Rosemount 1195 Integral Orifice Primary Element Quick Start Guide

Quick Start Guide
00825-0100-4686, Rev FB
Rosemount™ 1195 Integral Orifice Assembly
April 2021
Quick Start Guide April 2021
NOTICE
If the Rosemount 1195 Integral Orifice was ordered assembled to a Rosemount Pressure Transmitter, refer to the following Quick Start Guides for information on configuration and hazardous locations certifications:
1. Rosemount 3051S Quick Start Guide
2. Rosemount 3051SMV Quick Start Guide
3. Rosemount 3051 Quick Start Guide
WARNING
Process leaks could result in death or serious injury.
To avoid process leaks, only use the gasket designed to seal with the corresponding flange adapter. To avoid process leaks, only use the O-ring designed to seal with the corresponding flange adapter.
Contents
Rosemount 1195 Integral Orifice Assembly View......................................................................... 3
Location and orientation.............................................................................................................. 4
Primary element orientation........................................................................................................ 6
Primary element installation.........................................................................................................9
Preparing for operation.............................................................................................................. 12
Product certifications................................................................................................................. 17
2 www.emerson.com
A
B
C
D
E
F
G
April 2021 Quick Start Guide
1 Rosemount 1195 Integral Orifice Assembly
View
Figure 1-1: Enhanced Support Body
A. Manifold B. Gaskets C. Studs
D. Nuts
E. Transmitter F. Rosemount 1195 enhanced support body
G. Enhanced support orifice plate
(1)
(1)
Transmitter and housing are shown for clarity purposes - only supplied if ordered.
Quick Start Guide 3
U D
U D
U
D
Quick Start Guide April 2021

2 Location and orientation

Install the Rosemount 1195 Integral Orifice in the correct location within the piping branch to prevent inaccurate measurement caused by flow disturbances.

2.1 Straight pipe length

Use the upstream (U) and downstream (D) lengths provided below in conjunction with figures below to determine the appropriate upstream (U) and downstream (D) pipe lengths. For example, for a 1-in. line size with a beta ratio (×) of 0.4 using installation of , the straight length of upstream piping required is 25 x 1 = 25-in., and downstream 10 x 1 = 10-in.
Note
The Rosemount 1195 Integral Orifice comes with the associated pipe lengths (18D upstream and 8D downstream) when ordered with process pipe-end connections.
Straight run requirements
Figure 2-1: Reducer
(2 d to d over a length of 1.5 d to 3 d)
Figure 2-2: Single 90° Bend Flow from One Branch
Figure 2-3: Two or More 90° Bends in Same Planes
(2)
(2)
For dimensions, see Table 2-1
4 www.emerson.com
U D
U D
U D
April 2021 Quick Start Guide
Figure 2-4: Two or More 90° Bends in Different Planes
Figure 2-5: Expander
(0.5 d to d over a length of d to 2 d)
Figure 2-6: Ball/Gate Valve Fully Open
Table 2-1: Straight Run Requirements (in Pipe Diameters)
(1)
β
Figure 2-1
up­stream (U)
Figure 2-2
up­stream (U)
Figure 2-3
up­stream (U)
Figure 2-4
up­stream (U)
Figure 2-5
up­stream (U)
Figure 2-6
up­stream (U)
Figures 2-1 through 2-6 On
down­stream
(2)
(D)
0.20 20 24 25 30 22 22 10
0.40 20 25 27 31 22 22 10
0.50 20 25 28 33 23 23 10
0.60 20 27 31 37 25 25 10
0.70 23 32 35 42 28 28 10
0.75 25 35 38 45 30 30 10
(1) Interpolation of intermediate β values can be used. (2) All straight lengths are expressed as multiples of the pipe inside diameter (d) and
shall be measured from the upstream face of orifice plate.
Quick Start Guide 5
A
B
C
D
FLOW
A
C
B
D
Quick Start Guide April 2021

3 Primary element orientation

Figure 3-1: Rosemount 1195 Flowmeter Orientation with Traditional Style Manifold
Gas (horizontal) Gas (vertical)
Liquid (horizontal) Liquid (vertical)
Steam (horizontal) Steam (vertical)
6 www.emerson.com
A
C
B
FLOW
F
E
D
A
B
C
D
FLOW
April 2021 Quick Start Guide
1. 90° recommended zone
2. Vertical plane
3. Horizontal plane
1. 360° recommended zone
2. Block valves
3. Vent valves
Figure 3-2: Rosemount 1195 Flowmeter Orientation with Flange by Flange Manifold
Gas (horizontal) Gas (vertical)
Liquid (horizontal) Liquid (vertical)
Quick Start Guide 7
A
B
C
D
A
B
C
FLOW
F
E
D
Quick Start Guide April 2021
Gas (horizontal) Gas (vertical)
Steam (horizontal) Steam (vertical)
1. A. 120° recommended zone
2. B. Horizontal plane
3. C. Vertical plane
1. D. 360° recommended zone
2. E. Block valves
3. F. Vent valves
Note
For saturated steam that is not high quality, it is recommended to mount in
8 www.emerson.com
a vertical line to avoid damming effect of the liquid.
April 2021 Quick Start Guide

