaker (if available)
4. DC voltage for team connection (if team connection is used)
5. Additional external voltage (e.g. emergency shut-off)
Even deactivated Sunny Central units may contain voltages which are dangerous to the touch. After
deactivating the Sunny Central, wait at least 5 minutes until all capacitors are discharged before
starting to work on the Sunny Central.
When the DC fuses are inserted in the Sunny Central (on both team members if team connection is
used), there is a reverse voltage on the DC main and sub-distributors.
Disconnecting system parts without danger
We recommend additional DC circuit breakers for the Sunny Central, the main DC lines
and Sunny String-Monitors. DC circuit breakers allow system parts to be disconnected
without danger.
Ensure that the device cannot be reconnected
Ensure that the Sunny Central cannot be reactivated.
Ensure that no voltage is present in the system
Ensure that all internal and external sources of voltage are disconnected.
Installation GuideSC20_25_35-IEN09452111
Page 12
SafetySMA Solar Technology AG
Ground and short-circuit the unit if necessary (not on the DC side)
Ground and short-circuit the AC side. The DC side does not have to be grounded.
If necessary, cover or shield any adjacent live components
Cover or shield all adjacent live parts to prevent accidental contact.
2.2.5 General Information
Overvoltage and lightning protection
The devices have internal overvoltage protection on the AC and DC sides. However, the desired
protection level can only be achieved if a lightning protection area concept exists for the installation
building as per DIN VDE 0185-4, i.e. lightning conductors or combined surge and lightning
conductors (not included in delivery) are available at, among other locations, the building’s entrance
(transfer lightning protection area LPZ 1).
The combined overvoltage and lightning protection for the analog inputs can be ordered as an
option.
Emergency Shut-off
In photovoltaic systems with more than one Sunny Central, or additional external emergency shut-off
switches, the emergency-shut off circuits must be connected to one another. Only one Sunny Central
may supply the emergency shut-off circuit with voltage. For further information on connecting external
emergency shut-off switches, see section 6.10”Connecting the Emergency Shut-off” (page71).
Ear Protection
The device fans and the power unit create elevated levels of operating noise. In addition to this, a
fault in the device can lead to very high sound levels. While in the service room, we recommend that
you wear ear protection.
Burns
Immediately after disconnecting the Sunny Central, depending on the operating conditions, certain
components can be very hot (e.g. fuses, transformer core, sine wave filter, heatsinks etc.).
When working on hot components, we recommend that you wear gloves.
Torque
The circuit diagram contains a torque list. It provides details on all relevant torques. Observe these
torques when tightening the individual threaded connections. You can also ask Sunny Central Service
what the respective torques are.
Fuse Grip
A fuse grip is supplied with the Sunny Central for removing and inserting the fuses when the power
supply is disconnected. Additional safety equipment is required if fuses are not removed or inserted
when the power supply is disconnected.
12SC20_25_35-IEN094521Installation Guide
Page 13
SMA Solar Technology AGScope of Delivery
3 Scope of Delivery
3.1 Standard Scope of Delivery Sunny Central 200 / 250 / 250HE
PositionNumberName
A1DC- / inverter cabinet
B1AC cabinet
C1Document set
• Installation guide
• User manual
• Variant circuit diagram
• Commissioning report
D1Documentation of the optional insulation monitoring (Bender)
E1Fuse grip
F2Terminal profile 3 m
A1DC- / inverter cabinet
B1AC cabinet
C1Document set
• Installation guide
• User manual
• Variant circuit diagram
• Commissioning report
D1Documentation of the optional insulation monitoring (Bender)
E1Fuse grip
F2Terminal profile 3 m
G1Switch cabinet installation set
• Vertical baying clamp
• Angle bracket TS corner
• Horizontal baying clamp
• Baying quick connector
H16OBO cable clamp 16 – 22 mm
H212OBO cable clamp 28 – 34 mm
H324OBO cable clamp 22 – 28 mm
I16OBO clamping saddle
You can identify the Sunny Central using the type label. The type label is located on the inside of the
door of the Sunny Central.
The serial number (A) is printed on the type label and on the front side of the Sunny Central.
3.3.1 Check for transport damage
Ch eck the dev ice pac kag ing and t he S unn y Ce ntr al f or a ny po ssi ble damage and compare the scope
of delivery with the delivery documentation. In the case of damage to the device or unclear delivery
contents, immediately contact SMA Solar Technology.
16SC20_25_35-IEN094521Installation Guide
Page 17
SMA Solar Technology AGScope of Delivery
3.3.2 Storage
The transport packaging provides sufficient protection against moisture and damage when
transporting the Sunny Central.
Notice!
Penetrating moisture can damage the Sunny Central.
• The storage condition requirements are the same as the conditions for operating the
Sunny Central.
• Storing the Sunny Mini Central in packaging.
• Avoid extended storage.
• If stored for an extended period, remove moisture and soiling.
• Before commissioning, contact Sunny Central Service if the storage period is longer
than one year.
Installation GuideSC20_25_35-IEN09452117
Page 18
InstallationSMA Solar Technology AG
4 Installation
This section describes the transport options for the Sunny Central and the requirements of the
installation site.
Different transport and installation conditions apply to each Sunny Central. They are available in the
SMA Solar Technology download area.
Identifying cabinet units
The Sunny Central consists of 2 switch cabinets. If multiple Sunny Central units are
delivered, only install switch cabinets with the same serial number together.
4.1 Installation site requirements
Floor
The floor must guarantee solid and safe positioning of the Sunny Central. The floor must provide the
load-carrying capacity necessary to cope with the weight of the Sunny Central. Do not install the
Sunny Central on a slope. Level any unevenness in the floor.
Wall Clearances
When installing the Sunny Central, comply with the corresponding wall clearances for minimum
passages, escape routes and ventilation. The "Sunny Central Installation Requirements" (separate
document) contain the respective minimum clearances.
Inverter Protection Rating / EMC / Sound Levels
The Sunny Central is suitable for installation in dry areas with low dust levels. The Sunny Central was
designed for use in industrial environments in terms of the EMC thresholds (EMC = Electromagnetic
Compatibility) and sound levels.
4.2 Electrical Service Room
When installing and connecting the Sunny Central central inverter, observe the requirements for
electrical operating rooms, installing high-voltage current plants up to 1000 V, and the requirements
for passage widths and escape routes.
4.2.1 Minimum Passage Width
Note the following points for the escape routes in electrical service rooms:
• When the switch cabinet door is opened as far as possible, a minimum passage of 500 mm
(escape route) must remain.
• I n or der to c omp ly w ith the m ini mum pas sag e wi dth , if two swit ch cabinets are installed opposite
one another (e.g. in a station building), only one of the switch cabinets may be opened.
18SC20_25_35-IEN094521Installation Guide
Page 19
SMA Solar Technology AGInstallation
4.2.2 Design
The following illustration is a schematic of the layout of an electrical service room with a
Sunny Central 250HE.
4.3 Ventilation
An incoming air supply is required to cool the Sunny Central. In order to guarantee safe operation
and the maximum of feed-in power, the permitted ambient temperature must be observed.
The required air is drawn through the switch cabinet doors and is blown out via the top or the rear
wall of the cabinet unit depending on the Sunny Central model. This means that the devices can be
installed right next to one another. See the "Sunny Central Installation Requirements" (separate
document) for the air requirements as well as appropriate wall clearances. Filters are installed at the
air inlet openings. They clean the inlet air.
If the volu me of air at the installat ion sit e of the Sun ny Cent ral is insufficient, then on-site measures must
be taken to provide greater quantities of air (ventilation grilles, blowers, fans, etc.).
The inlet air must satisfy the requirements of classification 3S2. If a Sunny Central is used in a
chemically-active environment, the inlet air must satisfy the requirements of classification 3C1.
The central inverter can be operated in relative humidity from 15 ... 95 %.
Installation GuideSC20_25_35-IEN09452119
Page 20
InstallationSMA Solar Technology AG
The heat generated by the Sunny Central (exhaust air) must be dissipated to comply with the
maximum permitted ambient temperature. We recommend routing the exhau st air ( air duc t) out o f the
electrical service room.
Overview of the Air Inlets and Outlets
The positions of the air outlets differ depending on the Sunny Central model selected. During
installation, ensure that the air inlets and outlets are not covered.
Air Routing for the "EVR" Option
If the "EVR" option was selected, the exhaust air cannot be routed through the top of the
Sunny Central.
NOTICE!
Overheating impairs the operation of the Sunny Central.
Ensure that the Sunny Central is sufficiently cooled:
• Provide the required air volume for the Sunny Central.
• Clean the ventilation openings (filter pads) and the exhaust air bars at regular
intervals. See the Sunny Central maintenance manual for the exact cleaning intervals.
• Route the exhaust air separately from the individual cabinet units (air outlets of the
power units and the switch cabinet) to prevent thermal short circuits.
If routing the exhaust air through the rear wall of the Sunny Central, the exhaust air can be routed
directly out of the building via a weatherproof grille installed on-site in the building wall. The Sunny
Central can then be set up with the rear of the cabinet directly against the opening in the building
wall. Remove the finger guard from the fan openings and secure a seal or frame-like air hood to the
building wall.
DANGER!
Loss of limbs!
If the exhaust air is routed directly out of the building, the rotor blades of the fan are not
protected against contact.
