Peri SKYDECK Instructions For Assembly And Use

SKYDECK
Panel Slab Formwork
Instructions for Assembly and Use – Standard Confi guration
Edition 09 | 2016
Content
Overview
Main components 1 Key 2 Presentational reference 2
Introduction
Target groups 3 Additional technical documentation 3 Intended use 4 Care and maintenance instructions 5 Instructions for Use 5
Safety instructions
Cross-system 6 System-specific 7 Storage and transportation 7
Standard configuration
A1 Storage and transportation 8 A2 System components 11 A3 System dimensions 14 Notes regarding static calculations 14 Internal forces and rigidity 15 Load combinations 15 A4 Shuttering 17 Starting bay 17 Transverse bay 19 Longitudinal bay 20 Standard bay 21 A5 Compensations 24 System components 24 Edge Beam SRT 150, SRT 75 24 Filler Timber SPH 24 End Support SSL 24 Combihead SCK 25 Triangular Frame SDR 150/75, 75/75 28 Longitudinal compensations 28 Transverse compensations 31 A6 Shuttering around columns 34 1 recessed panel 34 2 recessed panels 35 3 recessed panels 36 Recessed main beams 37 Shifting the main beam axis 37 A7 Horizontal bracing 38 Transfer of horizontal loads into the
columns of the building 38 General 39 Bracing of the inner bay 39 Transfer of horizontal loads from a
casting segment 40 A8 Cantilevers, Guardrails 42 Bracing on leading edges to prevent
tipping 42 Guardrails with Handrail Unit SD 43 SKYDECK Guardrail Holder SGH and
Guardrail Post SGP 44
A9 SKYDECK platforms 46 Corner table (Area l) 47 Cantilevers (Area ll) 51 Open edge areas (Area lll) 52 Slab areas (Area lV) 52 Infill areas 52 Platform installation 53 Striking 54 Working and safety scaffold 55 A10 Changing direction 56
– System with Prophead SSK 56
– System with Drophead SFK 58 A11 Inclined slabs 60 Bracing with Tension Sleeve SAO and
Chain 3.0 kN 60 Bracing with Tension Unit SD 61 A12 Striking 62 A13 Site record 64
Design tables
A14 Horizontal loads with Slab Props PEP 65 A15 Inclined slabs 66 Maximum permissible slab inclination with
Tension Sleeve SAO and Chain 3.0 kN 66 Tension Unit SD – bracing angle 66 Tensile force of Tension Unit SD and
prop loads
– System with Drophead SFK 67
– System with Prophead SSK 70 A16 SKYDECK standard configuration 73 Prop loads
– System with Drophead SFK 73
– System with Prophead SSK 74
– Panel system 75 Striking guide values 75 A17 Filler plates, forming around columns 76 A18 Slab props 77
– PEP 20 77
– PEP 20 with Base MP 50 78
– PEP 30 79
– PEP 30 with Base MP 50 80
– PEP Ergo B 81
– PEP Ergo D 82
– PEP Ergo E 83
– MULTIPROP 250, 350, 480, 625 84
Components
Components
86
SKYDECK Panel Slab Formwork
Overview
Main components
4
3
1
2
1 Drophead SFK 2 Main Beam SLT 225 3 Panel SDP 4 Cover Strip SAL
1
2
1
3
4
SKYDECK Panel Slab Formwork
Overview
Key
Pictogram | Definition
Safety instructions
Note
Load-bearing point
Visual check
Tip
Personal protective equipment to prevent falling from a height (PPE)
Misapplication
Correct application
Dimension specifications
Dimensions are usually given in cm. Other units of measure, e.g. m, are shown in the illustrations. Load details are usually given in kg. Other measurement units, e.g. t, are specified in the illustrations.
Conventions
 Instructions are numbered with:
1. ..... , 2. ...... , 3. .....
 The result of an instruction is shown
by:
 Position numbers are clearly provided
for the individual components and are given in the drawing, e.g. 1, in the text in brackets, for example (1).
 Multiple position numbers, i.e. alter-
native components, are represented with a slash, e.g. 1 / 2.
Arrows
Arrow representing an action
Arrow representing a reaction of an action*
Forces
Presentational reference
The illustration on the front cover of these instructions is understood to be a system representation only. The assem­bly steps presented in these Instruc­tions for Assembly and Use are shown in the form of examples with only one component size. They are valid accord­ingly for all component sizes contained in the standard configuration.
For a better understanding, detailed il­lustrations are partly incomplete. The safety installations which have possibly not been featured in these detailed drawings must nevertheless still be available.
* If not identical to the action arrow
2
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
Introduction
Target groups
Contractors
These Instructions for Assembly and Use are designed for contractors who use the formwork systems for
 assembling, modifying and disman-
tling, or
 use them, e.g. for concreting, or  for other operations, e.g. carpentry or
electrical work.
Construction site coordinator
The Safety and Health Protection Coor­dinator*
 is appointed by the client,  must identify potential hazards during
the planning phase,
 determines measures that provide
protection against risks,
 creates a safety and health plan,  coordinates the protective measures
for the contractor and site personnel
so that they do not endanger each
other,
 monitors compliance with the protec-
tive measures.
Competent persons
Due to the specialist knowledge gained from professional training, work experi­ence and recent professional activity, the competent person has a reliable un­derstanding of safety-related issues and can correctly carry out inspections. De­pending on the complexity of the test to be undertaken, e.g. scope of testing, type of testing or the use of a certain measuring device, a range of specialist knowledge is necessary.
Qualified persons
Formwork systems may only be assem­bled, modified or dismantled by person­nel who are suitably qualified to do so. For the work to be carried out, the quali­fied persons must have received in­structions** which contain at least the following points:
 Explanation of the plan for the assem-
bly, modification or dismantling of the formwork in an understandable form and language.
 Description of the measures for as-
sembling, modifying or dismantling the formwork.
 Designation of the preventive meas-
ures to avoid the risk of persons and objects falling.
 Designation of the safety precautions
in the event of changing weather con­ditions which could adversely affect the safety of the formwork system as well as the personnel concerned.
 Details regarding the permissible
loads.
 Description of any other risks that are
associated with the assembly, modifi­cation or dismantling procedures.
In other countries, ensure that the relevant national guidelines and reg­ulations in the respective current version are complied with!
* Valid in Germany: Regulations for Occupa-
tional Health and Safety on Construction
Sites 30 (RAB 30)-
** Instructions are given by the contractor him-
self or a competent person selected by him.
Additional technical documentation
 Poster: SKYDECK  MULTIPROP Slab Props: Instructions for Assembly and Use  PEP Ergo Slab Props: Instructions for Assmbly and Use  Instructions for Use:
– Pallet Lifting Truck – Pallets and Stacking Devices – Stripping Cart ASW 465 – Stripping Cart Alu
– Transportation Fork SKYDECK SUG
 Technical Data Sheet for Anchor Bolt PERI 14/20 x 130  PERI Design Tables – Formwork and Shoring  Brochures:
– SKYDECK
– SKYDECK Beam Waler SD
SKYDECK Panel Slab Formwork
3
Introduction
Intended use
Product description
PERI products have been designed for exclusive use in the industrial and com­mercial sectors by qualified users only.
PERI SKYDECK is a panel slab form­work system used for constructing slab thicknesses up to 109 cm. Depending on the slab thickness and concrete strength, the SKYDECK Drophead al­lows striking to take place after only 1 day: see table containing minimum con­crete strength and striking guide values.
The SKYDECK Platform is a prefabricat­ed, folding scaffold platform for use as working and safety scaffold according to DIN 4420 Part 1. Immediately after concreting, it is available as safety scaf­fold to provide safe and secure working conditions on rising structures.
Classification is effected in Scaffold Group 2 (useful load per surface 150 kg/m²) . It is required for concreting floor slabs in skeleton construction (high-rise buildings) and for securing the open edges of the SKYDECK Slab Formwork System. A 1.30 m wide plat­form with guardrails provides safe work­ing conditions on the slab edges.
Features
The panels and main beams are made of aluminium which means they are very light. Accessories for infill areas, shuttering around columns and the slab edges are also available.
Due to early striking, the panels and main beams can be used for the next concreting cycle.
Only the props with dropheads and the cover strips remain in position until the full concrete strength has been reached. On-site material requirements are there­fore clearly reduced.
For supporting the SKYDECK panels, PERI MULTIPROPs or PEP Slab Props can be used.
The SKYDECK Platform consists of:
– 39 mm thick plywood decking fixed
to a supporting frame,
– a folding handrail unit that is screwed
to the supporting frame as a framed construction, and held by a securing lever when opened up.
The platform can be used on the edge of the floor slab as well as in the corner table area. For the various applications, three lengths are available.
SDB 150 L = 1.50 m SDB 225 L = 2.25 m SDB 300 L = 3.00 m
The SDB 225 Platform can also be used for side cantilevers of 75 cm to the right or left of the main beam.
Technical data System dimensions With Drophead SFK, Main Beam SLT 225
 230 x 150 cm, slab thickness max.
43 cm, as standard case presented in the Instructions for Assembly and Use
 230 x 75 cm, slab thickness max.
90 cm
 115 x 75 cm, slab thickness max.
109 cm with centre support
With Drophead SFK, Main Beam SLT 150
 155 x 150 cm, slab thickness max.
52 cm
 155 x 75 cm, slab thickness max.
109 cm
With Prophead SSK, Main Beam SLT 225
 225 x 150 cm, slab thickness max.
43 cm
 225 x 75 cm, slab thickness max.
90 cm
 112.5 x 75 cm, slab thickness max.
109 cm with centre support
With Prophead SSK, Main Beam SLT 150
150 x 150 cm, slab thickness max. 55 cm 150 x 75 cm, slab thickness max. 109 cm
For permissible slab thicknesses and available prop loads: see PERI Design Tables.
Assembly of the platform takes place with the crane from the outside of the building. It is set down on the cantile­vered main beams and automatically locks in position.
All steel parts are galvanized while all safety components are red pow­der-coated.
4
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
Introduction
Care and maintenance instructions
In order to maintain the value and opera­tional readiness of the formwork materi­als over the long term, clean the ele­ments after each use. Some repair work may also be inevita­ble due to the tough working conditions. The following points should help to keep care and maintenance costs as low as possible.
Spray the formwork on both sides with concrete release agent before each use; this allows easier and faster cleaning of the formwork. Spray the concrete re­lease agent very thinly and evenly!
Spray the rear side of the formwork with water immediately after concret­ing; this avoids any time-consuming and costly cleaning operations.
When used continuously, spray the pan­el formlining with the concrete release agent immediately after striking; then clean by means of a scraper, brush or rubber lip scraper. Important: do not clean formlining made of plywood with high-pressure equip­ment; this could result in the formlining being damaged.
Fix box-outs recesses and mounting parts with double-headed nails; as a re­sult, the nails can be easily removed lat­er, and damage to the formlining is largely avoided.
Close all unused anchor holes with plugs; this eliminates any subsequent cleaning or repair work. Anchor holes accidentally blocked with concrete are freed by means of a steel pin from the formlining side.
When placing bundles of reinforcement bars or other heavy objects on horizon­tally-stored formwork elements, suita­ble support, e.g. square timbers, is to be used; as a result, impressions and damage to the formlining are largely avoided.
Internal concrete vibrators should be fit­ted with rubber caps if possible; as a re­sult, any damage to the formlining is re­duced if the vibrator is accidently “in­serted” between the reinforcement and formlining.
Never clean powder-coated compo­nents, e.g. elements and accessories, with a steel brush or hard metal scraper; this ensures that the powder-coating re­mains intact.
Use spacers for reinforcement with large-sized supports or extensive areas of support; this largely avoids impres­sions being formed in the formlining when under load.
Mechanical components, e.g. spindles or gear mechanisms, must be cleaned of dirt or concrete residue before and af­ter use, and then greased with a suita­ble lubricant.
Provide suitable support for the compo­nents during cleaning so that no unin­tentional change in their position is pos­sible.
Do not clean components when sus­pended on a crane.
Instructions for Use
The use in a way not intended according to the Instructions for Assembly and Use, or any use deviating from the standard configuration or the intended use represents a misapplication with a potential safety risk, e.g. risk of falling.
Only PERI original components may be used. The use of other products and spare parts is not allowed.
Changes to PERI components are not permitted.
SKYDECK Panel Slab Formwork
5
Safety instructions
Cross-system
General
The contractor must ensure that the In­structions for Assembly and Use sup­plied by PERI are available at all times and are understood by the site person­nel.
These Instructions for Assembly and Use can be used as the basis for creat­ing a risk assessment. The risk assess­ment is compiled by the contractor. The Instructions for Assembly and Use do not replace the risk assessment!
Always take into consideration and com­ply with the safety instructions and per­missible loads.
For the application and inspection of PERI products, the current safety regu­lations and guidelines must be observed in the respective countries where they are being used.
Materials and working areas are to be inspected on a regular basis especially before each use and assembly for:
 signs of damage,  stability and
 function.
Damaged components must be ex­changed immediately on site and may no longer be used.
Safety components are to be removed only when they are no longer required.
Components provided by the contractor must conform with the characteristics required in these Instructions for As­sembly and Use as well as with all valid construction guidelines and standards. In particular, the following applies if nothing else is specified:
 Timber components: Strength
Class C24 for Solid Wood according to EN 338.
 Scaffold tubes: galvanised steel
tubes with minimum dimensions of Ø 48.3 x 3.2 mm according to EN 12811-1:2003 4.2.1.2.
 Scaffold tube couplings according
to EN 74.
Deviations from the standard configura­tion are only permitted after a further risk assessment has been carried out by the contractor.On the basis of this risk assessment, appropriate measures for working and operational safety as well as stability are to be determined. Corresponding proof of stability can be provided by PERI on request if the risk assessment and resulting measures to be implemented are made available.
Before and after exceptional occurrenc­es that may have an adverse effect re­garding the safety of the formwork sys­tem, the contractor must immediately
 create another risk assessment,
with appropriate measures for en­suring the stability of the formwork system being carried out based on the results,
 and arrange for an extraordinary in-
spection by a competent person. The aim of this inspection is to identify and rectify any damage in good time in order to guarantee the safe use of the formwork system.
Exceptional occurrences can include:
 accidents,  longer periods of non-use,  natural events, e.g. heavy rainfall,
icing, heavy snowfall, storms or earthquakes.
Assembly, modification and disman­tling work
Assembly, modification or dismantling of formwork systems may only be car­ried out by qualified persons under the supervision of a competent person. The qualified persons must have received appropriate training for the work to be carried out with regard to specific risks and dangers.
On the basis of the risk assessment and Instructions for Assembly and Use, the contractor must create installation in­structions in order to ensure safe as­sembly, modification and dismantling of the formwork system.
The contractor must ensure that the personal protective equipment required for the assembly, modification or dis­mantling of the system, e.g.
 safety helmet,  safety shoes,  safety gloves,  safety glasses,
is available and used as intended.
If personal protective equipment against falling (PPE) is required or specified in local regulations, the contractor must determine appropriate attachment points on the basis of the risk assess­ment. The personal protective equipment against falling to be used is determined by the contractor.
The contractor must
 provide safe working areas for site
personnel which are to be reached through the provision of safe ac­cess ways. Areas of risk must be cordoned off and clearly marked.
 ensure the stability during all stag-
es of construction, in particular dur­ing assembly, modification and dis­mantling of the formwork.
 ensure and prove that all loads can
be safely transferred.
Utilisation
Every contractor who uses or allows formwork systems or sections of the formwork to be used, has the responsi­bility for ensuring that the equipment is in good condition.
If the formwork system is used succes­sively or at the same time by several contractors, the health and safety coor­dinator must point out any possible mu­tual hazards and all work must be then coordinated.
6
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
Safety instructions
System-specific
Retract components only when the con­crete has sufficiently hardened and the person in charge has given the go­ahead for striking to take place.
Anchoring is to take place only if the an­chorage has sufficient concrete strength.
In order to avoid an overloading of the integrated temporary props, the load-bearing capacity of the slabs, plates and beams which have already been completed must be activated. For this, a free deflection possibility of these components is required. This takes place by releasing and re-installing all existing temporary props, and is also required for formwork systems where the prop head is an integral part of the slab formwork.
The load-distributing support used, such as planking, must match the respective base. If several layers are required, planks are to be arranged crosswise.
During striking, do not tear off the form­work elements with the crane.
The existing prop loads (see Tables) must be safely transferred by means of sufficiently load-bearing slab props or shoring systems.
SKYDECK Platforms are classified in Load Class 2 (permissible load
1.5 kN/m² – 150 kg/m²). They are availa­ble as working scaffold.
The horizontal fixed position of the slab formwork must be guaranteed. This is given with circumferential walls and pre-concreted beams. Otherwise, the transfer of the horizontal loads has to be guaranteed by means of other measures supplied by the contractor, e.g. bracing. Load assumptions for horizontal loads in accordance with DIN EN 12812.
When storing heavy items on the form­work, the load-bearing capacity must be taken into consideration.
Cantilevers may only be accessed after bracing has been mounted.
With all-round enclosed structure geom­etries, panels are to be fixed to the main beams by means of two Panel Clips SPK (21) each for wind speeds between
0.033 kN/m² (26 km/h) and dynamic pressure 0.061 kN/m² (36 km/h).
For unfavourable structure geometries or larger wind speeds, additional secur­ing measures are to be implemented, e.g.:
– ballast, – bracing, – dismantling the formwork etc.
Storage and transportation
Store and transport components ensur­ing that no unintentional change in their position is possible. Detach lifting ac­cessories and slings from the lowered components only if they are in a stable position and no unintentional change is possible.
Do not drop the components.
Use PERI lifting accessories and slings as well as only those load-bearing points provided on the component.
During the moving procedure
 ensure that components are picked
up and set down so that unintentional falling over, falling apart, sliding, fall­ing down or rolling is avoided.
 no persons are allowed to remain un-
der the suspended load.
Always guide pre-assembled scaffold­ing bays, scaffolding units or scaffolding sections with ropes when moving them by crane.
The access areas on the jobsite must be free of obstacles and tripping hazards as well as being slip-resistant.
For transportation, the surface must have sufficient load-bearing capacity.
Use original PERI storage and transport systems, e.g. crate pallets, pallets or stacking devices.
SKYDECK Panel Slab Formwork
7
A1 Storage and transportation
– Instructions for Use for PERI Pallet
and Stacking Devices must be followed at all times!
– Manually-created transport units
must be correctly stacked and secured!
– Pallets and stacked components
are to be protected against the ef­fects of the weather, e.g. secure packed components with tension straps against lifting!
– Always attach the 4-sling lifting
gear using the four load-bearing points!
Tra n s por t
PERI pallets and stacking devices are suitable for lifting by crane or forklift. They can also be moved with the PERI Pallet Lifting Trolley. All pallets and stacking devices can be lifted using both the longitudinal and front sides. The following are some examples.
Fig. A1.01 Fig. A1.02
Stacked with Panels SDP 150 x 75
Pallet SD: 48 pieces (Fig. A1.01 + A1.02) Pallet SD: 14 pieces (Fig. A1.04 + A1.05) The Pallet SD can also be used for storing other SKYDECK components, e.g. Main Beam SLT. (Fig. A1.03)
Lashing straps are manufactured ac­cording to DIN EN 12195-2, and are to be regularly checked in accordance with this standard.
Stacking:
2 loaded pallets, one on top of the other.
Fig. A1.04 Fig. A1.05Fig. A1.03
8
SKYDECK Panel Slab Formwork
A1 Storage and transportation
Pallet: Handrail Unit SD 150 Pallet: Handrail Unit SD 75
Number of handrail units per pallet
Handrail Unit SD 150: 10 pieces (Fig. A1.06) Handrail Unit SD 75: 10 pieces (Fig. A1.07)
Stacking:
2 loaded pallets, one on top of the other.
Loading sequence
1. Open locking mechanism on the pal­let frame.
2. Slide in one handrail unit and close locking mechanism.
3. Slide in additional handrail units. Handrail units lock automatically above the red bars.
4. Secure handrail units on the front side against sliding out. Insert retaining bar and lock in place.
Due to the powder coating, cleaning requirements are kept to a minimum. Panels and main beams are equipped with self-draining edges. They prevent the side areas from getting dirty and make cleaning easier. (Fig. A1.08)
Fig. A1.06
Fig. A1.07
Fig. A1.08
SKYDECK Panel Slab Formwork
9
A1 Storage and transportation
SKYDECK Platforms
The platforms can be stored in stacks of up to 5 elements.
Weights: SDB 300 184 kg / piece SDB 225 155 kg / piece SDB 150 108 kg / piece
Stacks of platforms can be lifted with a fork-lift truck using the long side. (Fig. A1.09) The stack can be moved with the crane by means of the external crane eyes. (Fig . A1.10 )
Ensure the platforms are evenly secured on lorries but not too tightly.
Fig. A1.09
Crane Eye
Fi g. A1.10
31,4
Crane Eye
10
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A2 System components
Propheads
Drophead SFK (1) Prophead SSK (6) Combihead SCK (7) Transition Head SDSK (26) Transition Head SDFK (27)
The Drophead SFK can be used for all standard situations and allows the re­moval of main beams and panels while simultaneously supporting the slab.
The Prophead SSK must be used in all starting fields. Prophead SSK and Combihead SCK are used, e.g. for com­pensations.
Prophead SDSK and Prophead SDFK are used when changing direction.
1
26
6
7
27
Main beams
– Main Beam SLT 225 – Main Beam SLT 150
For the exclusive use with the SKYDECK Platform SDB, a main beam which can accommodate the Platform SDB is available. It may only be used for the described purposes.
