Rosemount Sanitary Tank Spud Weld Guidelines Manuals & Guides

Reference Manual
00809-0100-4016, Rev DA September 2010
Sanitary Tank Spud
Sanit ary Tank Spud Weld Guidelines
This document is a welding guideline. Actual procedures and specifications vary based upon equipment and application.

TANK PREPARATION When preparing the tank, ensure an area wi th a minim um di amete r of 9 ¼-in.

is available to properly weld the tank spud, Figure 1-1 bullet 1. The center of the tank spud should be at least 1 ½-in. below the minimum measurement level, as shown in bullet 2 of Figure 1-1. In order to get a proper process fluid measurement, half of the remote seal diaphragm must be covered.
Figure 1-1. Tank Preparation
www.emersonprocess.com/rosemount
Bullet 3 shows the actual hole cut in the tank. Attempt to cut the hole as smoothly and as circular as possible. A torch cut is not recommended. The tank spud OD is 5.98-in. ±.010-in. When cutting the hole for the tank spud, the gap between the hole diameter and spud OD should be he ld to a min imum. It is recommended that the hole be no large r than 6.020-in. Anything larger than
6.020-in. could increase the amount of tank spud distortion. If a bevel(s) is required, an angle no larger than 37.5º is recommended; see
ASME B16.25 for more details. Bevels can be made on one or both sides of the tank. Do not grind or cut the bevel to a sharp point. Attempt to leave a flat area, as shown in Figure 1-2 below.
Sanitary Tank Spud
Figure 1-2. Bevel Example
Reference Manual
00809-0100-4016, Rev DA
September 2010
The flat area should be large enough to minimize spud distortion but small enough so that tank weld requirements can be met. Minimizing the bevel angle will decrease the amount of fill required during weld and minimize the number of weld passes. These best practices will decrease heat input and help mitigate distortion.

WELDING

Figure 1-3. O-ring Sealing Surfaces
Excessive heat will distort the tank spud. Allow adequate cooling time between passes.
Ensure spud is not assembled to transmitter and/or remote seal prior to welding.
Do not nick the sealing surfaces of the tank spud, the inner angled surfaces where the o-ring sits shown in Figure 1-3, as any irregularities may cause leaks.
1-2
Reference Manual
00809-0100-4016, Rev DA September 2010
Figure 1-4. Welding Sections Diagram
Sanitary Tank Spud
With the spud centered in the tank hole, make sure the inner surface of the spud is flush with the inner surface of the tank. The leak detection hole in the spud should be at the bottom of the spud. With the spud properly located, tack weld it into place using 4 tack welds, 90º from each other.
Begin welding on the inside of vessel. Weld in sections similar to the sequence in Figure 1-4.
Allow time to cool between weld sections. Weld should be cooled to 350º F or less after each pass while being cool to the touch is preferred. Use of a damp cloth or compressed air is allowed if rapid cooling is desired.
Repeat procedure on the outside of the tan k.
NOTE:
The number of weld passes should be kept to a minimum while maintaining tank weld standards and sanitary requirements. Additional weld passes are a significant contributor to spud distortion due to additional heat inp ut and added filler material in beveled area of hole. When fill passes are required, a 1/16-in. diameter weld rod is recommended.
1-3
Reference Manual
00809-0100-4016, Rev DA September 2010
Sanitary Tank Spud
Standard Terms and Conditions of Sale can be found at www.rosemount.com\terms_of_sale The Emerson logo is a trade mark and service mark of Emerson Electric Co. Rosemount and the Rosemount logotype are registered trademarks of Rosemount Inc. Coplanar is a trademark of Rosemount Inc. PlantWeb is a mark of one of the Emerson Process Management companies. HART is a registered trademark of the HART Communications Foundation.
OUNDATION fieldbus is a registered trademark of the Fieldbus Foundation.
F All other marks are the property of their respective owners.
©2010 Rosemount Inc. All rights reserved.
Emerson Process Management Rosemount Measurement
8200 Market Boulevard Chanhassen MN 55317 USA Tel (USA) 1 800 999 9307 Tel (International) +1 952 906 8888 Fax +1 952 949 7001
00809-0100-4016 Rev DA, 9/10
Emerson Process Management
Blegistrasse 23 P.O. Box 1046 CH 6341 Baar Switzerland Tel +41 (0) 41 768 6111 Fax +41 (0) 41 768 6300
Emerson FZE
P.O. Box 17033 Jebel Ali Free Zone Dubai UAE Tel +971 4 811 8100 Fax +971 4 886 5465
Emerson Process Management Asia Pacific Pte Ltd
1 Pandan Crescent Singapore 128461 Tel +65 6777 8211 Fax +65 6777 0947 Service Support Hotline : +65 6770 8711 Email : Enquiries@AP.EmersonProcess.com
Loading...