Qualcraft UltraPro Aluminum Outrigger System User Manual

ULTRA PRO SERIES
ALUMINUM OUTRIGGER
operational safety and
assembly instructions
Warranty
Guardian Fall Protection expressly warrants to the purchaser that all products are free from defect in material and workmanship at the time of shipment.
Guardian Fall Protection’s obligation under this warranty is limited to product replacement for a period of two (2) years from either (i) the date of first installation or use of the product or (ii) shipment to the purchaser, whichever period expires first. This warranty is not transferable.
No other person or firm is authorized to assume or assign for Guardian Fall Protection any other liability in connection with the sale or use of our products. Furthermore, this warranty is void if any product is changed or altered in any way or if the product is used in a manner other than for which it is intended. This warranty only covers defects in material and workmanship; it does not cover conditions resulting from normal wear and tear, neglect, abuse or accident.
* Guardian assumes no liability as to the information contained in this booklet. You are responsible to check the policies of your company and refer to state and federal
regulations pertaining to the proper use of fall protection equipment.
customer service
Please contact Guardian Fall Protection at 1-800-466-6385
with any questions or for any additional information.
62005
Prior to use, read and understand all manufacturer’s instructions
Meets
OSHA
Standards
Provided with equiPment. KeeP instructions for future reference.
IN-CAISO4GD-NA-01
Picture may differ from actual product
operational safety
read before beginning assembly.
failure to understand and folloW all safety rules and assembly instructions could result in serious inJury or deatH.
metal conducts electricity:
Do not use this equipment where contact may be made with power lines or other live electrical circuits.
operation and safety
A scaffold must be erected, altered, and dismantled by qualified workers or under the direct supervision of a qualified
person. The qualified person must ensure that the erection is carried out properly, and that the correct components
and materials are being used. Inspect before use. Do not use scaffold if damaged or parts are missing. Always use outriggers and guardrails when stacking units. Before scaffold units are to be stacked, a set of (4) Outriggers with casters shall be installed on the base section of
scaffolding. The casters must be the same size as the casters in the base scaffold. The scaffold height must not exceed three times its smallest base dimension (3 to 1 rule). Guardrails must be installed on all open sides of a working platform where a person could fall from a height
of 6 feet (1.8 meters) or higher. Check with federal, provincial/state and local codes for variances which
may be more restrictive. Guardrails must be installed so that gate swings inward over platform. There must be a minimum of two side braces installed in each scaffold level and evenly spaced throughout the scaffold.
Lack of adequate bracing could cause scaffold to collapse. Securely lock all braces and platform before each use. Always use casters locked to the side frames with the locking pins. Lock all casters before climbing. Erect to be plumb, level, rigid and square. Erect on firm, level ground. Never place anything under or attach anything to unit to increase height or to adjust to uneven surfaces. Acids are corrosive and can seriously affect strength. Do not expose unit to corrosive substances. Keep scaffold free of debris and unnecessary equipment. Do not climb scaffold unless scaffold has been levelled and all casters are locked. Never move a rolling scaffold when people are on it.
assembly instructions
1
Erect the scaffold (one or two frames high) by following the manufacturer instructions.
2
Install caster into outrigger and secure it with lock pin. Set caster brake.
3
Place outrigger to end frame at a 90° angle to the side brace.
4
Insert two retaining plates in the screw stem.
5
Lock outrigger into place by using two handle nuts. Tighten nut securely.
1
2
All photos and drawings in this booklet are for reference purposes only. Refer to applicable OSHA codes and regulations for the proper use of this equipment.
box contents
QTY. DESCRIPTION
4
Outriggers
4
Casters
4
Locking-pins
8
Handle nuts
8
Retaining plates
3
4
5
Loading...