Rittal 3311.490, 3311.491, 3311.492, 3311.493 Assembly And Operating Manual

Page 1
LCUDX
Assembly and operating instructions
3311.490
3311.491
3311.492
3311.493
Page 2
Foreword
EN
2 Rittal LCU DX
Dear Customer,
Thank you for choosing a Rittal Liquid Cooling Unit DX (also referred to hereafter as "LCU DX").
This documentation applies to the following devices in the LCU DX series (DX = Direct Expansion): – LCU DX 3 kW single –LCU DX 3 kW redundant – LCU DX 6.5 kW single – LCU DX 6.5 kW redundant
Those sections where information only applies to one of the units are labelled accordingly in the documentation.
Please take the time to read this documentation carefully and pay particular attention to the safety instructions in the text and to section 2 "Safety instructions".
This is the prerequisite for: – secure assembly of the LCU DX – safe handling and – the most trouble-free operation possible.
Please keep the complete documentation readily availa­ble so that it is always on hand when needed.
We wish you every success!
Your, Rittal GmbH & Co. KG
Rittal GmbH & Co. KG Auf dem Stützelberg
35745 Herborn Germany
Tel.: +49(0)2772 505-0 Fax: +49(0)2772 505-2319
E-mail: info@rittal.de www.rimatrix5.com www.rimatrix5.de
We are always happy to answer any technical questions regarding our entire range of products.
Page 3
Rittal LCU DX 3
Contents
EN
Contents
1 Notes on documentation .................. 4
1.1 CE label ........................................................ 4
1.2 Information on electromagnetic compatibility . 4
1.3 Storing the documents .................................. 4
1.4 Symbols in these operating instructions ........ 4
1.5 Associated documents ................................. 4
1.6 Normative instructions .................................. 4
1.6.1 Legal information concerning the operating
instructions ...........................................................4
1.6.2 Copyright ............................................................. 4
1.6.3 Revision ................................................................ 4
2 Safety instructions ............................ 5
2.1 Important safety instructions: ........................ 5
2.2 Service and technical staff ............................ 6
2.2.1 Personal safety equipment ................................... 6
2.3 Operator requirements .................................. 6
2.3.1 Abbreviated instructions ....................................... 6
2.3.2 System log ........................................................... 6
2.3.3 F-gas regulation ................................................... 7
2.3.4 Chemicals – Climate Protection Ordinance ........... 7
2.4 RoHS compliance ......................................... 7
3 Device description ............................ 8
3.1 General functional description ....................... 8
3.2 Air routing ..................................................... 8
3.3 Device assembly ........................................... 8
3.3.1 Internal unit (evaporator coil) ................................. 8
3.3.2 External unit (inverter-controlled cooling unit) ........ 9
3.3.3 Refrigerant lines and electrical pilot wires .............. 9
3.4 Proper and improper usage .......................... 9
3.5 Scope of supply for the LCU DX ................. 10
4 Transport and handling .................. 11
4.1 Transport .................................................... 11
4.2 Unpacking .................................................. 11
5 Assembly and siting ....................... 12
5.1 General ....................................................... 12
5.1.1 Siting location requirements ................................ 12
5.1.2 Relative positioning of the internal unit to the
external unit ........................................................ 12
5.1.3 Supply connections required at the installation
site .....................................................................12
5.1.4 Electromagnetic interference .............................. 12
5.2 Assembly procedure ................................... 12
5.2.1 Preparatory tasks ............................................... 12
5.2.2 Mounting the internal unit ................................... 13
5.2.3 Mounting the internal unit accessories ................ 13
5.2.4 Mounting the external unit .................................. 14
6 Installation ...................................... 16
6.1 General information ..................................... 16
6.2 Notes on pipework ...................................... 16
6.3 Connecting the condensate discharge ........ 18
6.4 Electrical connection ................................... 18
6.4.1 General .............................................................. 18
6.4.2 Connecting the external unit ............................... 19
6.4.3 Connecting the internal unit ................................ 19
6.5 Checking the entire system prior to
commissioning ........................................... 19
6.6 Installing the server .................................... 20
7 Operation ....................................... 22
7.1 Control and display devices ....................... 22
7.2 Switching the LCU DX on and off ............... 22
7.2.1 Switching on the internal and external units ........ 22
7.2.2 Switching off the internal and external units ........ 22
7.2.3 Switching off in an emergency ............................ 22
7.3 Setting the setpoint temperature ................ 22
8 Troubleshooting ............................. 24
8.1 General ...................................................... 24
8.2 List of error messages ................................ 24
9 Inspection and maintenance ........... 25
10 Storage and disposal ...................... 26
11 Technical specifications .................. 27
11.1 LCU DX 3 kW ............................................. 27
11.2 LCU DX 6.5kW ........................................... 28
11.3 Information about the refrigerant ................ 29
11.4 Cooling output ........................................... 29
11.4.1 LCU DX 3 kW ..................................................... 30
11.4.2 LCU DX 6.5 kW .................................................. 31
11.5 Overview drawings ..................................... 32
11.5.1 Internal unit LCU DX 3 kW and 6.5 kW ............... 32
11.5.2 Dimensions of internal unit LCU DX 3 kW and
6.5 kW ............................................................... 33
11.6 RI flow chart LCU DX ................................. 34
11.7 Circuit diagram ........................................... 35
11.7.1 Functional diagram, internal unit ......................... 35
11.7.2 Connection internal unit – external unit, external
interfaces ........................................................... 36
11.7.3 Circuit diagram, external unit .............................. 37
12 Spare parts .................................... 38
13 Accessories .................................... 39
14 Glossary ......................................... 40
15 Customer service addresses .......... 41
Page 4
1 Notes on documentation
EN
4 Rittal LCU DX
1 Notes on documentation
1.1 CE label
The declaration of conformity has been issued by the company Hannich GmbH and is included with the sup­ply of the LCU DX.
The cooling unit bears the following mark:
1.2 Information on electromagnetic com­patibility
The LCU DX is a class A device as defined by EN 55022. Under certain circumstances, the device may cause ra­dio interference in domestic environments. In such cas­es, the operator may be asked to implement appropriate measures.
1.3 Storing the documents
The assembly and operating instructions as well as all other applicable documents are an integral part of the product. They must be passed to those persons who are engaged with the unit and must always be available and on hand for the operating and maintenance person­nel.
1.4 Symbols in these operating instructions
The following symbols are used in this documentation:
This symbol indicates an "Action Point" and shows that you should perform an operation/procedure.
1.5 Associated documents
The general plant documentation for the room where the equipment is situated (construction specifications for the ventilation system) also applies in conjunction with these assembly and operating instructions.
1.6 Normative instructions
1.6.1 Legal information concerning the operating instructions
We reserve the right to make changes in content. Rittal GmbH & Co. KG and/or Hannich GmbH are not respon­sible for any damage which may result from failure to comply with these assembly and operating instructions. The same applies to failure to comply with the valid doc­umentation for any accessories used.
1.6.2 Copyright
The distribution and duplication of this document and the disclosure and use of its contents are prohibited un­less expressly authorised. Offenders will be liable for damages. All rights created by a patent grant or registration of a utility model or design are reserved.
1.6.3 Revision
Rev. 0A of 25/01/2016
Danger! Hazardous situation which will result in death or serious injury if the instructions are not followed.
Warning! Hazardous situation which may lead to death or serious injury if the instructions are not followed.
Caution! Hazardous situation which may lead to (minor) injuries if the instructions are not followed.
Note: Information concerning individual proce­dures, explanations, or tips for simplified ap­proaches. Also indicates situations which may result in material damage.
Page 5
Rittal LCU DX 5
2 Safety instructions
EN
2 Safety instructions
The devices in the LCU DX series from Rittal GmbH & Co. KG are developed and manufactured with due re­gard for all safety precautions. Nevertheless, the unit still poses a number of unavoidable dangers and residual risks. These safety instructions provide an overview of these dangers and the necessary safety precautions. In the interests of your own safety and the safety of oth­ers, please read these safety instructions carefully be­fore assembling and commissioning the LCU DX! Follow the user information found in these instructions and on the unit carefully.
2.1 Important safety instructions:
Danger! Electric shock! Contact with live electrical parts may re­sult in fatal injury. Before switching on, ensure that there is no possibility of accidental contact with live electrical parts. The unit has a high discharge current. Before connecting to the supply circuit, therefore, it is essential to make a 6 mm² earth connection (see section 11.7 "Cir­cuit diagram").