4 Primary element installation

Table 4-1: Stud and Nut Torque Specifications
Manifold studs Torque
All line sizes and gasket types 32 lb-ft.(44 N-m)
Orifice body studs Torque
All line sizes and gasket types 60 lb-ft.(82 N-m)
(1) Studs and nuts should be tightened to specification in two to three steps
following a cross pattern.
(2) Never reuse gaskets. Always replace gaskets after disassembly to ensure proper
seal.
(1) (2)
Figure 4-1: Rosemount 1195 Assembly Fastener Naming Convention
A. Transmitter bolts - 4x B. Manifold studs - 4x C. Orifice body studs - 2x
D. Orifice body studs - 4x
Procedure
1. Ensure that the side of the orifice plate marked inlet is facing upstream.
Quick Start Guide 9
Quick Start Guide April 2021
This stamping is found on the part of the orifice plate that extends beyond the orifice bodies.
2. Before pressurizing the line, ensure that the torque values are met. See and for torque requirements of manifold studs and orifice body
studs. See the appropriate transmitter manual for torque requirements of transmitter bolts.
3. Install the unit.
Option Description
Units with flanged process connections.
a. Install the flanges in the process pipe. The
distance between flanges should be equal to the overall length of the flowmeter, plus clearance for gaskets.
b. Install the unit between the flanges, using
studs, nuts, and gaskets appropriate for the flange size/rating and process conditions. Proper support is needed at the flange connections see .
Units with threaded
Install the unit using the appropriate threaded
connection hardware. process connections.
Units with socketweld bodies.
a. To ensure perpendicularity of the pipe to
the orifice fitting, the socket diameter is smaller than the standard pipe OD. The pipe OD must be machined-to-fit prior to welding.
b. To prevent damage, remove the
transmitter prior to welding.
4. Once the Rosemount 1195 is installed ensure that it is supported properly and take precautions to ensure that it is not used as a step. Refer to for support locations.
10 www.emerson.com
A A
B
April 2021 Quick Start Guide
Figure 4-2: Recommended Support Locations for Installation
A. Support B. No step
Quick Start Guide 11
Quick Start Guide April 2021

5 Preparing for operation

Note
Serious injury can occur by opening the valves when the pipes are pressurized. Do not bleed or vent process fluid if it is toxic or harmful to health or environment.

5.1 Direct mount for liquid applications 450 °F (232 °C) or less

Procedure
1. Pressurize line.
2. Open the equalizer valve.
3. Open the high and low side valves.
4. Bleed drain/vent valves until no gas is apparent in the liquid.
5. Close the vent/drain valves.
6. Close the low side valve.
7. Check the transmitter zero according to the transmitter product manual.
8. Close the equalizer valve.
9. Open the low side valve. The system is now operational.

5.2 Direct mount for gas applications 450 °F (232 °C) or less

Procedure
1. Pressurize line.
2. Open the equalizer valve.
3. Open the high and low side valves.
4. Open drain/vent valves to ensure no liquid is present.
5. Close the vent/drain valves.
6. Close the low side valve.
7. Check the transmitter zero according to the transmitter product manual.
8. Close the equalizer valve.
9. Open the low side valve. The system is now operational.
5.3

Direct mount for steam applications 450 °F (232 °C) or less

Procedure
1. Remove pressure from line.
12 www.emerson.com
April 2021 Quick Start Guide
2. Open equalizer, high, and low side valves.
3. Fill manifold and transmitter with water via drain vents.
4. Close low side valve.
5. Pressurize line.
6. Gently tap electronics body, manifold head, and integral orifice body with a small wrench to dislodge any entrapped air.
7. Check the transmitter zero according to the transmitter product manual.
8. Close equalizer valve.
9. Open the low side valve. The system is now operational.

