Pennco NATURAL GAS TO LP User Manual

Page 1
CONVERSION INSTRUCTIONS
NATURAL GAS TO LP (SEA LEVEL TO 2000 FEET)
Cast Iron Gas Fired Water Boilers
15B, BWB, UH15B, GMGWB
For Forced Hot Water
!
WARNING
This conversion kit shall be installed by a qualied
in these instructions is not followed exactly, a re,
an explosion or production of carbon monoxide may result causing property damage, personal injury or
loss of life. The qualied service agency is responsible
for the proper installation of this kit. The installation is not proper and complete until the operation of the
converted appliance is checked as specied in the
manufacturer’s instructions supplied with the kit.
Tools Required
Flat Head Screwdriver, 1/4” Nut Driver, 7/16” Open Ended Wrench, 3/16” Allen Wrench, 18” Manometer (or dial
manometer)
KIT CONTENTS
ITEM QTY.
Installation Instructions 1
Conversion Plate/Label 1
Pilot Orice - Spark 1
Pilot Orice - 24 Volt 1
Liquid Sealing Compound 1
Spring Kit 1
PILOT ORIFICES
MFG. PART NUMBER
Honeywell 390686-36*
*Use 390686-40 for Boilers Manufactured before July 2008 with Q381 Pilot.
Figure 1
Installation
1.
Turn off gas supply to the boiler.
!
WARNING
Electrical shock hazard. Turn OFF electrical power
supply at service panel before making electrical connections. Failure to do so could result in death or serious injury.
2.
Turn off all electrical to boiler.
3.
Remove front panel.
4.
Remove burner access door.
5.
Remove main gas burner tubes. See Figure 1.
6.
Remove main burner orices. See Figure 1.
7.
Install supplied LP gas main burner orices. See Table3 for orice size and quantities.
8.
Use 7/16” wrench, disconnect pilot tube from pilot. See Figure 2.
9.
Remove pilot orice. See Figure 2.
10.
Install LP gas pilot orice. See Figure 2.
11.
Apply liquid sealing compound to threads of pilot assembly tting.
12.
Attach pilot tube to pilot and securely tighten. See Figure 2.
13.
Replace main gas burner tubes.
14.
Remove the cover screw from gas valve pressure
regulator. See Figure 4.
BURNERS
GAS VALVE KNOB
ORIFICES
Figure 2
Pilot
Pilot Orice
Pilot Tube
P/N 24004821, Rev. D [11/2014]
Page 2
NATURAL GAS TO LP CONVERSION INSTRUCTIONS
15.
Remove adjustment screw by turning counterclockwise
. See Figure 4.
16.
Remove stainless steel Natural gas spring. See Figure 4.
NOTICE
Parts for steps 17, 18, 26, and 27 are located in Honeywell LP gas conversion kit HW#393691 for VR8200, VR8204, VR8300 and VR8304 gas valves.
17.
Insert Red LP gas spring. See Figure 4.
18.
Install new adjustment screw. Assure the screw top is ush with the regulator top. See Figure 4.
19.
Turn pressure regulator adjustment screw clockwise
eleven (11) complete turns. (This is starting point
for manifold pressure.)
20.
Install manometer to pressure tap on outlet side of gas
valve. See Figure 3.
21.
Turn electric and gas supply ON.
NOTICE
Gas inlet pressure is between minimum of 11” w.c.and maximum of 14” w.c.
22.
Check for gas leaks around all gas connections using
commercially available soap solution specically made
for leak detection.
!
DANGER
Fire Hazard. Do not use matches, candles, open ames, or other methods providing ignition source.
Failure to comply will result in death or serious injury.
!
CAUTION
WHAT TO DO IF YOU SMELL GAS
Do not try to light any appliance.
Do not touch any electrical switch; do not use any phone in your building.
• Immediately call your gas supplier from a neighbor’s phone. Follow gas supplier’s instructions.
If you cannot reach your gas supplier, call the re department.
Table 3 - MAIN BURNER ORFICES
INPUT (Btuh) ORIFICE QTY.
45,000 47 1
70,000 50 2
96,000 47 2
120,000 49 3
145,000 47 3
170,000
175,000
195,000 47 4
245,000 47 5
295,000 47 6
49 4
Figure 3 - Gas Valve
23.
While boiler is operating adjust manifold pressure
to 11” water column by turning pressure regulator adjustment screw. Check for CO2 and CO levels to
assure proper operation.
24.
Turn OFF electric and gas supply.
25.
Remove manometer. Replace pressure tap cover screw securely.
26.
Install black LP gas regulator adjustment cover screw
with o-ring. See Figure 4.
27.
Mount conversion label on gas valve.
28.
Turn electric and gas supply ON.
29.
Cycle boiler to ensure proper operation and lighting.
30.
Replace front panel.
31.
Fill out and afx conversion plate adjacent to
rating plate. Complete this step to provide proper
identication for customer service or technical support
issues.
2
Page 3
NATURAL GAS TO LP CONVERSION INSTRUCTIONS
Figure 4 - Gas Valve
Figure 5 - Burners, Gas Valve, & Manifold
• Thermostat actuates on call for heat, completing circuit to control.
Completed circuit to control activates circulator. Damper will close end switch inside the damper. This will complete circuit to ignition system and ignition takes place.
• Power is interrupted between control system and ignition system if boiler water temperature exceeds high limit setting on boiler mounted high limit control. Power remains off until boiler water temperature drops below high limit setting. Circulator continues to operate under
this condition until thermostat is satised.
Blocked ow of combustion products through boiler venting system causes blocked vent safety switch to
shut main burner gas off. If boiler ueway becomes blocked, ame rollout safety switch will shut main burner gas off. See Figure 5. If either condition occurs,
do not attempt to place boiler back into operation.
Contact qualied service agency.
Main burner ame should have well dened inner blue mantel with lighter blue outer mantel. See Figure 6.
Pilot ame should envelop ⅜ to ½ inch of tip of the pilot thermocouple, ignition/sensing electrode or mercury
sensor. See Figure 7.
Figure 6 - Burner with Mantel
Checking Gas Input Rate To Boiler
Adjust gas input to boiler by removing protective cap on pressure regulator and turning screw clockwise to increase input and counterclockwise to decrease input.
Set LP gas manifold pressure at approximately 11.0 inches water column. Manifold pressure is taken at outlet side of gas valve.
Check for CO2 and CO levels to assure proper operation.
Change burner ori ces if  nal manifold pressure varies more than plus or minus 0.3 inches water column from
specied pressure.
• Primary air adjustment is not necessary, therefore air
shutters are not furnished as standard equipment. Air
shutters are available on request where required by local codes or conditions.
3
Page 4
Figure 7 - Pilot
3/8” To 1/2”
In Flame
NATURAL GAS TO LP CONVERSION INSTRUCTIONS
Ignition
Electrode