• When cleaning the ventilation duct, switch off the Sunny Central.
• Do not start to clean the ventilation duct until the rotor blades of the fan have come
to a stop.
20SC20_25_35-IEN094521Installation Guide
Page 21
SMA Solar Technology AGInstallation
The following illustrations show examples of where the individual air inlets and outlets are located.
Sunny Central 200 air inlets
Sunny Central 200 air outlets
The position of the air outlets of the Sunny Central 200 depends on the variant. Depending on the
variant, the air outlets are on the rear or in the top of the Sunny Central.
Air outlets on the rearAir outlets in the top
Installation GuideSC20_25_35-IEN09452121
Page 22
InstallationSMA Solar Technology AG
Sunny Central 250 air inlets
Sunny Central 250 air outlets
The position of the air outlets of the Sunny Central 250 depends on the variant. Depending on the
variant, the air outlets are on the rear or in the top of the Sunny Central.
Air outlets on the rearAir outlets in the top
22SC20_25_35-IEN094521Installation Guide
Page 23
SMA Solar Technology AGInstallation
Sunny Central 250HE air inlets
Sunny Central 250HE air outlets
The position of the air outlets of the Sunny Central 250HE depends on the variant. Depending on the
variant, the air outlets are on the rear or in the top of the Sunny Central.
Air outlets on the rearAir outlets in the top
Installation GuideSC20_25_35-IEN09452123
Page 24
InstallationSMA Solar Technology AG
Sunny Central 350 air inlets and outlets
Supply airExhaust air
4.4 Transport Options
Sunny Centrals can be transported with a forklift, lifting cart or a crane fork. They consist of two switch
cabinet units, the DC- / inverter cabinet and the AC cabinet.
WARNING!
Danger of crushing if the switch cabinet unit tips over!
The Sunny Central can tip over during
transport if the center of gravity is not in the
middle.
• Only transport switch cabinet units
upright.
• The center of gravity is indicated on the
packaging and on the Sunny Central.
24SC20_25_35-IEN094521Installation Guide
Page 25
SMA Solar Technology AGInstallation
4.4.1 Transporting the Sunny Central using a Lifting Cart or Forklift
1. Use a TX30 torque wrench to remove the front and
rear base covers.
2. Pick up the switch cabinet unit with the lifting cart or
forklift.
3. Transport the switch cabinet unit to the installation
site.
4. Reattach the front and rear base covers.
Installation GuideSC20_25_35-IEN09452125
Page 26
InstallationSMA Solar Technology AG
4.4.2 Transporting the Sunny Central using a Crane
1. Use a TX30 torque wrench to remove the front and
rear base covers.
2. Pick up the switch cabinet unit with the crane fork.
3. Transport the switch cabinet unit to the installation
site.
4. Reattach the front and rear base covers.
26SC20_25_35-IEN094521Installation Guide
Page 27
SMA Solar Technology AGInstallation
4.5 Assembly at the Installation Site
The Sunny Centrals have a high dead weight. Additional anchoring in the floor or in the wall is
unnecessary.
4.5.1 Connecting Switch Cabinets to one Another
Enclosed documentation of the switch cabinet manufacturer
Follow the instructions in the enclosed documentation of the switch cabinet manufacturer to
connect the two switch cabinets to one another. The assembly procedure is described
there.
If you are using a Sunny Central 200 / 250 with the "Protection ag ain st c hem ica lly act ive sub sta nce s"
option, the switch cabinets must be connected to one another as described below.
1. Attach the included sealing material all around the cabinet frame of the AC cabinet.
A Seal material
2. Install the switch units at the installation site.
Installation GuideSC20_25_35-IEN09452127
Page 28
InstallationSMA Solar Technology AG
3. Connect the switch cabinet units at positions A and B with the provided bolts, washers, locking
washers and brackets. Follow the instructions in the enclosed Rittal documentation. The diagram
below shows Sunny Central 250 with the "Protection against chemically active substances"
option.
☑ The switch cabinet units are connected to each other.
28SC20_25_35-IEN094521Installation Guide
Page 29
SMA Solar Technology AGInstallation
4.5.2 Removing the Transport Locks
In some Sunny Centrals, the transformer is fitted with transport locks. They connect the transformer to
the switch cabinet. The following table shows the Sunny Centrals are fitted with a transport lock for
the transformers.
Sunny CentralTransformer transport lock
Sunny Central 200yes
Sunny Central 250yes
Sunny Central 250HEno
Sunny Central 350yes
1. Remove the transport lock bolts (A, B and C).
2. Remove the transport locks.
☑ The transport locks have been removed.
Installation GuideSC20_25_35-IEN09452129
Page 30
Internal Electrical ConnectionsSMA Solar Technology AG
5 Internal Electrical Connections
Circuit diagram and equipment identifier
The exact position of the individual connection points can be determined with the help of
the equipment identifier and the provided circuit diagram. In the front part of the circuit
diagram, you will find an overview with data on the cable number and the respective
connection point.
Electrical connections
For all electrical connections it is imperative that you comply with the supplied circuit
diagram.
The following steps must be taken to make the internal electrical connection:
• Connect the power cables
• Connect the PE connection
• Connect the control cables to the power unit
• Connect the Sunny Central Control to the power unit
• Connect the internal control cables
• Connect the insulation monitoring (optional)
• Fit the internal temperature sensor
• Connect the team cable (optional)
• Connect the EVR resistor (optional)
5.1 Preparatory Work for the Sunny Central 200 / 250 with the
"Protection against Chemically Active Substances" Option
The Sunny Central 200 / 250 units with the "Protection against chemically active substances" option
have an encapsulated design. The two switch cabinet units are separated by a side wall. There are
two sliding plates with a clamping felt in the side wall. The data and control lines are routed through
the sliding plates which connect the DC cabinet to the AC cabinet. The procedure is described below.
The following figures show the Sunny Central 250 with the "Protection against chemically active
substances" option as an example.
30SC20_25_35-IEN094521Installation Guide
Page 31
SMA Solar Technology AGInternal Electrical Connections
1. Open the knurled nuts on the sliding plates (A).
2. Move the sliding plates up or down.
3. Route the following wires through the clamping felt into the AC cabinet.
–Control lines
(see section 5.4”Connecting the Control Lines on the Transfer Terminal Strip” (page42)).
–Data lines
(see section 5.5”Connecting the Sunny Central Control to the Power Unit” (page43)).
– Internal control lines X8 and X9
(see section 5.6”Connecting the Internal Control Lines” (page44)).
– Insulation monitoring cable (optional)
(see section 5.7”Connecting Insulation Monitoring (optional)” (page45)).
– Temperature sensor
(see section 5.8”Installing the Internal Temperature Sensor” (page46)).
☑ The individual lines are routed through the clamping felt into the AC cabinet. They are
required in the following steps.
Notice!
Air permeable cable ducts cause corrosion in the Sunny Central.
• Press the sliding plates together with sufficient force.
• Tighten the knurled nuts on the sliding plates.
4. Connect the control cables to the transfer terminal strip.
☑ The control cables are connected.
Installation GuideSC20_25_35-IEN09452131
Page 32
Internal Electrical ConnectionsSMA Solar Technology AG
5.2 Connecting the Power Cables
5.2.1 Sunny Central 200 / 250 / 250HE
The power cables connect the power units in the DC / inverter cabinet with the sine wave filter in the
AC cabinet.
The power cables (U1, V1, W1) are already connected to the sine wave filter and cut to length, so
that the allocations on the power units are clear.
The following diagram shows the connection points of the power cables on the power unit of the
Sunny Central 250.
APower unit connection lugs
Procedure for power cabling:
1. Unscrew the protective cover of the power unit.
☑ The protective cover has been removed. The connections on the power unit are now
accessible.
2. Route the cables through the open side wall above the cabinet base plates into the DC- cabinet.
3. Use cable ties to bind the cables in the base of the switch cabinet.
4. Connect the left power unit first. Hold the bolts when tightening the nuts.
32SC20_25_35-IEN094521Installation Guide
Page 33
SMA Solar Technology AGInternal Electrical Connections
DANGER!
Danger of fire.
Incorrect connection of the power units can cause fires.
• Observe the sequence when connecting the power units.
4. Bind the power cable with cable ties. If you do not do so, pointed or sharp metal edges could
damage the insulation of the cable.
☑ Power cabling is complete.
5. Reattach the protective cover to the power unit.
☑ The protective cover has been fitted.
Installation GuideSC20_25_35-IEN09452135
Page 36
Internal Electrical ConnectionsSMA Solar Technology AG
5.2.3 Sunny Central 200 / 250 with the "Protection against
chemically active substances" option
The power cables connect the power units in the DC / inverter cabinet with the sine wave filters in the
AC cabinet. For the Sunny Central 200, 3 power cables must be connected and 6 are required for
the Sunny Central 250.
The power cables (U1, V1, W1) are already connected to the sine wave filter and cut to length, so
that the allocations on the power units are clear.
The following diagram shows the connection points of the power cables on the power unit of the
Sunny Central 250.
APower unit connection lugs
Procedure for power cabling:
1. Unscrew the protective cover of the power unit.
☑ The protective cover has been removed. The connections on the power unit are now
accessible.
