This document provides basic installation guidelines for the Rosemount 1195 Integral Orifice
Assembly. For comprehensive instructions for detailed configuration, diagnostics, maintenance,
service, installation, or troubleshooting refer to the Rosemount 1195 Reference Manual. The manual
and this guide are also available electronically on www.emerson.com.
If the Rosemount 1195 Integral Orifice was ordered assembled to a Rosemount Pressure Transmitter,
refer to the following Quick Start Guides for information on configuration and hazardous locations
certifications:
1. Rosemount 3051S Quick Start Guide
2. Rosemount 3051SMV Quick Start Guide
3. Rosemount 3051 Quick Start Guide
WARNING
Process leaks could result in death or serious injury.
To avoid process leaks, only use the gasket designed to seal with the corresponding flange adapter. To
avoid process leaks, only use the O-ring designed to seal with the corresponding flange adapter.
Contents
Rosemount 1195 Integral Orifice Assembly View......................................................................... 3
Location and orientation.............................................................................................................. 4
Primary element orientation........................................................................................................ 6
Primary element installation.........................................................................................................9
Preparing for operation.............................................................................................................. 12
E. Transmitter
F. Rosemount 1195 enhanced support body
G. Enhanced support orifice plate
(1)
(1)
Transmitter and housing are shown for clarity purposes - only supplied if ordered.
Quick Start Guide3
UD
UD
U
D
Quick Start GuideApril 2021
2Location and orientation
Install the Rosemount 1195 Integral Orifice in the correct location within the
piping branch to prevent inaccurate measurement caused by flow
disturbances.
2.1Straight pipe length
Use the upstream (U) and downstream (D) lengths provided below in
conjunction with figures below to determine the appropriate upstream (U)
and downstream (D) pipe lengths. For example, for a 1-in. line size with a
beta ratio (×) of 0.4 using installation of , the straight length of upstream
piping required is 25 x 1 = 25-in., and downstream 10 x 1 = 10-in.
Note
The Rosemount 1195 Integral Orifice comes with the associated pipe
lengths (18D upstream and 8D downstream) when ordered with process
pipe-end connections.
Straight run requirements
Figure 2-1: Reducer
(2 d to d over a length of 1.5 d to 3 d)
Figure 2-2: Single 90° Bend Flow from One Branch
Figure 2-3: Two or More 90° Bends in Same Planes
(2)
(2)
For dimensions, see Table 2-1
4www.emerson.com
UD
UD
UD
April 2021Quick Start Guide
Figure 2-4: Two or More 90° Bends in Different Planes
Figure 2-5: Expander
(0.5 d to d over a length of d to 2 d)
Figure 2-6: Ball/Gate Valve Fully Open
Table 2-1: Straight Run Requirements (in Pipe Diameters)
(1)
β
Figure
2-1
upstream
(U)
Figure
2-2
upstream
(U)
Figure
2-3
upstream
(U)
Figure
2-4
upstream
(U)
Figure
2-5
upstream
(U)
Figure
2-6
upstream
(U)
Figures
2-1
through
2-6
On
downstream
(2)
(D)
0.20 20242530222210
0.40 20252731222210
0.50 20252833232310
0.60 20273137252510
0.70 23323542282810
0.75 25353845303010
(1) Interpolation of intermediate β values can be used.
(2) All straight lengths are expressed as multiples of the pipe inside diameter (d) and
shall be measured from the upstream face of orifice plate.
Quick Start Guide5
A
B
C
D
FLOW
A
C
B
D
Quick Start GuideApril 2021
3Primary element orientation
Figure 3-1: Rosemount 1195 Flowmeter Orientation with Traditional
Style Manifold
Gas (horizontal)Gas (vertical)
Liquid (horizontal)Liquid (vertical)
Steam (horizontal)Steam (vertical)
6www.emerson.com
A
C
B
FLOW
F
E
D
A
B
C
D
FLOW
April 2021Quick Start Guide
1. 90° recommended zone
2. Vertical plane
3. Horizontal plane
1. 360° recommended zone
2. Block valves
3. Vent valves
Figure 3-2: Rosemount 1195 Flowmeter Orientation with Flange by
Flange Manifold
Gas (horizontal)Gas (vertical)
Liquid (horizontal)Liquid (vertical)
Quick Start Guide7
A
B
C
D
A
B
C
FLOW
F
E
D
Quick Start GuideApril 2021
Gas (horizontal)Gas (vertical)
Steam (horizontal)Steam (vertical)
1. A. 120° recommended zone
2. B. Horizontal plane
3. C. Vertical plane
1. D. 360° recommended zone
2. E. Block valves
3. F. Vent valves
Note
For saturated steam that is not high quality, it is recommended to mount in
8www.emerson.com
a vertical line to avoid damming effect of the liquid.