– Main Beam SLT 375
Panel SDP
The Panel SDP is available with the fol­lowing dimensions:
– Panel SDP 150x75 – Panel SDP 150x50 – Panel SDP 150x37.5 – Panel SDP 75x75 – Panel SDP 75x50 – Panel SDP 75x37.5
Fig. A2.01
Fig. A2.02
Fig. A2.03
Cover Strip SAL
The Cover Strip SAL is available with the following dimensions:
– Cover Strip SAL 150 – Cover Strip SAL 75 – Cover Strip SAL 50 – Cover Strip SAL 37.5
Fig. A2.04
SKYDECK Panel Slab Formwork
11
A2 System components
Slab props
Dropheads SFK, Propheads SSK, SDFK or Combiheads SCK fit on props with a hole diameter of ø 38 – 40 mm. With hole diameters > 40 mm, the heads must be bolted diagonally using 2 Bolts ISO 4016 M12 x 40-4.6 galv., Mu, item no. 035440. (Fig. A2.01)
26
1.2
1.1
II.
I.
Transition Heads SDSK (26) must al­ways be bolted: see A9 Changing direc­tion.
Prop loads over 33.3 kN: bolting on of drophead for use with PEP Slab Props using 2 Bolts DIN EN ISO 4016 M12 x 40-4.6 galv., Mu.
Preparing the Drophead
1. Push drophead wedge (1.1) and Drop­head (1.2) upwards as far as possible. (Fig. A2.06)
2. Insert drophead wedge.
3. Secure with hammer blow = shutter­ing position.
Drophead SFK is ready for use.
Preparing the slab props
1. Adjust the extension lengths of the props. Clear room height minus dimension x (Fig. A2.07). Take into consideration the different overall heights of the main beams: Main Beam SLT 225 = 24 cm / Main Beam SLT 150 = 19 cm.
2. Insert the prepared Drophead (1), Prophead (6) or Combihead (7) into the prop. The self-locking coupling is secured automatically. (Fig. A 2.01)
The prop is ready for use.
Fig. A2.05
Starting bay
Main Beam SLT 225
x = 41
6
Starting bay
Main Beam SLT 150
1, 6, 7, 27
Fig. A2.06
End bay
Main Beam SLT 225
x = 41
1
6
x = 33
End bay
Panel SDP
12
Fig. A2.07
x = 36
6
1
x = 41
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
x = 17
6
A2 System components
SKYDECK Platforms SDB
SKYDECK Platform SDB 150 SKYDECK Platform SDB 225 SKYDECK Platform SDB 300
External crane eye
Frame
Handrail
Internal crane eye, retracted
Decking
Box out for shutter­ing aid
Abb. A2.08
Preparation for Use:
Slide
Stacking base
Internal crane eye, retracted
External crane eye
Securing lever
Internal crane eye, raised
Slide
Internal crane eye
Take individual platforms from the stack, fold open the handrail and the securing lever drops down and secures it in a vertical position. (Fig. A2.09)
Is the securing lever engaged? Other­wise it may be necessary to secure it by hand.
For transportation by crane, the plat­form is attached to the concealed crane eyes with the two-sling lifting gear. (Fig . A 2.10)
Fig. A2.09
SKYDECK Panel Slab Formwork
Fi g. A 2.10
Handrail
Securing lever
13
A3 System dimensions
Notes regarding static calculations
This design information is used for the design and planning of the SKYDECK Slab Formwork System. It covers standard configurations for slab thicknesses from 0.14 m to 1.09 m.
Comparison of the design method
The design concept with partial safety factors
R
k
R
d
E
d
γ
F
F
k
Method of proof Method of proof
R
k
Fk · γ
γ
M
R
d
F
E
d
Key
= characteristic resistance
R
k
= design value of the resistance
R
d
= F
F
k
= design value of the action
E
d
= Rk = characteristic resistance (e.g. breaking load)
F
ult.
F
= permissible load-bearing capacity
perm.
= actual or characteristic action
actual
Rd ≥ E
The old design concept with the global safety factor
(see PERI Design Tables)
(= Rk)
F
ult.
γ
tot.
d
F
perm.
F
≥ F
F
(= Fk)
actual
F
ult.
F
(= Fk)
γ
tot.
perm.
= partial safety factor for the material
γ
M
actual
F
actual
(= Fk)F
perm.
actual
(steel ≈ 1.1 / concrete ≈ 1.5)
= partial safety factor for the load
γ
F
(permanent = 1.35 / changeable = 1.5)
= global safety factor ≈ γM · γF
γ
tot.
(steel ≈ 1.65 / concrete ≈ 2.25)
Design method used in this design information
This design information is based on the design concept with the global safety factor.
The tables of the prop loads include the permissible load-bearing capacities F
perm.
After multiplication using γF = 1.5, the maximum load-bearing capacity can also be converted into a design value of the resistance R
for the method with
d
partial safety factors.
14
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A3 System dimensions
Internal forces and rigidity
Permissible internal forces and rigidity for the design with single-span girders
perm. M
Item no. Designation
061100 16.0 22.0 119 8
06116 0 12.6 22.0 1198
061110 11.3 18.0 656
061045 2.9 8.0 91
061045 2.1 8.0 31
061047 3.0 8.0 88
061047 2.1 8.0 28
061049 0.7 2.4 32
061049 0.4 1.7 7
061050 0.6 2.4 29
061050 0.3 1.3 7
Main Beam SLT 225
Main Beam SLT 375
Main Beam SLT 150
Edge Beam SRT-2 150
Edge Beam SRT-2 turned
Edge Beam SRT-2 / 27
Edge Beam SRT-2 / 27 turned
Filler Timber SPH 150
Filler Timber SPH turned
Filler Timber SPH / 27
Filler Timber SPH / 27 turned
[kNm]
perm. Q
[kN]
Load combinations
Vertical loads Concreting
(according to DIN EN 12812) SKYDECK dead load Q Concrete load Q Equivalent load concreting Q
0.75 kN/m² ≤ Q4 ≤ 1.75 kN/m² Equivalent load working conditions Q
= 0.20 kN/m²
1
= 24.5 kN/m³ x d [m]
2,b
= 0.10 x Q
4
= 0.75 kN/m²
2,p
2,b
El
[kNm
2
]
Table A3.01
+ Q
+ Q
Total loa d Q = Q
1
2,b
2,p
+ Q
4
SKYDECK Platforms SDB
(according to DIN EN 12811) Load Class 2 q F
= 1.50 kN/m²
1
= 1.50 kN (500 x 500 mm²)
1
Horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position = 1% of the vertical load (DIN EN 12812; 9.3.4.2)
Wind loads
Working wind dynamic pressure q Maximum wind speed dynamic pressure q
= 0.20 kN/m² (DIN EN 12811-1; 6.2.7.4.2)
W,A
= 0.60 kN/m²
W,max
Height of the substitute area for equipment and materials on the scaffold level LF working wind h
= 0.40 m (DIN EN 12811-1, 6.2.7.4.2)
W,A
Height of the substitute area for equipment and materials on the scaffold level LF maximum wind speed h
= 0.20 m (DIN EN 12811-1, 6.2.7.4.1)
W,max
Wind on the side protection Working wind speed on SKYDECK Guardrail Holder SGH and Guardrail Post SGP q
= 0.183 kN/m
W,A, S
Maximum wind speed with SKYDECK Guardrail Holder SGH and Guardrail Post SGP q
= 0.550 kN/m²
W,max,S
SKYDECK Paneel Deckenschalung
Aufbau- und Verwendungsanleitung – Regelausführung
15
A3 System dimensions
Overview of the required frames: MRK with the use of MULTIPROP Towers PRK with the use of PEP Props
Frames
62.5 Steel
75 Steel
137.5 Steel
150 Steel
201.5 Alu
225 Alu
230 Alu
Table A3.0 2
MRK
Item no.
PRK
Item no.
028390 111811
028400 111812
028380 1118 13
028350 1118 14
028460 111815
028360 1118 16
028470 111817
SKYDECK system
– Inset beam at wall beginning with 75 cm panel span. – Inset prop at wall beginning with Combihead.
– Panel span 75 cm.
– Inset beam at wall beginning with 150 cm panel span.
– Panel span 150 cm.
– Inset prop at wall beginning under SLT 225 with Prophead
or Combihead.
– SLT 225 on Prophead or Combihead. – Use of Cantilever Beam SLT 375 on Prophead/Combihead
or corner tables.
– SLT 225 on Dropheads.
625
125
235
2015
2250
Fig. A3.01 Fig. A3.02
MRK
PRK 62,5
MRK / PRK 201,5
MRK
PRK 62,5
MRK / PRK 225
750
MRK
PRK
75
MRK / PRK 201,5MRK / PRK 225
MRK
PRK
75
MRK / PRK 201,5
125
235
2015
2300
1375 1500
MRK / PRK 137,5
MRK / PRK 201,5
MRK / PRK 137,5
MRK / PRK 230
MRK / PRK 150
MRK / PRK 201,5
MRK / PRK 150
MRK / PRK 230
150 0
MRK / PRK 150
2250
MRK / PRK 201,5
MRK / PRK 225
MRK / PRK 150
Fig. A3.03
MRK / PRK 225
3750
16
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A4 Shuttering
Starting bay
Shuttering using a safe mobile scaffold!
Position props and main beams
1. Position prop with Prophead (6) in one corner of the room (spacing: see Fig. A4.05).
2. Secure with tripod to prevent it from falling over.
3. Position prop with Drophead (1). Dis­tance from the wall 2.275 m. (Fig. A4.01)
4. Secure with tripod to prevent it from falling over.
5. Insert Main Beam SLT 225 (2) into the beam support of the Prophead and Drophead. The main beam connec­tion (2.1) must be mounted in the middle of the beam support (1.2) of the SKYDECK heads. (Fig. A4.02a / A4.02b / A4.02c)
6. Secure Main Beam SLT 225 (2) with Wall Holder SWH-2 (8).
7. Position second pair of props at a dis­tance of 1.50 m from the wall.
8. Insert Main Beam SLT 225 (2) in the beam support. (Fig. A4.02a / A4.02b / A4.02c / A4.04)
6
Fig. A4.01
2.1
2
1
1.2
Fig. A4.02a
1.2
Fig. A4.02b
Fig. A4.02c
1
8
Does the main beam connection (2.1) enclose the beam support (1.2)? (Fig. A4.02c)
Set up drophead props on the wall so that the drophead wedge can be re­moved during striking. The Main Beam SLT is always posi­tioned parallel to the longer wall side. Always check the rectangularity of the first bay.
Components
1 Drophead SFK 2 Main Beam SLT 6 Prophead SSK 8 Wall Holder SWH-2
Fig. A4.03
A
125
1375
Fig. A4.04
Section A-A
150 0
A
250
Fig. A4.05 Fig. A4.05a
2025
2275
SKYDECK Panel Slab Formwork
17
A4 Shuttering
Insert panels
1. Install panels (3) on the Main Beam SLT 225 (2).
The rack of the Main Beam SLT
fixes the panel in position.
2. Secure wall-side panel and Main Beam SLT with Wall Holder SWH-2 (8). (Fig. A4.06)
3. Install two additional panels. (Fig. A4.07)
The starting bay is complete.
(Fig. A4.08)
8
Spray the edge of the panel with re­lease agent before positioning.
Wall Holder SWH-2
The formwork surface area may only be accessed or loaded when Wall Holders SWH-2 have been installed!
The Wall Holder SWH-2 (8) is used to hold the slab formwork in a horizontal position during the assembly. It is in­stalled in longitudinal and transverse di­rections, and can fix the main beam as well as the panel. The Wall Holder SWH-2 (8) is mounted in every second bay.
Fig. A4.06
3
Fig. A4.07
Assembly
1. Insert tie rod with wingnut pivot plate through the available tie hole.
2. Place Main Beam SLT into the Wall Holder SWH-2 or push into the edge of the panel.
3. Tighten Wall Holder SWH-2 with Wingnut Pivot Plate on the wall.
4. Remove tripods. (Fig. A4.08)
The wall holder isassembled.
18
8
Fig. A4.08
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A4 Shuttering
Transverse bay
1. Position prop with Prophead SSK (6). Spacing 1.50 m.
2. Secure with tripod.
3. Position prop with Drophead SFK (1). Spacing 2.275 m.
4. Insert Main Beam SLT 225 (2) into the beam support of the Prophead and Drophead. (Fig. A4.09)
5. Secure with tripod.
6. Insert panels (3). (Fig. A 4.10 )
The transverse bay is complete.
(Fig. A4 .11)
Shuttering is carried out using a safe mobile scaffold!
Working in a transverse direction is rec­ommended. Use tripods again in the next bay.
1
2
6
Fig. A4.09
3
Components
1 Drophead SFK 2 Main Beam SLT 3 Panel SDP 6 Prophead SSK 8 Wall Holder SWH-2
Fi g. A 4.10
8
1,50 m
2,275 m
Fi g . A4.11
SKYDECK Panel Slab Formwork
19
A4 Shuttering
Longitudinal bay
Based on the risk assessment, the contractor must decide whether forming takes place from above or below!
1. Attach Main Beam SLT 225 (2) to the Drophead.
2. Connect prop with Drophead in the main beam. (Fig. A4.12)
3. Place prop in a vertical position. (Fig . A 4.12a)
4. Secure with tripod.
5. Proceed likewise with the second main beam and prop.
6. Insert panels (3). (Fig. A4.13)
7. Remove tripod and use again in the next bay.
The longitudinal bay is now com-
plete. (Fig. A4.14)
α
Fi g. A 4.12 Fig. A4.12a
Optimum angle for mounting the Main Beam SLT up to α 45°.
α
The main beam is correctly fitted only if the corner of the recess hangs under the prop without obstruction.
2
The Wall Holder SWH-2 (8) is mount­ed in every second bay.
Risk of falling!
– When lingering on the slab form-
work, measures must be taken to prevent falling, e.g. PPE.
– When shuttering from below, use
a safe and secure mobile scaffold; install panels overhead.
If the SKYDECK Guardrail Holder is used, this must be installed during set­ting of the panels. For details, see Sec­tion A8.
Components
2 Main Beam SLT 3 Panel SDP 4 Cover Strip SAL 5 Pallet SD 8 Wall Holder SWH-2 21 Panel Clip SPK
Fi g. A 4.13
3
During forming from above, press panel down with the foot when in­stalling.
8
8
8
8
20
Fi g. A 4.14
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A4 Shuttering
Standard bay
Due to the recurring assembly se­quence, always continue in the same way.
With all-round enclosed structure geom­etries, panels are to be fixed by means of two Panel Clips SPK (21) each time to the main beams for wind speeds be­tween 0.033 kN/m² (26 km/h) and dy­namic pressure 0.061 kN/m² (36 km/h). For unfavourable structure geometries or larger wind speeds, additional secur­ing measures are to be implemented, e.g.:
– ballast – bracing (Fig. A4.16) – dismantling the formwork etc.
1. Attach Main Beam SLT 225 (2) to the Drophead.
2. Connect prop with Drophead SFK in the raised main beam. (Fig. A4.15)
3. Place prop in a vertical position.
4. Insert panels (3).
The standard bay is now complete.
3
2
Fi g. A 4.15
21
21
Fi g. A 4.16
Fi g. A 4.17
50 mm
The Prophead SSK is not a substi­tute for the Drophead.
4
Without the Drophead, the Cover Strip (4) has no supporting effect.
SKYDECK Panel Slab Formwork
21
A4 Shuttering
Shuttering the casting segment
Set down Pallet SD (5) with panels (3) onto the forming area. Place panels in the main beams. Make empty pallets available in preparation for the striking process. (F ig. A 4 .18)
1. Shutter the standard fields until there is no more space for the Main Beam SLT 225 or Compensation Beam SLT150.
2. Form the infill areas. See A5.
3. Continually insert Cover Strip SAL (4). (Fig . A 4.19)
4. Thinly spray the forming area with a release agent – also from below if used for the first time.
Risk of slipping! The forming area becomes slippery through the use of release agents!
– Be extremely careful when access-
ing forming areas after spraying!
– Weather conditions are to be tak-
en into account!
5
3
Fi g. A 4.18
Regarding the tightness of the panel joints, e.g. for casting segments/setting of stopends, push the panels tightly together and secure on the last main beam with Panel Wedge Clips SPKK (20). (Fig. A4.20 – Fig. A4.22)
Panel Wedge Clip SPKK
The panel wedge clip is used to connect 2 panels with one main beam.
Possible applications
1. Panel joint in the middle of main beam
20
Fi g. A 4.19
2. Overlapping panel Side view
125
20
4
20
Fig. A4.20
22
Fig. A4.21 Fig. A4.22
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
23
A5 Compensations
System components
For the realization of compensations and shuttering of columns, a range of system components is available.
Secure filler plates with nails!
Edge Beam SRT 150-2, SRT 75
Install vertically (Fig. A5.01) or suspended. (Fig. A5.02) The locking pin (9.1/10.1) secures the Edge Beam SRT 150 (9) or SRT 75 (10):
– to the Main Beam SLT in a longitudi-
nal direction. (Fig. A5.01 + A5.02)
– to the Prophead SSK in a transverse
direction. (Fig. A5.03)
– to the Combihead SCK (7) in a longi-
tudinal direction. (Fig. A5.04)
– in the End Support SSL (11) in a longi-
tudinal direction. (Fig. A5.07)
SRT vertical
9/10
Fig. A5.01 Fig. A5.02
9
Fig. A5.03 Fig. A5.04
9.1/10 .1
The asterisk (*) refers to the installation in a suspended position.
SRT suspended*
9*/10*
7
12
9
Filler Timber SPH
Install Filler Timber SPH (12) vertically or horizontally.
– to the Combihead SCK. (Fig. A5.04) – nailed laterally on the panel. – horizontally, transverse to the sus-
pended Edge Beam SRT. (Fig. A5.05 + A5.06)
End Support SSL
Use the End Support SSL as height ad­justment for the transition from a stand­ard bay to an infill area. (Fig. A5.07) The End Support SSL must always be directly supported by means of a Prop­head, Drophead or Combihead. (Fig. A5.08)
Components
2 Main Beam SLT 3 Panel SDP 7 Combihead SCK 9 Edge Beam SRT-2 150 9* Edge Beam SRT-2 150, suspended 10 Edge Beam SRT-2 75 10* Edge Beam SRT-2 75, suspended 11 End Support SSL 12 Filler Timber SPH
Fig. A5.05
11
Fig. A5.06
Fig. A5.07
End Support SSL
11
Fig. A5.09Fig. A5.08
No End Support SSL without any direct support through Prophead, Drophead or Combihead.
24
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A5 Compensations
Combihead SCK
Use of longitudinal and transverse infills up to 25 cm. The cantilever of the Head Plate is in longitudinal direction ≤ 19 cm, in trans­verse direction ≤ 12.5 cm. The Combihead (7) (Fig. A5.11) is a se­cure, non-movable and non-twisting support for:
– Main Beam SLT 225 (2). – SLT 150 (2.5). (F i g. A5.10) – Panel SDP (3). (Fig. A5.12) – Edge Beam SRT (9) and Filler Timber
SPH (12) or timber provided by the contractor with b = 3.8 – 8 cm and h = 9.8 cm. (Fig. A5.13)
– End Support SSL (11). (Fig. A5.14)
Mounting the main beam
The Main Beam SLT must be mounted in the middle of the beam support of the SKYDECK Heads. The main beam connection (2.1) encloses the main beam support (7.1) of the head. (Fig . A 5 .10)
The Combihead SCK has 2 main beam supports and can be installed in both directions. In infill areas, the cantilever points towards the compensation.
2.1
7.1
2/2.5
Fi g. A 5 .10 Fig. A5.11
3
Fi g. A 5 .12
11
7.1
Fi g. A 5 .13
7
9 12
Exceptions:
The cantilever points towards the main beam
– when using the End Support,
(Fig. A5.14)
– when infill ≤ cantilever. (F i g. A5 .14a)
Placing the main beam
With inset props, the cantilever of the Combihead always points towards the main beam. Position the Combihead so that the main beam support is securely posi­tioned in the groove (2.8) of the main beam. (Fig. A5.15)
Fi g. A 5 .14 Fig. A5.14 a
2.8
7
Fi g. A 5 .15
SKYDECK Panel Slab Formwork
25
A5 Compensations
Insert panels
With direct panel support, install the cantilever of the Combihead in the di­rection of the infill area. (Fig. A5.16)
The teeth in the plastic racks (7.2) on the cantilever hold the panels (3) in 5 different positions. Select support posi­tion according to the compensation width. Position the cantilever of the Combihead SCK as close as possible to the wall in order to provide maximum support for the infill area. (Fig. A5.17c – A5.17d)
7
7.2
3
≤ 25
Fi g. A 5 .16 Fig. A5.17
Do not install panels in a longitudinal di­rection outside of the longitudinal axis of the Combihead. (Fig. A5.17e + A5.17f)
Components
1 Drophead SFK 2 Main Beam SLT 3 Panel SDP 7 Combihead SCK 14 Triangular Frame SDR
Fi g. A 5 .17a
Fi g. A 5 .17c
Fi g. A 5 .17e Fi g. A 5 .17 f
Fig. A5.17b
Fi g. A 5 .17d
26
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A5 Compensations
With a transverse positioned Combi­head, e.g. in compensation areas, place panels at least as far as the central axis or further!
Fi g. A 5 .18a Fig. A5.18 bFi g. A 5 .18
In corners where longitudinal and trans­verse compensations meet, the Combi­head (7) is aligned in the direction of the main beam. (Fig. A5.19 A)
Install the cantilever of the Combihead (7) up to the compensation area. (Fig. A5.19 B)
A
7
B
7
B
7
2
In the system with the Drophead (1), the Combihead (7) is always installed trans­versely if it is positioned under a cover strip. As a result, the panels are prevent­ed from slipping out of position. (Fig. A5.19 C)
Fi g. A 5 .19
SKYDECK Panel Slab Formwork
7
1
C
27
A5 Compensations
Triangular Frame SDR 150/75, 75/75
Form infill areas with inclined walls us­ing triangular frames.
Forming the infills
1. Continue forming in the system as long as possible.
2. Carry on forming operations with filler panels as well as transversely inserted panels – as for longitudinal and transverse compensations.