36SC20_25_35-IEN094521Installation Guide
Page 37
SMA Solar Technology AGInternal Electrical Connections
2. Route cables 2W1, 2V1 and 2U1 through the cable gland (B) into the DC cabinet.
3. Connect cables 2W1, 2V1 and 2U1 to the left power unit.
Installation GuideSC20_25_35-IEN09452137
Page 38
Internal Electrical ConnectionsSMA Solar Technology AG
DANGER!
Danger of fire.
Incorrect connection of the power units can cause fires.
• Observe the sequence when connecting the power units.
6. Tighten cable glands B and C (see figure page 37).
Notice!
Air permeable cable glands cause corrosion in the Sunny Central.
• Tighten the cable gland sufficiently.
7. Bind the power cable with cable ties. If you do not do so, pointed or sharp metal edges could
damage the insulation of the cable.
☑ Power cabling is complete.
8. Reattach the protective cover to the power unit.
☑ The protective cover has been fitted.
Installation GuideSC20_25_35-IEN09452139
Page 40
Internal Electrical ConnectionsSMA Solar Technology AG
5.3 Connecting the PE Connection
5.3.1 Sunny Central 200 / 250 / 250HE and 350
The PE rails of the two switch cabinets must be connected to one another. They are in the lower area
of the side walls. The required cables are included. The following diagram shows the connection point
of the PE connection of the Sunny Central 250 as an example.
Position of the PE rail
The exact position of the PE rail differs depending on the model. The exact position of the
PE rail can be determined with the help of the equipment identifier and the circuit diagram
enclosed.
1. Connect the PE cables to the marked PE rails.
2. Ensure that the PE connection is correct and secure.
☑ The PE cable is connected.
40SC20_25_35-IEN094521Installation Guide
Page 41
SMA Solar Technology AGInternal Electrical Connections
5.3.2 Sunny Central 200 / 250 with the "Protection against
chemically active substances" option
The PE rails for each cabinet are located in the lower region of the sides. The required cables are
included. The following diagram shows the connection point of the PE connection of the Sunny
Central 250.
Position of the PE rail
The exact position of the PE rail differs depending on the model. The exact position of the
PE rail can be determined with the help of the equipment identifier and the circuit diagram
enclosed.
1. Route the PE cable through the cable gland (A).
Installation GuideSC20_25_35-IEN09452141
Page 42
Internal Electrical ConnectionsSMA Solar Technology AG
2. Connect the PE cable to the marked grounding bar.
3. Tighten the cable gland (A).
Notice!
Air permeable cable glands cause corrosion in the Sunny Central.
• Tighten the cable gland sufficiently.
4. Ensure that the PE connection is correct and secure.
☑ The PE cable is connected.
5.4 Connecting the Control Lines on the Transfer Terminal Strip
The control lines are located in the transfer cable duct of the inverter cabinet The control lines are
marked with target designations. The following diagram shows the exact position of the transfer
terminal strip of the Sunny Central 250.
ATransfer terminal strip
Position of the transfer terminal strip
The exact position of the transfer terminal strip differs depending on the model. The exact
position of the individual terminals can be determined with the help of the equipment
identifier and the circuit diagram enclosed.
Allocation of the control lines
The terminal designation is used for unique allocation of the control lines
1. Connect the control lines on the transfer terminal strip.
☑ The control lines are connected.
42SC20_25_35-IEN094521Installation Guide
Page 43
SMA Solar Technology AGInternal Electrical Connections
5.5 Connecting the Sunny Central Control to the Power Unit
The data lines connect the Sunny Central Control to the controller board at the power unit. The data
line is fitted with a 4-pin plug-in contact.
The following diagram shows the plug-in contact on the controller board of the Sunny Central 250 as
an example.
AController board plug-in contact
Laying data lines
In order to guarantee interference-free signal transfer on the data line, it may not be laid
parallel to the power cables or in the cable duct. Instead, lay the data line freely in the
switch cabinet.
1. Connect the data line of the Sunny Central Control to the controller board at the power unit.
☑ The data line is connected.
Installation GuideSC20_25_35-IEN09452143
Page 44
Internal Electrical ConnectionsSMA Solar Technology AG
5.6 Connecting the Internal Control Lines
The internal control lines X8 and X9 are located in the transfer cable duct of the inverter cabinet. They
connect the AC cabinet to the controller board. The controller board is located on the power unit.
The following diagram shows the plug-in contact on the controller board of the Sunny Central 250 as
an example.
APlug-in contact for internal control lines X8 and X9
Position of the connection terminals of the control lines
The exact position of the plug-in contact differs depending on the mod el. The exa ct po sit ion
of the conn ection termina ls can b e dete rmined with the he lp of the equipment identifier and
the circuit diagram enclosed.
1. Connect control lines X8 and X9 to the controller board.
☑ The control lines are connected.
44SC20_25_35-IEN094521Installation Guide
Page 45
SMA Solar Technology AGInternal Electrical Connections
5.7 Connecting Insulation Monitoring (optional)
The 2-core connection line of the insulation monitoring system is located in the transfer duct. It connects
the DC cabinet to the insulation monitoring system. The insulation monitoring system is located in the
DC cabinet.
The following diagram shows the position of the insulation monitoring system in the Sunny
Central 250 as an example.
Position of the insulation monitoring system
The exact position of the insulation monitoring system differs depending on the model. The
exact position of the insulation monitoring system can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
1. Connect the insulation monitoring system.
☑ The insulation monitoring system is connected.
Installation GuideSC20_25_35-IEN09452145
Page 46
Internal Electrical ConnectionsSMA Solar Technology AG
5.8 Installing the Internal Temperature Sensor
Temperature sensor in the Sunny Central 350
The temperature sensor in the Sunny Central 350 is pre-installed ex works. Continue with
section 5.9”Sunny Central in Team Connection (optional)” (page47).
The internal temperature sensor records the temperature in the switch cabinet. It is located in the
transfer cable duct. The internal temperature sensor is fitted to the inside of the switch cabinet. A
corresponding top hat rail is pre-mounted at the marked installation location.
The following diagram shows the position of the internal temperature sensor in the Sunny Central 250
as an example.
Position of the internal temperature sensor
The exact position of the internal temperature sensor differs depending on the model. The
exact position of the internal temperature sensor can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
1. Click the temperature sensors into place in the top hat rail.
☑ The temperature sensor is installed.
46SC20_25_35-IEN094521Installation Guide
Page 47
SMA Solar Technology AGInternal Electrical Connections
5.9 Sunny Central in Team Connection (optional)
2 Sunny Centrals can also be connected to one another as an option. If team connection is used, the
internal team cabling of both switch cabinet units must be connected.
5.9.1 Connecting the Team Cable to
Sunny Central 200 / 250 / 250HE
Team cabling must be implemented for the team leader and the team device.
Te am c abl ing is p re- ins tal led in t he A C cabine t. T he t eam cab les a re i n th e AC cab ine t. T he c onn ect ion
terminals for team cabling are in the DC cabinet.
The following diagram shows the position of the connection terminals for team cabling in the
Sunny Central 250.
ATeam cable connection point
Position of the connection terminals for team cabling
The exact position of the connection terminals for team cabling can be determined with the
help of the equipment identifier and the circuit diagram enclosed.
1. Connect the team cable (L+) to L+ on the busbar.
2. Connect the team cable (L-) to L- on the busbar.
☑ The team cables are connected.
Installation GuideSC20_25_35-IEN09452147
Page 48
Internal Electrical ConnectionsSMA Solar Technology AG
5.9.2 Connecting Team Cables for Sunny Central 200 / 250 with
the "Protection against Chemically Active Substances" Option
Team cabling must be implemented for the team leader and the team device.
Te am c abl ing is p re- ins tal led in t he A C cabine t. T he t eam cab les a re i n th e AC cab ine t. T he c onn ect ion
terminals for team cabling are in the DC cabinet.
The following diagram shows the position of the connection terminals for team cabling in the
Sunny Central 250.
ATeam cable connection point
Position of the connection terminals for team cabling
The exact position of the connection terminals for team cabling can be determined with the
help of the equipment identifier and the circuit diagram enclosed.
48SC20_25_35-IEN094521Installation Guide
Page 49
SMA Solar Technology AGInternal Electrical Connections
1. Route the team cables through the cable glands
(A).
2. Tighten the cable gland (A).
Notice!
Air permeable cable ducts cause corrosion in the Sunny Central.
• Tighten the cable gland sufficiently.
3. Connect the team cable (L+) to L+ on the busbar.
4. Connect the team cable (L-) to L- on the busbar.
☑ The team cables are connected.
5.9.3 Team Cables for Sunny Central 350
Internal team cabling in the Sunny Central 350 is already completely connected when it leaves the
plant.
Installation GuideSC20_25_35-IEN09452149
Page 50
Internal Electrical ConnectionsSMA Solar Technology AG
5.10 Connecting the EVR Resistor (optional)
The EVR resistor increases the maximum permissible DC voltage which may be present at the device's
connection when idle to 1000 V DC. The EVR resistor is mounted on the top of the Sunny Central If
the EVR resistor is used, the exhaust air cannot be routed through the top of the Sunny Central. The
exhaust air is routed through the rear wall.
The following diagram shows the position of the EVR
resistor (A) using the Sunny Central 250 as an example.
Position of the connection terminals of the EVR resistor.