April 2021Quick Start Guide
4Primary element installation
Table 4-1: Stud and Nut Torque Specifications
Manifold studsTorque
All line sizes and gasket types32 lb-ft.(44 N-m)
Orifice body studsTorque
All line sizes and gasket types60 lb-ft.(82 N-m)
(1) Studs and nuts should be tightened to specification in two to three steps
following a cross pattern.
(2) Never reuse gaskets. Always replace gaskets after disassembly to ensure proper
A. Transmitter bolts - 4x
B. Manifold studs - 4x
C. Orifice body studs - 2x
D. Orifice body studs - 4x
Procedure
1. Ensure that the side of the orifice plate marked inlet is facing
upstream.
Quick Start Guide9
Quick Start GuideApril 2021
This stamping is found on the part of the orifice plate that extends
beyond the orifice bodies.
2. Before pressurizing the line, ensure that the torque values are met.
See and for torque requirements of manifold studs and orifice body
studs. See the appropriate transmitter manual for torque
requirements of transmitter bolts.
3. Install the unit.
OptionDescription
Units with
flanged process
connections.
a. Install the flanges in the process pipe. The
distance between flanges should be equal
to the overall length of the flowmeter, plus
clearance for gaskets.
b. Install the unit between the flanges, using
studs, nuts, and gaskets appropriate for the
flange size/rating and process conditions.
Proper support is needed at the flange
connections see .
Units with
threaded
Install the unit using the appropriate threaded
connection hardware.
process
connections.
Units with
socketweld
bodies.
a. To ensure perpendicularity of the pipe to
the orifice fitting, the socket diameter is
smaller than the standard pipe OD. The
pipe OD must be machined-to-fit prior to
welding.
b. To prevent damage, remove the
transmitter prior to welding.
4. Once the Rosemount 1195 is installed ensure that it is supported
properly and take precautions to ensure that it is not used as a step.
Refer to for support locations.
10www.emerson.com
AA
B
April 2021Quick Start Guide
Figure 4-2: Recommended Support Locations for Installation
A. Support
B. No step
Quick Start Guide11
Quick Start GuideApril 2021
5Preparing for operation
Note
Serious injury can occur by opening the valves when the pipes are
pressurized. Do not bleed or vent process fluid if it is toxic or harmful to
health or environment.
5.1Direct mount for liquid applications 450 °F (232 °C) or less
Procedure
1. Pressurize line.
2. Open the equalizer valve.
3. Open the high and low side valves.
4. Bleed drain/vent valves until no gas is apparent in the liquid.
5. Close the vent/drain valves.
6. Close the low side valve.
7. Check the transmitter zero according to the transmitter product
manual.
8. Close the equalizer valve.
9. Open the low side valve. The system is now operational.
5.2Direct mount for gas applications 450 °F (232 °C) or less
Procedure
1. Pressurize line.
2. Open the equalizer valve.
3. Open the high and low side valves.
4. Open drain/vent valves to ensure no liquid is present.
5. Close the vent/drain valves.
6. Close the low side valve.
7. Check the transmitter zero according to the transmitter product
manual.
8. Close the equalizer valve.
9. Open the low side valve. The system is now operational.
5.3
Direct mount for steam applications 450 °F (232 °C) or
less
Procedure
1. Remove pressure from line.
12www.emerson.com
April 2021Quick Start Guide
2. Open equalizer, high, and low side valves.
3. Fill manifold and transmitter with water via drain vents.
4. Close low side valve.
5. Pressurize line.
6. Gently tap electronics body, manifold head, and integral orifice body
with a small wrench to dislodge any entrapped air.
7. Check the transmitter zero according to the transmitter product
manual.
8. Close equalizer valve.
9. Open the low side valve. The system is now operational.
5.4Remote mount 850 °F (454 °C) or less
5.4.1Liquid applications-transmitter located below Rosemount 1195 Taps
Procedure
1. Pressurize line.
2. Open equalizer valve on transmitter manifold. Close equalizer valve
at integral orifice, if one is used.