3. Lay Triangular Frame (14) on the sup­port (Main Beam, Prophead or Combi­head, End Support). (Fig. A5.20)
4. Place the support on the wall side.
5. Install formlining and secure in posi­tion with nails.
14
Fig. A5.20
Longitudinal compensations
Secure filler plates with nails!
Drophead infills up to 2.25 m + 5 cm. Prophead infills up to 2.25 m.
Length of room minus n x 2.30 m (2.25 m) = compensation area. See Tables: Fillers / Forming around columns.
Forming longitudinal compensations between 75 cm and 2.25 m
1. Continue forming with prop, Compen­sation Beam SLT 150 (2.5) and Panel SDP (3) as in the standard bay. (Fig. A5.21)
2. Depending on the required load-bear­ing capacity, continue forming with filler panels. See PERI Tables.
3. Forming of gaps up to 75 cm, see following pages.
Fig. A5.21
1,5 m
2,25 m (+5 cm)
31 1
2.5
≤ 75 cm
11
– Take into account the load-bearing
capacity and supporting direction of the formlining. See PERI Tables.
– Timbers are securely nailed on the
panel inner side before panels are assembled. Use the nail holes in the panel edge struts.
28
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A5 Compensations
Gap 0 – 6 cm
1. Place Combihead SCK (7) or Prop­head SSK (6) in a recessed position under the Main Beam SLT (2.5).
2. Nail Filler Timber SPH (12) or timber up to max. 6 cm on the panel.
3. Install formlining (16) and secure with nails. (Fig. A5.22 + A5.23)
Gap 5 – 12.5 cm
1. Place Main Beam SLT (2) on inset prop with Combihead SCK (7) or Prophead SSK (6).
2. Place additional props with trans­versely positioned Combiheads SCK (7a) in an offset arrangement.
3. Install Filler Timber SPH (12) or Edge Beam SRT (9).
4. Position the formlining and secure with nails. (Fig. A5.24 + A5.25)
0 – 6 0 – 6
16
2.5
7
7 6
12
Fig. A5.23Fig. A5.22
5,1 – 12,4 5,1 – 12,4
12
7a
6
Components
1 Drophead SFK
2.5 Main Beam SLT 150 3 Panel SDP 6 Prophead SSK 7 Combihead SCK 9 Edge Beam SRT-2 150 11 End Support SSL 12 Filler Timber SPH 13 Timber 14 Triangular Frame 15 Additional prop with crosshead and
formwork girder
16 21 mm formlining provided by the
contractor
Fig. A5.24 Fig. A5.25
Offset prop arrangement.
SKYDECK Panel Slab Formwork
29
A5 Compensations
Gap 12.5 – 20 cm
1. Mount Combihead SCK turned by 180° (7) or Prophead SSK in the main beam support.
2. Install End Support, Filler Timber and Edge Beam.
3. Install formlining and secure in posi­tion with nails. (Fig. A5.26 + A5.27)
Gap 20 – 75 cm
1. Install Main Beam in Drophead SFK (1) (Fig. A5.31), with 180° turned Combihead SCK (7) (Fig. A5.32) or Prophead SSK (6) (Fig. A5.33).
2. Mount End Support (11) and Edge Beam (9).
3. Position additional prop with cross­head and formwork girder (15).
4. Install formlining and secure in posi­tion with nails. (Fig. A5.28 – A5.30)
Fig. A5.26
12
7
12 – 20 12 – 20
16 9
11
6
Fig. A5.27
20.1 – 79.9
9
11
15
1
Fig. A5.28
Fig. A5.29
20.1 – 74.9
7
20.1 – 74.9
30
6
Fig. A5.30
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A5 Compensations
Transverse compensations
Secure filler plates with nails!
Max. infills are 1.50 m. Infills are calculated based on length of room – n x 1.50 m. See Tables: Fillers / Forming around col­umns.
Forming the infills
3a
75
≤ 1.50 m
≤ 75
Transverse infill between 75 cm and
1.50 m
1. Continue forming with prop, Main Beam SLT 225 (2) and transverse­ly-positioned panel (3). Close the spacing to the next prophead with Panel SDP 75 x 75 (3a). (Fig. A5.31 + A5.32)
2. Depending on the required load-bear­ing capacity, continue forming with filler panels. See PERI Tables.
3. Form gaps up to 75 cm; see following pages.
– Take into account the load-bearing ca-
pacity and supporting direction of the formlining. See PERI Tables.
– Timbers are securely nailed or
screwed on the panel inner side be­fore panels are assembled. Use the nail holes in the panel edge struts.
1 151
Fig. A5.31
3
3a
2
Components
1 Drophead SFK 3 Panel SDP 6 Prophead SSK 7 Combihead SCK 9 Edge Beam SRT-2 150 11 End Support SSL 12 Filler Timber SPH 15 Additional prop with crosshead and
formwork girder
16 21 mm formlining provided by the
contractor
SKYDECK Panel Slab Formwork
Fig. A5.32
31
A5 Compensations
Gap 0 – 12 cm
1. Place Panel SDP (3) over the Main Beam SLT (2) and secure with Panel Wedge Clips (20). (Fig. A5.33 – A5.35)
2. Nail Filler Timber SPH (12) or timber (13) up to max. 6 cm on the panel. (Fig. A5.35) Screw Filler Timber SPH (12) or timber (13) up to max. 6 cm on the panel. (Fig. A5.36)
3. Install formlining (16) and secure with nails.
If panels (3) are placed over the main beam (2), the panel edge can not laterally stabilize the main beam.
Secure every main beam with a Panel
Wedge Clip SPKK to prevent overturning!
Fig. A5.33
12
0 – 6
0 – 12
1616
33
13
2
2020
11
Fig. A5.34
2 3
20
Gap 5 – 12.5 cm
1. Position Combihead SCK (7) with can­tilever in the direction of the infill.
2. Install Panel (3).
3. Install Edge Beam SRT-2 (9) or Filler Timber SPH (12) in the Combihead (7).
4. Install formlining (16) and secure with nails. (Fig. A5.36)
32
Fig. A5.35
Fig. A5.36
5.1 – 12.4
16
9/12
3
7
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A5 Compensations
Gap 12.5 – 25 cm
1. Position Combihead SCK (7) with can­tilever in the direction of the infill.
2. Install Panel (3).
3. Install Edge Beam SRT-2 (9) or Filler Timber SPH (12) in the Combihead.
4. Install formlining (16) and secure with nails. (Fig. A5.37)
Alternatively
1. Place Panel SDP (3) over the Main Beam SLT (2) and secure with Panel Wedge Clip (20).
2. Screw Filler Timber SPH (12) or tim­ber on the panel.
3. Position additional prop with cross­head (15) and formwork girder.
4. Install formlining (16) and secure with nails. (Fig. A5.38)
Gap 25 – 75 cm
1. Mount the Panel SDP (3) in the Main Beam (2).
2. Insert Edge Beam SRT-2 (9) in the Main Beam.
3. Position additional prop with cross­head (15) and formwork girder.
4. Install formlining (16) and secure with nails. (Fig. A5.39 + A5.40)
Fig. A5.37
12.5 – 24.9 12 – 24
9
3
7
20
16
12
12
20
1
Fig. A5.38
24 – 75
9
3
2
2
15
16
15
1
Components
1 Drophead SFK 2 Main Beam SLT 3 Panel SDP 6 Prophead SSK 7 Combihead SCK 9 Edge Beam SRT-2 150 12 Filler Timber SPH 13 Timber 15 Additional prop with crosshead and
formwork girder
16 Formlining 20 Panel Wedge Clip SPKK
Fig. A5.39
Fig. A5.40
3a
9
2
15
SKYDECK Panel Slab Formwork
33
A6 Shuttering around columns
1 recessed panel
Maximum column dimensions x = 55 cm, y = 138 cm.
Secure filler plates with nails!
Install Edge Beam SRT-2 150 vertically (9) or Filler Timber SPH 150 (12). During use, permissible loads must be observed; see Tables: Fillers / Forming around columns
Take into account the supporting direction of the formlining.
Alternatively: Install Edge Beam SRT-2 150 (9*) in a suspended position. (Fig. A6.03) Flatly position Filler Timber SPH or in­stall timber (13) supplied by the contrac­tor.
Fig. A6.01
Width of Influence
y
x
9/12
For 27 mm formlining: height of timber = 47 mm. Permissible widths of influence for flat Filler Timber SPH, see Table A6.02.
Components
9 Edge Beam SRT-2 150 10 Edge Beam SRT-2 75 9* Edge Beam SRT 150, suspended 10* Edge Beam SRT 75, suspended 12 Filler Timber SPH 13 Timber
Fig. A6.02
Fig. A6.04
Fig. A6.03
y
x
13
9*
34
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A6 Shuttering around columns
2 recessed panels
Maximum column dimensions x = 65 cm, y = 138 cm.
Secure filler plates with nails!
y
x
10*
Install Edge Beam SRT 150 (9) vertically at the panel edge. Insert Edge Beam SRT 150 (9*) in a suspended position at the column. Likewise, insert Edge Beam SRT 75 (10*) in the Edge Beam (9*) in a sus­pended position. (Fig. A6.05 + A6.06)
Maximum column dimensions x = 130 cm, y = 138 cm.
Depending on the slab thickness and prop width, the transverse-positioned filler plates are to be additionally sup­ported, see Table A6.02.
Fig. A6.05
Fig. A6.06
9* 9/129/12
y
x
12
Insert Edge Beam SRT-2 150 (9*) in a
Fig. A6.07
suspended position. Lay Filler Timber SPH 150 (12) in a flat position. Permissi­ble widths of influence for flat Filler Tim­ber SPH, see Table A6.02 on next page. (Fig. A6.07 + A6.08)
With smaller cross-sections, form infill areas with Panel SDP 37.5.
Take into account the supporting direc­tion of the formlining.
Fig. A6.08
SKYDECK Panel Slab Formwork
9*
35
A6 Shuttering around columns
3 recessed panels
Maximum column dimensions x = 138 cm, y = 142 cm.
L
SPH
L
SPH
Secure filler plates with nails!
Install Edge Beam SRT-2 150 (9) vertically, Edge Beam SRT-2 150 (9*) suspended, Filler Timber SPH 150 (12) horizontally. (Fig. A6.09, Fig. A6.10)
Fig. A6.09
Fi g. A 6 .10
y
x
12
9
129*
9
Additional Edge Beam SRT-2 150 (9) required with:
Slab thickness
d [m]
≤ 0.20
Column side
y [m]
no additional SRT
0.25 ≤ 0.40
0.30 ≤ 0.70
0.40 ≤ 1.15
Table A6.01
For other slab thicknesses, the values are interpolated linearly.
Take into account the supporting direction of the formlining.
Permissible width of influence of flat Filler Timber SPH, maximum deformation l/500
permissible width of influence Filler Timber SPH flat e
Slab thickness
with span L
100 80 60
SPH
[cm]
14 30 58 137 16 26 51 121 18 23 46 108 20 21 41 98 22 19 38 89 24 18 35 82 25 17 33 79 26 16 32 76 28 15 30 71 30 14 28 66 35 12 24 57 40 11 21 50 43 10 20 46
Table A6.02
SPH,fl at
[cm]
36
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A6 Shuttering around columns
Recessed main beams
Secure filler plates with nails! Secure props of the Edge Beam SRT (**) with tripod!
Components
9 Edge Beam SRT-2 150 6 Prophead SSK 11 End Support SSL
Only used if moving the main beam axis is not desired. (Fig. A6.11, Fig. A6.12)
Additional formlining support depending on the situation on site.
Fi g . A6.11
9
**
11
9
6
9
6
Shifting the main beam axis
(Fig. A6.13)
Secure Main Beam SLT (**) props that have been shifted with tripods!
In the area of the box out, screw timber (13) on the panel as filler support.
Take into account the supporting direction of the formlining.
Components
6 Prophead SSK 9 Edge Beam SRT-2 150 9* Edge Beam SRT 150, suspended 10 Edge Beam SRT-2 75 11 End Support SSL 12 Filler Timber SPH 13 Timber
Fi g. A 6 .12
Fi g. A 6 .13
Secure props by means of tripod.
**
13
**
9
SKYDECK Panel Slab Formwork
37
A7 Horizontal bracing
Transfer of horizontal loads into the columns of the building
The horizontal loads according to DIN EN 12812 are to be accommodated by the building walls, columns or bracings. SKYDECK is able to transfer these loads into the building columns according to Table A7.01 without requiring any addi­tional bracing. The prerequisite is that the building col­umns can accommodate the horizontal loads according to the table.
At the edge of the slab, corresponding loads, e.g. from the stopend formwork pressure, platforms or wind, must be separately anchored.
With a rectangular column grid, the largest column spacing is decisive.
Slab thickness Panel span Maximum perm.
column grid
(building columns)
[cm] [cm] a [m] H [kN]
14 150 10.31 9.44 16 150 9.26 8.48 18 150 8.39 7.6 9 20 150 7.6 8 7. 0 3 22 150 7.07 6.48 24 150 6.56 6.00 25 150 6.32 5.79 26 150 6 .11 5.59 28 150 5.71 5.23 30 150 5.37 4.92 35 150 4.63 4.24 40 150 4.06 3.72 43 150 3.77 3.45 45 75 3.59 3.29 50 75 3.21 2.94 55 75 2.90 2.66 60 75 2.68 2.45 65 75 2.48 2.27 70 75 2.31 2.12 75 75 2.17 1.99 80 75 2.05 1.8 8 85 75 1.95 1.78 90 75 1.85 1.70
Horizontal load
per column
(building column)
Example
Slab thickness 30 cm, panel span 150 cm.
permissible column grid without
bracing the SKYDECK: = 5.37 m (a).
Horizontal load to be transferred: H =
4.92 kN.
This load must be verified by the struc­tural engineer regarding the respective column in the actual building condition. (Fig. A7.01)
Tabl e A7.01
≤ a
≤ a
Fig. A7.01
38
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A7 Horizontal bracing
General
– Do not access the forming area be-
fore the formwork has been hori­zontally anchored!
– Do not access the cantilevers be-
fore the bracing has been mount­ed in a form-fitting manner!
Formwork positioned on open building edges or concreting sections, is to be secured against horizontal loads by means of bracing. Cantilevers, e.g. on edge bay, must be additionally vertically braced in order to prevent any tilting. Example calculation: see Transfer of horizontal loads from a casting seg­ment.
Bracing of the inner bay
– Maintain spacings – Bays must be braced longitudinally
and horizontally
Schematic representation
Influencing area, e.g. slab d = 25 cm.
Fig. A7.02
Longitudinal direction
Lateral direction
Assembly
1. Mount Base Plate on a sufficiently load-bearing surface area, e.g. using PERI Anchor Bolt 14/20x130, Item no.
124777. Take into consideration the Technical Data Sheet!
2. Attach Anchor Chain to the panels:
– In the longitudinal direction, attach
Anchor Chain (23) to the Tension Sleeve SAO (39). (Fig. A7.03)
– In the transverse direction, connect
panels to scaffold tube (31). Wrap Chain (23) around the scaffold tube. (Fig. A7.03a)
3. Secure Anchor Chain to Base Plate using bolts, and secure bolts by means of cotter pins. (Fig. A7.03b)
Components
23 Anchor Chain (permissible ten-
sion force = 3 kN)
24 Base Plate RS
24.1 Anchor Bolt PERI 14/20 x 130 31 Scaffold Tube 39 Tension Sleeve SAO
39
23
Fig. A7.03 Fig. A7.03a
24
31
23
Fig. A7.03b
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
24.1
39
A7 Horizontal bracing
Transfer of horizontal loads from a casting segment
Example 1 Open building edge on one side
Bracing in one building direction. (Fig. A7.05) Values: see Table A14.01.
Requirements
– Load Case Combination LFK 1:
Concreting – Load Case Combination LFK 2: Storm – Slab thickness d = 25 cm – Panel span = 1.50 m – 1 edge area – 9 inner bays
Number of chains
– The load case combination which re-
sults in the biggest value is decisive. – Permissible horizontal component of
the tension load on the anchor chain
= 3 kN x cos 60° = 1.5 kN. (Fig. A7.04)
1.50 kN
3.00 kN
60°
Fig. A7.04
2.60 kN
Calculation
Load Compilation LFK 1 Concreting
1 x H
edge area + 9 x H
load
inner bay = ∑H
load
2.447 kN + (9 x 0.54 kN) = 7.307 kN
Load Compilation LFK 2 Storm
1 x H
edge area + 9 x H
load
inner bay = ∑H
load
1.291 kN + (9 x 0.033 kN) = 1.588 kN
Number of chains
H = 1.588 kN < 7.307 kN LFK 1 Concreting is decisive
= H / perm. tension force of chain
n
chain
= 7.31 kN : 1.5 kN = 4.87 chains = 5 chains
2.447 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 kN
Cycle joint
Chain 1 Chain 2 Chain 3 Chain 4 Chain 5
Fig. A7.05
2.447 kN 0.54 kN0.54 kN0.54 kN
60°
Fig. A7.06
Load
Slab
thickness
[cm]
25 7.83 1.430 0.715 0.540 0.270 2.447 1.224 0.033 0.016 1. 291 0.645
Excerpt from Table A14.01
according
to DIN
EN 12 812
[kN/m²]
Horizontal Load
c = 1.50 m c = 0.75 m
from
stopend
formwork
pressure
edge area
from
stopend
formwork
pressure
Load Case Combination LFK 1: Concreting*
[kN]
Horizontal Load
Panel span c = 1.50 m
[kN] Horizontal Load
inner bay
Panel span c = 0.75 m
Panel span c = 1.50 m
edge area
Panel span c = 0.75 m
Load Case Combination LFK 2: Storm**
[kN] Horizontal Load
Panel span c = 1.50 m
inner bay
Panel span c = 0.75 m
[kN]
Horizontal Load
Panel span c = 1.50 m
[kN]
edge area
Panel span c = 0.75 m
40
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A7 Horizontal bracing
Example 2: Open building edge on both sides
Bracing in both building directions. (Fig. A7.08) Values: see Table A14.01.
Requirements
– Load Case Combination LFK 1:
Concreting – Load Case Combination LFK 2: Storm – Slab thickness d = 25 cm – Panel span = 1.50 m – 2 edge areas – 8 inner bays
Number of chains
– The load case combination which re-
sults in the biggest value is decisive. – Permissible horizontal component of
the tension load on the anchor chain
= 3 kN x cos 60° = 1.5 kN. (Fig. A7.04)
1.50 kN
3.00 kN
60°
Fig. A7.04
2.60 kN
Calculation
Load Compilation LFK 1 Concreting
2 x (H
edge area − stopendformwork pressure*)
load
+ (8 x H
inner bay) = ∑H
load
2 x (2.447 kN − 1.43 kN) + (8 x 0.54 kN) = 6.354 kN
Load Compilation LFK 2 Storm
2 x H
edge area + (8 x H
load
inner bay) = ∑H
load
2 x 1.291 kN + (8 x 0.033 kN) = 2.846 kN
Number of chains
H = 2.846 kN < 6.354 kN LFK 1 Concreting is decisive
= H / perm. tension force of chain
n
chain
= 6.54 kN : 1.5 kN = 4.236 chains = 5 chains per load direction
2.447
1.4 3 1.4 3
Chain 1 Chain 2 Chain 3 Chain 4 Chain 5
Fig. A7.07
0.540.540.540.540.540.540.540.54 2.447 kN
Fig. A7.08
1.02 kN*
1.4 3 k N
2.447 kN
60°
1.4 3 k N
2.447 kN
0.54 kN 0.54 kN0.54 kN
1.02 kN*
1.4 3 k N
2.447 kN
*The stopend formwork pressure is already included in Load Case Combination
=
1.02 kN
LFK 1 for edge areas. Through reciprocal elimination on both sides of the open building edge, this value must be deducted from both sides.
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
41
A8 Cantilevers, Guardrails
Bracing on open building edges to prevent tipping
39
Horizontal loads must be additional­ly taken into consideration and transferred, e.g. with bracing; see Sect i o n A7.
Cantilevers with Panels SDP
Mount Tension Sleeve SAO (39) on main beam. Distance to inner prop max. 50 cm. Brace using Anchor Chain (23), Base Plate (24) and Anchor Bolt (24.1). (Fig. A8.01) Max. slab overhang: 37.5 cm.
Cantilevers with SKYDECK Platforms SDB
(Fig. A8.02 + A8.03) See Cantilevers with Panels SDP.
Corner table:
The Main Beams SLT “A + B” receive 2-fold horizontal load from the wind and 1-fold load from the stopend formwork pressure. Additional bracing is required.
Fig. A8.03 shows only bracing from Load Case Tilting. Take into account Section A9 SKYDECK Platforms!
Fig. A8.01
Fig. A8.02
90°
≤ 54
2.25 m
90°
≤ 50
2.25 m
39
23
24
24.1
23
24
24.1
≤ 3 7. 5
≤ 3 7. 5
Components
23 Anchor Chain (permissible ten-
sion force = 3 kN)
24 Base Plate RS
24.1 Anchor Bolt PERI 14/20 x 130 39 Tension Sleeve SAO 45 SKYDECK Platform SDK
45c
45a B
45a
Fig. A8.03
42
≤ 37,5 cm
A
≤ 37,5 cm
45c 45b
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A8 Cantilevers, Guardrails
Guardrails with Handrail Unit SD
– SD 75
– SD 150 The SKYDECK Handrail Unit SD secures site personnel working on a casting seg­ment against falling in the main field di­rection.
Risk of falling! During assembly of the Handrail Unit, measures must be taken to prevent falling, e.g. PPE!
Assembly
A free length of at least 35 cm must be available on the main beam in order to be able to mount a Handrail Unit SD. (Fig. A8.04a)
1. Pull lug (25.1) upwards. (Fig. A8.07)
2. Move the Handrail Unit SD (25) firstly
in the direction of the building edge (l.)and then downwards (ll.) (Fig. A8.04a)
3. Place Handrail Unit SD with the hooks
(25.2) between the two teeth (2.2) which are free on the main beam.