The exact position of the EVR resistor be determined with the help of the equipment
identifier and the circuit diagram enclosed.
1. Slide the EVR resistor between the rails onto the top of the Sunny Central.
2. Remove the 9 bolts on the protective grille of the EVR resistor.
3. Remove the protective grille forwards.
4. Connect the PE cable in the EVR resistor to the bolt on the left side.
5. Secure the EVR resistor to the rails using the two bolts on the left and right in the EVR resistor.
6. Connect the power cables (included) as shown in the circuit diagram provided.
7. Secure the protective grille to the EVR resistor using the 9 bolts.
☑ The EVR resistor is connected.
50SC20_25_35-IEN094521Installation Guide
Page 51
SMA Solar Technology AGExternal Connections
6 External Connections
WARNING!
Risk of death due electric shock when live parts of the low-voltage grid are
touched!
• Only work on the Sunny Central when it is switched off and voltage-free.
• All applicable safety requirements regarding the low-voltage grid must be observed.
WARNING!
Danger of fire in the event of direct contact of copper and aluminum.
If copper and aluminum come into contact, the contact surface between the cable lug and
the connection guide can oxidize. This causes the contact point to heat up. In turn, this can
cause a fire.
• Use a cupal washer or a copper-aluminum cable lug.
Connection Sizing
The installation conditions (separate document) contain the maximum connection cross
sections of the lines and cable lugs. You can download the installation conditions in the
Download area of www.SMA.de/en.
Electrical connections
For all electrical connections, it is imperative that you use the supplied circuit diagram.
The following steps, explained in the next sections, are required for the external electrical connection.
•Connect the AC grid
• Connect the PE connection to the equipotential bonding (Sunny Central 250HE only)
• Connect the internal AC power supply
•Connect the DC cable
• Connect the team cable (optional)
• Connect the analog inputs
• Connect the communication
• Connect the emergency shut-off
• Connect the overvoltage protection
Installation GuideSC20_25_35-IEN09452151
Page 52
External ConnectionsSMA Solar Technology AG
6.1 Removing the Sliding Plates
The external cables are fed in via the base of the Sunny Central. To do so, sliding plates in the base
must be removed. The following diagram shows the position of the sliding plates in the DC- / inverter
cabinet and in the AC cabinet.
1. Remove the sliding plates (A) in the front area of the DC- / inverter cabinet and the AC cabinet.
2. Keep the sliding plates in a safe place. After completing the installation work, the sliding plates
must be reinstalled. (See section 6.11”Fitting the Sliding Plates” (page72)).
NOTICE!
Soiling in the Sunny Central adversely affects operation.
• I f no wor k is perf orm ed o n th e Su nny Cen tra l (e .g. at ni ght ), re-insert the sliding plates
to protect the Sunny Central against soiling.
52SC20_25_35-IEN094521Installation Guide
Page 53
SMA Solar Technology AGExternal Connections
6.2 Connecting the AC Grid
6.2.1 Connecting the AC Cable to the Sunny Central 200 / 250
Grid Structure
Sunny Centrals are configured for a TN-C grid connection. They can also be connected to
TN-S or TT grids. To do so, remove the jumper between N and PE on the grid connection.
An IT grid can be implemented specifically for each project. Contact the Sunny Central
Service Line.
Fuse Links
The grid con nection ca ble mus t be fus ed at th e nominal current indicated on the type plate.
If the specified nominal current differs from the nominal current of the fus e plug, use the fu se
plug with the next highest nominal current.
The AC grid connection points are at the bottom left of the AC cabinet.
The following illustration shows the connection points for the AC grid in the Sunny Central 250 as an
example.
Position of the AC grid connection points
The exact position of the AC grid connection points differs depending on the model. The
exact position of the AC grid connection points can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
1. Route the cable through the base opening into the AC cabinet.
2. Fit cable lugs to the cable.
3. Connect the cable.
4. Fit the strain relief of the AC grid connection lines. Use the enclosed cable clamps to secure the
strain relief to the cable rail.
Installation GuideSC20_25_35-IEN09452153
Page 54
External ConnectionsSMA Solar Technology AG
Observe the field of rotation.
The field of rotation at the grid connection points must be right. If the field of rotation is not
right, the Sunny Central will output an error message.
☑ The AC cables are now connected.
6.2.2 Connecting the AC Cable to the Sunny Central 350
Grid Structure
Sunny Centrals are configured for a TN-C grid connection. They can also be connected to
TN-S or TT grids. To do so, remove the jumper between N and PE on the grid connection.
An IT grid can be implemented specifically for each project. Contact the Sunny Central
Service Line.
Fuse Links
Fuse the grid connection cable at the nominal current indicated on the type plate. If the
specified nominal current differs from the nominal current of the fuse plug, use the fuse plug
with the next highest nominal current.
The AC grid connection points are at the top of the AC cabinet.
The following illustration shows the connection points for the AC grid in the Sunny Central 350 as an
example.
Position of the AC grid connection points
The exact position of the AC grid connection points differs depending on the model. The
exact position of the AC grid connection points can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
54SC20_25_35-IEN094521Installation Guide
Page 55
SMA Solar Technology AGExternal Connections
1. Route the cable through the cable glands in the top into the interior of the switch cabinet.
2. Fit cable lugs to the cable.
3. Connect the cable.
4. Tighten the cable gland.
Observe the field of rotation.
The field of rotation at the grid connection points must be right. If the field of rotation is not
right, the Sunny Central will output an error message.
☑ The AC cables are now connected.
6.2.3 Connecting the AC Cable to the Sunny Central 250HE
The Sunny Central 250HE is designed for connection to a medium voltage transformer. The grid
connection form of the Sunny Central is an IT grid. In an IT grid, only the housings of the equipment
are grounded. An insulation fault between the external line and the ground grounds the external line
and causes increased voltage in the intact external line. The AC connection is 3-phase. The nominal
voltage (U) between the external lines is 270 V, the nominal voltage between the external line and
the ground is (U
)1000 V (depending on the current operating status of the Sunny Central).
0
DANGER!
Danger of fire.
During operation, there are nominal voltages of up to 1000 V to the ground in an IT grid.
If unsuitable AC cables are used, a fire could break out.
• Use only AC cables suitable for nominal voltages of up to 1000 V.
• Use only AC cables which are resistant to grounding and short circuits.
The connection to the fuse switch in the AC cabinet is 3-phase.
Installation GuideSC20_25_35-IEN09452155
Page 56
External ConnectionsSMA Solar Technology AG
The following diagram shows the connection points for the AC grid of the Sunny Central 250HE as
an example.
Position of the AC grid connection points
The exact position of the AC grid connection points differs depending on the model. The
exact position of the AC grid connection points can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
1. Route the cable through the base opening into the AC cabinet.
2. Fit cable lugs to the cable.
3. Connect the cable.
4. Fit the strain relief of the AC grid connection lines. Use the enclosed cable clamps to secure the
strain relief to the cable rail.
Observe the field of rotation.
The field of rotation at the grid connection points must be right. If the field of rotation is not
right, the Sunny Central outputs an error message.
☑ The AC cables are now connected.
56SC20_25_35-IEN094521Installation Guide
Page 57
SMA Solar Technology AGExternal Connections
6.3 Connecting the External PE Connection
(Sunny Central 250HE only)
The grid connection form of the Sunny Central is an IT grid. The PE rail in the AC cabinet must be
incorporated in the equipotential bonding to ground the Sunny Central 250HE housing.
PE cable sizing
Use PE cables with a line cross section of at least 1 x 50 mm2.
The following diagram shows the connection point of the external PE connection.
Position of the PE rail
The exact position of the PE rail can be determined with the help of the equipment identifier
and the circuit diagram enclosed.
1. Route the cable through the base opening into the AC cabinet.
2. Connect the PE cable in the AC cabinet.
☑ The PE cable is connected.
Installation GuideSC20_25_35-IEN09452157
Page 58
External ConnectionsSMA Solar Technology AG
6.4 Connecting the Internal AC Power Supply
The power required to operate the Sunny Central 200, Sunny Central 250 and Sunny Central 350
is either supplied via an external power supply or tapped internally. If the power is tapped internally,
the energy yield decreases by the system's own power requirements (fan, heater) of the Sunny
Central.
In the Sunny Central 250HE, an internal supply transformer can be connected in addition to the
ex ter nal pow er s upp ly. For det ail ed i nfo rma tio n on conn ect ing the internal supply transformer, see the
Technical Information "Sunny Central - Important Information on Internal Supply Transformers). The
standard grid connection structure for the internal power supply is a TN-S grid.
The Sunny Central 200 requires a single phase internal supply, the Sunny Central 250,
Sunny Central 250HE and Sunny Central 350 require a three-phase internal supply.
Circuit breaker for Internal Supply
Protect the grid connection line with a circuit breaker. See the Technical Data (see
section 8”Technical Data” (page81)) for notes on dimensioning the line circuit breaker.
The following diagram shows the connection terminals for the internal AC power supply in the
Sunny Central 250.
58SC20_25_35-IEN094521Installation Guide
Page 59
SMA Solar Technology AGExternal Connections
The following diagram shows the connection terminals for the internal AC power supply in the
Sunny Central 350.