Danger! Injury caused by fan impellers. Keep persons and objects away from the fan impellers. Do not remove covers until the power supply is disconnected and impellers are immobilised. Always use mechanical protection when work­ing. Shut down the respective fan during maintenance work, if possible. Tie long hair back. Do not wear loose clothing. The fans will start up again automatically following a power disruption.
Danger! Hot components may cause in­jury! The external unit and the pipelines are hot during operation, and may cause burns on direct contact.
Danger! Risk of poisoning from refriger­ant gases created under the influence of heat. When carrying out welding and solder­ing work, shortness of breath or asphyx­iation may occur. The refrigerant is heavier than air, and in high concentrations may cause short­ness of breath and asphyxiation, by dis­placing the oxygen.
Danger! Risk of poisoning from refriger­ant gases created under the influence of heat. When carrying out welding and solder­ing work on the refrigerant circuit, use protective gloves and breathing appara­tus with a filter. Even a very low concentration of refrig­erant may cause the refrigerant to de­compose in combination with a naked flame, and cause acute shortness of breath.
Danger! Risk of injury from incorrect in­stallation. Installation of the refrigerant lines and other media connections must only be carried out by qualified plumbers or cooling technology specialists.
Danger! Threat to the environment from escaping refrigerant! Never allow the refrigerant to escape into the environment if at all possible (see section 2.3.3 "F-gas regulation").
Danger! Injury due to falling loads! Do not stand under suspended loads when transporting the unit with a hoist trolley, a forklift, or a crane.
Warning! Danger of cut injuries, espe­cially from the sharp edges of the fan module and heat exchanger module. Put on protective gloves before begin­ning assembly or cleaning work.
Page 6
2 Safety instructions
EN
6 Rittal LCU DX
As a general requirement, please observe the following five safety rules to DIN EN 50110-1 (VDE 0105-1) when working in and on the LCU DX, in order to avoid acci­dents:
1. Switch off! Switch off the on-site power supply to the LCU DX.
2. Secure against reactivation.
3. Ensure that all poles are de-energised.
4. Earth and short-circuit.
5. Cover or shield adjacent, live parts.
2.2 Service and technical staff
The installation, commissioning, maintenance and repair of this unit may only be carried out by trained, qualified mechanical, electro-technical and refrigeration engi­neering specialists. Only properly instructed personnel may service a unit while in operation.
2.2.1 Personal safety equipment
Personal safety equipment, which should as a minimum include thermally insulated gloves and protective gog­gles, is to be worn during any work on this unit when personnel might come into contact with refrigerant (see section 11.3 "Information about the refrigerant"). Additionally, in the event of fire, airtight respiratory masks must be worn.
2.3 Operator requirements
In accordance with EU Regulation 842/2006, for a total refrigerant fill volume of more than 2.5 kg (R410A), the operator must carry out a leak test at least once a year. This fill volume is achieved or exceeded with a pipe length of > 28 m. Any leaks that are detected must be repaired immedi­ately.
2.3.1 Abbreviated instructions
The operator must ensure that abbreviated instructions containing the following information are available in a readily accessible location on the LCU DX:
1. Name, address and telephone number of the instal­lation company, its customer service department, or the customer service department of the owner/op­erator, or as a minimum requirement, the individual responsible for the cooling system, together with the address and telephone number of the fire brigade, police, hospitals and burn victims centres.
2. Type of refrigerant: R410A, comprising 50% di­fluoromethane R32 (CH
2F2
) and 50% R125 penta-
fluoroethane (C
2HF5
);
3. Instructions for switching off the cooling system in an emergency (see section 7.2.3 "Switching off in an emergency");
4. The maximum permissible pressures (see sec­tion11 "Technical specifications").
2.3.2 System log
Under DIN EN 378, the operator is required to keep a system log and ensure that it is regularly updated. The system log should contain the following information:
1. Details of all repair work
2. Quantity and type (new, reused or recycled) of refrig­erant added, quantity of refrigerant removed
Warning! Injuries from escaping refriger­ant. Escaping gas may freeze the skin. Be­fore working on the cooling circuit, put on protective gloves and goggles.
Caution! Risk of malfunction or damage! Do not modify the unit. Use only original spare parts.
Caution! Risk of malfunction or damage! Proper operation can only be ensured if the unit is operated under the intended ambient conditions. As far as possible, observe the ambient conditions for which the unit was designed, e.g. tem­perature, humidity, air purity.
Caution! Risk of malfunction or damage! All media required for the control sys­tem, such as the correct fill volume of re­frigerant, must be available throughout the entire operating period of the device.
Caution! Risk of malfunction or damage! Installation, and in particular the laying of the refrigerant pipework between the internal and external unit, must only be carried out by trained, qualified and ac­credited cooling system specialists.
Caution! Risk of malfunction or damage! In order to prevent EMC-related mal­functions during operation, and to allow access for servicing purposes, cross­wiring through the LCU DX to the bayed racks is prohibited.
Note: Rittal offers leak testing of the device as a service.
Page 7
Rittal LCU DX 7
2 Safety instructions
EN
3. Outcome of any analysis of reused refrigerant, if available
4. Origin of reused refrigerant
5. Amendments to and replacement of system com­ponents
6. Results of all regular routine checks and
7. Any significant shutdowns
2.3.3 F-gas regulation
Regulation (EC) No. 842/2006 of the European Parlia­ment and of the Council of 17 May 2006 on certain fluor­inated greenhouse gases entered into force on 4 July
2006. The Regulation regulates the reduction of emis-
sions, the use, recovery and destruction of certain fluor­inated greenhouse gases, and the labelling and disposal of products and equipment containing such gases.
Leak test pursuant to Article 3 (containment)
3kg – 30kg at 12-month intervals (or 6 kg in hermet-
ically sealed systems), – 30 kg – 300 kg at 6-month intervals, – more than 300 kg at 3-month intervals.
2.3.4 Chemicals – Climate Protection Ordinance
This Ordinance applies in addition to the aforementioned Regulation (EC) No. 842/2006 of the European Parlia­ment and of the Council of 17 May 2006 on certain fluor­inated greenhouse gases.
2.4 RoHS compliance
The LCU DX fulfils the requirements of EU Directive 2011/65/EC on the Restriction of Use of Certain Hazard­ous Substances in Electrical and Electronic Equipment (RoHS) of 8 June 2011.
Note: Corresponding information about the RoHS Directive may be found on our website at www.rittal.com/RoHS.
Page 8
3 Device description
EN
8 Rittal LCU DX
3 Device description
3.1 General functional description
The Liquid Cooling Unit DX (DX = Direct Expansion) is essentially a split cooling unit used to dissipate heat losses from server enclosures or for the effective cooling of devices built into a server enclosure. The air routing in the LCP DX supports the "front to back" cooling principle of the devices built into the server enclosure. The hot air expelled by the devices in the server enclosure is drawn in by the fans at the rear di­rectly from the server enclosure or Micro Data Center and then routed through the heat exchanger module. In the heat exchanger module, the heated air is directed through a heat exchanger (refrigerant evaporator), and its thermal energy (heat loss from the server enclosure) is removed from the refrigerant via evaporation. This pro­cess cools the air to a freely selectable temperature, and it is then routed directly in front of the 482.6 mm (19") level in the server enclosure or Micro Data Center. The setpoint (outlet temperature from the cooling unit or server air intake temperature) may be set in the range +18°C to +28°C.
Fig. 1: Air routing on the LCU DX – Top view
Key
1 Installed equipment in the server 2 Server enclosure/Micro Data Center 3Air outlet 4 Heat exchanger 5Fan 6 Air inlet
In the LCU DX, the temperature of the incoming cold air (server air intake) is controlled by continuously compar-
ing the actual temperature with the setpoint temperature (preset to +22°C). If the actual temperature exceeds the setpoint tempera­ture, the speed of the compressor is automatically in­creased, providing a greater cooling output from the heat exchanger, until the setpoint temperature is reached. In the LCU DX, the measured temperature of the extract­ed warm air is used to determine and control the re­quired fan speed. Any condensate incurred is collected in the integral con­densate collecting tray below the heat exchanger, and from there is routed outside via a condensate discharge hose.
3.2 Air routing
In order to achieve sufficient cooling in the server enclo­sure, it is important to ensure that the cooling air passes through the interior of the built-in devices rather than flowing past at the sides. Targeted air routing inside the server enclosure has a major effect on the thermal output to be dissipated. In order to ensure targeted air routing in the system, the server enclosure should be divided vertically into warm air and cold air sections. Essentially, this is already en­sured by the 482.6 mm (19") arrangement and the in­stallation of "front to back" vented servers. Consistent sub-division is achieved with additional plastic foam strips and air baffle plates on the left and right of the
482.6 mm (19") level (see section 13 "Accessories").