The lug falls downwards. Hooks
engage and are secured. If the lug is not completely down, then press lug (25.1) downwards by stepping on it. (Fig. A8.05) The Handrail Unit is installed. (Fig. A8.06)
Fig. A8.04
II.
Fig. A8.04a
25
I.
≥ 35 cm
Main bay direction
25
25.1
25.2
Fig. A8.05
2.2
– Is the lug completely folded down?
– Do the hooks enclose the teeth of the
main beam? (Fig. A8.05)
Dismantling
1. Pull lug (25.1) upwards. (Fig. A8.07)
Hooks are released.
2. Lift out Handrail Unit SD (25) and
place in Pallet Handrail Unit SD 150 x
75.
SKYDECK Panel Slab Formwork
Fig. A8.06
Fig. A8.06a
25.2
25.1
Fig. A8.07
43
A8 Cantilevers, Guardrails
SKYDECK Guardrail Holder SGH and Guardrail Post SGP
Risk of falling! During assembly, measures must be taken to prevent falling, e.g. PPE!
Assembly
Continuous mounting of Guardrail Hold­er SGH (17) between the panels. To do so, place the guardrail holder laterally offset on the main beam and slide in. Spacing max. 1.55 m.
Wind safeguard measure: with wind speeds > 90 km/h, remove the top guardrail board. Adapt working area ac­cordingly to suit changed guardrail situa­tion.
After the last row of panels, mount the Guardrail Holder SGH for the End Guard­rail Frame on all main beams:
1. Start with the guardrail holder on the outer right-hand side (17.1) – as viewed when standing in front of the formwork. Mounting bar is pointing to the left.
2. Mount all other guardrail holders (17) with the mounting bar pointing to the right. (Fig. A8.09) The mounting bars overlap in the first bay.
3. Insert guardrail posts (18).
4. Insert guardrail boards and secure with nails. (Fig. A8.10)
Components
Fig. A8.09
Fi g. A 8 .10
18
17
17
17.1
17
17 Guardrail Holder SGH 18 Guardrail Post SPG 20 Panel Wedge Clip SPKK
44
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
SKYDECK Panel Slab Formwork
45
A9 SKYDECK platforms
Overview
The SKYDCK Platform SDB is a prefab­ricated, foldable scaffold platform for use as working scaffold following DIN EN 12811, Load Class 2, with a permis­sible load of 1.5 kN/m² (150 kg/m²). It secures the open buiding edges of the SKYDECK slab formwork.
Assembly of the slab formwork in con­nection with SKYDECK Platform SDB is carried out in four areas. ( I – IV) The sequence must be maintained. (Fig. A9.01)
Risk of falling!
– Ensure that end-to-end side pro-
tection is installed on slabs that have been completed!
– Cantilevers should not have form-
work erected or be stepped on be­fore being firmly secured with ten­sion chains.
– Work to be carried out by qualified
personnel only!
When using SKYDECK platforms, no safety scaffold is required for the levels below.
SLT 375 SLT 225
SDB 300SDB 300SDB 150SDB 150
II
Inner platform
I
IV
SLT 225
III
Outer platform
SLT 375
Fig. A9.01
46
Corner table
SDB 300 SDB 300 SDB 150 SDB 225
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
SPKK (20)
SLT 375
A9 SKYDECK platforms
Corner table (Area l)
Risk of falling! Ensure that end-to-end side protec­tion is installed on slabs that have been completed!
Begin forming operations on a free building corner. The corner table is assembled on the previously concreted slab in the inside of the building. Subsequently, position in the corner (Area I) and secure against tipping. (Fig. A9.01)
Frame assembly
1. Spindle out the MULTIPROP Props MP (35) 3 cm on a narrow side. The two props opposite (35.1) are not spindled out. As a result, the height difference resulting from the different installations of the main beam is com­pensated. The exact height adjust­ment takes place later.
2. Four MULTIPROP Props are placed in a 1.50 m x 2.25 m grid with the spin­dles (inner tube) downwards and formed into a base frame using MULTIPROP MRK 150 (36) and MRK225 (36.1) Frames. (Fig. A9.02) Mount the frame at the same level above the slab. Locking wedges (36.2) are facing outwards.
3. Attach two Propheads SSK (6) on the extended props.
Assembly of the main beams
1. Insert each Main Beam SLT 375 into a main beam groove:
– Use two Bolts M12 x 140 DIN 6914
for fixing timbers 8/12. – 2 x Table Connector STV (38). – Sequence and alignment of bolts
and table connectors: see
Fig. A9.03.
2. Mount Main Beam SLT 375 (2.6) and set the beam down on the front prop.
3. Push the Table Connector STV up to the MULTIPROP Props and make a secure connection by tightening the ring bolts. (Fig. A9.03a)
36 3 6 .1 35 .1
35
3
Fig. A9.02
Main Beam Support SSK (shown without table connector).
Fig. A9.03
Components
2.6 Main Beam SLT 375 6 Prophead SSK 35 MULTIPROP Prop MP 36 MULTIPROP Frame MRK 37 Bolt M12 x 140 38 Table Connector STV
3
0
0
Afterwards, mount the Table Connector STV.
6
37
36.2
37
38
38
2.6
38
Fig. A9.03a
SKYDECK Panel Slab Formwork
47
A9 SKYDECK platforms
4. Insert two SAO Tension Sleeves approx. 1 m in each of the grooves of 3 Main Beams SLT 375. Tension sleeves later lie between the two bot­tom main beams.
5. Position Main Beams SLT 375 (2.6) transversely with 1.50 m spacings on the already assembled main beams. At the rear, all three beams have an overhang of 37.5 cm. The first beam is laterally inset 37.5 cm on the lower beam.
6. Insert additional Tension Sleeves SAO (39) on both sides as far as the bot­tom main beams.Push the previously mounted tension sleeves inwards against the bottom main beams. (Fig. A9.04a)
7. Connect the beams together by tight­ening the tension sleeves.
Mounting the timbers
Timbers are required for load distribu­tion when directly reaching under with the transportation fork.
1. Attach 2 timbers with min. 8/12/225 (40) (supplied by contractor) to the hex. bolts using nuts and washers. (Fig. A9.04)
2. Diagonally brace the timbers.
Fig. A9.04a
Fig. A9.04
39
2.6
40
12
37
Insert panels
The first row of panels (3) is moved
37.5 cm and begins in the centre aligned
to the first bottom main beams.
1. Insert the SDP 150 x 75 panels from below and secure to the main beams with two SPK Panel Clamps per panel.
2. The middle panels are additionally fixed to the front outer panels using two Panel Wedge Clamps SPKK each.
3. On the side cantilevered slab edge: install the Guardrail Holder SGH.
4. Mount Guardrail Posts SGP and hand­rail boards as anti-fall protection. (Fig. A9.05)
Components
2.6 Main Beam SLT 375 17 Guardrail Holder SGH 20 Panel Wedge Clip SPKK 21 Panel Clip SPK 37 Bolt M12 x 140 39 Tension Sleeve SAO 40 Timber
Fig. A9.05
20 21
3
17
48
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A9 SKYDECK platforms
Supporting the top main beams
1. Insert Table Connector STV into the longitudinal grooves of the top main beams (2.6) which are later posi­tioned in the building.
2. Fix 2 MULTIPROP Props MP (35)
1.50 m from the cantilevered girder end using the Table Connector STV (38).
3. Brace the MULTIPROP Props MP with MULTIPROP Frame MRK 150 (36).
4. Connect the Frames MRK 150 to the Frames MRK 225 (36.1) with at least one scaffold tube L = 2.25 m (31) and three scaffold couplings. (Fig. A9.06)
5. Mount the inner SKYDECK Platform SDB (45). (Fig. A9.06a)
6. Insert Panels SDP.
2.6 2.6
38
35
36 31
Position corner table
Follow Instructions for Use, SKYDECK Lifting Fork!
1. Raise the corner table using the SKYDECK Transportation Fork and extend the Props MP to the required length.
2. Position the corner table at the corner of the building so that the front MULTIPROP Props MP (35) are as close as possible to the edge of the building. (Fig. A9.06a)
Risk of falling!
– Do not erect formwork or step on
corner table before the tension chains are securely fixed.
– Do not close the filler areas until
the corner table has been securely fixed and SKYDECK platforms have been attached.
Components
Fig. A9.06
Corner column
35
36 31
35
45
Building edge
Fig. A9.06a
2,25 m
Kantholz
2.6 Main Beam SLT 375 31 Scaffold Tube 35 MULTIPROP Prop MP 36 MULTIPROP Frame MRK 38 Table Connector STV 45 SKYDECK Platform SDK
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
49
A9 SKYDECK platforms
Tensioning the corner tables
Use anchor chains for securing the ta­bles to the floor.
1. Attach one tension chain (23) to the outer Table Connector STV (38) on each of the bottom Main Beams SLT 375, and diagonally tension.
2. Attach one tension chain (23.1) to the Tension Sleeve SAO to the first top and inner-positioned Main Beam SLT 375, and diagonally tension.
3. On the middle, top main beam, attach two tension chains to the Tension Sleeves SAO. Diagonally (23.2) ten­sion the first tension chain; the sec­ond tension chain (23.3) is vertically tensioned. (Fig. A9.07 + A9.07a)
38
23.1 23
23.2
23.3
Risk of falling! During assembly, measures must be taken to prevent falling, e.g. PPE!
4. Mount the SKYDECK Platform SDB (45): see A9 Platform installation.
5. Close the filler areas: see A5 Com­pensations and A6 Shuttering of columns.
Fig. A9.07
Edge of building
38
Scaffold coupling
MRK 150
additional propPropadditional prop
2323
38
23.1
38
Components
23 Tension chain 38 Table Connector STV 45 SKYDECK Platform SDK
50
45
Fig. A9.07a
Corner column
23.2
23.3
Filler area
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A9 SKYDECK platforms
Cantilevers (Area ll)
3 3 3a 3
max. Z = 3.0 kN
Risk of falling!
– Ensure that end-to-end side pro-
tection is installed on slabs that have been completed!
– Do not erect formwork or step on
cantilevered tables before the ten­sion chains are securely fixed.
Continue forming after erecting the cor­ner table (Area I) in Area II with main beams. Main beams are laid parallel to the upper beams of the corner table. Start shuttering at the edge of the slab.
1. Place prop with Drophead SFK (1) at slab edge and secure with tripod.
2. Connect Main Beam SLT 375 (2.6) and support by means of a second prop with Prophead SSK (6) after
2.275 m at the edge of the building. (Formed exclusively with prophead; position front prop at a distance of
2.25 m).
3. Mount Tension Sleeve SAO (39) in the main beam groove. Distance ≤50 cm from the non-cantilevered end.
4. Attach tension chain (23) with turn­buckle to the eye at the top, and anchor to the ground by means of a base plate (24). (Fig. A9.08)
5. From below, bay by bay immediately install 3 Panels 150 x 75 (3) and 1 Filler Panel 150 x 37.5 (3a) as far as the platform support (2.7) of the Main Beam SLT 375. For example, with the PERI Stripping Cart ASW 465.
23
24
Fig. A9.08
Connection
Main Beam
Support
SFK
Fig. A9.09
60° – 9 0°
1
39
≤ 50
2,275 m*
*with the installation of Frames MRK 230 or
MRK 225: turn the Prophead SSK by 45°.
2.6 2.7
6*
Side protection
37, 5
– Depending on the thickness of the
slab, position additional props and girders at corresponding distances.
– In those areas where the 1.50 m grid
is interrupted by columns etc., a75cm bay may be installed. Ten ­sionSleeves SAO are used to secure
– Are the props in line with the props of
the corner table? (Fig. A9.08)
– Is the Main Beam SLT mounted cen-
trally in the beam support of the heads? Does the main beam connec­tion enclose the main beam support of the head? (Fig. A9.09)
against tipping.
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
Components
1 Drophead SFK
2.6 Main Beam SLT 375
2.7 Platform Support 3 Panel SDP 150 x 75 3a Panel SDP 150 x 37.5 6 Prophead SSK 10 Edge Beam SRT 19 Timber 20 Panel Wedge Clip SPKK 23 Tension chain 24 Base Plate RS 39 Tension Sleeve SAO
51
A9 SKYDECK platforms
Open edge areas (Area lll)
Start shuttering on structural constraint points (e.g. wall, casting segment) and work towards the corner table, Area II.
Slab area (Area lV)
When all edge areas are formed, the slab surface Area IV is formed in the usual way with SKYDECK.
Regarding the tightness of the panel joints, e.g. for casting segments/setting of stopends, push the panels tightly together and secure on the last main beam with Panel Wedge Clips SPKK (20).
Components
2 Main Beam SLT 225
2.6 Main Beam SLT 375 10 Edge Beam SRT 19 Timber 20 Panel Wedge Clip SPKK 45 SKYDECK Platform SDB 300 46 SKYDECK Platform SDB 150 47 SKYDECK Platform SDB 225
Infill areas
Risk of falling!
– Do not erect formwork or step
on cantilevered tables before the tension chains are securely fixed.
– When lingering on the slab form-
work, measures must be taken to prevent falling, e.g. PPE.
– Clearly mark unsecured building
edges!
Close infill areas in the inner area, close infill areas at unsecured building edges after the platforms have been installed.
19
10
20
Fi g. A 9 .10
Fi g . A9.11
52
20
III
2
2.62.62.6 45 46 47
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A9 SKYDECK platforms
Platform installation
Risk of falling!
– Cantilevers should not have form-
work erected or be stepped on be­fore being firmly secured with ten­sion chains.
– When lingering on the slab form-
work, measures must be taken to prevent falling, e.g. PPE.
– Clearly mark unsecured building
edges!
Begin with the platform assembly in one area in which there is no risk of falling to the rear or at the side (e.g. Area II, see Ground Plan Fig. A9.01).
1. With the help of the Erection Aid SSH, access the recess of the plat­form decking and pull the platform out from its safe position. (Fig. A9.12)
2. Move the platform into position at an angle from above in front of the last panel onto the cantilevered main beam.
3. By further lowering the platform, pos­itive assembly is carried out:
– The slide (45.1) on the underside of
the platform is secured when posi­tioned in the platform support (2.7) on the Main Beam SLT 375. (Fig. A 9.12a)
 The platform is locked in position
and secured against tipping.
– The slide safety device locks into
the teeth of the main beam.
 The platform is secured against
moving in the longitudinal direction of the beam.
4. Detach both crane hooks. Site per­sonnel must wear personal protection equipment (PPE) to prevent falling!
– Crane eye swivels downwards and
the securing hook grips under the self-draining edges of the main beam. If necessary, press down the crane eye.
 The platform is additionally
secured against tipping and lifting. (Fig. A9.12b)
5. Install other platforms in the same way with the shuttering aid.
6. Close infill areas < 75 cm using con­tractor’s own resources, e.g. scaffold planks 24 x 4.5 cm.
Shuttering Aid SSH
Fi g. A 9 .12
Anti-slip device
2.7
Fig. A9.12a Fi g. A 9 .12 b
45.1
7. Handrails for infill areas are created using handrail boards 3 x 15 cm and toe boards (use nail holes in platform guardrails) or standard couplings and scaffold tubes.
For difficult assembly situations, e.g. wind, guide the platform with 2 shutter­ing aids. (Fig. A9.13)
Fi g. A 9 .13
Securing hook
Self-draining edges
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
53
A9 SKYDECK platforms
Striking
Risk of falling! When attaching the platforms to the crane lifting gear, site personnel must wear personal protection equipment (PPE) to prevent falling.
Open edge areas
1. Strike the SKYDECK slab formwork in Area IV, see ground plan Fig. A9.01, in the direction of the slab edge up to the last but one bay of the cantile­vered edge area.
2. Important: do not lower the props (1c,
35) of the cantilevered Main Beams SLT 375 (2.6), do not release the
bracing!
3. Lower the dropheads or props (1a, 1b).
4. Strike the panels and main beams in the last but one standard bay (A). (Fig. A9.15). Do not strike bays B + C yet!
5. Mount end-to-end side protection on slabs that have been completed.
6. Attach 2-sling lifting gear to crane eyes of the platform decking.
 The securing hook is released.
7. The platforms are now moved to the next place of use. (Fig. A9.14)
8. Loosen the tension chains in the edge area (bays B + C), lower the drop­heads or props, remove panels and main beams.
Corner table
1. If this has not already been done: mount end-to-end side protection on slabs that have been completed.
2. Raise the external and internal plat­forms.
3. Move the SKYDECK Transportation Fork under the timbers of the table.
4. Loosen the tension chains on the cor­ner tables.
5. Retract the MULTIPROP Props MP. Inareas with parapet walls, continue to retract or remove the props.
6. Lower the corner table.
7. Remove the infill area around the col­umns.
8. Move the table horizontally in the direction of Area III.
Components
1 Drophead SFK
2.6 Main Beam SLT 375
2.7 Platform Support 23 Tension chain 24 Base Plate RS 35 MULTIPROP Prop MP 45 SKYDECK Platform SDK
Fi g. A 9 .15
54
Fi g. A 9 .14
A B C 352.6
1b1a 1c
Instructions for Assembly and Use – Standard Configuration
Crane eyes
1,30 m
29,5
SKYDECK Panel Slab Formwork
A9 SKYDECK platforms
Working and safety scaffold
Use the SKYDECK Platform SDB 300 for longer slab sections. Also for corner tables, the Platform SDB 300 can be used instead of the Platform SDB 150. Use the Platform SDB 225 as a com­pensation platform.
The Platform SDB 225 has 4 slides on the underside. This means the platform can therefore cantilever to the right or the left by 75 cm if required. This is nec­essary to accommodate interruptions such as columns, offset walls or at an external wall. (Fig. A 9.16)
The various platforms in use form a working and safety scaffold according to DIN 4420, Part 1. With 1.30 m platform width they fulfil the safety scaffold requirements for a maximum 3.0 m falling height, which is required for the construction of sup­ports or columns. (Fig. A 9.17)
1.50
2.25
Fi g. A 9 .16
Slide
Slide
DIN 4420 T1, Table 1:
to
min.
2,00 3,00
0,90 1,3 0
Falling height H [m]
Min. spacing B [m]
Do not assemble push-pull props on the platform nor store materials! (Fig . A 9 .17a) Take into account the permissible load
2
of 1.5 kN/m² (150kg/m
)!
H
B
Fi g. A 9 .17 Fig. A9.17a
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
55
A10 Changing direction
System with Prophead SSK
If the Prophead SSK is used in the main bay, then the Transition Head SDFK (26) is to be used when changing direction. Mount the Transition Head SDSK with the two bolts and nuts (26.1) – which are included in the delivery – on the slab props. During assembly of the prophead en­sure that group of nuts (26.1) point to­wards the support of the MULTIPROP Props. Otherwise, overlapping may oc­cur between the nuts and weld seam.
Changing the main bay direction by90°
With the change in direction, the main bays are turned 90° without having to assemble a new system. As a result, T- and L-shaped ground plans are possible. The change of direction is realized using the Main Beams SLT 150 in the outer row of the main bay.
Fig. A10.01
Starting bay of the trans-
verse bay direction
6
A
6 3
26
26.1 26.1
X
6 2
26
2
1.50 m
2.5
1.50 m
A
26
B
B
Main bays
Main bay direction
– The Transition Head SDSK with
the two bolts and nuts (26.1) – which are included in the delivery – must be mounted on the slab prop.
– The Prophead SDSK for changing
direction must be used with 3 Main Beams SLT!
Overview
(Fig. A10.02)
Assembly of main bay direction
Assemble slab formwork in the direc­tion of the main bay with slab props, Prophead SSK (6), Main Beam SLT 225 (2) and Panels SDP (3): see Section A4 Shuttering.
6
Fig. A10.0 2
Section A-A
6
Fig. A10.02a
3
Transverse bay direction
2
2.5
26
2.5 26
2 6
56
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A10 Changing direction
Changing direction
Main bay direction
1. Install slab prop with Prophead SDSK (26) with a spacing of 1.50 m and secure with tripods.
2. Mount Main Beam SLT 150 (2.5) – instead of SLT 225. (Fig. A10.02 + A10.02a)
Transverse bay direction
3. Continue assembling in the direction of the transverse bay with slab prop, Prophead SSK (6) and Main Beams SLT: see Section A4 Shuttering. (Fig. A10.02 + A10.03) Secure slab props with tripods.
4. Install Panels SDP 150 x 75 (3) in the direction of the transverse bay. (Fig. A10.02)
5. If a gap occurs with the Panel SDP between the transverse bay direction and main bay direction, this is closed using filler timber (12) and filler plates (16). (Fig. A10.04)
Required components per change of direction bays
Detail X
without filler timber
Transverse bay direction
2
Fig. A10.0 3
Section B-B
with filler timber
Transverse bay
3
direction
2.5
26
Main bay direction
16
2.5
12
26 Prophead SDSK* 1x
26.1 Bolt M12 with MP Nut 2x 6 Prophead SSK 1x
2.5 Main Beam SLT 150 1x 2 Main Beam SLT 225** 1x 3 Panel SDP** x 12 Filler Timber SPH 1x 16 Filler plate 1x
* Transition Head SDSK ** Depending on size of bay or plan
2
Fig. A10.0 4
2.5
26.1
SKYDECK Panel Slab Formwork
57
A10 Changing direction
System with Drophead SFK
If the Drophead SFK is used in the main bay, then the Transition Head SDFK (27) is to be used when changing direction. It consists of a Drophead (27.1) and Con­nector (27.2).
Changing the main bay direction by 90°
With the change in direction, the main bays are turned 90° without having to assemble a new system. As a result, T- and L-shaped ground plans are possible.
The change of direction is realized using Main Beams SLT, additional slab props with Transition Head SDFK in the outer row of the main bay as well as the Frame MRK.
