RIGOL RM-DS2000 User manual

2 Installation Tool
PH2 Phillips Screwdriver (recommended).
3 Installation Space
The following requirements must be fulfilled by the machine cabinet in which the instrument is mounted.
The dimensions of the instrument after being installed are shown below (the unit is mm).
4 Installation Procedures
Only authorized operators can execute the installation operation. Improper installation might result in damage of the instrument or incorrect installation of the instrument on the rack.
(4). Load into the machine cabinet: mount the rack with the instrument fixed to it into a
standard 19-inch machine cabinet with four M6 screws and four M6 square nuts.
(5). Post-installation notice: the r ack occupies a height of 5U. The holes pointed o ut by the
arrows are installation holes. Note that they should be aligned with during installation
(1). Install the side plates: fix the side plates (left and right) onto the bottom plate of the
rack using four M4 screws.
(2). Install the front plate: fix the front plate onto the side plates (left and right) of the rack
using six M4 screws.
(3). Place the instrument: place the instrument by aligning it with the edges of the side
plates (left and right) and front plate of the rack and fix the instrument onto the bottom plate through presser feet using four M4 screws.
(4). Load into the machine cabinet: mount the rack with the instrument fixed to it into a
standard 19-inch machine cabinet with four M6 screws and four M6 square nuts.
(5). Post-installation notice: the r ack occupies a height of 5U. The holes pointed o ut by the
arrows are installation holes. Note that they should be aligned with during installation