If the LCU DX is used to cool a TS IT server enclosure, it is important that this is sealed, by fitting the enclosure with side panels, roof and gland plates. Any existing ca­ble entries should be sealed e.g. using suitable brush strips. Whilst the system is in operation, both the front and the rear doors should be kept completely shut. No slotted doors should be used. When using in the Micro Data Center, the LCU DX is in­serted in a sealed safe structure for application-related reasons.
3.3 Device assembly
3.3.1 Internal unit (evaporator coil)
The internal unit of the LCU DX may be bayed either on the right or left of a server enclosure or Micro Data Center. To this end, the internal unit is mounted directly
5
4
3
6
1
2
Note: The 482.6 mm (19") level must likewise be completely sealed. This is already the case in a fully configured server enclosure. With a partially configured server enclosure, the open height units (U) of the 482.6 mm (19") level must be sealed with blanking plates, which are available as Rittal accessories (see section 13 "Accessories").
Page 9
Rittal LCU DX 9
3 Device description
EN
on fixing brackets on the rear wall of the evaporator coil. The evaporator coil has two condensate collecting trays to enable installation on the left or right of the enclosure. The bottom condensate discharge in each case remains unused. The internal unit is comprised of the following compo­nents: – Housing of powder-coated sheet steel. – Two condensate collecting trays in the enclosure (bot-
tom/top) so that the evaporator coil can be used in
two installation positions. The discharge connection of
the condensate tray has a diameter of 12 mm. – Direct refrigerant evaporator coil of inner-grooved
copper core pipes with aluminium membranes. The
evaporator coil is pressurised with exhaust air from the
server in order to ensure heat absorption (heat dissi-
pation) via the refrigerant flowing into the copper
pipes. – Evaporator coil fan as linear controlled EC fan. – Full electronic control of all components in the internal
unit, for evaporator coil fan speed control, server in-
take air temperature control, and power demand from
the external unit. The controller has temperature sen-
sors built into the intake and exhaust side of the inter-
nal unit, as well as on the evaporator coil itself. – Additional temperature sensor in the server front.
3.3.2 External unit (inverter-controlled cooling
unit)
The external unit is comprised of the following compo­nents: – Housing of weather-proof, stove-enamelled sheet
steel. – Compressor for compressing and circulating the re-
frigerant from the low-pressure side (internal unit) to
the high-pressure side (external unit). The motor is ac-
tivated by an external inverter, which controls the
speed of the compressor and therefore allows the
cooling output to be precisely adapted to the actual
cooling requirement. – Full electronic control of all components and measure-
ment devices on the external unit, including various
sensors and pressure measuring devices. – Condenser for condensing the compressed refriger-
ant so that it can be returned to the evaporator coil via
the expansion valve in liquid form. The condenser is
comprised of copper core pipes with aluminium mem-
branes and a DC fan motor, which is speed-controlled
to adjust the output. – Electronic expansion valve to supply the evaporator
coil with the required volume of refrigerant, so as to
ensure the corresponding optimum thermal absorp-
tion capacity to suit the current output requirements.
The expansion valve is electronically regulated via the
pilot wire from the evaporator coil.
3.3.3 Refrigerant lines and electrical pilot wires
The medium connection lines between the internal unit and the external unit are comprised of the following components: – Pair of refrigerant lines as a refrigerant suction line (re-
turn) and refrigerant liquid line (inlet), including conden­sate insulation. Refrigerator-quality copper pipes should be cleaned and dried (to DIN EN 12735-1/DIN
1786) and sealed before use.
– Electrical and pilot wire lines between the internal unit
and the external unit in a UV-resistant design.
3.4 Proper and improper usage
The LCU DX is used to dissipate low to medium heat losses and for the effective cooling of devices built into a server enclosure/Micro Data Center. The unit is de­signed solely for static use in sealed rooms. The unit is state of the art and built according to recog­nised safety regulations. Nevertheless, improper use can pose a threat to the life and limb of the user or third parties, or result in possible damage to the system and other property. Consequently, the unit must only be used properly and in a technically sound condition! Any malfunctions which impair safety should be rectified immediately. Proper usage also includes following the operating in­structions and fulfilling the inspection and maintenance conditions. Inappropriate use can be dangerous. Examples of inap­propriate use include: – Use of another external unit – Improper operation – Use of a refrigerant other than R410A – Use of a refrigerant fill volume other than that specified – Installation of the external unit in an unsuitable position – Improper rectification of malfunctions – Use of replacement parts which are not authorised by
Rittal GmbH & Co. KG
– Non-static use, e.g. on moving or vibrating machines
Page 10
3 Device description
EN
10 Rittal LCU DX
3.5 Scope of supply for the LCU DX
The supply of an LCU DX in the "single" variant includes the following:
The supply of an LCU DX in the "redundant" variant in­cludes the following:
Qty. Parts
1
LCU DX
, ready to connect, consisting of:
1 Internal unit
1 Remote control/operating unit
1 Holder for operating unit (482.6 mm (19") con-
sole, 3 U)
1 Temperature sensor, server front
1 Condensate discharge hose with copper si-
phon
1 External unit
1 Set of accessories for mounting the internal
unit and for the air block panel
1 Assembly and operating instructions
Tab. 1: Scope of supply of an LCU DX, "single" variant
Qty. Parts
1
LCU DX
, ready to connect, consisting of:
1 Internal unit
2 Remote control/operating unit
1 Holder for operating unit (482.6 mm (19") con-
sole, 3 U)
2 Temperature sensor, server front
1 Condensate discharge
2 External unit
1 Set of accessories for mounting the internal
unit and for the air block panel
1 Assembly and operating instructions
Tab. 2: Scope of supply of an LCU DX, "redundant" variant
Page 11
Rittal LCU DX 11
4 Transport and handling
EN
4 Transport and handling
4.1 Transport
The LCU DX is delivered shrink-wrapped on a pallet.
4.2 Unpacking
Remove the packaging materials from the unit.
Check the unit for any damage that may have oc-
curred during transport.
Place the unit in its intended location.
Caution! Because of its height and narrow base, the LCU DX is liable to tip over. Risk of toppling, especially after the unit is re­moved from the pallet!
Caution! Transportation of the LCU DX without a pallet: Use only suitable and technically sound lifting gear and load-bearing devices with sufficient load capacity.
Note: After unpacking, the packaging materials must be disposed of in an environmentally friendly way. They consist of the following materials: Wood, polyethylene film (PE film), strap, edge protectors.
Note: Damage and other faults, e.g. incomplete de­livery, should be reported immediately, in writing, to the shipping company and to Rittal GmbH & Co. KG.
Page 12
5 Assembly and siting
EN
12 Rittal LCU DX
5 Assembly and siting
5.1 General
5.1.1 Siting location requirements
To ensure proper functioning of the LCU DX, the follow­ing conditions for the siting location of the device must be observed.
Climatic conditions
When choosing a siting location for the internal unit and external unit, please observe the values pre­scribed in section 11 "Technical specifications" for the
ambient temperature, dewpoint and air purity. According to ASHRAE Directive TC 9.9, a maximum room temperature of 30°C at 50% relative humidity must be observed at the internal unit's siting location. This equates to a dew point of 19°C. If these limits are ex­ceeded, there is a risk of condensation forming on the air outlet of the internal unit.
Floor conditions
– The floor of the installation space should be rigid and
level. – Choose the location carefully so that the unit is not sit-
uated on a step or uneven surface, etc.
Minimum required thermal output in the enclosure
In order to achieve continuous operation of the LCU DX, a heat load of at least 1 kW (3 kW version) or 3 kW (6.5 kW version) respectively must be installed in the en­closure. Otherwise, intermittent operation of the system may occur.
5.1.2 Relative positioning of the internal unit to
the external unit
The internal unit and the external unit must be connect­ed with a suitable copper pipe connection to DIN EN 378-2. The entire system must then be filled with refrig­erant (cf. section 6.2 "Notes on pipework"). The following distances and geodetic height differences must not be exceeded when installing the internal unit and external unit:
5.1.3 Supply connections required at the installa­tion site
Power is usually supplied to the external unit.
LCU DX 3 kW
LCU DX 6.5 kW
5.1.4 Electromagnetic interference
– Interfering electrical installations (high frequency) are
to be avoided.
5.2 Assembly procedure
5.2.1 Preparatory tasks
The internal unit may be mounted both on the right and on the left of the TS IT server enclosure. Before the internal unit of the LCU DX can be installed in a TS IT server enclosure, the following work should be carried out.
Slide the 482.6 mm (19") mounting angles 50 mm away from you.