Position of the AC grid connection terminals
The exact position of the AC grid connection terminals differs depending on the model. The
exact position of the AC grid connection terminals can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
6.4.1 Connecting the External Power Supply
1. Route the cable through the base opening into the AC cabinet.
2. Compress the AC grid connection terminals with a screwdriver.
3. Insert the cable into the terminal clamp.
4. Remove the screwdriver.
☑ The internal AC power supply is connected.
6.4.2 Connecting the Internal Power Supply
1. Bridge the terminal clamps in accordance with the circuit diagram.
2. Compress the AC grid connection terminals with a screwdriver.
3. Insert the cable into the terminal clamp in accordance with the circuit diagram.
4. Remove the screwdriver.
☑ The internal AC power supply is connected.
Installation GuideSC20_25_35-IEN09452159
Page 60
External ConnectionsSMA Solar Technology AG
6.5 Connecting the DC Cable
The DC- / inverter cabinet contains optional high and low voltage fuses. They allow the string
distribution boxes (e.g. Sunny Main Box) to be connected. All Sunny Centrals are equipped with one
busbar per potential as standard.
Protected inputs on the Sunny Central
The Sunny Central has protected inpu ts o n the DC s ide . The num ber depends on the device
type. The number of DC inputs in the various Sunny Centrals is specified in the Technical
Data.
NOTICE!
Insufficient voltage resistance of the DC connection cable can cause short circuits
which damage the Sunny Central.
• Use only DC cables which are sufficiently voltage-resistant.
60SC20_25_35-IEN094521Installation Guide
Page 61
SMA Solar Technology AGExternal Connections
6.5.1 Sunny Central 200 / 250 / 250HE
The following diagram shows the connections of the DC inputs in the Sunny Central 250 as an
example.
ADC cable connection point
Position of the DC inputs
The exact position of the DC inputs differs depending on the model. The exact position of
the DC inputs can be determined with the help of the equipment identifier and the circuit
diagram enclosed.
1. Route the cable through the base opening into the DC cabinet.
2. Fit cable lugs to the cable.
3. Connect the cable.
4. Fit the strain relief of the AC grid connection lines. Use the enclosed cable clamps to secure the
strain relief to the cable rail.
☑ The DC cables are now connected.
Installation GuideSC20_25_35-IEN09452161
Page 62
External ConnectionsSMA Solar Technology AG
6.5.2 Sunny Central 350
The following diagram shows the connections of the DC inputs in the Sunny Central 350 as an
example.
ADC cable connection point
Position of the DC inputs
The exact position of the PE rail differs depending on the model. The exact position of the
DC inputs can be determined with the help of the equipment identifier and the circuit
diagram enclosed.
The DC fuses are arranged in 2 rows. The cables are initially connected to the DC fuses of the rear
mounting plate. The front DC cables cannot be connected to the fuses until the rear DC cables have
been connected.
62SC20_25_35-IEN094521Installation Guide
Page 63
SMA Solar Technology AGExternal Connections
1. Remove the front mounting plate with the DC fuse units.
2. Route the cable through the base opening into the DC cabinet.
3. Fit cable lugs to the cable.
4. Connect the cables to the DC fuses of the rear mounting plate.
5. Fit the strain relief of the DC cables. The cable clamps required are included. Secure the cable
clamps to the cable rail.
6. Reattach the front mounting plate.
☑ The cables are connected to the DC fuses of the rear mounting plate.
7. Route the cable through the opening into the DC cabinet.
8. Fit cable lugs to the cable.
9. Connect the cable to the DC fuses of the front mounting plate.
10. Fit the strain relief of the AC grid connection lines. Use the enclosed cable clamps to secure the
strain relief to the cable rail.
☑ The DC cables are now connected.
Installation GuideSC20_25_35-IEN09452163
Page 64
External ConnectionsSMA Solar Technology AG
6.6 Connecting the Team Cable (optional)
The power cables in team connection connect the team leader to the team device. The cables required
(standard length 5 m) are included. If the cable length is insufficient, another cable can be used. This
cable must have a DC voltage resistance of 1000 V and be designed for the expected DC team
cu rre nt a t a n omi nal out put of 1 00 % . Se e th e fo llo win g ta ble for t he r equ ire d in for mat ion on D C te am
current.
Sunny CentralMaximum DC current input Maximum DC team current
Sunny Central 200472 A236 A
Sunny Central 250591 A296 A
Sunny Central 350800 A400 A
Th e co nnection ter min als for t eam con nec tio n are loc ate d in the cab ine t. T he f oll owi ng diagr am s how s
the position of the connection terminals in the Sunny Central 250.
ATeam cable connection point
Position of the connection terminals for the team connection.
The precise position of the connection terminals for the team connection differs depending
on the model. The exact position of the connection terminals can be determined with the
help of the equipment identifier and the circuit diagram enclosed.
1. Route the cable through the base opening into the DC cabinet.
2. Fit cable lugs to the cable.
3. Connect the cable.
64SC20_25_35-IEN094521Installation Guide
Page 65
SMA Solar Technology AGExternal Connections
4. Fit the strain relief. Use the enclosed cable clamps to secure the strain relief to the cable rail.
☑ The team cables are connected.
6.7 Analog Inputs
Connecting the Overvoltage Protection (optional)
The combined overvoltage and lightning protection for the signal inputs is available as an option.
Position of the overvoltage protection.
The exact position of the overvoltage protection can be determined with the help of the
equipment identifier and the circuit diagram enclosed.
6.7.1 Analog Sensors
The Sunny Central allows a PT 100 temperature sensor and two additional sensors (pre-configured
as ExtSollrr and ExtGlolrr) on the Sunny Central Control panel via the customer’s terminal strip. See
the table below for the respective connection options available for the customer. These sensors can
be configured by the customer.
Connecting the Sensors
The procedure for connecting the sensors to the terminal strip in the Sunny Central Control
is described in the documentation included.
Configuring the Sensors
Please refer to the Sunny Central operating instructions for detailed information.
6.7.2 External Signals
Other than the analog sensors, three further signal transducers can be connected (preconfigured as
ExtAlarm, ExtSolP and ExtSolQ). These signals have a direct effect on the operation of the Sunny
Central.
The external alarm input (ExtAlarm) can be used to monitor the function of the medium voltage
transformer, for example. Note that sensors often require a 24 VDC power supply. It can be tapped
internally in the Sunny Central, or provided by an external source of power. The circuit diagram
provided must be followed when connecting external signal transducers.
The other analog inputs (ExtSolP, ExtSolQ) help to regulate the effective and reactive power of the
Sunny Central. These sensors are also connected to the customer’s terminal strip.
Installation GuideSC20_25_35-IEN09452165
Page 66
External ConnectionsSMA Solar Technology AG
6.7.3 Overview of the Analog Inputs
Assignment of the analog inputs on the Sunny Central Control
When connecting the analog inputs and for the digital signals, it is obligatory to follow the
included circuit diagram.
The connection is made at the connection terminals. Here, the connections for fourconductor and two-conductor sensors should be noted and any required measuring
converters should be made available.
Analog InputsAinNameMeaning
CustomerAin 1 ExtSolPExternal default nominal value for active power
CustomerAin 3 ExtSollrrExternal radiation sensor
CustomerAin 4 ExtGlolrrPyranometer (measurement of global solar
irradiation)
CustomerAin 5 ExtAlarmExternal alarm input, e.g. for monitoring the
functioning of the medium-voltage transformer
CustomerAin 6 ExtSolQExternal default nominal value for reactive power
CustomerAin 8 TmpExt CExternal temperature sensor / PT 100
6.7.4 Handling Notes for Shielded Contacts
Always use a shielded product for external signal and bus lines. Contact the shield on the shield rail
with the shield clamps over a large area. Use the shield clamps provided for the connection.
The connection terminals of the signal and bus lines are in the AC cabinet. The following diagram
shows the position of the connection terminals in the Sunny Central 250.
AConnection point for shielded contact rail
66SC20_25_35-IEN094521Installation Guide
Page 67
SMA Solar Technology AGExternal Connections
The following diagram shows the position of the connection terminals in the Sunny Central 350.
AConnection point for shielded contact rail
Position of the connection terminals for signal and bus lines.
The exact position of the connection terminals for signal and bus lines can be determined
with the help of the equipment identifier and the circuit diagram enclosed.
NOTICE!
Damage to the shield clamps.
• Only tighten the shield clamps hand-tight.
• Tightening the shield clamps using a screwdriver can damage the insulation.
1. Remove the line insulation.
2. Attach the shield clamp.
☑ The shield clamp snaps into place.
3. Tighten the shield clamps hand-tight. Tightening
using a screwdriver is not necessary.
Installation GuideSC20_25_35-IEN09452167
Page 68
External ConnectionsSMA Solar Technology AG
6.8 Remote Deactivation Unit
In addition to the key switch, another deactivation device can be implemented It is installed on the
terminals in the Sunny Central. For this purpose, a 230 V power supply must be connected with the
internal terminal.
Remote deactivation unit
For special project-specific requirements, the Sunny Central can be fitted with a remote
deactivation unit combined with monitoring of the activation condition. This switching
option allows the Sunny Central to be controlled from a control center without activating
the key switch on the Sunny Central.
When connecting the remote deactivation unit, the circuit diagram included must be
observed.
