U306-1030(00)
070 00012 32035 9
Manifold Electronic Control System
Installation Instructions
MSB-M
MSB-C1
Note:
Up to 5 water heaters can be connected together using
•
the MSB-M and MSB-C1 kits.
•
When over 5 water heaters are connected together,
MSB-M units are connected using MSB-C2 kits.
•
If multiple MSB-M are used, then at least three water heaters
should be connected to each MSB-M.
Ex: With 7 water heaters, one MSB-M should control 4 water
heaters and the other MSB-M should control 3 water heaters.
United States & Canada: For use with Rinnai Tankless Water
•
Heaters (except for models V53e, V53i and R63LSe which must
use pressure activation valves, PVA).
Please contact Rinnai if you have further questions on the
•
applicable water heater models.
For Unit 1:
1) Remove the screw from the
sheet metal reinforcement plate
located at the bottom of the
water heater cabinet, and then
use it to secure the Control Board
to the water heater cabinet.
If installing on a condensing
water heater, refer to the additional instruction showing
below. *
2) Connect the connector
from Communication Cable A (18
inch, 450 mm cable) to socket No. 1
on Control Board.
Ground wire of
Communication Cable A
WARNING
Disconnect all water heaters from their power source before carrying out
the following installation procedures.
NOTE: The front cover panels of each water heater must be removed prior
to completing the following installation procedures.
Kit Components
MSB-M (Pack A)
(For wiring Units 1 and 2)
Parts List
Part Qty
Control Board
Communication Cable A
(18 in, 450 mm)
Communication Cable B
(9.8 ft, 3 m)
Cable tie bracket 2
Cable tie 2
Instruction Sheet 1
bracket 1
Screw 2
Part Qty
Communication Cable B
1
(9.8 ft, 3 m)
1
Cable tie bracket 2
Cable tie 2
1
Instruction Sheet 1
Note: One MSB-C1 is required
for each water heater (Units 3, 4,
and 5)
MSB-C1 (Pack B)
(For wiring Units 3, 4 and 5)
Parts List
1
3) Connect the connector from
Communication Cable A to the
4-pin socket located at the top of
the water heater control board.
Communication Cable A
ground wire terminal should be
grounded with the PC board
ground wire.
Ground wire of
Communication Cable A
4) Attach the cable tie bracket to
the bottom of the water heater
cabinet using the existing screw.
Loosely secure the cable tie
through the bracket and around
the communication cable. DO NOT
TIGHTEN THE CABLE TIE AT THIS
TIME - the Communication Cables B
from the other water heaters must
be secured by this cable tie.
Master
2nd
3rd
4th
5th
Communication Cable A
Water Heater
Control
Communication Cables B
MSB Communication cable (MSB-C2)
On the 2nd to 5th MSB boards, set to 1 unit ready.
Control Board
* These condensing water heaters require a bracket for the
control board:
RC98HPi (REU-KA3237FFUD)/RC98HPe (REU-KA3237WD)
/RC80HPi (REU-KA2530FFUD)/RC80HPe (REU-KA2530WD)
/REU-KM3237FFUD/REU-KM3237WD/ REU-KM2635FFUD
/REU-KM2635WD
Attach the control board to this bracket with one screw in Step 1.
Install the bracket
Attach the control board
Install the bracket with one screw as shown above and
continue with the rest of the installation.
For Units 2, 3, 4, and 5:
5) Run the 4-pin connector of
Communication Cable B (9.8 ft, 3 m
cable) up through the cable
access in the bottom of
Unit 1’s cabinet.
6) Connect the connector of the
Communication Cable B to socket
2 on the Control Board. The
Communication Cable B ground
wire terminals should be grounded
with the MSB ground wire and
Communication Cable A ground
wire terminal.
Ground wires of
Communication Cable B
7) Run the other end of
Communication Cable B through
the cable access in the bottom of
Unit 2’s cabinet.
System Operation
• The Control Board can
electronically connect up to 25
water heaters.
• When multiple water heaters
are operating, they will attempt
to supply equal amounts of hot
water.
• On initial water ow demand,
from 1 to 3 units which can be
determined by Dip SW setting
of Master MSB board will open
their servos valves until ow
demand is determined. See
Dip SW table for open water
ow valve. Only the necessary
number of water heaters will
begin to re to meet demand.
Water heaters not ring will
close their valves.
• As the default setting, 3 units will
open its servo valve until ow
demand is determined.
It is recommended that the dip
•
switch settings on MSB boards
other than the Master MSB board
be set for 1 unit ready.
• When installation is completed,
do a test run for all units.
• After the test run, check and clean
the water lter on all units.
• The temperature setting for all
of the connected water heaters
is controlled by the
temperature controller
connected to the water heater
with the Master MSB Board.
Temperature controllers
connected to the other units
will provide maintenance
codes for their respective units.
• If water heaters do not use a
temperature controller, the
temperature setting for the
water heater with the Master
MSB board is used.
• If a water temperature over
140 degree F is desired, then
an MCC-91 controller needs to
be connected to Master
Control Board.
• For proper operation, it is not
recommended that dierent
models be connected together.
Combining dierent models may
result in lower performance.
• The order in which each water
heater operates is occasionally
rotated to ensure equal usage
among the entire system.
8) Connect the 4-pin connector
from Communication Cable B to the
4-pin socket located at the top of
the water heater control board of
Unit 2. Communication Cable B
ground wire terminal should be
grounded with the PC board
ground wire.
Ground wire of
Communication Cable B
Dip SW table for open water ow servo valve
When viewing the installed MSB board, the dip switch will be as
shown below (upside down).
3 units ready (default) 2 units ready 1 unit ready
No1 ON
No2 ON
Dip SW
setting
No1 OFF
No2 OFF
No1 ON
No2 OFF
NOTE: In a recirculation system, in order to increase the temperature setting, it is necessary to turn off the power supply to the
circulation pump, increase the temperature setting, and then turn
the pump back on. No additional action is necessary when
decreasing the temperature setting.
Indicator lights on the Control Board indicate the status of each
of the water heaters as follows:
9) Attach the cable tie bracket to
the bottom of the water heater
cabinet using the existing screw.
Pull all of the excess cable up into
Unit 2’s cabinet, and then secure it
tightly to the bracket using the
cable tie.
10) Repeat steps 5 to 9 for Units 3,
4, and 5, as applicable.
Note: Communication Cable B for
Unit 3 plugs into socket 3, Unit 4
plugs into socket 4, etc.
11) After making all of the
connections to the Control Board,
tighten all of the cable ties used to
secure the Communication Cables.
12) Place the front cover panels
back on each of the water heaters
using (4) screws.
LED 1 ~ 5
Solid
Flashing Slowly (1.2
sec on / 0.5 sec o)
Flashing Quickly
(0.5 sec on / 0.5 sec
o)
O
LED 6
(Working with multiple MSB boards)
LED 1 ~ 5
EXPLANATION
Water ow servo valve is open when water
heater is in standby or working.
Water ow servo valve is closed when water
heater is not operating.
An error is detected. A temperature controller
must be connected to this unit to read the
error code.
No unit detected at this connection.
13) Restore power to the water
heaters.