Recommendation: Where necessary, these values should be achieved by installing an additional room air­conditioning system.
Position Distance
Maximum equivalent pipeline length
LCU DX 3 kW: 30 m LCU DX 6.5 kW: 50 m
Of which maximum height difference
12 m
Tab. 3: Distances and height differences
Connection type Connection description
Electrical connection LCU DX 3 kW
230 V, 1~, N, PE, 50 Hz
Electrical fuse provid­ed by the customer
16 A, miniature circuit-breaker with C characteristic
Refrigerant connec­tion
Copper pipework
Tab. 4: Supply connections for the LCU DX 3 kW
Connection type Connection description
Electrical connection LCU DX 6.5 kW
230 V, 1~, N, PE, 50 Hz
Electrical fuse provid­ed by the customer
20 A, miniature circuit-breaker with C characteristic
Refrigerant connec­tion
Copper pipework
Tab. 5: Supply connections for the LCU DX 6.5 kW
Note: Installation in a Micro Data Center is de­scribed in the assembly instructions for the Micro Data Center. The assembly parts re­quired for the internal unit are included with the supply of the Micro Data Center.
Note: The LCU DX may only be operated in combi­nation with 482.6 mm (19") mounting angles. Installation with a 482.6 mm (19") mounting frame is not possible.
Page 13
Rittal LCU DX 13
5 Assembly and siting
EN
Fig. 2: Move the 482.6 mm (19") level sideways
Ensure that the front distance from the 482.6 mm (19") mounting angle to the front edge of the TS frame is at least 100 mm.
Fig. 3: Move the 482.6 mm (19") level in the depth
Position the punched section with mounting flange as shown in the assembly drawing (Fig. 18) and attach it to the inner level of the TS frame (mounting side).
Remember to maintain a distance of at least 15 cm between the roof plate and the top edge of the internal unit.
Locate the two mounting devices supplied loose for installing the internal unit into the lower punched sec­tion with mounting flange.
Fig. 4: Arrangement of the internal unit
Key
1 Internal unit 2 Rear wall of internal unit 3 Mounting device 4 Punched section with mounting flange 5 Assembly screw
5.2.2 Mounting the internal unit
Position the internal unit on the mounting devices in such a way that the air outlet opening is on the opera­tor side of the server enclosure, and the fans are in the rear section. The end face of the internal unit must be flush with the front edge of the TS frame.
Align the internal unit horizontally.
In this position, screw the internal unit to the punched section with mounting flange using the attachment points provided (at the top and bottom of the rear pan­el).
5.2.3 Mounting the internal unit accessories
Install the remote control (3U trim panel) with the built­in operating units at the top of the 482.6 mm (19") lev­el, on the maintenance side of the rack.
Fig. 5: Mounting the internal unit accessories
Key
1 Remote control (3U trim panel) 2 Control and display device 1 3 Control and display device 2 4 Second control and display device 1 for "redundant" ver-
sion
For the "single" version, fit the external temperature sensor included with the supply in a suitable position in front of the server installations.
5 4
2
1
3
4
3
1 2
Page 14
5 Assembly and siting
EN
14 Rittal LCU DX
For the "redundant" version, fit the second external temperature sensor included with the supply, likewise in a suitable position in front of the server installations.
5.2.4 Mounting the external unit
The external unit may be secured to a solid wall or onto a flat roof or concrete surface using wall brackets (ac­cessory, not included with the supply). Please observe the following instructions regarding the installation site: – The external unit is weather-resistant and may there-
fore be installed completely in the open air, with no need for a weather protection canopy etc.
– For continuous operation, the base surface must rise
above the snow zone.
– It is also important to ensure that foreign bodies such
as leaves cannot be drawn into the external unit.
– The external unit must not be exposed to extreme
wind conditions, otherwise the heat exchanger could be excessively under-cooled, or the fan would need to work against the wind and be unable to move the re­quired volume of air.
– If necessary, a wind break should be installed at a dis-
tance of 1 m from the device.
– If the unit is installed underneath a canopy, there must
be a distance of at least 2 m between the floor and the
canopy. The following distances should be observed for mainte­nance purposes:
Fig. 6: Distances from external unit
Key
1 Air inlet 2Distance > 300mm 3 Clearance for maintenance: Distance > 600 mm 4Air outlet 5Distance > 200mm 6 External unit 7Distance > 600mm 8 Roof area/foundations 9 Strip foundation 10 Assembly screws/vibration dampers
The installation site of the external unit must be care­fully selected to ensure an adequate supply and distri­bution of the airflow, even in unfavourable conditions.
Install the external unit on brackets, remembering to observe the required minimum distance from the wall.
Attach the external unit to the base plate to avoid the risk of tipping over.
Fig. 7: Attachment points for external unit
Key
1 4 x M10 plugs per external unit 2Distance > 600mm
2
10
6
6
6
7
8
9
1
1
2
3
4
5
2
1 1
Page 15
Rittal LCU DX 15
5 Assembly and siting
EN
Fig. 8: Top view of attachment points
Key
1 For 3 kW unit: 550 mm
For 6.5 kW unit: 560 mm 2 Distance 1000 mm 3 For 3 kW unit: 325 mm
For 6.5 kW unit: 335 mm 4 12 x 20 mm elliptical drilled holes
1 12
3
4
Page 16
6 Installation
EN
16 Rittal LCU DX
6 Installation
6.1 General information
The internal unit and the external unit must be connect­ed with suitable copper pipework. With the TS IT server enclosure, this pipework can either be inserted into the enclosure from above or from below. When using in a Micro Data Center, a cable duct is pro­vided and this must be used for inserting the pipework into the safe. In its delivered state, the internal unit is filled with 1.5 bar nitrogen. It is therefore crucial that the following steps are carried out in the order shown.
6.2 Notes on pipework
The following basic rules should be observed when con­necting the internal unit and external unit.
General information
1. The pipes may only be made from special copper piping that has been cleaned on the inside and sealed at both ends. The material of the copper pipework must comply with the specifications out­lined in EN 12735-1 / EN 12735-2 and DIN 8964-3.
2. The external diameters of the copper pipes for the intake gas line from the internal unit to the external unit, as well as the liquid line from the external unit to the internal unit, must comply with the values given in section 11 "Technical specifications".
In order to ensure the correct spatial arrangement of the pipework, particular consideration should be given to the position of the individual pipes, the flow conditions (two-phase flow, oil transportation in part-load opera­tion), condensation processes, thermal expansion, vi­bration, and good accessibility.
As a general rule, pipelines should be laid in such a way as to prevent damage associated with routine activities. For safety reasons, and in order to protect the environ­ment, the following aspects should be taken into ac­count when laying pipework:
1. There must not be any threat to human safety, i.e. escape and emergency vehicle routes must not be obstructed or restricted in any way. No detachable connections or fittings must be positioned in publicly accessible areas.
2. Pipework should be protected from the thermal in­fluence of hot lines and heat sources by means of spatial separation.
3. Refrigerant lines must be protected or covered if there is a risk of damage.
4. Flexible connecting parts such as connection lines between indoor and outdoor devices that could be­come displaced during regular work operations must be protected against mechanical damage.
5. The maximum distance between the supports of the copper pipes is 1 m for pipelines with 1/4" to 3/8",
1.25 m for pipelines with 1/2" to 5/8" and 2 m for pipelines with 3/4" to 7/8".
Laying the pipework
1. The equivalent length of the overall line between the internal unit and the external unit must not exceed the maximum length as set out in section 11 "Tech­nical specifications". To calculate the equivalent length, in addition to the actual length of the pipeline, you should also make allowance for the equivalent length of curves and valves.
2. The number of curves should be kept to a bare min­imum so as to avoid pressure losses. Where curves are unavoidable, the radius chosen should be as large as possible.
3. Generally speaking, the lines between the internal unit and external unit should take the shortest pos­sible route. Exceptions are only admissible to avoid unnecessary bends or circumvent extreme heat sources.
4. Where possible, refrigerant lines should not be rout­ed through rooms where people spend a lot of time, such as offices or meeting rooms.
5. The intake gas line must be laid with an incline of 1% in the direction of flow of the refrigerant.
6. When laying refrigerant lines, please ensure that there is no overarching of liquid lines and no dipping of gas lines (intake gas line). Oil could collect here, or in the case of the liquid line, gas bubbles could form.
Caution! Risk of malfunction or damage! Installation work, particularly the laying of the refrigerant pipework between the internal and external unit of the LCU DX, must only be carried out by trained, qualified and accredited cooling system specialists.