Required components per change of direction bays
1 Drophead SFK 1x 2 Main Beam SLT 225 1x 2a Main Beam SLT 150 / 225 1x 3 Panel SDP 150 x 75 1x
3.1 Panel SDP 150 x 37.5 1x 9 Edge Beam SRT 150 1x 11 End Support SSL 1x 12 Filler Timber SPH 1x 16 Filler plate 1x
27.1 Drophead SDFK* 1x
27.2 Connector SDFK* 1x 30 Tripod 1x
Fig. A10.0 5
A
2
Starting bay of the trans-
verse bay direction
2
1,50 m
2
Transverse bay direction
27.1
1a
1b
1
27.2
1.50 m
30
2a
B B
30
2a
2a
3.1
27
Main bays
1
27, 11
X
27, 11
1 2
16
27, 11
11
1
2
A
Main bay direction
* Transition Head SDFK
Overview
(Fig. A10.06 + A10.06a)
Assembly of main bay direction
Assemble slab formwork in the direc­tion of the main bay with slab props, Drophead SFK (1), Main Beam SLT 225 (2) and Panels SDP (3): see Section A4 Shuttering.
58
Fig. A10.0 6
Section A-A Change in direction in the edge bay with
Main Beam SLT 375
33a 3 3 .1 9/12
2
2.5 11
30
Fig. A10.0 6a
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A10 Changing direction
Changing direction
Main bay direction
1. Insert the Connector (27.1) with the groove bolt into the Main Beam SLT 225 (main bay) and tighten by hand. (Fig. A10.07)
2. Mount the Transition Head SDFK (27.2) individually or with the slab prop in the connector. (Fig. A10.07a)
3. Mount the second Drophead SDFK at a distance of 1.50 m. (Fig. A10.06)
2
27.1
27.2
Fig. A10.07aFig. A10.07
First transverse bay 1.50 m x 1.50 m
4. Position one slab prop with Drophead SFK (1a) in the direction of the trans­verse bay. (Fig. A10.06)
5. Position second slab prop with Drop­head SFK (1b) and secure slab props with tripods (30). (Fig. A10.06)
6. Mount Main Beam SLT 150 / 225 (2a) in the Dropheads. (Fig. A10.06, A10.0 8, A10.08a)
Additional transverse bays
Assemble additional transverse bays in the same way as the first transverse bay along the Main Beam SLT 225. (Fig. A10.0 6)
– Spacing (bay width) 1.50 m, – without Frame MRK,
see Section A4 Shuttering.
Install Panel SDP:
Insert panels in the direction of the main bay.
1. Insert Panel SDP 150 x 75 (3a).
2. Insert Filler Panel SDP 150 x 37.5 (3.1).
3. Fix End Support SSL (11) to the Main Beam SLT in the filler area. Install Edge Beam SRT 150-2 (9) as well as Filler Timber SPH 225 (12) and filler plates (16), see Section A5 Infills. (Fig. A10.06, A10.06a, A10.08a)
Transverse bay
direction
2a
2a
Main bay direction
27
Transverse bay direction
9
16
11
27
11
Detail X
2
without filler timber
Fig. A10.0 8
1
12
9
Section B-B
with filler timber
Fig. A10.0 8a
Continue assembling the transverse bays
Assemble transverse bay with slab props, Drophead SFK (1), Main Beam SLT 225 (2) and Panels SDP (3), see Section A4 Shuttering.
If a Drophead SDFK encounters the po­sition of a Drophead SFK in the direction of the main bay, a 75 cm intermediate bay is to be installed. After this, installa­tion continues with spacings of 1.50 m. (Fig. A10.09)
SKYDECK Panel Slab Formwork
1.50 m1.50 m 0.75
Fig. A10.0 9
59
A11 Inclined slabs
The Main Beam SLT must be positioned in the direction of the slab inclination. Align Props with Drophead SFK at right-angles to the Main Beams SLT
225. The use with Prophead SSK is also pos­sible. (Fig. A11.01)
α = 60°
39
β
90°
When using PEP Slab Props, the Drop­head SFK is diagonally bolted by means of 2 Bolts M12 x 35-8.8 and Nut M12. Tension forces and prop loads: see Ta­ble A15.01.
Bracing with Tension Sleeve SAO and Chain 3.0 kN
Assembly
1. Set up first bay with tripods or Frame MRK.
2. Mount Base Plate (24) on a suffi­ciently load-bearing surface area, e.g. using PERI Anchor Bolt 14/20x130, Item no. 124777. Take into considera­tion the Technical Data Sheet!
3. Screw on Tension Sleeve SAO (39) to Main Beam SLT.
4. Attach Anchor Chain (23) to Tension Sleeve SAO (39).
5. Secure Anchor Chain to Base Plate using bolts, and secure bolts by means of cotter pins.
6. Tension Anchor Chain. (Fig. A11.01)
23
24
Fi g . A11. 0 1
Components
23 Anchor Chain (permissible ten-
sion force = 3 kN)
24 Base Plate RS
24.1 Anchor Bolt PERI 14/20 x 130 39 Tension Sleeve SAO
60
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A11 Inclined slabs
Bracing with Tension Unit SD
Bracing angle α selection: see Table A15.0 2. Tension forces and prop loads: see Tables A15.03 – A15.08.
Assembly
1. Position slab prop with tripod.
2. Place the Tension Unit Upper Part (41.1) on the end plates of the Main Beam SLT (2.8) and attach the Main Beam to the Drophead SFK. (Fig. A11.03)
3. Swivel up the Main Beam with the second slab prop. Tension Unit must lie on the end plates of the Main Beam SLT.
4. Mount Base Plate (24) on a suffi­ciently load-bearing surface area, e.g. using PERI Anchor Bolt 14/20x130, Item no. 124777. Take into considera­tion the Technical Data Sheet!
5. Insert the Tie Yoke of the Tension Unit Upper Part onto the Tie Rod (41.3), secure with the Hex. Nut SW30/50 (42), and attach to the Tension Unit Upper Part. (Fig. A11.03 + A11.04)
6. Fix Tension Unit Lower Part (41.2) to the Base Plate by means of bolts, and secure bolts using cotter pins. (Fig. A11.02)
7. Insert Tie Yoke of the Tension Unit Lower Part onto the Tie Rod, secure with Triple Wingnut DW 15 (43), and attach to the Tension Unit Lower Part. (Fig. A11.05 + A11.06)
8. Tension the Tension Unit using a Triple Wingnut.
Components
41.1
Fi g . A11. 0 2
2.8
Fi g . A11. 0 3
41.3
41.1
β
β
90°
α
licht
h
41.2
24
41.1
42
41.3
Fi g . A11. 0 4
43
41.2
Fi g . A11. 0 5
24 Base Plate RS
24.1 Anchor Bolt PERI 14/20 x 130 41 Tension Unit SD
Fi g . A11. 0 6
SKYDECK Panel Slab Formwork
61
A12 Striking
Setting times: see Tables! Keep access ways free!
Dismantling takes place from a safe and secure position, e.g. with PERI Stripping Cart ASW 465.
Lowering
– Lower dropheads over large area. Re-
lease wedges with hammer. Pay at­tention to direction of wedge!
 Between the panel and slab
underside there is a clearance of approx. 6 cm. (Fig. A12.01)
Edge infills
Striking takes place firstly on the trans­verse infills and then the longitudinal infills.
– Remove props and store in pallets. – Dismantle system supplements such
as filler timbers, edge beams, end supports and combiheads, and store in pallets. (Fig. A12.02)
– Remove filler plates.
Fig. A12.01
Striking is carried out by means of a safe mobile scaffold!
Fig. A12.02
62
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A12 Striking
Panels
Always begin in the corner where both infills meet.
– Dismantle Panel SDP in one bay after
the other – begin with the middle pan­el.
– Lift panel and push approx. 10 cm in
the direction of the compensation area. Pivot downwards and store in pallets.
(Fig. A12.03)
Main beams
– Pivot Main Beam SLT slowly down-
wards, remove and store in pallets.
(Fig. A12.04)
Only drophead props (1) with Cover Strips SAL (4) remain standing. (Fig. A12.05)
Remaining areas
– Remove props on walls and store in
pallets.
– Remove filler areas around columns.
After reaching the required concrete strength
– lower drophead props, remove props
and store in pallets.
– remove Cover Strips SAL (4).
With larger spans, begin in the middle with lowering and removal of the props.
Cleaning
Clean SKYDECK components before the next use and spray once again, e.g. with PERI Bio Clean. See introduction “Cleaning and mainte­nance”.
Fig. A12.03
Fig. A12.04
1
4
Fig. A12.05
SKYDECK Panel Slab Formwork
63
A13 Site record
Company: Project: Component:
This page is to be copied, filled out and filed in the daily construction records.
............................................................................................................................
............................................................................................................................
............................................................................................................................
Slab thickness
Clear room height
Prop length
= clear room height – formwork assembly height (with Drophead: 41 cm)
Max. panel span
Selected prop
Actual prop load
(according to PERI Tables)
Direction of assembly
≤ zul. Stützenlast
(nach PERI Tabellen)
= ............................................ cm
= ............................................ m
= ............................................ m
= ............................................ cm
= ............................................
= ............................................ kN
Inner tube bottom ...............
Outer tube bottom ..............
= ............................................ kN
Check whether above assumptions and/or specifications apply on the construction site
Slab thickness
Max. panel span
Selected prop
Selected prop length
Direction of assembly
Are all props in both axes in a vertical position? ≤ 1%
Horizontal support for the formwork available in all directions?
Mounted parts are obviously undamaged?
Required bracing has been mounted?
Check to be carried out on the construction site before concreting Execution / Installation of the formwork
= ............................................ cm
= ............................................ cm
= ............................................ m
= ............................................ m
Inner tube bottom ................
Outer tube bottom ...............
................................................
................................................
................................................
................................................
yes
yes
yes
yes
Place Date Site manager in charge
(Signature)
64
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A14 Horizontal loads with Slab Props PEP
System with Drophead SFK or Prop­head SSK and Main Beam SLT 225
– Horizontal loads per boundary bay
are determined for an open build­ing edge on one side!
– Bolt Drophead SFK to Slab Prop
PEP!
– Increase prop loads in the braced
areas by ΔV = 2.60 kN!
Slab
thickness
[cm]
14 5.13 0.518 0.259 0.354 0.17 7 1.349 0.675 0.033 0.016 1. 232 0.616
16 5.62 0.650 0.325 0.388 0.19 4 1.516 0.758 0.033 0.016 1.232 0.616
18 6 .11 0.798 0.399 0.422 0 . 211 1.6 97 0.849 0.033 0.016 1.2 32 0.616
20 6.60 0.960 0.480 0.455 0.228 1. 893 0.947 0.033 0.016 1.232 0.616
22 7.09 1.13 7 0.568 0.489 0.245 2.104 1.0 52 0.033 0.016 1.25 6 0.628
24 7. 5 8 1.328 0.664 0.523 0.262 2.329 1.165 0.033 0.016 1.279 0.639
25 7. 8 3 1.430 0.715 0.540 0.270 2.447 1.224 0.033 0.016 1. 291 0.645
26 8.07 1.5 35 0.767 0.557 0.278 2.569 1.28 5 0.033 0.016 1.302 0.651
28 8.56 1.75 6 0.878 0.591 0.295 2.824 1.412 0.033 0.016 1.3 26 0.663
30 9.05 1.991 0.996 0.624 0.312 3.094 1.547 0.033 0.016 1.349 0.675
35 10.38 2.701 1.351 0.716 0.358 3.895 1. 948 0.033 0.016 1.40 8 0.704
40 11.73 3.528 1.764 0.809 0.405 4.815 2.408 0.033 0.016 1.466 0.733
43 12.5 4 4.077 2.039 0.865 0.433 5.425 2.712 0.033 0.016 1.501 0.751
45 13.08 2.233 0.451 2.926 0.016 0.762
50 14.4 3 2.756 0.498 3.500 0.016 0.792
55 15.77 3.335 0.544 4.129 0.016 0.821
60 17.12 3.969 0.591 4.814 0.016 0.850
65 18.47 4.658 0.637 5.553 0.016 0.879
70 19.82 5.402 0.684 6.347 0.016 0.909
75 21.0 8 6.152 0.727 7.145 0.016 0.938
80 22.30 6.930 0.769 7.9 6 8 0.016 0.967
85 23.53 7.75 4 0.812 8.838 0.016 0.996
90 24.75 8.623 0.854 9.753 0.016 1.026
Load
according
to DIN
EN 12 812
[kN/m²]
Horizontal Load
c = 1.50 m c = 0.75 m
from stopend
formwork
pressure
[kN] Load case combination LFK 1: Concreting*
edge area
from stopend
formwork
pressure
Horizontal Load
Panel
span
c = 1.50 m
[kN] Horizontal Load
inner bay
Panel
span
c = 0.75 m
c = 1.50 m
Panel
span
[kN] Horizontal Load
edge area
Panel
span
c = 0.75 m
Load case combination LFK 2: Storm**
[kN] Horizontal Load
inner bay
Panel
span
c = 1.50 m
Panel
span
c = 0.75 m
Panel
span
c = 1.50 m
[kN]
edge area
Panel
span
c = 0.75 m
Table A14.01
* Load case combination LFK 1: working operations + tilting position + stopend formwork
pressure + working wind speed.
** Load case combination LFK 2: tilting position (without concrete load) + maximum wind speed [before concreting].
SKYDECK Panel Slab Formwork
65
A15 Inclined slabs
Maximum permissible slab inclination with Tension Sleeve SAO and Chain 3.0 kN
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position = 1% of the vertical load (DIN EN 12812; 9.3.4.2)
Angle α between Chain and SLT 225 = 60° Max. tension force of Tension Sleeve SAO and Anchor Chain = 3.0 kN
Panel span c = 1.50 m [cm] Panel span c = 0.75 m [cm]
max. slab inclination max. slab inclination
Slab thickness
[cm] [kN/m2] [kN] [%] [°] [kN] [%] [°]
14 5.13 20.3 5.4 3.1 11.4 11.1 6.3
16 5.62 22.0 4.8 2.8 12.3 10.2 5.8
18 6.11 23.7 4.3 2.5 13.1 9.4 5.4
20 6.60 25.4 3.9 2.2 14.0 8.7 5.0
22 7.09 27.1 3.5 2.0 14.8 8.1 4.6
24 7. 5 8 28.7 3.2 1.8 15.7 7.6 4.3
25 7.8 3 29.6 3.1 1.8 16.1 7.3 4.2
26 8.07 30.4 2.9 1.7 16.5 7.1 4.1
28 8.56 32.1 2.7 1.5 17.4 6.6 3.8
30 9.05 33.8 2.4 1.4 18.2 6.2 3.6
35 10.38 38.4 1.9 1.1 20.5 5.3 3.0
40 11.73 4 3 .1 1.5 0.8 22.8 4.6 2.6
43 12.5 4 45.9 1.3 0.7 24.2 4.2 2.4
45 13.08 25.2 4.0 2.3
50 14.4 3 2 7. 5 3.5 2.0
55 15.77 29.8 3.0 1.7
60 17.12 32 .1 2.7 1.5
65 18.47 34.5 2.4 1.3
70 19.82 36.8 2.1 1.2
75 21.0 8 39.0 1.8 1.1
80 22.30 41.1 1.7 0.9
85 23.53 43.2 1.5 0.8
90 24.75 45.3 1.3 0.8
Load
DIN EN 12812
increased prop
load Incline Angle
increased prop
load Incline Angle
Table A15 .01
SKYDECK Tension Unit SD – bracing angle α selection
Angle α
Tension Unit
SD
30 ° 1.72 m 2.01 m 1.73 m 2.02 m
35 ° 2.02 m 2.34 m 2.04 m 2.36 m
40 ° 2.37 m 2.71 m 2.39 m 2.73 m
45 ° 2.77 m 3.12 m 2.80 m 3.15 m
50 ° 3.25 m 3.60 m 3.28 m 3.63 m
55 ° 3.84 m 4 .16 m 3.88 m 4.20 m
60 ° 4.60 m 4.87 m 4.65 m 4.91 m
Table A15 .02
possible clear room height
with SSK and SLT 225
min h
minimum clearance
max h
minimum clearance
66
possible clear room height
with SFK and SLT 225
min h
minimum clearance
max h
minimum clearance
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A15 Inclined slabs
Tension force of Tension Unit SD and system prop loads with Drophead SFK
– The Drophead SFK is bolted to the
PEP Slab Props.
– The PEP Props are to be assem-
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position
= 1% of the vertical load (DIN EN 12812; 9.3.4.2)
bled with the inner tube bottom.
Inclination of slab 1%
max. inclination
Angle α
Tension Unit
SD
Incline
[%]
Angle β
[°]
Slab thickness 20 cm, q = 6.60 kN/m
30 ° 1.0% 0.6 ° 22.8 kN 3.9 kN 24.7 kN 3.2 kN 24.3 kN 2.4 kN 24.0 kN
35 ° 1.0% 0.6 ° 22.8 kN 4.2 kN 25.2 kN 3.3 kN 24.7 kN 2.5 kN 24.2 kN
40 ° 1.0% 0.6 ° 22.8 kN 4.5 kN 25.6 kN 3.6 kN 25 .1 kN 2.7 kN 24.5 kN
45 ° 1.0% 0.6 ° 22.8 kN 4.8 kN 26.2 kN 3.9 kN 25.5 kN 2.9 kN 24.8 kN
50 ° 1.0% 0.6 ° 22.8 kN 5.3 kN 26.8 kN 4.3 kN 26.0 kN 3.2 kN 25.2 kN
55 ° 1.0% 0.6 ° 22.8 kN 6.0 kN 27.6 k N 4.8 kN 26.7 kN 3.6 kN 25.7 kN
60 ° 1.0% 0.6 ° 22.8 kN 6.8 kN 28.7 kN 5.5 kN 27.5 k N 4.1 kN 26.3 kN
Slab thickness 24 cm, q = 7.58 kN/m
30 ° 1.0% 0.6 ° 26.2 kN 4.5 kN 28.4 kN 3.6 kN 28.0 kN 2.7 kN 27.5 k N
35 ° 1.0% 0.6 ° 26.2 kN 4.8 kN 28.9 kN 3.8 kN 28.3 kN 2.9 kN 27. 8 kN
40 ° 1.0% 0.6 ° 26.2 kN 5 .1 kN 29.4 kN 4.1 kN 28.8 kN 3.1 kN 28.1 kN
45 ° 1.0% 0.6 ° 26.2 kN 5.5 kN 3 0.1 k N 4.4 kN 29.3 kN 3.3 kN 28.5 kN
50 ° 1.0% 0.6 ° 26.2 kN 6 .1 kN 30.8 kN 4.9 kN 29.9 kN 3.7 kN 29.0 kN
55 ° 1.0% 0.6 ° 26.2 kN 6.8 kN 31.8 kN 5.5 kN 30.6 kN 4.1 kN 29.5 kN
60 ° 1.0% 0.6 ° 26.2 kN 7.8 kN 32.9 kN 6.3 kN 31.6 kN 4.7 kN 30.2 kN
Slab thickness 25 cm, q = 7.83 kN/m
Standard
prop
Full load
2
2
2
5 connected bays 4 connected bays 3 connected bays
Tension
force Tension Unit SD
Braced prop
full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
full load
V
ges
30 ° 1.0% 0.6 ° 27.0 k N 4.7 kN 29.4 kN 3.7 kN 28.9 kN 2.8 kN 28.4 kN
35 ° 1.0% 0.6 ° 27.0 k N 4.9 kN 29.9 kN 4.0 kN 29.3 kN 3.0 kN 28.7 kN
40 ° 1.0% 0.6 ° 27.0 k N 5.3 kN 30.4 kN 4.2 kN 29.7 kN 3.2 kN 29.1 kN
45 ° 1.0% 0.6 ° 27.0 k N 5.7 kN 31.1 kN 4.6 kN 30.3 kN 3.4 kN 29.4 kN
50 ° 1.0% 0.6 ° 27.0 k N 6.3 kN 31.8 kN 5.0 kN 30.9 kN 3.8 kN 29.9 kN
55 ° 1.0% 0.6 ° 27.0 k N 7.1 kN 32.8 kN 5.7 kN 31.6 kN 4.2 kN 30.5 kN
60 ° 1.0% 0.6 ° 2 7.0 kN 8 .1 kN 34.0 kN 6.5 kN 32.6 kN 4.9 kN 31.2 kN
Slab thickness 30 cm, q = 9.05 kN/m
30 ° 1.0% 0.6 ° 31.2 kN 5.4 kN 33.9 kN 4.3 kN 33.4 kN 3.2 kN 32.8 kN
35 ° 1.0% 0.6 ° 31.2 kN 5.7 kN 34.5 kN 4.6 kN 33.8 kN 3.4 kN 33.2 kN
40 ° 1.0% 0.6 ° 31.2 kN 6 .1 kN 35.2 kN 4.9 kN 34.4 kN 3.7 kN 33.6 kN
45 ° 1.0% 0.6 ° 31.2 kN 6.6 kN 35.9 kN 5.3 kN 35.0 kN 4.0 kN 34.0 kN
50 ° 1.0% 0.6 ° 31.2 kN 7. 3 kN 36.8 kN 5.8 kN 35.7 kN 4.4 kN 34.6 kN
55 ° 1.0% 0.6 ° 31.2 kN 8.2 kN 37.9 kN 6.5 kN 36.6 kN 4.9 kN 35.2 kN
60 ° 1.0% 0.6 ° 31. 2 k N 9.4 kN 39.3 kN 7. 5 kN 37.7 kN 5.6 kN 3 6 .1 kN
Table A15 .03
SKYDECK Panel Slab Formwork
2
67
A15 Inclined slabs
System with Drophead SFK Tension force of Tension Unit SD and prop loads
– The Drophead SFK is bolted to the
PEP Slab Props.
– The PEP Props are to be assem-
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position
= 1% of the vertical load (DIN EN 12812; 9.3.4.2)
bled with the inner tube bottom.