3. Open high and low side transmitter manifold valves and high and low
block valves at integral orifice.
4. Bleed drain/vent valves on transmitter manifold until no air is
present.
5. Close transmitter manifold drain vent valves, then bleed vent valves
at the integral orifice block valves until no air is present.
6. Close vent valves at integral orifice block valves.
7. Close equalizer valve at transmitter manifold.
8. Close low and high side block valves at integral orifice.
9. Open vent valves at integral orifice block valves.
10. Check transmitter zero according to transmitter manual.
11. Close vent valves at integral orifice block valves.
12. Open high and low side block valves at integral orifice. The system is
now operational.
Quick Start Guide13
FLOW
A
B
C
D
E
Quick Start GuideApril 2021
5.4.2Gas applications-transmitter located above Rosemount 1195 Taps
Figure 5-1: Remote Gas Service
A. High valve
B. Vent
C. Low valve
D. Equalizer valve
(3)
Procedure
1. Pressurize line.
2. Open equalizer valve on transmitter manifold.
3. Open high and low side transmitter manifold valves.
4. Open drain/vent valves on transmitter manifold to ensure no liquids
are present.
5. Close drain/vent valves.
6. Close low side transmitter manifold valve.
7. Check transmitter zero according to transmitter manual.
8. Close equalizer on transmitter manifold.
9. Open low side valve on transmitter manifold. The system is now
operational.
(3)
Applicable to both body assemblies.
14www.emerson.com
FLOW
A
B
C
D
E
F
April 2021Quick Start Guide
5.4.3Steam service-transmitter located below Rosemount 1195 Taps
Figure 5-2: Remote Steam and Liquid Service
A. Vent
B. High valve
C. Equalizer valve
D. Vent valves
E. Low valve
(4)
Procedure
1. Remove pressure from line or close block valves at integral orifice.
2. Open equalizer valves, high and low side valves on the transmitter
manifold. Close equalize valve at integral orifice, if one is used.
3. Open vent valves at integral orifice block valves. To vent sensing
lines.
4. Fill transmitter manifold and instrument lines with water via low side
vent at integral orifice block valves.
5. Open and close vent valves at transmitter to bleed out trapped air.
6. Close the equalizer valve at transmitter manifold.
(4)
Quick Start Guide15
7. Complete filling the low side and high side sensing lines.
Applicable to both body assemblies.
Quick Start GuideApril 2021
8. Gently tap electronics body, transmitter manifold, instrument lines,
and integral orifice with a small wrench to dislodge any trapped air.
9. Check transmitter zero according to transmitter manual.
10. Close vent valves at integral orifice block valves.
11. If block valves at integral orifice had been closed they should now be
opened. System is now operational for steam flow measurement.
16www.emerson.com
April 2021Quick Start Guide
6Product certifications
6.1Approved Manufacturing Locations
Emerson — Shakopee, Minnesota USA
Rosemount DP Flow Design and Operations — Boulder, Colorado USA
Emerson GmbH & Co. OHG — Wessling, Germany
Emerson Asia Pacific Private Limited — Singapore
Emerson Beijing Instrument Co., Ltd — Beijing, China
6.2European Directive Information
The EU declaration of conformity for all applicable European directives for
this product can be found on Emerson.com/Rosemount. A hard copy may be
obtained by contacting our local sales office.
European Pressure Equipment Directive PED (2014/68/EU)
Refer to EU declaration of conformity for conformity assessment.
Pressure Transmitter — See appropriate Pressure Transmitter QSG:
Nameplate indicated design conditions shall never be exceeded.
• Rosemount 3051S with HART Protocol Quick Start Guide
• Rosemount 3051SMV Flowmeter Quick Start Guide
• Rosemount 3051 Quick Start Guide
6.3
Quick Start Guide17
Hazardous Locations Certifications
For information regarding the transmitter product certification, see the
appropriate transmitter QSG:
• Rosemount 3051S with HART Protocol Quick Start Guide
• Rosemount 3051SMV Flowmeter Quick Start Guide
• Rosemount 3051 Quick Start Guide
Quick Start GuideApril 2021
Figure 6-1: Rosemount 1195 Declaration of Conformity Revision V
Emerson Terms and Conditions of Sale are
available upon request. The Emerson logo
is a trademark and service mark of
Emerson Electric Co. Rosemount is a mark
of one of the Emerson family of
companies. All other marks are the
property of their respective owners.
www.emerson.com
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.