6.9 Connecting the Communication
6.9.1 NET Interface
The NET interface is used for communication with the Sunny Data Control, PC, modem or Sunny
WebBox. The NET interface is option-dependent. An Ethernet, ISDN or analog interface can be
implemented.
The NET interface is located in the AC cabinet. The following diagram shows the position of the NET
interface (A) in the Sunny Central 250.
Position of the NET interface
The exact position of the NET interface can be determined with the help of the equipment
identifier and the circuit diagram enclosed.
68SC20_25_35-IEN094521Installation Guide
Page 69
SMA Solar Technology AGExternal Connections
6.9.2 RS485 data line for communication with Sunny StringMonitors
Communication between the Sunny Central Control and the optional Sunny String-Monitors (DC
distributor with integrated string current monitoring) is implemented via an RS485 data line, using the
COM1 port of the Sunny Central Control. The RS485 data line of the string current monitoring of the
Sunny Central String monitor is connected to the HUB assembly in the Sunny Central.
The hub is located in the AC cabinet. The following diagram shows the position of the hub in the
Sunny Central 250HE.
Installation GuideSC20_25_35-IEN09452169
Page 70
External ConnectionsSMA Solar Technology AG
In the Sunny Central 350, the HUBs are guided on terminals (A). The following diagram shows the
position of the connection terminals in the Sunny Central 350.
Position of the HUB
The exact position of the HUB can be determined with the help of the equipment identifier
and the circuit diagram enclosed.
Sunny String-Monitor Technical Description
For further information on the connection of the RS485 cabling, see the Sunny StringMonitor technical description.
6.9.3 Serial Interfaces for Team Connection
If team connection is used, communication connection is implemented via the COM1 port on both
Sunny Cent ral Con trols. Ter minati on then takes pl ace in the Su nny Central Control. The Sunny Central
Controls are preterminated at the factory.
1. Remove the jumper on the HUB (RS485 OUT).
2. Insert the CAT5 cable (CAT5 cable included).
Sunny String-Monitor Technical Description
The documentation provided with the Sunny Central String monitors contains a detailed
description of the installation of the integrated string current monitoring.
70SC20_25_35-IEN094521Installation Guide
Page 71
SMA Solar Technology AGExternal Connections
6.10 Connecting the Emergency Shut-off
The Sunny Central is equipped with an internal emergency shut-off switch ex-works.
Position of the emergency shut-off terminals.
The exact position of the emergency shut-off terminals can be determined with the help of
the equipment identifier and the circuit diagram enclosed. The connection must be made in
accordance with the circuit diagram.
An external emergency shut-off function can be connected in the Sunny Central. The terminals for the
external emergency shut-off are bridged ex-works. Remove the jumper if an external emergency shutoff is to be connected. Comply with the provided circuit diagram to connect the external emergency
shut-off.
Emergency shut-off circuit
If several Sunny Centrals are operated in one system, they must all be switched off when one
emergency shut-off switch is activated (creation of an emergency shut-off circuit). Connect all
emergency shut-off switches in the emergency shut-off circuit in series.
WARNING!
If emergency shut-off function fails, the protection function is impaired.
• In systems with more than one Sunny Central, the emergency shut-off circuits of the
Sunny Centrals must be connected to one another.
• Only supply the emergency shut-off circuits of one Sunny Central with power.
• Test the function of the emergency shut-off circuits.
Installation GuideSC20_25_35-IEN09452171
Page 72
External ConnectionsSMA Solar Technology AG
6.11 Fitting the Sliding Plates
After completing the installation work, the sliding plates must be reinstalled. This protect the Sunny
Central against dirt and soiling.
1. Stick the provided sealing tape (A) to the front side
of the sliding plates.
2. Seal the cable inlet (seal any free space with polyurethane foam).
3. Reattach the sliding plates in the front area of the DC- / inverter cabinet and AC cabinet.
☑ The sliding plates are now reattached.
72SC20_25_35-IEN094521Installation Guide
Page 73
SMA Solar Technology AGCommissioning
7 Commissioning
Warranty or Guarantee Claims
Warranty or guarantee claims may only be asserted if initial commissioning has been
performed by SMA Solar Technology or if the provided Commissioning Report for Sunny
Central Systems has previously been completed, signed and returned to SMA Solar
Technology.
Test and rectify any faults.
Rectify wiring faults based on the existing documentation and the circuit diagram.
The commissioning report supports you in the commissioning procedure.
1. Before initial commissioning, check the work carefully.
2. Check voltages and polarity on both DC- and AC sides. The voltages and polarity may not
exceed the limit values permitted by the inverter.
The main tests for commissioning are described below.
Necessary Tests
The following conditions must be fulfilled before commissioning:
• All electrical connections made on-site must be checked for correct connection and secure
attachment.
• The entire electrical system, including the photovoltaic generator, must be tested by the system
installer in accordance with DIN VDE 0100-600 "Installing Low-Voltage Systems - Part 6: Tests".
A test report of the tests made in accordance with DIN VDE 0100-600 must be completed.
Additional tests are required for medium voltage systems if applicable. The grounding
resistance of the system must be measured as part of this test. The grounding resistance is a key
to the safety of the system.
• The voltages on the Sunny Central must be tested.
Switching elements
When delivered, all switching elements, e.g. circuit beakers and motor overload switches
in the Sunny Central are switched off.
Installation GuideSC20_25_35-IEN09452173
Page 74
CommissioningSMA Solar Technology AG
7.1 Checking the Sunny Central Cabling
All electrical connections made on-site must be checked for correct connection and secure attachment.
Checking Connections
See the documentation provided and the circuit diagram for the precise electrical
connections.
In particular, not the following points:
• Misconnections.
• Incorrect polarity, in particular for power connections.
Make sure that everything is securely in place.
• Check that the connections have been tightened. Where possible, avoid retightening
in accordance with the torque specifications in the circuit diagram.
• Only tighten loose connections in accordance with the torque specification in the
circuit diagram.
Checking Internal Connections
• Check that the plugs of the transfer terminal strip are in the correct sequence and are securely
in place.
• Check that the transformer or sine wave filter connections are securely in place and have the
correct phase sequence.
• Check that the data and control lines on the power unit are correctly connected.
• Check that the data line for insulation monitoring is correctly connected.
• Check the installation location of the internal temperature sensor.
• Check the internal power cabling of the team connection (optional).
• Check the connection between the PE rails of the partial barrier.
Checking the AC Grid Connection
• Check the connections to ensure that they are securely in place.
• Check the phase sequence.
• Check the correct connection in accordance with the circuit diagram.
• Check the PE-N bridge for the grid structure TN-C or TN-S on-site and remove it if necessary.
• Check the correct installation of the covers. Correct installation means that contact protection is
guaranteed.
Equipotential Bonding
• Sunny Central 250HE only: Ensure that the Sunny Central 250HE is connected to the
equipotential bonding of the installation site.
• Check that the connections are secure.
74SC20_25_35-IEN094521Installation Guide
Page 75
SMA Solar Technology AGCommissioning
Checking the Internal AC Power Supply
• Check the connections to ensure that they are securely in place.
• If power is supplied internally from the grid feed line, check that the jumper required is correctly
positioned in accordance with the circuit diagram.
• If a separate external power supply from the power grid is used, check that the connection line
is securely in place.
– Remove the jumpers where applicable.
• Check that the connection is correct in accordance with the circuit diagram.
• Check that contact protection is guaranteed.
Checking the DC Cabling
• Check that the connection is securely in place.
• Check the polarity of the DC cables.
• Check that the connection is correct in accordance with the circuit diagram.
• Check the correct installation of the covers. Correct installation means that contact protection is
guaranteed.
Checking the Team Cabling (optional)
• Check that the connection is securely in place.
• Check that the connection is correct in accordance with the circuit diagram.
• Check the correct installation of the covers. Correct installation means that contact protection is
guaranteed.
7.1.1 Checking the Connection of the Serial Interfaces
Checking the external communication and the string current monitoring.
• Check the cabling of the connection of the data lines to the Sunny String-Monitor HUB.
• Check the connection of the NET interface.
• Check that the connection is correct in accordance with the circuit diagram.
7.1.2 Checking the Emergency Shut-Off Cabling
• Check that the connection is securely in place.
• Check that the connection is correct in accordance with the circuit diagram.
• Check that the emergency shut-off circuit is only supplied with power by one Sunny Central.
• Check that contact protection is guaranteed.
Installation GuideSC20_25_35-IEN09452175
Page 76
CommissioningSMA Solar Technology AG
7.1.3 Checking the Thermostat and Hygrostat Settings
The device contains adjustable thermostats for controlling the cabinet ventilators and the overtemperature shut-off system. The heating system is controlled by an adjustable hygrostat. All
thermostats and hygrostats are pre-adjusted before delivery.
Checking the settings of the thermostats and the hygrostat
Compare the settings with the specifications in the circuit diagram. If they deviate, set the
values specified in the circuit diagram.
System check
The system must be checked by the system installer.
7.2 Checking the Voltages on the Sunny Central
WARNING!
Danger of fire if the connection is faulty.
Procedure before the commissioning test:
• Switch the Sunny Central to "Stop".
• Ensure that the fuses are not inserted.
• Ensure that the internal main switch, circuit breaker and automatic fuse are not
activated.
• Leave the service room before switching on the voltage.