5.4 Remote mount 850 °F (454 °C) or less

5.4.1 Liquid applications-transmitter located below Rosemount 1195 Taps

Procedure
1. Pressurize line.
2. Open equalizer valve on transmitter manifold. Close equalizer valve at integral orifice, if one is used.
3. Open high and low side transmitter manifold valves and high and low block valves at integral orifice.
4. Bleed drain/vent valves on transmitter manifold until no air is present.
5. Close transmitter manifold drain vent valves, then bleed vent valves at the integral orifice block valves until no air is present.
6. Close vent valves at integral orifice block valves.
7. Close equalizer valve at transmitter manifold.
8. Close low and high side block valves at integral orifice.
9. Open vent valves at integral orifice block valves.
10. Check transmitter zero according to transmitter manual.
11. Close vent valves at integral orifice block valves.
12. Open high and low side block valves at integral orifice. The system is now operational.
Quick Start Guide 13
FLOW
A
B
C
D
E
Quick Start Guide April 2021

5.4.2 Gas applications-transmitter located above Rosemount 1195 Taps

Figure 5-1: Remote Gas Service
A. High valve
B. Vent C. Low valve D. Equalizer valve
(3)
Procedure
1. Pressurize line.
2. Open equalizer valve on transmitter manifold.
3. Open high and low side transmitter manifold valves.
4. Open drain/vent valves on transmitter manifold to ensure no liquids
are present.
5. Close drain/vent valves.
6. Close low side transmitter manifold valve.
7. Check transmitter zero according to transmitter manual.
8. Close equalizer on transmitter manifold.
9. Open low side valve on transmitter manifold. The system is now
operational.
(3)
Applicable to both body assemblies.
14 www.emerson.com
FLOW
A
B
C
D
E
F
April 2021 Quick Start Guide

5.4.3 Steam service-transmitter located below Rosemount 1195 Taps

Figure 5-2: Remote Steam and Liquid Service
A. Vent B. High valve C. Equalizer valve
D. Vent valves
E. Low valve
(4)
Procedure
1. Remove pressure from line or close block valves at integral orifice.
2. Open equalizer valves, high and low side valves on the transmitter manifold. Close equalize valve at integral orifice, if one is used.
3. Open vent valves at integral orifice block valves. To vent sensing lines.
4. Fill transmitter manifold and instrument lines with water via low side vent at integral orifice block valves.
5. Open and close vent valves at transmitter to bleed out trapped air.
6. Close the equalizer valve at transmitter manifold.
(4)
Quick Start Guide 15
7. Complete filling the low side and high side sensing lines.
Applicable to both body assemblies.
Quick Start Guide April 2021
8. Gently tap electronics body, transmitter manifold, instrument lines, and integral orifice with a small wrench to dislodge any trapped air.
9. Check transmitter zero according to transmitter manual.
10. Close vent valves at integral orifice block valves.
11. If block valves at integral orifice had been closed they should now be opened. System is now operational for steam flow measurement.
16 www.emerson.com
April 2021 Quick Start Guide

6 Product certifications

6.1 Approved Manufacturing Locations

Emerson — Shakopee, Minnesota USA
Rosemount DP Flow Design and Operations — Boulder, Colorado USA
Emerson GmbH & Co. OHG — Wessling, Germany
Emerson Asia Pacific Private Limited — Singapore
Emerson Beijing Instrument Co., Ltd — Beijing, China

6.2 European Directive Information

The EU declaration of conformity for all applicable European directives for this product can be found on Emerson.com/Rosemount. A hard copy may be obtained by contacting our local sales office.
European Pressure Equipment Directive PED (2014/68/EU)
Refer to EU declaration of conformity for conformity assessment.
Pressure Transmitter — See appropriate Pressure Transmitter QSG:
Nameplate indicated design conditions shall never be exceeded.
Rosemount 3051S with HART Protocol Quick Start Guide
Rosemount 3051SMV Flowmeter Quick Start Guide
Rosemount 3051 Quick Start Guide
6.3
Quick Start Guide 17

Hazardous Locations Certifications

For information regarding the transmitter product certification, see the appropriate transmitter QSG:
Rosemount 3051S with HART Protocol Quick Start Guide
Rosemount 3051SMV Flowmeter Quick Start Guide
Rosemount 3051 Quick Start Guide
Quick Start Guide April 2021
Figure 6-1: Rosemount 1195 Declaration of Conformity Revision V
18 www.emerson.com
April 2021 Quick Start Guide
Quick Start Guide 19
Quick Start Guide April 2021
20 www.emerson.com
April 2021 Quick Start Guide
Quick Start Guide 21
Quick Start Guide April 2021

6.4 China RoHS

22 www.emerson.com
April 2021 Quick Start Guide
Quick Start Guide 23
*00825-0100-4686*
00825-0100-4686, Rev. FB
Quick Start Guide
April 2021
For more information:
©
2021 Emerson. All rights reserved.
Emerson Terms and Conditions of Sale are available upon request. The Emerson logo is a trademark and service mark of Emerson Electric Co. Rosemount is a mark of one of the Emerson family of companies. All other marks are the property of their respective owners.
www.emerson.com
Loading...