Penberthy Armored Gagecocks - Series 600, Penberthy-EN Manuals & Guides

Page 1
InstallatIon, operatIon and maIntenance InstructIons
Before installation these instructions must be read fully and understood
Emersonwill,at its option, replace or repair any products which fail during the warranty period due to defective material or workmanship.
Prior to submitting any claim for warranty service, the owner must submit proof of purchase to Emerson and obtain written authorization to return the product. Thereafter, the product shall be returned to Emerson, with freight paid.
TABLE OF CONTENTS
Product warranty ................................................ 1
1. About the manual .......................................... 2
2. Introduction ................................................... 2
2.1 System description .................................. 2
3. Available models ........................................... 3
3.1 Design ratings .......................................... 3
4. Inspection ...................................................... 3
4.1 User's rating inspection .......................... 3
5. Installation ..................................................3-4
5.1 Piping strain ............................................. 3
5.2 Differential thermal expansion ............... 4
5.3 Mounting .................................................. 4
6. Operation ....................................................... 4
6.1 Hydrostatic test ........................................ 4
7. Maintenance ...............................................4-5
7.1 Preventative maintenance ...................... 4
7.2 Ball check shut-off .................................. 5
7.3 Troubleshooting ....................................... 5
8. Removal - disassembly - reassembly ......... 6
8.1 Disassembly ............................................. 6
8.2 Reassembly .............................................. 6
9. Disposal at end of useful life ........................ 6
10. Telephone assistance ................................... 6
11. Exploded parts diagram ................................ 7
Tables and figures
Table 1 Design ratings .................................... 3
Figure 1 PTFE tape wrapping ........................... 4
Figure 2 Exploded parts diagram .................... 7
This warranty shall not apply if the product has been disassembled, tampered with, repaired or otherwise altered outside of Emerson's factory, or if it has been subject to misuse, neglect or accident.
The responsibility of Emerson hereunder is limited to repairing or replacing the product at its expense. Emerson shall not be liable for loss, damage or expenses related directly or indirectly to the installation or use of its products or from any other cause or for consequential damages. It is expressly understood that Emerson is not responsible for damage or injury caused to other products, buildings, personnel or property, by reason of the installation or use of its products.
This is Emerson’s sole warranty and in lieu of all other warranties, expressed or implied which are hereby excluded, including in particular all warranties of merchantability or fitness for a particular purpose.
This document and the warranty contained herein may not be modified and no other warranty, expressed or implied, shall be made by or on behalf of Emerson unless made in writing and signed by the company's general manager or director of engineering.
Product warranty
Emerson warrants its Penberthy products as designed and manufactured to be free of defects in the material and workmanship for a period of one year after the date of installation or eighteen months after the date of manufacture, whichever is earliest.
Emerson.com/FinalControl © 2017 Emerson. All rights reserved. VCIOM-04039-EN 18/03
Page 2
InstallatIon, operatIon and maIntenance InstructIons
1 ABOUT THE MANUAL
This manual has been prepared as an aid and guide for personnel involved in installation or maintenance. All instructions must be read and understood thoroughly before attempting any installation, operation, or maintenance.
SAFETY INSTRUCTIONS
Emerson does not have any control over the manner in which its gagecock set is handled, installed or used and Emerson cannot and does not warrant or guarantee that a gagecock set is suitable or compatible for the user's specific application.
WARNING
Vessel fluids may be pressurized and can exit vessel connections unexpectedly due to apparatus or material failure. Safety glasses should be worn when installing a gagecock. Failure to follow any instruction could possibly result in a malfunction of the gagecock with resulting sudden release of pressure, severe physical injury or property damage.
2 INTRODUCTION
Penberthy armored gagecocks are used to isolate gage glass, magnetic gages or other apparatus from the holding or pressure vessel. Penberthy Series 600 gagecocks are supplied in pairs, (upper and lower), and are available with socketweld, flanged and NPT connections. These gagecocks are equipped, as a standard feature, with a floating shank union vessel connection, which permits up to ⅜" (10 mm) variation in center to center distance and with ball check shut-offs to prevent leakage of contained fluid in case of accidental gage glass breakage. Series 600 gagecocks for process use should include ball check shut-off feature. Gagecocks without the ball check shut-off feature will not stop leakage of contained fluid automatically in the event of accidental gage glass breakage.