Checking the AC Grid Voltage
• Measure and record AC voltages
–L1-L2
–L1-L3
–L2-L3
–L1-N
–L2-N
–L3-N
Check that the field of rotation is to the right.
Deviating grid voltage
If the grid voltage deviates greatly, adjust the transmission ratio of the medium-voltage
transformer if applicable.
76SC20_25_35-IEN094521Installation Guide
Page 77
SMA Solar Technology AGCommissioning
Checking the Internal AC Power Supply
• Measure and record AC voltages
–L1-L2
–L1-L3
–L2-L3
–L1-N
–L2-N
–L3-N
Checking DC Voltages
WARNING!
Danger of arcing if the measuring device is incorrectly connected.
• Ensure that the measuring device is connected correctly.
• Select the appropriate measuring range.
• Measure and record the DC voltage for every input.
• Check that the polarity of each input is correct.
• Check the correct polarity of the DC busbar in the Sunny Central.
• Measure the voltage for every input and every pole to ground.
– If the value is stable, a short to ground is present.
• Measure and compare the voltages of the individual inputs. The voltages must be
approximately equal.
• The voltage must not exceed the maximum DC voltage of the inverter.
NOTICE!
Damage to the Sunny Central via excessive DC voltages
The DC voltage of the photovoltaic generator must never exceed the maximum permissible
inverter voltage.
•U
= 1000 V for Sunny Central standard / HE with the EVR option
PV
•UPV = 880 V for Sunny Central standard / HE
Installation GuideSC20_25_35-IEN09452177
Page 78
CommissioningSMA Solar Technology AG
7.3 Preparation for Commissioning
Fault display on the Sunny Central Control
See the Sunny Central user manual for details on troubleshooting.
If you cannot rectify the fault, contact the SMA Serviceline.
Preparatory Work
1. Disconnect all voltages.
2. Ensure that no voltage is present in the system.
3. Set the device to "Stop".
4. Insert the fuses.
5. Fit the covers.
6. Activate the internal main switch.
7. Close the circuit breakers.
8. Activate the automatic fuses.
9. Close the doors.
10. Leave the service room before switching on the voltage.
Switch on the voltages.
1. Activate the internal AC power supply externally.
☑ The Sunny Central boots and displays "Grid fault".
2. Activate the AC grid voltage externally.
☑ "Grid fault" is acknowledged automatically after a short period.
– Check the current values of the grid voltage on the display.
78SC20_25_35-IEN094521Installation Guide
Page 79
SMA Solar Technology AGCommissioning
Checking the Emergency Shut-off
DANGER!
Death resulting from electric shock and burning upon touching the mediumvoltage grid's live components.
• Do not touch parts other than those described in the instructions.
3. Open the switch cabinet doors of the AC cabinet.
4. Ensure that the emergency shut-off on the outside of
the device is not activated.
5. Tape all door contact switches to the "On" position.
☑ During normal operation, both signal lights (A)
of the emergency shut-off relay must illuminate.
6. If a n emerg enc y sh ut- off swi tch is n ow acti vat ed, the
signal lights of the "Off" emergency shut-off relay
must switch.
☑ The Sunny Central Control displays error
message "206" and the fault must be
acknowledged manually.
7. Unlock the emergency shut-off and acknowledge
th e fa ult on t he S unn y Ce ntr al C ont rol . Th e fau lt i s on ly d isp layed on the Sunny Central on which
the emergency shut-off was activated.
8. Release door contact switches (remove the adhesive tape).
9. Close the cabinet doors.
Test for Emergency Shut-off Circuits.
If one emergency shut-off switch is activated, the emergency shut-off relay in all Sunny
Centrals must be activated.
If an external emergency shut-off switch is activated, the Sunny Central does not indicate a
fault.
10. Check the operation of each individual emergency shut-off switch. Test the switches on the
cabinet, in the stations, and the other external emergency shut-off switches.
DC voltages
11. Switch on the external DC voltages.
Installation GuideSC20_25_35-IEN09452179
Page 80
CommissioningSMA Solar Technology AG
Checking the Polarity of the Team Cables (optional
1. Open the door
WARNING!
Danger of arcing if the measuring device is incorrectly connected.
• Ensure that the measuring device is connected correctly.
• Select the appropriate measuring range.
2. Check that the polarity of connections to the team contactor established on-site is correct.
3. Close the door.
7.4 Switching On
The system may not be switched on until the following points are ensured:
• All tests and measurements have been performed.
• All values measured are within the permissible range.
• All switch cabinet doors must be closed.
☑ The inverter is now completely connected on the AC side and DC side.
Switching on the Sunny Central
1. Turn the key switch to the "Start" position.
2. Leave the service room.
☑ The Sunny Central will start automatically. First, the grid voltage and frequency parameters
are checked. After approx. 20 seconds, the motorized DC switch is activated automatically
and starts the photovoltaic generator.
After a wait period, the grid contactor is activated and the Sunny Central enters feed-in mode.
All device parameters are preset, even for options ordered. See the Sunny Central user manual for
notes on system-optimized parameter settings. Turn the key switch to the "Stop" position to configure
the Sunny Central.
Continue by commissioning the Sunny String-Monitors and external communication. The
commissioning process for the Sunny String-Monitors is described in the Sunny String-Monitor
installation guide.
80SC20_25_35-IEN094521Installation Guide
Page 81
SMA Solar Technology AGTechnical Data
8 Technical Data
8.1 Sunny Central 200
Input Specifications
Nominal power DCP
Maximum PV power (recommended)P
DC voltage range (MPPT)U
Maximum permissible DC voltageU
Maximum permissible DC voltage with EVRU
Maximum permissible DC currentI
Voltage ripple, PV voltageU
PV
PV
DC
DC
DC EVR
DC
PP
Number of DC inputs / connection points5 / DC fuses
a)
Specifications apply for irradiation values = 1,000 (kWh / kWp x year)
b)
U
DCmin
at U
+/– 5 % and cos ϕ = 1
AC,Nom
Output Values
Nominal AC output powerP
Operating grid voltage +/– 10 %U
Nominal AC currentI
Grid structureTT, TN-S, TN-C
Operating range, grid frequencyf
Harmonic distortion of grid current< 3 % at nominal power
Power factorcos ϕ> 0.98 % at nominal power
a)
P
nom
at U
+ 5 % and cos ϕ = 1
AC,Nom
AC
AC
AC,Nom
AC
210 kW
230 kWp
450 V – 820 V
a)
b)
880 V
1000 V (optional)
472 A
<3%
a)
200 kW
400 V
289 A
50 Hz - 60 Hz
Efficiency
Max. efficiency P
AC, max
Euro-Etaη
η95.7 %
euro
94.5 %
Dimensions
a)
Width / Height / Depth (W / H / D)
(Standard)
b)
Width / Height / Depth (W / H / D)
(for "Protection against chemically active
substances" option)
Weight: approx.1600 kg
a)
The switch cabinet is raised by 210 mm for the EVR option.
b)
The switch cabinet is raised by 210 mm for the EVR option.
Installation GuideSC20_25_35-IEN09452181
800 mm + 1200 mm / 2120 mm / 850 mm
1200 mm + 1200 mm / 2120 mm / 850 mm
Page 82
Technical DataSMA Solar Technology AG
Power Consumption
Own consumption in operation (P
Standby operating consumption (P
External power supply / grid structure230 V, 50 Hz / 60 Hz / TN-S, TT
External pre-fuse for internal power supplyB 16 A, 1 pole
)< 1000 W
day
)< approx. 70 W
night
Sunny Central Control Interfaces
Communication (NET Piggy-Back, optional)Analog, ISDN, Ethernet
Analog Inputs1 x PT 100, 2 x A
Overvoltage protection for analog inputsOptional
Sunny String-Monitor connection (COM1)RS485
PC interface (COM3)RS232
Floating contact (external fault detector)1
a)
Terminal for an analog sensor provided by the customer in two-wire and four-wire version.
a)
in
Standards
EMCEN 61000-6-2, EN 61000-6-4
CE conformityYes
Protection rating and ambient conditions
Protection rating as per EN 60529IP 20
Permissible ambient temperatures–20 °C ... +40 °C
Relative humidity, non-condensing15 % ... 95 %
Maximum altitude above sea level1000 m
Fresh air consumption3300 m³/h
82SC20_25_35-IEN094521Installation Guide
Page 83
SMA Solar Technology AGTechnical Data
8.2 Sunny Central 250
Input Specifications
Nominal power DCP
Maximum PV power (recommended)P
DC voltage range, (MPPT)U
Maximum permissible DC voltageU
Maximum permissible DC voltage with EVRU
Maximum permissible DC currentI
Voltage ripple, PV voltageU
PV
PV
DC
DC
DC EVR
DC
PP
Number of DC inputs / connection points8 / DC fuses
a)
Specifications apply for irradiation values = 1,000 (kWh / kWp x year)
b)
U
DCmin
at U
+/– 5 % and cos ϕ = 1
AC,Nom
Output Specifications
Nominal AC output powerP
Operating grid voltage +/– 10 %U
Nominal AC currentI
Grid structureTT, TN-S, TN-C
Operating range, grid frequencyf
Harmonic distortion of grid current< 3 % at nominal power
Power factorcos ϕ> 0.98 % at nominal power
a)
P
nom
at U
+ 5 % and cos ϕ = 1
AC,Nom
AC
AC
AC,Nom
AC
262 kW
290 kWp
450 V – 820 V
a)
b)
880 V
1000 V (optional)
591 A
<3%
a)
250 kW
400 V
361 A
50 Hz - 60 Hz
Efficiency
Max. efficiency P
AC, max
Euro-Etaη
η96.1 %
euro
95.2 %
Dimensions
Width/Height/Depth(W/H/D)
1200 mm + 1200 mm / 2120 mm / 850 mm
a)
Weight: approx.2070 kg
a)
The switch cabinet is raised by 210 mm for the EVR option.