Note: Installation of the pipework, creation of a vac­uum and filling with refrigerant must only be carried out by qualified, accredited special­ists in accordance with the valid technical regulations. Furthermore, when carrying out the installa­tion, it is important to observe all the pipe­work instructions in section 6.2.
Note: Routing and support of the pipework has a significant influence on a cooling system's operational reliability and service-friendliness.
Page 17
Rittal LCU DX 17
6 Installation
EN
7. For intake gas lines laid vertically with the direction of flow pointing upwards (external unit is above the in­ternal unit), an oil elevation arc should be provided at least every 3 m of line length. The pre-insulated pairs of lines may be laid with no distance between them.
Protecting the pipework
1. Suitable precautions should be taken to prevent ex­cessive vibrations or pulsations. In particular, care should be taken to prevent the direct transmission of noise or vibrations onto or through the supporting structure and the connected devices.
2. Safety devices, pipework and fittings should be pro­tected from unfavourable environmental influences as far as possible. Due consideration should be giv­en to unfavourable environmental influences, such as the risk of water collecting, relief lines freezing, or dirt and waste accumulating.
3. With long pipelines, adequate precautions should be taken with regard to expansion and contraction.
4. The pipelines of cooling systems should be de­signed and laid in such a way that the system cannot be damaged by liquid slugging (hydraulic shock).
5. Pipelines with detachable connections must not be positioned in public thoroughfares, vestibules, stair­wells, steps, entrances, exits or in ducts or shafts with unsecured openings to such areas, unless pro­tected against disconnection.
6. Pipelines without detachable connections, valves, control and regulatory devices that are protected against accidental damage may be positioned in public thoroughfares, stairwells or vestibules, pro­vided they are situated at least 2.2 m above the ground.
Pipe supports
1. Both horizontal and vertical lines must be laid with vi­bration-damping elements (such as rubber seals). These must be used at a spacing of at least 2 m.
2. Take care to ensure that the first pipe support be­hind the internal unit and in front of the external unit does not exert any mechanical pressure (via the pipe) on the component. Pipe supports must not be located too close to bends, to give the lines space to expand.
Create the pipework system
1. To create the refrigerant pipework system, open the ends of the lines on the internal unit. Upon opening, gas should flow out audibly (from the nitrogen filling provided in the factory) as an indication that there are no leaks in the cooling circuit.
2. Only cut pipes to length using a pipe cutter.
3. Never saw pipes, as this could create swarf.
4. Only solder pipes under nitrogen or helium! To this end, allow dry inert gas to flow into the pipe at one end of the pipeline which has already been created. Before starting, introduce a powerful current, reduce this to a minimum when you start soldering, and maintain this weak flow of protective gas throughout the entire soldering process.
5. Before soldering the final connection, loosen the screw connection on the external unit, or leave it un­tightened throughout, so that overpressure cannot build up in the pipeline system. Immediately after soldering, tighten the screw connection.
6. The pipelines may only be connected to the external unit with flares. However, flare connections should be restricted to soft pipes! After cutting the pipes to length, adjust to the correct internal diameter with light flaring. The flares must be tightened with the prescribed torque using a torque wrench.
Low-temperature insulation of the liquid line and intake gas line
1. Both lines outside and inside the building should be equipped with low-temperature insulation to DIN 4140 made from UV-resistant HT/Armaflex or an equivalent material.
2. We recommend a wall thickness of 9 mm
Leak test / conducting the leak test
The system must undergo leak testing as a complete system. A test should also be carried out on site once the installation is complete. Multiple techniques may be used to test for leaks, de­pending on the manufacturing conditions, such as pres­surisation with inert gas, or leak detection using radioac­tive gas. In order to avoid emissions of hazardous sub­stances, the pressure test may be carried out with inert gas such as nitrogen, helium or carbon dioxide. Oxy­acetylene and hydrocarbons must not be used for safety reasons. Air and gas mixtures are to be avoided, since certain mixtures may be hazardous. The manufacturer must select a test method which al­lows suitable results to be achieved in accordance with the requirements outlined below.
Note: Vibrations and pulsations should be as­sessed with the system operational at maxi­mum condensation temperature and when switching the system on and off, which has unfavourable impacts on the pipework.
Note: The internal unit is pressurised (filled with pro­tective gas)!
Page 18
6 Installation
EN
18 Rittal LCU DX
Connections must be checked with a detector or using a technique with a detection sensitivity as described in EN 1779 with a bubble test (application of liquid) if the test pressure is 1 x PS.
The manufacturer must verify that the test method used complies with the aforementioned requirements. EN 1779:1999 may be used as a basis for this test. The detector must be calibrated at regular intervals as per the manufacturer's instructions. Any leak detected must be repaired and subjected to a further leak test.
1. Systems with dry nitrogen should be tested at a maximum overpressure of 28 bar. When doing so, the shut-off valves on the external unit should remain closed. The external unit is pre-filled with refrigerant and this must not be allowed to escape.
2. Check the complete pipe network and the system parts for leaks. We recommend using Nekal spray to check every connection, including screw connec­tions, for leak-proofness.
Evacuating
1. After checking for leaks, remove the air from the sys­tem. To do so, connect a vacuum pump and evac­uate to a pressure of < 0.3 mbar (absolute pressure).
2. Break the vacuum at least twice, refill the system with nitrogen, and evacuate again. Where possible, implement double-sided evacuation of the suction side and the pressure side of the compressor, to which end a test/measurement connection must be made in the liquid line.
Filling with refrigerant
1. The external unit is prefilled in the factory, the fill vol­ume is adequate for a 5 m line pair. For longer pipe lengths, additional refrigerant should be added in accordance with section 11 "Technical specifica­tions".
2. The system must only be filled gravimetrically (i.e. by weight) using refrigerant as the liquid in the liquid line. Only liquid R410A should be added. After­wards, switch on the device and whilst it is running, continue carefully restricted filling via the intake side of the external unit until the required fill volume has been added.
3. The set volume of refrigerant is determined by weighing the refrigerant bottle during the filling pro­cess.
4. The additional fill volume or the new total fill volume should be noted on the rating plate and operating manual.
6.3 Connecting the condensate discharge
Any condensate which may develop is collected in the condensate collecting tray of the internal unit. For univer­sal use, the internal unit has two condensate collecting trays which may be fitted on the left or right of the enclo­sure, depending on the installation position.
Connect the discharge hose supplied loose (internal diameter 12 mm) at the bottom connection (external diameter 12 mm). The tray at the top is not used.
Route the discharge hose to a drain with odour seal provided by the customer, so that any condensate can be discharged from the device.
6.4 Electrical connection
6.4.1 General
The electrical connection can only be made on the ex­ternal unit. The internal unit is supplied with power via the external unit. A 3-wire power cable should be used for this purpose. The corresponding pilot wires from the internal unit to the external unit should be laid with the re­frigerant lines in accordance with section 11.7 "Circuit diagram".
Note: Lower test pressures are admissible, provid­ed there is an equivalent detection sensitivity.
Note: In order to ensure safe condensate dis­charge, the following points should be ob­served: – Lay the discharge hose so that it always
runs downhill and without any kinks.
– Do not constrict the hose cross-section.
Note: Please keep the wiring plan readily available so that it is always on hand when needed. This is the only authoritative documentation for this unit.
Caution! Work on electrical systems or equip­ment may only be carried out by an elec­trician or by trained personnel under the guidance and supervision of an electri­cian. All work must be carried out in ac­cordance with electrical engineering regulations.
Contact with live electrical parts may re­sult in fatal injury.
The unit may only be connected after the aforementioned personnel have read this information!
Use only insulated tools.
Page 19
Rittal LCU DX 19
6 Installation
EN
6.4.2 Connecting the external unit
Power is supplied to the external unit via a 3-wire con­nection cable (230–240 V, 1~, N, PE). As external units are generally sited outdoors, a UV-resistant cable should be used.
Strip approximately 45 mm from the rubber sheathing of the connection cable.
Trim the neutral conductor (N) and the phase conduc­tor (L) to a length of approximately 35 mm. Leave the length of the PE conductor at approximately 45 mm.
Remove approximately 9 mm from the insulation of all conductors with a suitable tool.
Fig. 9: Dimensions for removing the rubber sheathing and in-
sulation
Attach wire end ferrules without insulating collar to the ends of the cables, using a four-jaw pressing tool.
Insert the cable into the connection box in the device from below.
Attach the cooling unit to the strain relief provided.
Connect the cable in the connection box as shown in the circuit diagram in section 11.7 "Circuit diagram" to the correspondingly labelled terminals (PE, L1, N).
Connect the external units using an all-pole isolating device as described in DIN EN 60335-2-40. This dis­connector device must ensure at least 3 mm contact opening when switched off.