2.1 System description
Penberthy armored gagecocks comprised six basic components. Each component may vary slightly, depending on the desired physical and mechanical properties for the gagecock. Use the exploded parts view in Section 11 as additional reference material. Body: a pressure retaining structure through which fluid passes to enter a gage glass or other apparatus. Provides a rigid connection to the vessel and seating surfaces for most gagecock components. Series 600 are offset pattern bodies. Ball checks: sphere installed loosely within the body of the gagecock that seats to prevent significant leakage when a differential pressure surge occurs (e.g., mechanical failure). Ball checks are omitted for ASME steam service. Trim: wetted parts that control the fluid path from the vessel to the gage glass or other apparatus mechanically. The ball and stem act to seal and release the fluid. In the event of mechanical failure, the ball will seat to prevent large quantities of the contained fluid from exiting the vessel. Fluid is allowed to exit the vessel into the gage glass or other apparatus when the stem is screwed away from its seated position. The fluid is sealed when the stem is screwed into its seated position.
The bonnet provides a compression surface between the process fluid and the stem packing. A stem packing gland is used to compress the packing against the bonnet and around the stem to prevent leakage. Stem packing: under compression the stem packing is forced to mold around the stem and prevent leakage of media during operation. Gage connection: provides connection between the gagecock and the gage glass or other apparatus. Lever: rotated to engage threads and provide screw action of stem.
2
Page 3
InstallatIon, operatIon and maIntenance InstructIons
3 AVAILABLE MODELS
Series 600 gagecocks are offset pattern gagecocks available with a rigid connection to the gage (Model 630), threaded in renewable seat, backseating stem and an O-ring seal on the vessel tailpipe.
3.1 Design ratings at maximum and minimum operating temperatures (see Table 1)
To determine the maximum allowable working pressure for a specific temperature within the design limits stated below, the user must refer to relevant technical data sheets or, when provided, the specifically stated design limits on a product proposal.
WARNING
NEVER exceed these design ratings or application data. Exceeding design ratings or application data may result in mechanical failure of gagecock components resulting in serious personal injury or property damage.
4 INSPECTION
On receipt of a gagecock set, check all components carefully for damage incurred in shipping. If damage is evident or suspected, do not attempt any installation. Notify the carrier immediately and request a damage inspection. Refer to exploded view drawing in Section 11 toinventory parts.
4.1 User’s rating inspection
The user should confirm that:
1. The gagecock set model number and pressure/temperature rating stamped on nameplate conforms to the description on the user's purchase order.
2. The operating conditions described in the purchase order agree with the actual operating conditions at the installation site.
3. The actual operating conditions at the installation site are within the application data shown on the relevant technical data sheet or product proposal referred to previously.
4. The materials of construction of the gagecock set are compatible with both the contained fluid and the surrounding atmosphere in the specific application.
SAFETY INSTRUCTIONS
If the size, model or performance data of the gagecock as received does not conform with any of the criteria above, do not proceed with installation. Contact an authorized Penberthy distributor for assistance. The use of an incorrect gagecock can result in unacceptable performance and potential damage to the gage.
5 INSTALLATION
Installation should only be undertaken by qualified personnel who are familiar with this equipment. They should have read and understood all of the instructions in this manual. The user should refer to relevant technical data sheets or product proposal to obtain dimensional information for specific size and model gagecock. Recommendations on gagecock installations are not necessarily related to the installation of flat glass liquid level gages. The number of different types of gage and gagecock installations is too great to explain adequately in an installation manual. Therefore, it is the user's responsibility to assure that knowledgeable installation personnel plan and carry out the installation in a safe manner. The following are some of the guidelines that should be employed:
5.1 Piping strain
The gagecock should be mounted and connected so that it can support the gage without binding. Torsional stresses can make it difficult or impossible to seal tailpipes. Although union connections will allow marginal errors in piping alignment, misalignment can still create unusual strain on connectors. Gages not properly supported by brackets may subject the gagecock to stresses that can cause leaks or mechanical failure. Typical gage load should NOT exceed 50 lbs (22.7 kg) per gagecock.
