PITT Cooking Systems EBEKO Installation manual

Page 1
Instructions for installation of support set
Contents of package: Tools needed:
2x support beams
4x inserts
16x cross-point screws 4,2x16 mm
1. Determine the dimensions of the cabinet and cut the support beams with the saw. ATTENTION! Correct length of the beam =
the dimension of cabinet on the inside - 4 mm.
Measuring tape
Cross-point screwdriver
Metallic saw
Installation instructions Front Side
2. Place the inserts into the ends of the beams that have been cut to size.
3. Place the beams between the cabinet and position it against the under side of the PITT® cooking unit. ATTENTION: FOR THE
POSITIONING, SEE STEP 4.
* Minimum distance of 80 mm
*
*
4. Position the beams in such a way that the screws, gas connection and the electricity block are freely accessible.
5. Push the beams firmly against the underside of the PITT cooking unit and tighten the lower two screws by hand. Repeat this step for the other side of the cabinet.
®
6. Push the beams firmly against the underside of the PITT cooking unit and tighten the upper two screws completely. Then, tighten the lower screws completely.
®
www.pittcooking.com
INFS2019-1-PC/EN
Page 2
Installation instructions Front Side
!
S
S
S
S
!
1. Overview of the various parts.
!
4. Turn all set screws back to approxi­mately 3 mm above the unit. Then place
the heat conductor on the unit.
2. Carefully press the sealing ring over the edge of the heat shield. Check whether the ring fits well in its entirety.
5. Place the flanges in the designated cutouts and position the unit carefully under the worktop. Check that the heat conductor is positioned correctly.
S
3. Overview of the set screws (S).
6. Check that the flanges are centered in the cutouts. Note: if this is not the case, the flanges will not function properly.
S
10. Note: the adhesive strip under the sealing scale of the knob may not yet be
removed.
!
13. Correct centered gas taps.
11. Slide the unit carefully into position until the gas taps are vertically aligned with the cutouts in the front frame (or blende).
75 mm
14. Measure the distance between the front of the unit and the front frame (or blende) again. This distance must be 75
mm.
12. Tighten the set screws from the back to the front until the gas taps are centered with the cutouts. Check that all screws are tightened.
15. Remove the adhesive strip from the sealing scale. Press the knob and the sealing scale as a one on the gas tap, so that they are centered and aligned.
7. Place the heat shields including the sealing ring (step 2) on the burners and screw them with the supplied screws.
Important!
When the control knobs are not properly adjusted the burners will not ignite or burn evenly.
8. Always make sure that the V-shaped indicator is in line with the shaft of the burner housing of the wok burner. This heat shield is attached with three screws.
!
75 mm
9. Measure the distance between the front of the unit and the front frame (or blende). This distance must be 75mm.
13-15mm
16. Check whether the knobs stick out sufficiently. The knobs should have a distance of 13-15 mm above the sealing
scales.
!
17. Check that the knobs turn smoothly and return to the rest position after pressing. If necessary, remove the sealing scale and replace them again.
!
18. Connect the unit to gas and electricity and ignite the burners. If the flames go
out after ignition, the knobs have to be adjusted again (step 9).
!
For warranty and the proper functioning of the cooking unit ensure the mounting is as described in this manual to the letter.
19. Support the unit with the double PITT® cooking support set. (see enclosed installation instructions)
20. Check that the heat conductor makes full contact with the worktop.
21. The unit is now ready for use.