The customer should provide a pre-fuse in the supply line to the external unit, as specified on the rating plate of the device.
6.4.3 Connecting the internal unit
Connecting the internal unit simply entails connecting the cables routed from the external unit, which comprise a data line and a 230 V pilot wire as described in section 11.7 "Circuit diagram". The fault signals may be picked off at the internal unit (floating contacts).
Should you wish to switch the internal unit on and off via a remote switch (e.g. for an external fire shutoff), connect a remote contact (normally open contact) in the electronic box to terminals L1 and 11 for the "sin­gle" version and terminals L1 and 11 as well as L2 and 23 ("remote" or "ON/OFF") for the "redundant" version (see section 11.7.3 "Circuit diagram, external unit"). In
the closed state, the system is then deactivated. If both terminals are jumpered, the status message "– –" will appear in the display.
6.5 Checking the entire system prior to
commissioning
Before operating the cooling system, the entire system, including the complete cooling system, must be checked for conformity with the relevant diagrams, sys­tem flow charts and piping and instrumentation dia­grams, and wiring plans. Cooling systems must be checked by a trained plant in­spector (as defined in EN 13313) and should include a review of the following points:
1. Inspect the documents.
2. Check the safety switchgear for pressure limiting to
ensure that the safety switchgear for pressure limit­ing is operational and correctly installed.
3. Check selected hard solder connections on pipe-
work for compliance with EN 14276-2.
Caution! Follow the connection regulations of the appropriate electrical power company.
The voltage specified in the wiring plan or on the rating plate must match the mains voltage.
The unit has a high discharge current. Before connecting to the supply circuit, therefore, it is essential to make a 6 mm² earth connection (see section 11.7 "Cir­cuit diagram").
The pre-fuse specified in the wiring plan / rating plate should be provided to protect the cable and equipment from short-circuits. The unit must be individu­ally fused.
The unit must be connected to the mains using an all-pole red/yellow isolating de­vice as described in DIN EN 60335-2-40, which ensures at least 3 mm contact opening when switched off.
No additional control equipment may be connected upstream of the device at the supply end.
45
99
Danger! Take utmost care not to short-circuit the phase conductor with the zero conduc­tor or the earth conductor. Otherwise, there is a risk of damage or injury.
Page 20
6 Installation
EN
20 Rittal LCU DX
4. Check the refrigerant pipelines.
5. Inspect the report on the cooling system leak test.
6. Visually inspect the cooling system.
7. Check the labels. This inspection must be documented; see EN 378-2, section 6.4.3. No cooling system may be operated with­out the correct documentation. The installer must document the fact that the system was installed in accordance with the construction re­quirements and state the safety and control device set­tings, if adjustable, following commissioning. This docu­mentation must be kept by the installer and presented upon request.
6.6 Installing the server
As a general rule, the cooling system is designed for "front to back" cooling – in other words, the devices in­stalled in the enclosure must likewise follow this air rout­ing. To this end, the area in front of the 482.6 mm (19") level is supplied completely with cold air. The servers draw the cooling air they require from this area, and ex­pel the warm air downwards or sideways. The area at the rear may reach a high temperature. This is intention­al, since it increases the transmission performance of the heat exchanger in the internal unit.
Distribute the equipment you wish to install evenly across the 482.6 mm (19") level.
Close any areas you do not require with 482.6 mm (19") blanking plates.
Cover the side opposite the internal unit in the enclo­sure with an air baffle plate (see section 13 "Accesso­ries").
Fig. 10: Air baffle plate on the side opposite the LCU internal
unit
Key
1 Air baffle plate
Exchange the brush strip of the standard air baffle plate in the TS IT server enclosure for the brush strip with shorter brushes included with the supply of the LCU DX. The brush strip is included with the supply in two parts.
Remove the top corner of the air baffle plate near the TS frame using an angle grinder or other suitable tool.
Fig. 11: Cut-out in the air baffle plate
Key
1TS frame 2 Cut-out for TS frame 3 Air baffle plate
Fig. 12: Dimensions of the cut-out
Partition the remaining gap between the 482.6 mm (19") level and the internal unit, as well as above and below the internal unit, using the foamed plastic sup­plied loose with the LCU DX.
Cut the foamed plastic to the required size.
1
2
3
1
45
Page 21
Rittal LCU DX 21
6 Installation
EN
Fig. 13: Partitioning with foamed plastic pieces on the side of
the LCU internal unit
Key
1 Partitioning above 2 Partitioning inside 3 Partitioning below
3
1
2
Page 22
7 Operation
EN
22 Rittal LCU DX
7Operation
This section describes operation of the LCU DX using the control and display devices.
7.1 Control and display devices
Control and display device 1 is located in the 3U trim panel on the maintenance side of the rack. In the "single" version, there is one such display device installed, and in the "redundant" version there are two.
Fig. 14: Control and display device 1
Key
1ON/OFF button 2 "Up" button (temperature) 3 "Down" button (temperature)
Control and display device 2 is likewise located in the 3U trim panel on the maintenance side of the rack. In both the "single" version and in the "redundant" version, there is only one control device of this type installed. In addition to control and display device 1, control and display device 2 regulates the start-up response follow­ing a power failure or if the minimum cooling load is un­dercut.
Fig. 15: Control and display device 2
Key
1 "Up" button (temperature) 2 "Down" button (temperature) 3ON/OFF button 4Set button 5 Defrost switch (deactivated) 6Light
Control and display device 3 is located on the end face of the internal unit. In the "single" version, there is one such control and display device installed, and in the "re­dundant" version there are two. The operating status can be read from control and dis­play device 3 on the internal unit. In addition to the con-
trol lights for operation, malfunction and defrost, the set temperature or a fault code can be read from the two­digit LCD display.
Fig. 16: Control and display device 3
Key
1 Manual (to request operating statuses) 2 Operation (permanently illuminated during operation,
flashes when the system is being booted up) 3 Timer (no function) 4DEF/FAN (no function) 5 Alarm (flashes red in case of malfunction) 6 LCD display 1 and 2 (displays a fault code in case of an
alarm)
7.2 Switching the LCU DX on and off
7.2.1 Switching on the internal and external units
Once both the internal unit and the external unit are elec­trically connected, carry out the following two steps:
Switch on the on-site power supply to the external unit. The internal unit is supplied with power via the external unit.
Switch on the LCU DX on control and display device 1 using the "ON/OFF button".
7.2.2 Switching off the internal and external units
To switch off the LCU DX and the condenser, proceed as follows:
Switch off the LCU DX on control and display device 1 using the "ON/OFF button".
Switch off the on-site power supply to the external unit.
7.2.3 Switching off in an emergency
To switch off the LCU DX in an emergency, proceed as follows:
Switch off the on-site power supply to the external unit.
7.3 Setting the setpoint temperature
The setpoint temperature (outlet temperature of the in­ternal unit or server air intake temperature) is set on con­trol and display devices 1 and 2 using the arrow keys. It is essential that both values are set identically. Observe the manufacturer's information on temperature settings for the components built into the server enclo­sure. We recommend a setting within the range 22°C– 25°C. Because the LCU DX cannot actively regulate hu­midity, where necessary the set temperature should be adjusted in line with the ambient conditions.
2
1
3
2
1
3
5
6
4
1 2345 6 7
Page 23
Rittal LCU DX 23
7 Operation
EN
First set the required setpoint temperature on control and display device 1.
For the "redundant" version, also set the same set­point temperature on control and display device 2.
On control and display device 2, keep the Set button held down for 3 seconds. Your setting is displayed.
Using the arrow keys, set the same setting as previ­ously set on control and display device 1.
Confirm this value by pressing the Set button again. The setpoint is displayed on control and display unit 2.
As a general rule, the setpoints on all control compo­nents should be set to the same value.
Page 24
8 Troubleshooting
EN
24 Rittal LCU DX
8 Troubleshooting
8.1 General
If there is a malfunction or alarm on the device, a corre­sponding error message will be displayed on control and display device 3. In the event of a serious malfunction, the red LED will be illuminated and the alarm relay will
switch (collective fault signal). The corresponding fault code may be read from the 2-digit LCD display.
8.2 List of error messages
Note: For technical queries, or if servicing is re­quired, please contact Rittal using the ad­dresses shown in section 15 "Customer service addresses".
