Wiring up the POD Point Solo
( See Fig 7-8 )
• With the rear unit securely fitted to the wall, the electrical
supply connection can be made.
• As the installation route of the wiring will vary with each
installation, the rear unit has been designed to accept
supply conduit entry on either the left, right sides or via rear
entry.
• The choice of entry point used will determine the amount
of insulation that needs to be cut away for the internal
wiring connection of the unit. The diagram below
illustrates the connection terminals for the electrical supply
cables.
Ensure that power cables are connected to the appropriate terminal as follows:
• Live 1: Brown
• Live 2: Black ( 3 - Phase Units Only )
• Live 3: Grey ( 3 - Phase Units Only )
• Neutral: Blue
• Earth: Green/Yellow
All of the cables that are to be connected into the supply terminals should have their insulation
stripped back 12~15mm to provide good contact to the screw terminals/jaws.
Before final assembly is performed an earth loop impedance test and polarity check shall be
performed at the unit connections to confirm the installation is sound.
Commissioning/Registering the unit
Domestic/OLEV installs
On power up of the POD Point Solo the LED’s on the front should illuminate in white. When the Communications
module has initialised the LED’s should change to magenta. When the unit has registered with the Pod Point
server the LED’s should then go blue with a short magenta flash. This process may take several minutes
depending on GSM network and server load.
If the LED’s remain white for a prolonged period of time there may be no GSM signal or the sim card is not
inserted correctly.
Public places installs
Visit the PP Install App to commission this unit.
Fitting the front of the Unit
Once the rear unit has been fitted, the wiring to the unit connected and tested, the front cover can be fitted in
place. Prior to fitting the front cover, visually check the internal connections, remove any debris that may have
entered the unit during installation and check that the front cover mating seal is in place. Place the cover on the
housing, using the top fixing as a point of reference, the front cover can then be secured in place at 5 points. The
unit is supplied with both pozidriv and T15 pin torx screws if additional security is required.
Final Electrical Testing
To meet the BS7671 (17th edition) requirements for testing of an electrical installation, the following tests and
checks shall be performed by a competent electrical installer before during or after a POD Point Solo unit is
installed:
• A visual inspection of the installation including the existing electrical installation.
• Verification of the characteristics of the electrical supply at the origin of the installation to
confirm the supply is suitable for the additional load.
• A test to confirm the continuity of the circuit protective conductors.
• A test to confirm the integrity of the circuit insulation resistance.
• A test to confirm the polarity of the installation is correct.
• Where applicable a test to confirm the earth electrode resistance is within acceptable
tolerances (or)
• An earth fault loop impedance test
• A test of the mechanical operation of residual current devices (RCD’s)
• A test to confirm the operation of residual current devices (RCD’s) is within stipulated
timescales (at the rated current and at five times the rated current operating current.)
• A test or calculated measurement of the prospective fault current.
• A verification of the functional operation of the POD Point Solo unit
Fig 7. Wiring of 1-Phase
Solo unit
Fig 8.Wiring of 3-Phase
Solo unit
In accordance with ‘Part P’ of the Building
Regulations (England & Wales) all notifiable
electrical installation work performed in domestic
dwellings must be carried out by a competent
electrical installer registered with a government
approved Part P Competency Scheme or
subjected to verification by the local building
control department. In Scotland all work must
be carried out by an electrical installer registered
with a Building Standards Scheme such as those
run by SELECT or the NICEIC.
NOTE: In England & Wales the installation of a
new circuit or a connection point for equipment
outside of the equipotential zone is notifiable.
Note for
commisioning
If you do not have access to the App,
please text the details listed below to this
phone number: 07805888545
• Site operator’s name
• Site operator’s email address
• Site operator’s phone
number
• Location of the unit
• Name of the unit (e.g.: John-
Mary)
• PG-number of the unit (e.g.:
PG - 90001)
POD Point July 2015
PP - D - 001
POD Point Technical Manual
5