Inclination of slab 5%
Angle α
Tension Unit
SD
max. inclination
Incline
[%]
Angle β
Standard
prop
[°]
Full load
5 connected bays 4 connected bays 3 connected bays
Tension
force Tension Unit SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Slab thickness 20 cm, q = 6.60 kN/m²
30 ° 5.0% 2.9 ° 22.8 kN 9.2 kN 27.4 k N 7.4 k N 26.5 kN 5.5 kN 25.5 kN
35 ° 5.0% 2.9 ° 22.8 kN 9.7 kN 28.4 kN 7. 8 kN 2 7. 2 kN 5.8 kN 2 6 .1 kN
40 ° 5.0% 2.9 ° 22.8 kN 10.4 kN 29.5 kN 8.3 kN 28.1 kN 6.2 kN 26.8 kN
45 ° 5.0% 2.9 ° 22.8 kN 11.3 kN 30.7 kN 9.0 kN 29 .1 kN 6.8 kN 27.6 k N
50 ° 5.0% 2.9 ° 22.8 kN 9.9 kN 30.4 kN 7.4 k N 28.5 kN
55 ° 5.0% 2.9 ° 22.8 kN 11.1 k N 31.9 kN 8.3 kN 29.6 kN
60 ° 5.0% 2.9 ° 22.8 kN 9.6 kN 31.1 k N
Slab thickness 24 cm, q = 7.58 kN/m²
30 ° 5.0% 2.9 ° 26.2 kN 10.6 kN 31.4 kN 8.5 kN 30.4 kN 6.3 kN 29.3 kN
35 ° 5.0% 2.9 ° 26.2 kN 11.2 k N 32.6 kN 8.9 kN 31.3 kN 6.7 kN 30.0 kN
40 ° 5.0% 2.9 ° 26.2 kN 11.9 kN 33.8 kN 9.6 kN 32.3 kN 7.2 k N 30.8 kN
45 ° 5.0% 2.9 ° 26.2 kN 12.9 kN 35.3 kN 10.4 kN 33.5 kN 7.8 k N 31.6 kN
50 ° 5.0% 2.9 ° 26.2 kN 11.4 kN 34.9 kN 8.5 kN 32.7 kN
55 ° 5.0% 2.9 ° 26.2 kN 12.8 kN 36.6 kN 9.6 kN 34.0 kN
60 ° 5.0% 2.9 ° 26.2 kN 11.0 k N 35.7 kN
Braced prop
Full load
V
ges
Slab thickness 25 cm, q = 7.83 kN/m²
30 ° 5.0% 2.9 ° 27.0 k N 10.9 kN 32.5 kN 8.7 kN 31.4 kN 6.6 kN 30.3 kN
35 ° 5.0% 2.9 ° 27.0 k N 11.5 kN 33.6 kN 9.2 kN 32.3 kN 6.9 kN 31.0 kN
40 ° 5.0% 2.9 ° 27.0 k N 12.3 kN 34.9 kN 9.9 kN 33.4 kN 7. 4 kN 31.8 kN
45 ° 5.0% 2.9 ° 27.0 k N 13.4 kN 36.5 kN 10.7 kN 34.6 kN 8.0 kN 32.7 kN
50 ° 5.0% 2.9 ° 27.0 k N 11. 8 kN 36.0 kN 8.8 kN 33.8 kN
55 ° 5.0% 2.9 ° 27.0 k N 13.2 kN 37.8 k N 9.9 kN 35 .1 kN
60 ° 5.0% 2.9 ° 27.0 k N 11. 3 kN 36.8 kN
Slab thickness 30 cm, q = 9.05 kN/m²
30 ° 5.0% 2.9 ° 31.2 kN 12.6 kN 37.5 kN 10.1 k N 36.3 kN 7.6 k N 35.0 kN
35 ° 5.0% 2.9 ° 31.2 kN 13.3 kN 38.9 kN 10.7 kN 37. 3 kN 8.0 kN 35.8 kN
40 ° 5.0% 2.9 ° 31.2 kN 14.3 kN 40.4 kN 11. 4 kN 38.6 kN 8.6 kN 36.7 kN
45 ° 5.0% 2.9 ° 31.2 kN 15.5 kN 42.2 kN 12.4 kN 40.0 kN 9.3 kN 3 7. 8 kN
50 ° 5.0% 2.9 ° 31.2 kN 13.6 kN 41.6 kN 10.2 kN 39.0 kN
55 ° 5.0% 2.9 ° 31.2 kN 15.2 kN 43.7 kN 11.4 k N 40.6 kN
60 ° 5.0% 2.9 ° 31.2 kN 13.1 kN 42.6 kN
Table A15 .04
SKYDECK Panel Slab Formwork
68
Instructions for Assembly and Use – Standard Configuration
A15 Inclined slabs
System with Drophead SFK Tension force of Tension Unit SD and prop loads
– The Drophead SFK is bolted to the
PEP Slab Props.
– The PEP Props are to be assem-
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position
= 1% of the vertical load (DIN EN 12812; 9.3.4.2)
bled with the inner tube bottom.
Inclination of slab 9%
Angle α
Tension Unit
SD
max. inclination
Incline
[%]
Angle α
Standard
prop
[°]
Full load
5 connected bays 4 connected bays 3 connected bays
Tension
force Tension Unit SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Slab thickness 20 cm, q = 6.60 kN/m²
30 ° 9.0% 5.1 ° 22.8 kN 14.5 kN 30.0 kN 11.6 kN 28.6 kN 8.7 kN 27.1 kN
35 ° 9.0% 5.1 ° 22.8 kN 15.3 kN 31.5 kN 12. 2 kN 29.8 kN 9.2 kN 28.0 kN
40 ° 9.0% 5.1 ° 22.8 kN 13.1 kN 31.2 kN 9.8 kN 2 9.1 kN
45 ° 9.0% 5.1 ° 22.8 kN 10.6 kN 30.3 kN
50 ° 9.0% 5.1 ° 22.8 kN 11.7 kN 31.7 kN
55 ° 9.0% 5.1 ° 22.8 kN
60 ° 9.0% 5.1 ° 22.8 kN
Slab thickness 24 cm, q = 7.58 kN/m²
30 ° 9,0% 5,1 ° 26,2 kN 16,6 kN 34,5 kN 13,3 kN 32,8 kN 10,0 kN 31,1 k N
35 ° 9,0% 5,1 ° 26,2 kN 17,6 k N 36,2 kN 14,0 kN 34,2 kN 10,5 kN 32,2 kN
40 ° 9,0% 5,1 ° 26,2 kN 15,0 kN 35,8 kN 11, 3 kN 33,4 kN
45 ° 9,0% 5,1 ° 26,2 kN 12,2 kN 34,8 kN
50 ° 9,0% 5,1 ° 26,2 kN 13,4 kN 36,4 kN
55 ° 9,0% 5,1 ° 26,2 kN
60 ° 9,0% 5,1 ° 26,2 kN
Braced prop
Full load
V
ges
Slab thickness 25 cm, q = 7.83 kN/m²
30 ° 9.0% 5.1 ° 2 7. 0 kN 17. 2 kN 35.6 kN 13.7 kN 33.9 kN 10.3 kN 32.2 kN
35 ° 9.0% 5.1 ° 2 7.0 kN 18 .1 kN 37.4 kN 14.5 kN 35.3 kN 10.9 kN 33.3 kN
40 ° 9.0% 5.1 ° 2 7. 0 kN 15.5 kN 37.0 k N 11.6 k N 34.5 kN
45 ° 9.0% 5.1 ° 2 7. 0 kN 12.6 kN 35.9 kN
50 ° 9.0% 5.1 ° 2 7. 0 kN 13.9 kN 37.6 kN
55 ° 9.0% 5.1 ° 2 7.0 kN
60 ° 9.0% 5.1 ° 2 7. 0 kN
Slab thickness 30 cm, q = 9.05 kN/m²
30 ° 9.0% 5.1 ° 31.2 kN 19.8 kN 41.1 k N 15.9 kN 39.2 kN 11. 9 kN 3 7. 2 kN
35 ° 9.0% 5.1 ° 31. 2 kN 21.0 kN 43.2 kN 16.8 kN 40.8 kN 12.6 kN 38.4 kN
40 ° 9.0% 5.1 ° 31.2 kN 17.9 k N 42.7 kN 13.5 kN 39.9 kN
45 ° 9.0% 5.1 ° 31.2 kN 14.6 kN 41.5 kN
50 ° 9.0% 5.1 ° 31.2 kN 16.0 kN 43.5 kN
55 ° 9.0% 5.1 ° 31. 2 kN
60 ° 9.0% 5.1 ° 31.2 kN
Table A15 .05
SKYDECK Panel Slab Formwork
69
A15 Inclined slabs
System with Prophead SSK Tension force of Tension Unit SD and prop loads
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position = 1% of the vertical load (DIN EN 12812; 9.3.4.2)
Inclination of slab 1%
Angle α
Tension Unit
SD
max. inclination
Incline
[%]
Angle β
Standard
prop
[°]
Full load
5 connected bays 4 connected bays 3 connected bays
Tension
force Tension Unit SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Slab thickness 20 cm, q = 6.60 kN/m²
30 ° 1.0% 0.6 ° 22.3 kN 3.9 kN 24.2 kN 3.1 kN 23.8 kN 2.3 kN 23.4 kN
35 ° 1.0% 0.6 ° 22.3 kN 4.1 kN 24.6 kN 3.3 kN 24.1 kN 2.4 kN 23.7 kN
40 ° 1.0% 0.6 ° 22.3 kN 4.4 kN 25.1 k N 3.5 kN 24.5 kN 2.6 kN 24.0 kN
45 ° 1.0% 0.6 ° 22.3 kN 4.7 kN 25.6 kN 3.8 kN 24.9 kN 2.8 kN 24.3 kN
50 ° 1.0% 0.6 ° 22.3 kN 5.2 kN 26.3 kN 4.2 kN 25.5 kN 3.1 kN 24.7 kN
55 ° 1.0% 0.6 ° 22.3 kN 5.8 kN 27.0 k N 4.7 kN 26 .1 kN 3.5 kN 25.1 k N
60 ° 1.0% 0.6 ° 22.3 kN 6.7 kN 28.1 kN 5.3 kN 26.9 kN 4.0 kN 25.7 kN
Slab thickness 24 cm, q = 7.58 kN/m²
30 ° 1.0% 0.6 ° 25.6 kN 4.4 kN 27.8 k N 3.5 kN 27. 4 kN 2.7 kN 26.9 kN
35 ° 1.0% 0.6 ° 25.6 kN 4.7 kN 28.3 kN 3.7 kN 27.7 kN 2.8 kN 2 7. 2 kN
40 ° 1.0% 0.6 ° 25.6 kN 5.0 kN 28.8 kN 4.0 kN 28.2 kN 3.0 kN 27. 5 kN
45 ° 1.0% 0.6 ° 25.6 kN 5.4 kN 29.4 kN 4.3 kN 28.7 kN 3.3 kN 27. 9 kN
50 ° 1.0% 0.6 ° 25.6 kN 6.0 kN 30.2 kN 4.8 kN 29.2 kN 3.6 kN 28.3 kN
55 ° 1.0% 0.6 ° 25.6 kN 6.7 kN 31.1 kN 5.4 kN 30.0 kN 4.0 kN 28.9 kN
60 ° 1.0% 0.6 ° 25.6 kN 7.7 kN 32.2 kN 6.1 kN 30.9 kN 4.6 kN 29.6 kN
Braced prop
Full load
V
ges
Slab thickness 25 cm, q = 7.83 kN/m²
30 ° 1.0% 0.6 ° 26.4 kN 4.6 kN 28.7 kN 3.7 kN 28.3 kN 2.7 kN 2 7. 8 kN
35 ° 1.0% 0.6 ° 26.4 kN 4.8 kN 29.2 kN 3.9 kN 28.6 kN 2.9 kN 28.1 kN
40 ° 1.0% 0.6 ° 26.4 kN 5.2 kN 29.8 kN 4.1 kN 2 9.1 k N 3.1 kN 28.4 kN
45 ° 1.0% 0.6 ° 26.4 kN 5.6 kN 30.4 kN 4.5 kN 29.6 kN 3.4 kN 28.8 kN
50 ° 1.0% 0.6 ° 26.4 kN 6.2 kN 31.2 kN 4.9 kN 30.2 kN 3.7 kN 29.3 kN
55 ° 1.0% 0.6 ° 26.4 kN 6.9 kN 32.1 kN 5.5 kN 31.0 kN 4.1 kN 29.8 kN
60 ° 1.0% 0.6 ° 26.4 kN 7.9 kN 33.3 kN 6.3 kN 31. 9 kN 4.8 kN 30.5 kN
Slab thickness 30 cm, q = 9.05 kN/m²
30 ° 1.0% 0.6 ° 30.5 kN 5.3 kN 33.2 kN 4.2 kN 32.7 kN 3.2 kN 32 .1 kN
35 ° 1.0% 0.6 ° 30.5 kN 5.6 kN 33.8 kN 4.5 kN 33.1 kN 3.4 kN 32.5 kN
40 ° 1.0% 0.6 ° 30.5 kN 6.0 kN 34.4 kN 4.8 kN 33.6 kN 3.6 kN 32.9 kN
45 ° 1.0% 0.6 ° 30.5 kN 6.5 kN 3 5 .1 kN 5.2 kN 34.2 kN 3.9 kN 33.3 kN
50 ° 1.0% 0.6 ° 30.5 kN 7.1 k N 36.0 kN 5.7 kN 34.9 kN 4.3 kN 33.8 kN
55 ° 1.0% 0.6 ° 30.5 kN 8.0 kN 37.1 k N 6.4 kN 35.8 kN 4.8 kN 34.5 kN
60 ° 1.0% 0.6 ° 30.5 kN 9.2 kN 38.5 kN 7.3 k N 36.9 kN 5.5 kN 35.3 kN
Table A15 .06
SKYDECK Panel Slab Formwork
70
Instructions for Assembly and Use – Standard Configuration
A15 Inclined slabs
System with Prophead SSK Tension force of Tension Unit SD and prop loads
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position = 1% of the vertical load (DIN EN 12812; 9.3.4.2)
Inclination of slab 5%
Angle α
Tension Unit
SD
max. inclination
Incline
[%]
Angle β
Standard
prop
[°]
Full load
5 connected bays 4 connected bays 3 connected bays
Tension
force Tension Unit SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Slab thickness 20 cm, q = 6.60 kN/m²
30 ° 5.0% 2.9 ° 22.3 kN 9.0 kN 26.8 kN 7.2 k N 25.9 kN 5.4 kN 25.0 kN
35 ° 5.0% 2.9 ° 22.3 kN 9.5 kN 27.7 kN 7.6 kN 26.6 kN 5.7 kN 25.6 kN
40 ° 5.0% 2.9 ° 22.3 kN 10.2 kN 28.8 kN 8 .1 kN 27.5 kN 6.1 k N 26.2 kN
45 ° 5.0% 2.9 ° 22.3 kN 11.0 k N 30 .1 kN 8.8 kN 28.5 kN 6.6 kN 27.0 kN
50 ° 5.0% 2.9 ° 22.3 kN 12.1 kN 31.6 kN 9.7 kN 29.7 kN 7. 3 kN 2 7. 8 kN
55 ° 5.0% 2.9 ° 22.3 kN 13.6 kN 33.4 kN 10.9 kN 31.2 kN 8.2 kN 29.0 kN
60 ° 5.0% 2.9 ° 22.3 kN 15.6 kN 35.8 kN 12.5 kN 33.1 kN 9.4 kN 30.4 kN
Slab thickness 24 cm, q = 7.58 kN/m²
30 ° 5.0% 2.9 ° 25.6 kN 10.3 kN 30.8 kN 8.3 kN 29.7 kN 6.2 kN 28.7 kN
35 ° 5.0% 2.9 ° 25.6 kN 10.9 kN 31.9 kN 8.7 kN 30.6 kN 6.6 kN 29.3 kN
40 ° 5.0% 2.9 ° 25.6 kN 11.7 k N 33.1 kN 9.4 kN 31.6 k N 7. 0 kN 3 0 .1 kN
45 ° 5.0% 2.9 ° 25.6 kN 12.7 kN 34.5 kN 10.1 k N 32.7 kN 7.6 k N 31.0 kN
50 ° 5.0% 2.9 ° 25.6 kN 13.9 kN 36.3 kN 11.1 k N 34.1 kN 8.4 kN 32.0 kN
55 ° 5.0% 2.9 ° 25.6 kN 15.6 kN 38.4 kN 12.5 kN 35.8 kN 9.4 kN 33.3 kN
60 ° 5.0% 2.9 ° 25.6 kN 17.9 k N 41.1 k N 14.3 kN 38.0 kN 10.7 kN 34.9 kN
Braced prop
Full load
V
ges
Slab thickness 25 cm, q = 7.83 kN/m²
30 ° 5.0% 2.9 ° 26.4 kN 10.7 kN 31.8 kN 8.5 kN 30.7 kN 6.4 kN 29.6 kN
35 ° 5.0% 2.9 ° 26.4 kN 11.3 k N 32.9 kN 9.0 kN 31.6 kN 6.8 kN 30.3 kN
40 ° 5.0% 2.9 ° 26.4 kN 12.1 kN 34.2 kN 9.7 kN 32.6 kN 7.2 k N 31.1 kN
45 ° 5.0% 2.9 ° 26.4 kN 13.1 kN 35.7 kN 10.5 kN 33.8 kN 7. 8 kN 32.0 kN
50 ° 5.0% 2.9 ° 26.4 kN 14.4 kN 37.4 k N 11.5 k N 35.2 kN 8.6 kN 33.0 kN
55 ° 5.0% 2.9 ° 26.4 kN 16.1 k N 39.6 kN 12. 9 kN 37.0 k N 9.7 kN 34.4 kN
60 ° 5.0% 2.9 ° 26.4 kN 18.5 kN 42.4 kN 14.8 kN 39.2 kN 11.1 k N 36.0 kN
Slab thickness 30 cm, q = 9.05 kN/m²
30 ° 5.0% 2.9 ° 30.5 kN 12.3 kN 36.7 kN 9.9 kN 35.5 kN 7. 4 kN 34.2 kN
35 ° 5.0% 2.9 ° 30.5 kN 13.1 kN 38.0 kN 10.4 kN 36.5 kN 7.8 k N 35.0 kN
40 ° 5.0% 2.9 ° 30.5 kN 14.0 kN 39.5 kN 11. 2 kN 37.7 k N 8.4 kN 35.9 kN
45 ° 5.0% 2.9 ° 30.5 kN 15.1 k N 41. 2 kN 12.1 kN 39.1 k N 9.1 kN 3 7. 0 kN
50 ° 5.0% 2.9 ° 30.5 kN 16.6 kN 43.3 kN 13.3 kN 40.7 kN 10.0 kN 38.2 kN
55 ° 5.0% 2.9 ° 30.5 kN 18.6 kN 45.8 kN 14.9 kN 42.8 kN 11. 2 kN 39.7 kN
60 ° 5.0% 2.9 ° 30.5 kN 21.4 kN 49.1 k N 17.1 kN 45.4 kN 12.8 kN 41.7 kN
Table A15 .07
SKYDECK Panel Slab Formwork
71
A15 Inclined slabs
System with Prophead SSK Tension force of Tension Unit SD and prop loads
Considered horizontal loads
Horizontal load from working operations = 1% of the vertical load (DIN EN 12812; 8.2.2.2) Horizontal load from the tilting position = 1% of the vertical load (DIN EN 12812; 9.3.4.2)
Inclination of slab 9%
Angle α
Tension Unit
SD
max. inclination
Incline
[%]
Angle β
Standard
prop
[°]
Full load
5 connected bays 4 connected bays 3 connected bays
Tension
force Tension Unit SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Braced prop
Full load
V
ges
Tension
force
Tension Unit
SD
Slab thickness 20 cm. q = 6.60 kN/m²
30 ° 9.0% 5.1 ° 22.3 kN 14.1 kN 29.3 kN 11.3 kN 27.9 kN 8.5 kN 26.5 kN
35 ° 9.0% 5.1 ° 22.3 kN 15.0 kN 30.9 kN 12.0 kN 29.1 k N 9.0 kN 27. 4 kN
40 ° 9.0% 5.1 ° 22.3 kN 16.0 kN 32.6 kN 12.8 kN 30.5 kN 9.6 kN 28.4 kN
45 ° 9.0% 5.1 ° 22.3 kN 17.3 k N 34.5 kN 13.9 kN 32 .1 kN 10.4 kN 29.6 kN
50 ° 9.0% 5.1 ° 22.3 kN 19.1 kN 36.9 kN 15.2 kN 34.0 kN 11. 4 k N 31.0 k N
55 ° 9.0% 5.1 ° 22.3 kN 21.4 kN 39.8 kN 17.1 k N 36.3 kN 12.8 kN 32.8 kN
60 ° 9.0% 5.1 ° 22.3 kN 19.6 kN 39.3 kN 14.7 kN 35.0 kN
Slab thickness 24 cm. q = 7.58 kN/m²
30 ° 9.0% 5.1 ° 25.6 kN 16.2 kN 33.7 kN 13.0 kN 32.1 kN 9.7 kN 30.5 kN
35 ° 9.0% 5.1 ° 25.6 kN 17.2 k N 35.4 kN 13.7 kN 33.5 kN 10.3 kN 31.5 kN
40 ° 9.0% 5.1 ° 25.6 kN 18.4 kN 37.4 k N 14.7 kN 35.0 kN 11. 0 kN 32.7 kN
45 ° 9.0% 5.1 ° 25.6 kN 19.9 kN 39.7 kN 15.9 kN 36.8 kN 11. 9 k N 34.0 kN
50 ° 9.0% 5.1 ° 25.6 kN 21.9 kN 42.4 kN 17.5 kN 39.0 kN 13.1 kN 35.6 kN
55 ° 9.0% 5.1 ° 25.6 kN 19.6 kN 41.7 kN 14.7 kN 37. 6 kN
60 ° 9.0% 5.1 ° 25.6 kN 22.5 kN 4 5.1 kN 16.9 kN 40.2 kN
Braced prop
Full load
V
ges
Slab thickness 25 cm. q = 7.83 kN/m²
30 ° 9.0% 5.1 ° 26.4 kN 16.8 kN 34.8 kN 13.4 kN 33.1 kN 10.1 k N 31.5 kN
35 ° 9.0% 5.1 ° 26.4 kN 17.7 kN 36.6 kN 14.2 kN 34.6 kN 10.6 kN 32.5 kN
40 ° 9.0% 5.1 ° 26.4 kN 19.0 kN 38.6 kN 15.2 kN 36.2 kN 11. 4 k N 33.7 kN
45 ° 9.0% 5.1 ° 26.4 kN 20.6 kN 41.0 kN 16.4 kN 3 8 .1 kN 12.3 kN 35 .1 kN
50 ° 9.0% 5.1 ° 26.4 kN 22.6 kN 43.7 kN 18.1 k N 40.3 kN 13.6 kN 36.8 kN
55 ° 9.0% 5.1 ° 26.4 kN 20.3 kN 43.0 kN 15.2 kN 38.9 kN
60 ° 9.0% 5.1 ° 26.4 kN 23.3 kN 46.6 kN 17.4 kN 41.5 kN
Slab thickness 30 cm. q = 9.05 kN/m²
30 ° 9.0% 5.1 ° 30.5 kN 19.4 kN 40.2 kN 15.5 kN 38.3 kN 11.6 k N 36.4 kN
35 ° 9.0% 5.1 ° 30.5 kN 20.5 kN 42.3 kN 16.4 kN 40.0 kN 12. 3 k N 37.6 k N
40 ° 9.0% 5.1 ° 30.5 kN 21.9 kN 44.6 kN 17.5 k N 41.8 kN 13.2 kN 39.0 kN
45 ° 9.0% 5.1 ° 30.5 kN 23.8 kN 47. 3 kN 19.0 kN 44.0 kN 14.3 kN 40.6 kN
50 ° 9.0% 5.1 ° 30.5 kN 20.9 kN 46.6 kN 15.7 kN 42.6 kN
55 ° 9.0% 5.1 ° 30.5 kN 23.4 kN 49.7 kN 17.6 kN 44.9 kN
60 ° 9.0% 5.1 ° 30.5 kN 20.2 kN 48.0 kN
Table A15 .08
SKYDECK Panel Slab Formwork
72
Instructions for Assembly and Use – Standard Configuration
A16 SKYDECK
Prop loads with Drophead SFK
Main Beam SLT 225
Panel span c 1.50 m Panel span c 0.75 m Panel span c 1.50 m Panel span c 0.75 m
Prop load
[kN]
with
Centre
Support
Slab thickness d [m]
Load q* [kN/m²]
0.14 5.13 17.7 7 8.8 7 11.9 7
0.16 5.62 19.4 7 9.7 7 13.1 7
0.18 6.11 21.1 7 10.5 7 14.2 7
0.20 6.60 22.8 7 11.4 7 15.3 7
0.22 7. 0 9 24.5 7 12.2 7 16.5 7
0.24 7.58 26.2 7 13.1 7 17.6 7
0.25 7.83 27.0 7 13.5 7 18.2 7
0.26 8.07 27.8 7 13.9 7 18.8 7
0.28 8.56 29.5 16.2 7 7 14.8 7 19.9 7
0.30 9.05 31.2 17. 2 7 7 15.6 7 21.0 7
0.35 10.38 35.8 19.7 7 7 17.9 7 24.1 7
0.40 11.7 3 40.5 22.3 6 7 20.2 7 27. 3 7
0.43 12.54 43.3 23.6 6 6 21.4 7 29.2 6
0.45 13.0 8 24.8 6 22.6 7 30.4 6
0.50 14.43 2 7. 4 6 24.9 7 33.5 6
0.52 14.96 28.4 6 25.8 7 7 34.8 6 17. 4 7
0.55 15.77 27. 2 7 7 18.3 7
0.60 17.12 29.5 17.7 7 7 19.9 7
0.65 18.47 31.9 19 .1 7 7 21.5 7
0.70 19.82 34.2 20.5 6 7 23.0 7
0.75 21.0 8 36.4 21.8 6 7 24.5 7
0.80 22.30 38.5 2 3 .1 6 7 25.9 7
0.85 23.53 40.6 24.3 6 7 2 7. 3 7
0.90 24.75 42.7 25.6 6 7 28.8 6
0.95 25.98 26.9 7 30.2 6
1.00 2 7. 20 28.2 6 31.6 6
1.05 28.43 29.4 6 33.0 6
1.09 29.35 30.4 6 3 4.1 6
SSK
Deflection
line**
with
Centre
Support
SSK
Prop load
[kN]
with
Centre
Support
SSK
Deflection
line**
with
Centre
Support
SSK
Prop load
[kN]
with
Centre
Support
SSK
Main Beam SLT 150
Deflection
line**
with
Centre
Support
SSK
Prop load
[kN]
with
Centre
Support
SSK
Deflection
line**
with
Centre
Support
SSK
*Load according to DIN EN 12812:
Dead load
Concrete load
Equivalent load: concret-
ing
Equivalent load: working
= 0.20 kN/m
Q
1
Q
= 24.5 kN/m3 x d [m]
2.b
= 0.10 x Q2.b
Q
4
0.75 kN/m Q
= 0.75 kN/m
2.p
2
2
≤ Q4 ≤ 1.75 KN/m
2
conditions
Total loa d
**
Deflection according to DIN 18202. assuming perfect levelling.