No. Description of malfunction LED 1
Operation
LED 2 Timer
LED 3
DEF. FAN
LED 4 Alarm
Malfunction
code in display
1 Clash between operating modes 5 Hz E0
2
Communication malfunction between in­ternal and external unit
5Hz E1
3
Temperature sensor for server air intake defective or missing
5Hz E2
4
Pipe temperature sensor T2 defective or missing
5Hz E3
5
Register temperature sensor T2B defec­tive or missing
5Hz E4
6 EEPROM defective 1 Hz E7
7 Error in external unit 1 Hz Ed
8
KJR 10 B blocked by operation with re­mote ON/OFF contacts on the clamping strip
1Hz CP
9
Display cold air or defrosting Continu-
ous light
Continu­ous light
Page 25
Rittal LCU DX 25
9 Inspection and maintenance
EN
9 Inspection and maintenance
The following maintenance work should be carried out on the LCU DX: – The condensate discharge device should be checked
regularly for correct functioning.
– Regularly check the refrigerant circuit and all main
components for correct functioning (at least once a year according to DIN EN 378).
– Regularly check for leaks using a suitable device (an-
nually) as required by the F-gas regulation (see section 2.3.3 "F-gas regulation" and section 2.3.4 "Chemicals – Climate Protection Ordinance").
Note: At an ambient temperature of 40°C, the nom­inal service life of the built-in fan is 40,000 op­erating hours.
Page 26
10 Storage and disposal
EN
26 Rittal LCU DX
10 Storage and disposal
During storage, both the internal as well as the external unit must stand upright. Disposal can be performed at the Rittal plant. Please contact us for advice.
Caution! Risk of damage! The LCU DX must not be subjected to temperatures above +50°C during stor­age.
Caution! Risk of environmental contami­nation! Never allow refrigerant from the cooling circuit or oil from the compressor to es­cape into the environment. Refrigerant and oil must be properly dis­posed of in accordance with the valid national legislation and regulations.
Page 27
Rittal LCU DX 27
11 Technical specifications
EN
11 Technical specifications
11.1 LCU DX 3 kW
Technical specifications Internal unit
External unit
Description/Model No. 3311490: LCU DX 3 kW "single" version
Description/Model No. 3311491: LCU DX 3 kW "redundant" version
Dimensions and weight
Dimensions (width x height x depth) [mm] 105 x 1550 x 820 810 x 558 x 310
Weight, max. [kg] 48 38
Electrical connection
Type of electrical connection Connection clamp
Rated voltage [V, Hz] 1~/N/PE 230, 50
Rated current [A] 7
Start-up current [A] 4.9
Pre-fuse T [A] 16
Max. power consumption [kW] 1.6
Duty cycle [%] 100 100
Cooling output
Nominal cooling output [kW] L22* L35 3.5 (* server inlet air temperature)
Power consumption at nominal cooling output [kW] L22* L35 1.35 (* server inlet air temperature)
Energy Efficiency Ratio (EER) L22 L35 2.6
Air throughput, max. [m
3
/h] 2,500
Cooling circuit
Refrigerant / filled weight [kg] R410A/1.8 (Fluid Group 2)
Additional refrigerant from the 5th metre [g/m] 30
Max. permissible pressure [bar] PS HP: 42
PS LP: 28
Pipe cross-section, intake gas line 1/2"
Pipe cross-section, liquid line 1/4"
Other information
Storage temperatures [°C] -20…+50
Temperature range [°C] +15…+35 -20…+45
IP protection category IEC 60529 IP 20 IP X4
Noise level [dB (A)] 65 (distance 1 m) 40 (Open air above reflective
flooring, distance 10 m)
Colour RAL 7035 White
Tab. 6: Technical specifications for the LCU DX 3 kW
Page 28
11 Technical specifications
EN
28 Rittal LCU DX
11.2 LCU DX 6.5kW
Technical specifications Internal unit
External unit
Description/Model No. 3311492: LCU DX 6.5 kW "single" version
Description/Model No. 3311493: LCU DX 6.5 kW "redundant" version
Dimensions and weight
Dimensions (width x height x depth) [mm] 105 x 1550 x 820 845 x 700 x 320
Weight, max. [kg] 48 48
Electrical connection
Type of electrical connection Connection clamp
Rated voltage [V, Hz] 1~/N/PE 230, 50
Rated current [A] 15.9
Start-up current [A] 5.4
Pre-fuse T [A] 20
Max. power consumption [kW] 3.6
Duty cycle [%] 100 100
Cooling output
Nominal cooling output [kW] L22* L35 6.2 kW (* server inlet air temperature)
Power consumption at nominal cooling output [kW] L22* L35 3.14 kW (* server inlet air temperature)
Energy Efficiency Ratio (EER) L22 L35 1.97
Air throughput, max. [m
3
/h] 4,800
Cooling circuit
Refrigerant / filled weight [kg] R410A/1.8 (Fluid Group 2)
Additional refrigerant from the 5th metre [g/m] 30
Max. permissible pressure [bar] PS HP: 42
PS LP: 28
Pipe cross-section, intake gas line 5/8"
Pipe cross-section, liquid line 3/8"
Other information
Storage temperatures [°C] -20…+50
Temperature range [°C] +15…+35 -20…+45
IP protection category IEC 60529 IP 20 IP X4
Noise level [dB (A)] 66 (distance 1 m) 40 (Open air above reflective
flooring, distance 10 m)
Colour RAL 7035 White
Tab. 7: Technical specifications for the LCU DX 6.5 kW
Page 29
Rittal LCU DX 29
11 Technical specifications
EN
11.3 Information about the refrigerant
To avoid damage to the device, Rittal prescribes the use of refrigerant R410A. R410A is virtually azeotropic and is comprised of equal parts of R32 and R125. The basic properties of R410A are: – No ozone depletion potential –Clear – Liquefied gas smelling of ether – Non-combustible – Low toxicity
11.4 Cooling output
Due to the device configuration comprising two sub­units, and the partially linear operation of the compo­nents (fan, inverter-controlled cooling unit), the cooling output of the device is dependent on various factors: – External temperature at the installation site of the ex-
ternal unit – Thermal output from the server enclosure – Inlet temperature of hot air into the internal unit – Settings – Position of the sensor on the front of the server
Due to the control response, the temperature directly at the air outlet of the internal unit may fluctuate between
-3 K and +4 K. A fluctuation period lasts one to two min­utes. On average, the temperatures at the air outlet of the internal unit are within the tolerance of ±2 K.
Caution! The LCU DX may only be operated with refrigerant R410A. Use of any other re­frigerant will invalidate the guarantee.
Caution! Risk of malfunction or damage! Installation, and in particular laying of the refrigerant pipework between the in­ternal and external unit of the LCU DX, must only be carried out by trained, qualified and accredited cooling system specialists.
Property Value
Composition 50%: R32 (CH
2F2
)
50%: R125 (C2HF5)
Molar mass [g/mol] 72.585
Boiling point [°C] -52.7
Vapour pressure [bar] 12.46 at 15°C
Relative density 1.11 at 15°C
Tab. 8: Material data for R410A
Note: Safety data sheets are available for down­loading at www.rittal.com.