Power Consumption
Own consumption in operation (P
Standby operating consumption (P
External power supply / grid structure3 x 400 V, 50 Hz / 60 Hz / TN-S, TT
External pre-fuse for internal power supplyB 16 A, 3 pole
Installation GuideSC20_25_35-IEN09452183
)< 1500 W
day
)<approx.80W
night
Page 84
Technical DataSMA Solar Technology AG
Sunny Central Control Interfaces
Communication (NET Piggy Back, optional)Analog, ISDN, Ethernet
Analog Inputs1 x PT 100, 2 x A
Overvoltage protection for analog inputsOptional
Sunny String-Monitor connection (COM1)RS485
PC interface (COM3)RS232
Floating contact (external fault detector)1
a)
Terminal for an analog sensor provided by the customer in two-wire and four-wire version.
a)
in
Standards
EMCEN 61000-6-2, EN 61000-6-4
CE conformityYes
Protection rating and ambient conditions
Protection rating as per EN 60529IP 20
Permissible ambient temperatures–20 °C ... +40 °C
Relative humidity, non-condensing15 % ... 95 %
Maximum altitude above sea level1000 m
Fresh air consumption4200 m³/h
84SC20_25_35-IEN094521Installation Guide
Page 85
SMA Solar Technology AGTechnical Data
8.3 Sunny Central 250HE
Input Specifications
Nominal power DCP
Maximum PV power (recommended)P
DC voltage range, (MPPT)U
Maximum permissible DC voltageU
Maximum permissible DC voltage with EVRU
Maximum permissible DC currentI
Voltage ripple, PV voltageU
PV
PV
DC
DC
DC EVR
DC
PP
Number of DC inputs / connection points8 / DC fuses
a)
Specifications apply for irradiation values = 1,000 (kWh / kWp x year)
b)
U
DCmin
at U
+/– 5 % and cos ϕ = 1
AC,Nom
Output Specifications
Nominal AC output powerP
Operating grid voltage +/– 10 %U
Nominal AC currentI
Grid structureIT
Operating range, grid frequencyf
Harmonic distortion of grid current< 3 % at nominal power
Power factorcos ϕ> 0.9 % at nominal power
a)
P
nom
at U
+ 5 % and cos ϕ = 1
AC,Nom
AC
AC
AC,Nom
AC
261 kW
285 kW
450 V – 820 V
a)
b)
880 V
1000 V (optional)
591 A
<3%
a)
250 kW
270 V
535 A
50 Hz - 60 Hz
Efficiency
Max. efficiency PAC,
max
Euro-Etaη
η97.5 %
euro
96.7 %
Dimensions
Width/Height/Depth(W/H/D)
1200 mm + 1200 mm / 2120 mm / 850 mm
a)
Weight: approx.1170 kg
a)
The switch cabinet is raised by 210 mm for the EVR option.
Power Consumption
Own consumption in operation (P
Standby operating consumption (P
External power supply / grid structure3 x 400 V, 50 Hz / 60 Hz / TN-S, TT
External pre-fuse for internal power supplyB 16 A, 3 pole
Installation GuideSC20_25_35-IEN09452185
)< 1500 W
day
)<approx. 80W
night
Page 86
Technical DataSMA Solar Technology AG
Sunny Central Control Interfaces
Communication (NET Piggy Back, optional)Analog, ISDN, Ethernet
Analog Inputs1 x PT 100, 2 x A
Overvoltage protection for analog inputsOptional
Sunny String-Monitor connection (COM1)RS485
PC interface (COM3)RS232
Floating contact (external fault detector)1
a)
Terminal for an analog sensor provided by the customer in two-wire and four-wire version.
a)
in
Standards
EMCEN 61000-6-2, EN 61000-6-4
CE conformityYes
Protection rating and ambient conditions
Protection rating as per EN 60529IP 20
Permissible ambient temperatures–20 °C ... +40 °C
Relative humidity, non-condensing15 % ... 95 %
Maximum altitude above sea level1000 m
Fresh air consumption3500 m³/h
86SC20_25_35-IEN094521Installation Guide
Page 87
SMA Solar Technology AGTechnical Data
8.4 Sunny Central 350
Input Specifications
Nominal power DCP
Maximum PV power (recommended)P
DC voltage range, (MPPT)U
Maximum permissible DC voltageU
Maximum permissible DC voltage with EVRU
Maximum permissible DC currentI
Voltage ripple, PV voltageU
PV
PV
DC
DC
DC EVR
DC
PP
Number of DC inputs / connection points12 / DC fuses
a)
Specifications apply for irradiation values = 1,000 (kWh / kWp x year)
b)
U
DCmin
at U
+/– 5 % and cos ϕ = 1
AC,Nom
Output Specifications
Nominal AC output powerP
Operating grid voltage +/– 10 %U
Nominal AC currentI
Grid structureTT, TN-S, TN-C
Operating range, grid frequencyf
Harmonic distortion of grid current< 3 % at nominal power
Power factorcos ϕ> 0.98 % at nominal power
a)
P
nom
at U
+ 5 % and cos ϕ = 1
AC,Nom
AC
AC
AC,Nom
AC
369 kW
405 kWp
450 V – 820 V
a)
b)
880 V
1000 V (optional)
800 A
<3%
a)
350 kW
400 V
505 A
50 Hz - 60 Hz
Efficiency
Max. efficiency PAC,
max
Euro-Etaη
η96.0 %
euro
95.2 %
Dimensions
Width/Height/Depth(W/H/D)
1600 mm + 1200 mm / 2120 mm / 850 mm
a)
Weight: approx.2800 kg
a)
The switch cabinet is raised by 210 mm for the EVR option.
Power Consumption
Own consumption in operation (P
Standby operating consumption (P
External power supply / grid structure3 x 400 V, 50 Hz / 60 Hz / TN-S, TT
External pre-fuse for internal power supplyB 16 A, 3 pole
Installation GuideSC20_25_35-IEN09452187
)< 2500 W
day
)< approx. 70 W
night
Page 88
Technical DataSMA Solar Technology AG
Sunny Central Control Interfaces
Communication (NET Piggy Back, optional)Analog, ISDN, Ethernet
Analog Inputs1 x PT 100, 2 x A
Overvoltage protection for analog inputsOptional
Sunny String-Monitor connection (COM1)RS485
PC interface (COM3)RS232
Floating contact (external fault detector)1
a)
Terminal for an analog sensor provided by the customer in two-wire and four-wire version.
a)
in
Standards
EMCEN 61000-6-2, EN 61000-6-4
CE conformityYes
Protection rating and ambient conditions
Protection rating as per EN 60529IP 20
Permissible ambient temperatures–20 °C ... +40 °C
Relative humidity, non-condensing15 % ... 95 %
Maximum altitude above sea level1000 m
Fresh air consumption6500 m³/h
88SC20_25_35-IEN094521Installation Guide
Page 89
SMA Solar Technology AGContact
9 Contact
If you have technical problems concerning our products, contact our Service Line. We require the
following information in order to provide you with the necessary assistance:
The information contained in this document is the property of SMA Solar Technology AG. Publishing its content, either partially or
in full, requires the written permission of SMA Solar Technology AG. Any internal company copying of the document for the
purposes of evaluating the product or its correct implementation is allowed and does not require permission.
Exclusion of liability
The general terms and conditions of delivery of SMA Solar Technology AG shall apply.
The content of these documents is continually checked and amended, where necessary. However, discrepancies cannot be
excluded. No guarantee is made for the completeness of these documents. The latest version is available online at www.SMA.de
or from the usual sales channels.
Guarantee or liability claims for damages of any kind are excluded if they are caused by one or more of the following:
• Damages during transportation
• Improper or inappropriate use of the product
• Operating the product in an unintended environment
• Operating the product whilst ignoring relevant, statutory safety regulations in the deployment location
• Ignoring safety warnings and instructions contained in all documents relevant to the product
• Operating the product under incorrect safety or protection conditions
• Altering the product or supplied software without authority
• The product malfunctions due to operating attached or neighboring devices beyond statutory limit values
• In case of unforeseen calamity or force majeure
The use of supplied software produced by SMA Solar Technology AG is subject to the following conditions:
• SMA Solar Technology AG rejects any liability for direct or indirect damages arising from the use of software developed by
SMA Solar Technology AG. This also applies to the provision or non-provision of support activities.
• Supplied software not developed by SMA Solar Technology AG is subject to the respective licensing and liability agreements
of the manufacturer.
SMA Factory Warranty
The current guarantee conditions come enclosed with your device. These are also available online at www.SMA.de and can be
downloaded or are available on paper from the usual sales channels if required.
Trademarks
All trademarks are recognized even if these are not marked separately. Missing designations do not mean that a product or brand
is not a registered trademark.