SKYDECK Panel Slab Formwork
Q = Q1 + Q
2.b
+ Q
2.p
+ Q
When calculating the prop load. the actual extension length may be used. The exact extension length of the prop when using the SKYDECK drophead is: clear room height minus 0.41 m. Prop loads over 33.3 kN:
2
bolting on of Drophead for use with PEP Slab Props using 2 Bolts DIN EN ISO 4016 M12 x 40-4.6 galv.. Mu.
4
73
A16 SKYDECK
Prop loads with Prophead SSK
Main Beam SLT 225 Main Beam SLT 150
Panel span c 1.50 m Panel span c 0.75 m Panel span c 1.50 m Panel span c 0.75 m
Prop load
[kN]
with
Centre
Support
Slab thickness d [m]
Load q* [kN/m²]
SSK
Deflection
line**
with
Centre
Support
SSK
Prop load
[kN]
with
Centre
Support
SSK
Deflection
line**
with
Centre
Support
SSK
Prop load
[kN]
with
Centre
Support
SSK
Deflection
line**
with
Centre
Support
SSK
Prop load
[kN]
with
Centre
Support
SSK
Deflection
0.14 5.13 17. 3 7 8.7 7 11.5 7
0.16 5.62 19.0 7 9.5 7 12.6 7
0.18 6.11 20.6 7 10.3 7 13.7 7
0.20 6.60 22.3 7 11.1 7 14.9 7
0.22 7. 0 9 23.9 7 12.0 7 16.0 7
0.24 7.58 25.6 7 12.8 7 17.1 7
0.25 7.83 26.4 7 13.2 7 17.6 7
0.26 8.07 27.2 7 13.6 7 18.2 7
0.28 8.56 28.9 16.2 7 7 14.4 7 19.3 7
0.30 9.05 30.5 17.1 7 7 15.3 7 20.4 7
0.35 10.38 35.0 19.6 7 7 17.5 7 23.4 7
0.40 11.7 3 39.6 22.2 6 7 19.8 7 26.4 7
0.43 12.54 42.3 23.7 6 6 21.2 7 28.2 6
0.45 13.0 8 24.7 6 2 2.1 7 29.4 6
0.50 14.43 27.3 6 24.3 7 32.5 6
0.55 15.77 29.8 6 26.6 7 35.5 6 17.7 7
0.60 17.12 28.9 7 19.3 7
0.65 18.47 31. 2 19.0 7 7 20.8 7
0.70 19.82 33.4 20.4 7 7 22.3 7
0.75 21.0 8 35.6 21.7 6 7 23.7 7
0.80 22.30 37.6 23.0 6 7 25.1 7
0.85 23.53 39.7 24.2 6 7 26.5 7
0.90 24.75 41.8 25.5 6 7 27.8 6
0.95 25.98 26.7 7 29.2 6
1.00 2 7. 20 28.0 6 30.6 6
1.05 28.43 29.3 6 32.0 6
1.09 29.35 30.2 6 33.0 6
line**
with
Centre
Support
SSK
*Load according to DIN EN 12812:
Dead load
Concrete load
Equivalent load: concreting
Equivalent load:
working conditions
Total loa d
Deflection according to DIN 18202, assuming perfect levelling.
**
= 0.20 kN/m
Q
1
Q
= 24.5 kN/m3 x d [m]
2.b
= 0.10 x Q2.b
Q
4
0.75 kN/m Q
= 0.75 kN/m
2.p
Q = Q1 + Q
2
2
≤ Q4 ≤ 1.75 KN/m
2
+ Q
2.b
74
2.p
+ Q
When calculating the prop load, the actual extension length may be used. The exact extension length of the prop when using the SKYDECK Prophead is: clear room height minus 0.33 m.
2
4
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A16 SKYDECK
Prop loads in panel system Striking guide values
Panel system
Slab thickness
d [m]
0.14 5.13 5.78 7
0.16 5.62 6.33 7
0.18 6 .11 6.88 7
0.20 6.61 7. 4 3 7
0.22 7.10 7. 9 8 7
0.24 7. 5 9 8.53 7
0.25 7. 8 3 8.81 7
0.26 8.08 9.09 7
0.28 8.57 9.64 7
0.30 9.06 10.19 7
0.35 10.39 11. 6 9 7
0.40 11.74 13.21 7
0.42 12.28 13.82 6
0.45 13.09 14.73 6
0.50 14.4 4 16.24 6
0.55 15.79 17.76 6
Load q*
[kN/m²]
Prop load
[kN]
75
* Deflection to
DIN 18202, line
150
* Deflection according to DIN 18202. Assuming perfect levelling.
Calculation basis:
*Load according to EN 12812
Dead load
Concrete load
Equivalent load: concreting
Equivalent load:
working conditions
Total loa d
= 0.20 kN/m
Q
1
Q
= 24.5 kN/m3 x d [m]
2.b
= 0.10 x Q2.b
Q
4
0.75 kN/m Q
= 0.75 kN/m
2.p
Q = Q1 + Q
2.b
+ Q
Striking guide values* [Days] for the Drophead System.
Slab thickness
d [m]
0.14 15 10 6 5
0.16 13 8 5 4
0.18 11 6 4 3
0.20 9 5 3 2
0.22 8 4 3 2
0.25 7 4 2 2
0.30 6 3 2 2
0.35 5 3 2 1
0.40 – 1.0 9 5 2 1 1
Required concrete
strength f
[N/mm2]
ck,cub e
*Guide values for striking time [days] for
panels and main beams with an average
curing temperature [°C] of
10° 20°
2
2
≤ Q4 ≤ 1.75 KN/m
2
+ Q
2.p
4
2
The required concrete strength at the time of striking is decisive. This is to be calculated by suitable methods.
Guidelines according to DIN 1045 must also be taken into account, e.g. curing. A minimum of 1.88 cm²/m (Q 188) is required for the bottom reinforcement layer. For systems without any centre support of the main beams, a live load of 1 kN/m² on the slab which has struck early, is to be considered. * Guide values according to Leonhard for cement Z 35, CEM I 32.5 R.
SKYDECK Panel Slab Formwork
75
A17 SK YDECK
Filler plates, forming around columns
Perm. width B [m] of the filler plate
Perm. width of influence eB [m] for shuttering columns
Case 1
Slab
thickness
d [m]
0.14 0.65 0.71
0.16 0.62 0.69
0.18 0.60 0.68
0.20 0.58 0.65
0.22 0.57 0.64
0.24 0.55 0.63
0.25 0.55 0.61
0.26 0.54 0.61
0.28 0.53 0.60
0.30 0.52 0.59
0.35 0.49 0.58
0.40 0.47 0.56
0.43 0.46 0.54
0.45 0.46 0.53
0.50 0.44 0.52
0.52 0.44 0.51
0.55 0.43 0.51
0.60 0.42 0.50
0.65 0.41 0.49
0.70 0.40 0.48
0.75 0.39 0.47
0.80 0.39 0.46
0.85 0.38 0.46
0.90 0.37 0.45
0.95 0.37 0.45
1.00 0.36 0.44
1.05 0.36 0.44
1.09 0.35 0.43
Note: Deflection single span beam B/300.
Fin Ply 21 mm
Spruce 400
parallel/cross
Fin Ply 21 mm
parallel/cross
Case 2
Spruce 400
Case 1
Filler Timber SPH or Edge Beam SRT-2
Case 2
Combihead SCK
Filler Timber SPH or Edge Beam SRT-2
B
B
max. 10 cm
Panel 150
Slab
thickness
d [m]
0.14 1.14 0.49
0.16 1.01 0.43
0.18 0.90 0.38
0.20 0.81 0.35
0.22 0.74 0.32
0.24 0.68 0.29
0.25 0.65 0.28
0.26 0.63 0.27
0.28 0.59 0.25
0.30 0.55 0.23
0.35 0.47 0.20
0.40 0.41 0 .18
0.43 0.39 0.16 1.70 0.72
0.45 0.37 0.16 1.63 0.69
0.50 0.33 0.14 1.48 0.63
0.52 0.32 0 .14 1.43 0.61
0.55 1.35 0.57
0.60 1.25 0.53
0.65 1.16 0.49
0.70 1.0 8 0.46
0.75 1.01 0.43
0.80 0.96 0.41
0.85 0.91 0.38
0.90 0.86 0.37
0.95 0.82 0.35
1.00 0.78 0.33
1.05 0.75 0.32
1.09 0.73 0.31
L/500 = 3 mm L/500 = 1,5 mm
SRT-2 SPH SRT-2 SPH
e
B
Panel 75
Perm. span L [m] of the Edge Main Beams
Beam used
GT 24 4.61 3.93 3.45 3 .12 2.86 2.66 2.51 2.26 2.06 1. 97 1.91
VT 20 3.89 3.32 2.92 2.63 2.42 2.22 1.97 1.78 1.62 1.55 1.50
KH 10/16 3.79 3.23 2.84 2.56 2.35 2.10 1.86 1.68 1.53 1.46 1.42
0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.05 1.09
Slab thickness [m]
Perm. width B [m] of the filler plate max. 0.40 m
L L
76
Panel 150 or 75
Filler Timber SPH or Edge Beam SRT-2
B
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A18 Slab props
PEP 20
Permissible prop load [kN] according to the type test
PEP 20-300
PEP 20-350
PEP 20-400
PEP 20-500
PEP 20 N 260*
L = 1.51 – 2.60 m
Outer tube
Extension
length [m]
bottom
1.60 35.0 35.0
1.70 35.0 35.0
1.8 0 35.0 35.0 36.4 36.4
1.9 0 35.0 35.0 36.4 36.4
2.00 33.5 35.0 36.1 36.4 36.4 36.4
2.10 31.9 35.0 33.2 36.4 36.4 36.4
2.20 30.9 35.0 31.4 36.4 36.4 36.4
2.30 29.8 35.0 29.9 36.4 36.4 36.4 36.4 36.4
2.40 28.6 35.0 28.7 36.4 36.4 36.4 36.4 36.4
2.50 27.1 32.9 27.7 36.4 36.4 36.4 36.4 36.4
2.60 24.8 29.4 26.9 36.3 34.8 36.4 36.4 36.4
2.70 25.7 32.7 33.4 36.4 36.4 36.4
2.80 24.0 29.3 3 2.1 36.4 36.4 36.4 36.4 36.4
2.90 22.3 26.5 31.1 36.4 36.4 36.4 36.4 36.4
3.00 20.5 23.9 3 0.1 36.4 36.4 36.4 36.4 36.4
3.10 28.3 35.7 34.6 36.4 36.4 36.4
3.20 26.5 32.5 33.5 36.4 36.4 36.4
3.30 24.8 29.7 32 .1 36.4 36.4 36.4
3.40 23.1 2 7. 2 30.5 36.4 36.4 36.4
3.50 21.3 24.8 28.7 34.9 36.4 36.4
3.60 26.9 32.1 36.4 36.4
3.70 25.3 29.8 36.4 36.4
3.80 23.7 27.6 36.4 36.4
3.90 22.3 25.5 36.4 36.4
4.00 20.7 23.5 35.3 36.4
4.10 33.3 36.4
4.20 31.5 36.4
4.30 29.8 35.0
4.40 28.2 32.9
4.50 26.8 30.8
4.60 25.3 28.9
4.70 24.1 27. 2
4.80 22.8 25.7
4.90 21.5 24.1
5.00 20.3 2 2.1
Inner tube
bottom
L = 1.71 – 3.00 m
Outer tube
bottom
Inner tube
bottom
L = 1.96 – 3.50 m
Outer tube
bottom
Inner tube
bottom
L = 2.21 – 4.00 m
Outer tube
bottom
Inner tube
bottom
L = 2.71 – 5.00 m
Outer tube
bottom
Inner tube
bottom
All PEP 20 Props correspond to Class D of DIN EN 1065, i. e. the permissible load for all extension lengths is a mini­mum of 20 kN.
When using PERI Slab Tables, the permissible load for all PEP 20 Props is a minimum of 30 kN over the entire extension lengths due to the clamping in the Table Swivel Head or UNIPORTAL Head.
SKYDECK Panel Slab Formwork
*For the N Props, a use of the inner tube at the bottom is only possible in connection with PERI Slab Tables or SKYDECK (bolted head).
77
A18 Slab props
PEP 20 with Base MP 50
Permissible prop load [kN] according to the type test
PEP 20-300
PEP 20-350
PEP 20-400
PEP 20-500
PEP 20 N 260*
L = 1.51 – 2.60 m
Outer tube
Overall height
[m]
2.10 35.3 35.3
2.20 35.3 35.3
2.30 35.3 35.3 35.3 35.3
2.40 33.2 35.3 35.3 35.3
2.50 31.0 35.3 33.8 35.3 35.3 35.3
2.60 29.5 35.3 30.9 35.3 35.3 35.3
2.70 27. 8 35.3 28.7 35.3 35.3 35.3
2.80 26.5 33.7 2 7. 0 35.3 35.3 35.3 35.3 35.3
2.90 25.6 29.8 25.6 34.7 35.3 35.3 35.3 35.3
3.00 23.7 26.7 24.4 31.2 34.0 35.3 35.3 35.3
3.10 21.6 23.9 23.5 28.0 31.9 35.3 35.3 35.3
3.20 22.4 25.5 30.2 35.3 35.3 35.3
3.30 20.7 23.2 28.8 35.3 35.3 35.3 35.3 35.3
3.40 19.3 21.2 27. 6 33.2 34.7 35.3 35.3 35.3
3.50 17.5 19.2 26.2 29.8 32.9 35.3 35.3 35.3
3.60 24.6 27.8 31.3 35.3 35.3 35.3
3.70 22.9 25.3 29.9 34.3 35.3 35.3
3.80 21.3 23.5 28.2 31.8 35.3 35.3
3.90 19.8 21.9 26.5 29 .1 35.3 35.3
4.00 18.3 20.1 24.8 26.9 35.3 35.3
4.10 23.2 25.3 35.3 35.3
4.20 21.8 23.5 35.3 35.3
4.30 20.4 22.1 34.6 35.3
4.40 19.1 20.6 32.7 35.3
4.50 17.8 19.2 30.7 33.2
4.60 28.4 31.2
4.70 27.2 29 .1
4.80 25.7 2 7. 6
4.90 24.3 26.0
5.00 23.1 24.6
5.10 21. 9 23.3
5.20 20.8 2 2.1
5.30 19.7 20.9
5.40 18.5 19.4
5.50 17. 6 17.7
bottom
(prop extension
+ 50 cm)
Inner tube
bottom
L = 1.71 – 3.00 m
Outer tube
bottom
Inner tube
bottom
L = 1.96 – 3.50 m
Outer tube
bottom
Inner tube
bottom
L = 2.21 – 4.00 m
Outer tube
bottom
Inner tube
bottom
L = 2.71 – 5.00 m
Outer tube
bottom
Inner tube
bottom
78
*For the N Props, use of the inner tube at the bottom is only possible in connection with PERI Slab Tables or SKYDECK (bolted head).
SKYDECK Panel Slab Formwork
Instructions for Assembly and Use – Standard Configuration
A18 Slab props
PEP 30
Permissible prop load [kN] according to the type test
PEP 30-150
L = 0.96 – 1.50 m
Outer tube
Extension
length [m]
bottom
1.00 36.4 36.4
1.10 36.4 36.4
1.20 36.4 36.4
1.3 0 35.9 36.4
1.40 35.3 36.4
1.50 34.5 36.4 42.9 42.9
1.60 42.9 42.9
1.70 42.9 42.9
1.8 0 4 2.1 42.9 42.9 42.9
1.9 0 39.7 42.9 42.9 42.9
2.00 37.9 42.9 42.9 42.9 45.5 45.5
2.10 36.4 42.9 42.9 42.9 45.5 45.5
2.20 35.5 42.9 42.9 42.9 45.5 45.5
2.30 34.3 41.5 42.9 42.9 45.5 45.5 41.5 41.5
2.40 33.1 38.7 42.7 42.9 45.5 45.5 41.5 41.5
2.50 31.0 35.9 41.1 42.9 45.5 45.5 41.5 41.5
2.60 40.0 42.9 45.5 45.5 41.5 41.5
2.70 38.5 42.9 45.5 45.5 41.5 41.5
2.80 36.9 41.6 45.5 45.5 41.5 41.5
2.90 34.2 38.3 45.0 45.5 41.5 41.5
3.00 31. 3 34.8 43.6 45.5 41.5 41.5
3.10 41.4 44.2 41.5 41.5
3.20 38.7 42.1 41.5 41.5
3.30 36.1 38.7 41.5 41.5
3.40 33.3 35.7 41.5 41.5
3.50 30.7 32.5 41.5 41.5
3.60 41.5 41.5
3.70 41.3 41.5
3.80 38.5 41.3
3.90 35.9 38.1
4.00 33.2 34.9
Inner tube
bottom
PEP 30-250
L = 1.46 – 2.50 m
Outer tube
bottom
Inner tube
bottom
PEP 30-300
L = 1.71 – 3.00 m
Outer tube
bottom
Inner tube
bottom
PEP 30-350
L = 1.96 – 3.50 m
Outer tube
bottom
Inner tube
bottom
PEP 30-400
L = 2.21 – 4.00 m
Outer tube
bottom
Inner tube
bottom
All PEP 30 Props correspond to Class E of DIN EN 1065, i. e. the permissible load for all extension lengths is a mini­mum of 30 kN.