Page 30
11 Technical specifications
EN
30 Rittal LCU DX
11.4.1 LCU DX 3 kW
Exterior temperature [°C] -18
Setpoint [°C] ± 2 K 222528
Cooling output [kW] min./max. 1.00 3.00 1.00 3.00 1.00 3.00
Power consumption [kW] 0.41 0.64 0.46 0.65 0.45 0.68
Tab. 9: Exterior temperature -18°C
Exterior temperature [°C] -5
Setpoint [°C] ± 2 K 222528
Cooling output [kW] min./max. 1.00 3.00 1.00 3.20 1.00 3.50
Power consumption [kW] 0.46 0.57 0.46 0.66 0.46 0.68
Tab. 10: Exterior temperature -5°C
Exterior temperature [°C] 10
Setpoint [°C] ± 2 K 222528
Cooling output [kW] min./max. 1.00 3.50 1.00 3.50 1.00 3.50
Power consumption [kW] 0.43 0.62 0.45 0.69 0.48 0.68
Tab. 11: Exterior temperature 10°C
Exterior temperature [°C] 20
Setpoint [°C] ± 2 K 222528
Cooling output [kW] min./max. 1.00 3.50 1.00 3.50 1.00 3.50
Power consumption [kW] 0.49 0.99 0.46 1.05 0.49 0.68
Tab. 12: Exterior temperature 20°C
Exterior temperature [°C] 35
Setpoint [°C] ± 2 K 222528
Cooling output [kW] min./max. 1.00 3.50 1.00 3.50 1.00 3.50
Power consumption [kW] 1.00 1.35 0.62 1.43 0.62 0.68
Tab. 13: Exterior temperature 35°C
Exterior temperature [°C] 44
Setpoint [°C] ± 2 K 222528
Cooling output [kW] min./max. 1.00 3.50 1.00 3.50 1.00 3.50
Power consumption [kW] 1.02 1.45 0.97 1.52 0.97 0.68
Tab. 14: Exterior temperature 44°C
Page 31
Rittal LCU DX 31
11 Technical specifications
EN
11.4.2 LCU DX 6.5 kW
Exterior temperature [°C] -18
Setpoint [°C] ± 2 K 22 25 28
Cooling output [kW] min./max. 3.006.503.006.503.006.50
Power consumption [kW] 1.45 2.03 1.66 2.10 1.52 2.10
Tab. 15: Exterior temperature -18°C
Exterior temperature [°C] -5
Setpoint [°C] ± 2 K 22 25 28
Cooling output [kW] min./max. 3.006.503.006.503.006.50
Power consumption [kW] 1.65 2.10 1.48 2.10 1.60 2.10
Tab. 16: Exterior temperature -5°C
Exterior temperature [°C] 10
Setpoint [°C] ± 2 K 22 25 28
Cooling output [kW] min./max. 3.006.503.006.503.006.50
Power consumption [kW] 1.57 2.06 1.53 2.18 1.66 2.18
Tab. 17: Exterior temperature 10°C
Exterior temperature [°C] 20
Setpoint [°C] ± 2 K 22 25 28
Cooling output [kW] min./max. 3.006.503.006.503.006.50
Power consumption [kW] 1.80 2.63 1.86 2.67 1.89 2.67
Tab. 18: Exterior temperature 20°C
Exterior temperature [°C] 35
Setpoint [°C] ± 2 K 22 25 28
Cooling output [kW] min./max. 3.006.203.006.503.006.50
Power consumption [kW] 2.18 3.14 2.27 3.20 2.27 3.12
Tab. 19: Exterior temperature 35°C
Exterior temperature [°C] 44
Setpoint [°C] ± 2 K 22 25 28
Cooling output [kW] min./max. 3.004.003.004.003.005.00
Power consumption [kW] 1.66 1.80 1.72 1.96 1.80 2.25
Tab. 20: Exterior temperature 44°C
Page 32
11 Technical specifications
EN
32 Rittal LCU DX
11.5 Overview drawings
11.5.1 Internal unit LCU DX 3 kW and 6.5 kW
Fig. 17: Overview drawing of internal unit LCU DX 3 kW and 6.5 kW ("redundant" version)
Key
1 Insert for data and supply cables 2 Refrigerant line for "single" version (1 pair) 3 Refrigerant line for "redundant" version (2 pairs) 4 Condensate discharge
2/3
2/3
1
3
3
4
1
Page 33
Rittal LCU DX 33
11 Technical specifications
EN
11.5.2 Dimensions of internal unit LCU DX 3 kW and 6.5 kW
Fig. 18: Dimensions of internal unit LCU DX 3 kW and 6.5 kW
Outlet zone for cold air
Condensate runoff for left-side installation
Refrigerant connections
Inspection opening for electronics
Condensate runoff for right-side installation
Intake zone for hot air
Mounting holes
Page 34
11 Technical specifications
EN
34 Rittal LCU DX
11.6 RI flow chart LCU DX
Fig. 19: RI flow chart
Shut-off valve
Internal part External part
Electronic
expansion valve
Capillaries Capillaries
Condenser
Evaporator
coil
4-way valve
Compressor
Cooling
Heating
Accumulator
Refrigerant,
gas
Refrigerant,
liquid
Page 35
Rittal LCU DX 35
11 Technical specifications
EN
11.7 Circuit diagram
11.7.1 Functional diagram, internal unit
Fig. 20: Functional diagram, internal unit
Redundancy changeover
Remote control (3 U)
Control and display
device 1
Control and display
device 1
"redundant"
Control and display
device 2
DIXELL
Control and display device 3
Control and display device 3
WAGO
connector
X3
Sensor A
Optional
Fans 1 and 2 Fans 1-4
Midea
Motherboard, internal unit
WAGO connector, internal unit A
Electrical connection diagram
Midea
Motherboard, internal unit
"Redundant" version only
WAGO connector, internal unit B
Page 36
11 Technical specifications
EN
36 Rittal LCU DX
11.7.2 Connection internal unit – external unit, external interfaces
Fig. 21: Connection internal unit – external unit, external interfaces
COM-NO
Connector, internal unit A
SK 3311.490 to SK 3311.493
Connector, internal unit B
SK 3311.491 and SK 3311.493
Caution: 230 V~
Remote switching on/off
Shielded cable
Shielded cable
Collective fault signal
Operation
Connection by the customer
Open = On
COM-NC
COM-NO
Caution: 230 V~
Remote switching on/off
Collective fault signal
Operation
Open = On
COM-NC
Connection by the customer
Connection by the customer
SK 3311.490, …491, …492 and …493
Voltage 230 V~/1/N/PE, 50 Hz
External unit A
Supply lead
Connection by the customer
SK 3311.491 and …493
Voltage 230 V~/1/N/PE, 50 Hz
External unit B
Supply lead
Electrical connection diagram,
internal unit – external unit
Page 37
Rittal LCU DX 37
11 Technical specifications
EN
11.7.3 Circuit diagram, external unit
Fig. 22: Circuit diagram, external unit
IPM board
Inverter board
Motherboard
External temperature
sensor
Register sensor
Hot gas sensor
Electronic
expansion
valve
4-way valve
Compressor heater
Floor heating
DC
fan
motor
Compressor
Main supply lead
3 x 2.5 mm²
Fuse as per table
Connection cable
to internal unit
3 x 2.5 mm²
Pilot wire
3 x 0.75 mm²
Only shielded cable should
be used as the pilot wire
Inductor coil
Page 38
12 Spare parts
EN
38 Rittal LCU DX
12 Spare parts
Item Qty. / Packs of
Evaporator coil control board 1
Display 1
Compressor 1
Inverter motherboard 1
Electronic expansion valve 1
Evaporator coil fan 1
Dixell (evaporator coil) 1
Temperature sensor hot/cold air 1
Refrigerant filter 2
Tab. 21: List of spare parts – LCU DX
Page 39
Rittal LCU DX 39
13 Accessories
EN
13 Accessories
Item Model No. Qty. / Packs of Remarks
Refrigerant pipe kit 1
Refrigerant pipe kit 20 m, insulated, for LCU DX 3 kW 3311.495 1
Refrigerant pipe kit 20 m, insulated, for LCU DX
6.5 kW
3311.496 1
Tab. 22: List of accessories – LCU DX
Page 40
14 Glossary
EN
40 Rittal LCU DX
14 Glossary
1U server:
1 U servers are very flat and deep, modern high per­formance servers, whose height corresponds to one height unit (1 U = 44.54 mm, the smallest standard height division). Typical dimensions are (W x D x H)
482.6 mm (19") x 800 mm x 1 U. These systems normally include 2 CPUs, many GB RAM and hard drives, so that they require up to 100 m
3
/h cooling air at a maximum of 32°C.
482.6 mm (19") level: The front sides of the devices built into the server en­closure form the 482.6 mm (19") level.
Blade server:
By orienting dual CPU systems vertically and placing up to 14 units on a common backplane to provide for signal routing and power supply, a blade server is cre­ated. Blade servers can "generate" up to 4.5 kW heat loss per 7 U and 700 mm depth.
"Front to back" cooling principle:
The devices built into the server enclosure are normally cooled according to the "front to back" cooling princi­ple. Under this cooling principle, cold air supplied by exter­nal air conditioning is blown to the front of the server enclosure. The fans in the devices built into the server enclosure direct this air horizontally through the server enclosure. The air is warmed through this process and is exhausted out of the rear of the enclosure.
Hot spot:
A hot spot is the concentration of thermal energy in a small area. Hot spots normally lead to local overheating and can cause system malfunctions.
Switch:
Multiple servers normally communicate with one an­other and in the network using switches. Because as many inputs as possible are located on the front side of switches, they frequently have an air­flow from the side, not "front to back" cooling.
Page 41
Rittal LCU DX 41
15 Customer service addresses
EN
15 Customer service addresses
For technical queries, please contact: Tel.: +49(0)2772 505-9052 E-mail: info@rittal.de Homepage: www.rittal.com
For complaints or service requests, please contact: Tel.: +49(0)2772 505-1855 E-mail: service@rittal.de
Rittal GmbH & Co. KG Auf dem Stützelberg 35745 Herborn Germany
Page 42
◾Enclosures ◾ Power Distribution ◾Climate Control ◾ IT Infrastructure ◾ Software & Services
You can find the contact details of all Rittal companies throughout the world here.
www.rittal.com/contact
02.2016
Loading...