When using PERI Slab Tables, the per­missible load for all PEP 30 Props is a minimum of 40 kN (PEP 30-150 = 35 kN) over the entire extension lengths due to the clamping in the Table Swivel Head or UNIPORTAL Head.
SKYDECK Panel Slab Formwork
79
A18 Slab props
PEP 30 with Base MP 50
Permissible prop load [kN] according to the type test
PEP 30-250
L = 1.46 – 2.50 m
Outer tube
Overall height
[m]
2.00 41.6 41.6
2.10 41.6 41.6
2.20 41.6 41.6
2.30 38.9 41.6 41.6 41.6
2.40 36.1 41.6 41.6 41.6
2.50 33.9 41.6 41.6 41.6 4 4 .1 44.1
2.60 32.2 41.0 41. 6 41.6 4 4.1 4 4.1
2.70 30.8 38.7 41.6 41.6 4 4 .1 44.1
2.80 29.7 35.3 40.3 41.6 44.1 4 4 .1 40.3 40.3
2.90 2 7.5 31.3 38.3 41.6 4 4.1 4 4 .1 40.3 40.3
3.00 25.9 27. 6 36.5 41. 3 44.1 4 4.1 40.3 40.3
3.10 35 .1 40.0 4 4 .1 44.1 40.3 40.3
3.20 32.9 36.8 43.8 4 4 .1 40.3 40.3
3.30 31.1 33.2 41.7 44.1 40.3 40.3
3.40 28.5 30.3 38.8 41.8 40.3 40.3
3.50 26.1 27.1 37.1 39.7 40.3 40.3
3.60 34.8 36.5 40.3 40.3
3.70 32.4 33.5 40.3 40.3
3.80 30.0 30.9 40.3 40.3
3.90 27.8 28.7 40.3 40.3
4.00 25.6 26.3 39.4 40.3
4.10 36.7 3 7. 9
4.20 34.3 35.2
4.30 32.0 32.9
4.40 29.9 30.5
4.50 27.6 28.2
bottom
(prop extension
+ 50 cm)
Inner tube
bottom
PEP 30-300
L = 1.71 – 3.00 m
Outer tube
bottom
Inner tube
bottom
PEP 30-350
L = 1.96 – 3.50 m
Outer tube
bottom
Inner tube
bottom
PEP 30-400
L = 2.21 – 4.00 m
Outer tube
bottom
Inner tube
bottom
80
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A18 Slab props
PEP Ergo B
Permissible prop load [kN] according to type test
PEP Ergo B-300
L = 1.97 – 3.00 m
Outer tube
Extension
length [m]
bottom
2.00 30.0 30.0
2.10 29.8 30.0
2.20 27.0 30.0
2.30 24.6 30.0 30.0 28.6
2.40 23.0 30.0 28.6 28.6
2.50 21.4 30.0 25.5 28.6
2.60 20.3 29.5 23.1 28.3
2.70 19.3 27. 4 21.2 28.0
2.80 18.2 24.8 19.8 27.4
2.90 16.9 22.2 18.6 26.0
3.00 15.6 20.2 17.5 24.4
3.10 16.3 22.7
3.20 15.2 20.8
3.30 14. 2 19.0
3.40 13.2 17.4
3.50 12.4 15.7
Inner tube
bottom
PEP Ergo B-350
L = 2.25 – 3.50 m
Outer tube
bottom
Inner tube
bottom
Note:
■
PERI PEP Ergo B-300 and PEP Ergo B-350 Props meet the load-bearing capacity requirements of Prop Class B as stipulated in DIN EN 1065.
■
General Building Inspectorate Approval Z-8.311-934 issued by the German Institute for Building Technology (DIBt).
SKYDECK Panel Slab Formwork
81
A18 Slab props
PEP 30 with Base MP 50
Permissible prop load [kN] according to type test
PEP Ergo D-150
L = 0.98 – 1.50 m
Outer tube
Extension
length [m]
bottom
1.00 30.0 30.0
1.10 30.0 30.0
1.20 30.0 30.0
1.3 0 30.0 30.0
1.40 28.4 30.0
1.50 26.4 30.0 35.0 35.0
1.60 35.0 35.0
1.70 32.8 35.0
1.8 0 30.7 35.0
1.9 0 2 9.1 35.0
2.00 28.1 35.0
2.10 27. 2 35.0
2.20 26.4 34.0
2.30 25.7 32.3 40.0 40.0
2.40 24.2 29.4 40.0 40.0
2.50 22.4 26.2 40.0 40.0
2.60 37. 8 40.0 40.0 40.0
2.70 35.1 40.0 40.0 40.0
2.80 33.0 40.0 40.0 40.0
2.90 31.1 40.0 40.0 40.0
3.00 29.6 40.0 40.0 40.0
3.10 2 8.1 38.6 3 7.7 40.0
3.20 26.9 34.7 35.6 40.0
3.30 25.0 31.5 33.7 40.0 40.0 40.0
3.40 23.1 28.6 32.3 40.0 40.0 40.0
3.50 21.2 25.8 30.7 39.3 40.0 40.0
3.60 28.6 35.9 40.0 40.0
3.70 26.7 32.9 40.0 40.0
3.80 24.9 30.2 40.0 40.0
3.90 23.1 27. 8 40.0 40.0
4.00 21.4 25.3 40.0 40.0
4.10 39.0 40.0
4.20 36.3 40.0
4.30 33.8 39.0
4.40 31.6 36.7
4.50 29.6 34.3
4.60 27.8 32.1
4.70 26.1 3 0.1
4.80 24.5 28.2
4.90 23.0 26.4
5.00 21.4 24.7
Inner tube
bottom
PEP Ergo D-250
L = 1.47 – 2.50 m
Outer tube
bottom
Inner tube
bottom
PEP Ergo D-350
L = 2.26 – 3.50 m
Outer tube
bottom
Inner tube
bottom
PEP Ergo D-400
L = 2.51 – 4.00 m
Outer tube
bottom
Inner tube
bottom
PEP Ergo D-500
L = 3.26 – 5.00 m
Note:
■
PERI PEP Ergo D-150, PEP Ergo D-250, PEP Ergo D-350, PEP Ergo D-400 and PEP Ergo D-500 Props fulfil Prop Class D load-bearing capacity requirements of DIN EN 1065.
■
In addition, the PEP Ergo D-250 Prop fulfils Prop Class B requirements as stipulated in DIN EN 1065.
■
General Building Inspectorate Approval Z-8.311-934 for PERI PEP Ergo D-150 and PEP Ergo D-250.
■
General Building Inspectorate Approval Z-8.311-941 for PERI PEP Ergo D-350, PEP Ergo D-400 and PEP Ergo D-500.
82
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
A18 Slab props
PEP Ergo B
Permissible prop load [kN] according to type test
PEP Ergo E-300
L = 1.96 – 3.00 m
Outer tube
Extension
length [m]
bottom
2.0 50.4 50.4
2.1 50.4 50.4
2.2 50.4 50.4
2.3 50.4 50.4
2.4 50.4 50.4
2.5 48.9 50.4
2.6 46.2 50.3 50.4 50.4
2.7 44.4 48.8 50.4 50.4
2.8 42.5 46.7 50.4 50.4
2.9 40.5 44.0 50.4 50.4
3.0 38.0 39.6 50.4 50.4
3.1 50.4 50.4
3.2 50.4 50.4
3.3 50.4 50.4
3.4 50.4 50.4
3.5 4 8.1 50.4
3.6 45.4 50.4
3.7 42.1 47. 4
3.8 39.1 43.7
3.9 36.2 39.8
4.0 33.1 35.3
Inner tube
bottom
PEP Ergo E-400
L = 2.51 – 4.00 m
Outer tube
bottom
Inner tube
bottom
Note:
■
PERI PEP Ergo E-300 and PEP Ergo E-400 Props fulfil Prop Class E load-bearing capacity requirements of DIN EN 1065.
■
General Building Inspectorate Approval Z-8.311-941 of the German Institute for Building Technlogy (DIBt).
SKYDECK Panel Slab Formwork
83
A18 Slab props
MULTIPROP 250, 350, 480, 625
Permissible prop load [kN] according to the type test
MP 250
L = 1.45 – 2.50 m
Extension
length [m]
1.45 75.5 78.5
1.50 75.5 78.5
1.60 75.5 78.5
1.70 75.5 78.5
1.8 0 73.8 78.5
1.9 0 70.6 78.5
1.9 5 68.0 78.5 91.0 90.1
2.00 67.3 78.5 91.0 90.1
2.10 65.7 76.8 86.0 90.1
2.20 64.1 7 5 .1 80.6 9 0 .1
2.30 62.5 72.6 75.1 89.8
2.40 60.8 6 9 .1 70.7 87. 9
2.50 59.2 65.6 66.4 86.1
2.60 63.7 8 3.1 88.5 73.6
2.70 61.1 80.1 83.7 73.3
2.80 59.2 7 7.1 78.8 72.9
2.90 5 7. 4 74.1 74.0 72.6
3.00 56.0 70.3 6 9 .1 72.2
3.10 54.5 66.6 64.9 71.4
3.20 52.9 61.8 60.7 70.7
3.30 51.3 57.1 56.5 70.0
3.40 47.7 51.7 54.1 68.2
3.50 44.2 46.4 51.8 66.5
3.60 49.4 64.7
3.70 47. 5 60.4
3.80 45.7 56.1
3.90 43.8 51. 8
4.00 41. 8 48.4
4.10 39.7 45.0
4.20 3 7.7 41.6
4.30 35.8 39.3 57.9 45.7
4.40 33.9 3 7. 0 56.3 45.7
4.50 32.0 34.8 54.7 45.7
4.60 30.2 32.5 52.5 4 5 .1
4.70 28.3 30.2 50.3 44.4
4.80 26.4 2 7. 9 47.9 43.5
4.90 45.2 42.4
5.00 42.5 41. 3
5.10 39.9 39.9
5.20 3 7. 2 38.5
5.30 34.9 37.1
5.40 32.8 35.6
5.50 30.8 3 4 .1
5.60 29.3 32.6
5.70 27.8 31.2
5.80 26.4 29.6
5.90 25.1 27. 9
6.00 23.8 26.2
6.10 22.7 24.8
6.20 21.6 23.4
6.25 21.0 22.7
Outer tube
bottom
Inner tube
bottom
Outer tube
MULTIPROP Props are classified according to official approval as follows:
MP 250 Class T 25 MP 350 Class R 35
Note:
To release the loads > 60 kN, we recommend using the HD Wingnut Spanner, Item no. 022027. When using PERI Slab Tables, the permissible load of the MULTIPROP MP 350 Prop is a minimum of 56 kN and a minimum of 36 kN for the MP 480 over the entire extension length which is due to the clamping in the Table Swivel Head or UNIPORTAL Head.
MP 350
L = 1.95 – 3.50 m
bottom
MP 480 Class D 45 MP 625 Class D 60
Inner tube
bottom
MP 480
L = 2.60 – 4.80 m
Outer tube
bottom
Inner tube
bottom
MP 625
L = 4.30 – 6.25 m
Outer tube
bottom
Inner tube
bottom
84
Instructions for Assembly and Use – Standard Configuration
SKYDECK Panel Slab Formwork
SKYDECK Panel Slab Formwork
85
SKYDECK Panel Slab Formwork
2
4
0
Item no. Weight kg
Panels SDP
061000 061011 061020 061010 061013 061030
15.500
11.700
9.780
8.560
6.350
5.250
061160 25.700 Main Beam SLT 375
Panel SDP 150 x 75 Panel SDP 150 x 50 Panel SDP 150 x 37.5 Panel SDP 75 x 75 Panel SDP 75 x 50 Panel SDP 75 x 37.5
Panel with 9 mm plywood.
For cantilevers.
L B
1500 750 1500 500 1500 375 750 750 750 500 750 375
L
B
0
1
2
2
1
9 9
061100 15.600 Main Beam SLT 225
For standard fields.
3750
1042 1042
450 750 375 375 750 450
300 300
82 266
225 0
300 300
82 266
4503753 75450
2 1
2 1
0 4 2
86
SKYDECK Panel Slab Formwork
Item no. Weight kg
061110 9.690 Main Beam SLT 150
For filler areas.
150 0
112 0
190 190
80
0 9 1
2 1
061026 061027 061024 061038
061045 061046
1.580
0.794
0.524
0.400
5.740
2.720
Cover Strips SAL Cover Strip SAL 150 Cover Strip SAL 75 Cover Strip SAL 50 Cover Strip SAL 37.5
Plastic. Panel with 21 mm plywood. For use with drophead SFK.
Edge Beams SRT-2 Edge Beam SRT-2 150 Edge Beam SRT-2 75
For longitudinal and transverse filling, for shutte­ring around columns. Panel with 21 mm plywood.
L
1500 750 500 375
L
78
3
5 2 2
49
1500 / 750
1488 / 738
8 9
87
SKYDECK Panel Slab Formwork
Item no. Weight kg
061210 6.180 Drophead SFK
With self-locking coupling. Supports main beam as well as cover strip and formlining. Lowering height 6 cm. For 21 mm plywood formlining.
061200 3.860 Prophead SSK
With self-locking coupling. Supports main beams, panels, edge girders and filler timber.
40
250
8 5 2
0 6
0 5
0 6
2 1 6 1
0 9 3
9 4 5
0 5 2
061180 5.340 Combihead SCK
With self-locking coupling. Supports main beams, panels, edge girders and filler timber.
305
0
9 5 2
0 5 2
5
1 6 1
88
SKYDECK Panel Slab Formwork
Item no. Weight kg
Filler Timbers SPH
061049 061036
061021 061022
3.350
5.020
8.660
5.350
Filler Timber SPH 150 Filler Timber SPH 225
For compensations with 21 mm plywood formlining.
Triangular Frames SDR Triangular Frame SDR 150 x 75 Triangular Frame SDR 75 x 75
For compensations on inclined walls. For compen­sations with 21 mm plywood formlining.
49
1500 / 2250
8 9
061051 5.250 Wall Holder SWH-2
For horizontal anchoring at the wall. Attach to every second girder or panel.
0 9 4 1
202 100
2 0 1 1
89
SKYDECK Panel Slab Formwork
Item no. Weight kg
061023 2.140 End Support SSL
To be used as compensation to the filler area and to be fixed to the drophead SFK.
061290 0.133 Panel Clip SPK
Fixes panel on main beam.
1 2 1
50 33
2 0 1
0
6
1
86165
061280 0.778 Panel Wedge Clip SPKK
Fixes panel on main beam.
061052 2.590 Table Connector STV
For assembling SKYDECK Slab Tables. Also allows the fixing of intermediate props at the main beam.
061300 2.240 Erection Aid SSH
For forming with SKYDECK. Adjustable in
7.5-cm-increments.
6 1 1
116 80
330
86
0 7
90
2325 - 3750
SKYDECK Panel Slab Formwork
Item no. Weight kg
061310 0.996 Tension Sleeve SAO
For bracing cantilevered main beams.
Technical Data
Permissible tension force 3.0 kN.
2 5 2 1
6
123633 12.100 Tension Unit SD
061060 108.000 Platform SDB 150
Work and safety scaffold. Scaffold width 1.30 m. With continuous 39 mm thick decking and foldable handrail frame.
143
70
Technical Data
Permissible load 150 kg/m
3855
2
.
0 8
6 5 1
061061 153.000 Platform SDB 225
Work and safety scaffold. Scaffold width 1.30 m. With continuous 39 mm thick decking and foldable handrail frame.
1490 1433
Technical Data
Permissible load 150 kg/m
2240
6 0 0 1
1288
2
.
0 2 2 1
91
SKYDECK Panel Slab Formwork
Item no. Weight kg
061062 185.000 Platform SDB 300
Work and safety scaffold. Scaffold width 1.30 m. With continuous 39 mm thick decking and foldable handrail frame.
Technical Data
Permissible load 150 kg/m
2990
2
.
061250 4.760 Guardrail Holder SGH, Alu
For assembling a guardrail with SKYDECK.
Accessories
061260 6.150
Guardrail Post SGP
061260 6.150 Guardrail Post SGP
As guardrail for different systems.
Technical Data
Maximum width of influence 1.55 m.
5
0 0 3
1500
1640
0 2 1
8 5 4 2
6
3
0
0
3
92
3 3 4
8 3
3
4
3
1
4
8 6 7 1
6535
SKYDECK Panel Slab Formwork
Item no. Weight kg
065073 1.370 Anchor Chain 3.0 kN, l = 2.5 m Technical Data
Permissible tension force 3.0 kN.
065074 0.450 Turnbuckle 3.0 kN, M12 Technical Data
Permissible tension force 3.0 kN.
1
6
min 220 max 300
2500
5 1
028100 1.830 Base Plate for RS
For assembly of RS Push-Pull Props.
124777 0.210 Anchor Bolt PERI 14/20 x 130
For temporary fixation to reinforced concrete structures.
123970 0.047 Screw-On Sleeve PERI M16/164
For temporary mounting of components on rein­forced concrete slabs.
Complete with
1 pc. 018050 Pin Ø 16 x 65/86, galv. 1 pc. 018060 Cotter Pin 4/1, galv.
150
Ø13
Ø21
90
5 8
0 1
Note
See PERI data sheet! Drilling Ø 14 mm.
Ø14
130
SW 24
Note
Inserted into the fresh concrete immediately after concreting.
123973 0.240
Accessories
Bolt ISO 4014 M16 x 130-8.8, galv.
4 3
23Ø
9 8
1 5 5 1
93
SKYDECK Panel Slab Formwork
Item no. Weight kg
061530 82.400 Pallet SD 150 x 225, galv.
For stacking and transportation of 48 SKYDECK Panels 150 x 75.
Complete with
5 pc. 100707 Lashing 25 x 5750 mm
Note
Follow Instructions for Use!
Technical Data
Permissible load-bearing capacity 750 kg.
0 5 2
0 5 5 1
0 1 1 2
061500 76.700 Pallet SD 150 x 75, galv.
For stacking and transportation of 14 SKYDECK Panels 150 x 75.
2310
Note
Follow Instructions for Use!
Technical Data
Permissible load-bearing capacity 1.0 t.
0
3
2
7
7
9
1
1
1630 760
6401510
94
SKYDECK Panel Slab Formwork
Item no. Weight kg
061510 105.000 Pallet Lifting Trolley 1800 mm
For moving pallets and crate pallets.
Note
Follow Instructions for Use!
Technical Data
Forklift arm length 1800 mm, forklift arm width 550 mm, stroke range 115 mm. Permissible load-bearing capacity 2.0 t.
.
061520 403.000 Transportation Fork SUG, galv.
For moving SKYDECK Slab Tables.
Note
Follow Instructions for Use!
Technical Data
Permissible load-bearing capacity 1.0 t.
0 4 2 3
9 2 4 1
390 0 1224
0 0 8 2
95
SKYDECK Panel Slab Formwork
Item no. Weight kg
035500 72.800 Stripping Cart, Alu
Mobile working scaffold. Height-adjustable in 25-cm-increments. Platform height max. 2.00 m.
Note
Follow Instructions for Use!
Technical Data
Permissible load 100 kg/m
1800 750
2
.
5 3 0 3
96
SKYDECK Panel Slab Formwork
Item no. Weight kg
102031 363.000 Stripping Cart ASW 465, compl.
Mobile working scaffold. Height-adjustable in 30-cm-increments. Platform height max. 4.65 m.
Packed in: Ring Pallet USP 104 Item no. 100678, with Lashing Strap 25 x 5750 Item no. 100707 (x 1) and Scaffold Tube Steel L = 1000 Item no. 100706 (x 6).
Complete with
1 pc. 102025 Folding Base Unit 160/190 ASW 6 pc. 102035 Vertical Frame 70/90 ASW 6 pc. 102034 Vertical Frame 70/120 ASW 2 pc. 102026 Entry Platform 190 ASW 1 pc. 102030 Toe-Board Set 70/190 ASW 4 pc. 102027 Double Guardrail 190 ASW 3 pc. 102028 Diagonal Brace 210 ASW 2 pc. 102029 Horizontal Brace 190 ASW 12 pc. 102807 Ballast 10 kg ASW 2 pc. 103040 Lateral complete ASW 1 pc. 102587 Center part ASW galv.
Note
Follow Instructions for Use!
Technical Data
Permissible load 100 kg/m
2
.
2360 1 100
102807
102587
103040
102035
102025
102026
0 5 1 1
102027
102028
100678
102034
102030
102029
97
SKYDECK Panel Slab Formwork
Item no. Weight kg
Handrail Units SD
118331 118323
13.500
18.000
Handrail Unit SD 75 Handrail Unit SD 150
For assembling a Guardrail on a casting segment with SKYDECK. Assembling in a rectangular angle on top of the Main Beams.
750 / 1500 343
7 3 5 1
126630 123.000 Pallet Handrail Unit SD 75
For stacking and transportation of 10 SKYDECK Handrail Units SD 75.
Note
Follow Instructions for Use!
Technical Data
Permissible load-bearing capacity 150 kg.
1995 1030
0 0 1
2115
8 3 0 1
1150
0 5 7
98
Loading...