TABLE 1 - DESIGN RATINGS AT MAXIMUM AND MINIMUM OPERATING TEMPERATURES
Maximum allowable working pressure
Material of construction
Carbon steel 316 STS
6000 psig (41370 kPa) at -20°F (-29°C) to +400°F (204°C) 6000 psig (41370 kPa) at -20°F (-29°C) to +400°F (204°C)
Carbonite packing w/FKM O-ring PTFE packing w/PTFE O-ring
6000 psig (41370 kPa) at -20°F (-29°C) to +500°F (260°C)
6000 psig (41370 kPa) at -325°F (-199°C) to +500°F (260°C)
3
Page 4
InstallatIon, operatIon and maIntenance InstructIons
5.2 Differential thermal expansion
High mechanical loading may be imposed on a gagecock by expanding and contracting gages due to hot or cold service. Such mechanical loads on the gagecock must be minimized by controlling process conditions in the system or by using expansion loops.
5.3 Mounting
1. Prior to installation, turn the handwheel of each gagecock clockwise until the stem closes against the seat.
2. Wrench tighten tailpipes of upper and lower gagecocks to the vessel using PTFE tape, or equivalent, on all male tapered pipe thread connections as shown in Figure 1. If the gagecock is flanged or weld mount, use proper industry standard procedures.
3. If installing with a flat glass gage, follow all installation instructions for the specific liquid level gage as there are many points to consider on gage installation; among them, piping strain, differential thermal expansion, weight and bolt torque.
6 OPERATION
Before initializing gagecock operation, check that all installation procedures have been completed. Use only qualified, experienced personnel who are familiar with gagecock equipment and thoroughly understand the implications of the tables and all the instructions. Check to determine that all connections are pressure tight.
WARNING
Gagecock installations should be brought into service slowly. Gagecocks should be opened slightly, and the gagecock assembly temperature and pressure allowed to equalize slowly. If the gagecocks are equipped with ball checks, the gagecocks must be opened all the way after the pressure and temperature have equalized to permit operation of the automatic ball check in the event of gage glass failure. Failure to follow the recommended operating procedures can result in severe personal injury or property damage.
6.1 Hydrostatic test
Take all precautions necessary to handle the possibility of leakage during the test. Hydrostatic pressure test all installations to 100psig (690 kPa) and correct any leakage before proceeding.
7 MAINTENANCE
WARNING
Use only qualified, experienced personnel who are familiar with gagecock equipment and thoroughly understand the implications of the tables and all the instructions. DO NOT proceed with any maintenance unless the gagecock assembly has been relieved of all pressure or vacuum, has been allowed to reach ambient temperature and has been drained or purged of all fluids. Failure to do so can cause serious personal injury and property damage.
The user must create maintenance schedules, safety manuals and inspection details for each gagecock. These will be based upon the users own operating experience with their specific application. Realistic maintenance schedules can only be determined with full knowledge of the services and application situations involved. During system shutdown, the gagecocks should be left open to permit the gage to lose pressure and cool with the rest of the system. Failure to leave the gagecock open during system shutdown may trap high-pressure fluid in thegage.
7.1 Preventative maintenance
On all installations, the following items should be evaluated regularly by the user for purposes of maintenance:
1. Leakage around stem area.
2. Internal stem leak.
3. Leakage around union vessel connections.
4. Internal or external corrosion.
The user must determine an appropriate maintenance schedule necessary for his or her specific application upon evaluation of their own operating experience. Realistic maintenance schedules can only be determined with full knowledge of the services and application situation involved.
FIGURE 1
PTFE tape
Direction of wrap
4
Page 5
InstallatIon, operatIon and maIntenance InstructIons
7.2 Ball check shut-off
SAFETY INSTRUCTIONS
Ball checks, when installed, may fail to seat due to corrosion of the ball or seat, foreign material in ball chamber or viscous material in the ball chamber. A routine operational test of the ball check can prevent significant seepage of liquid inthe event of glass breakage.
An operational check can be performed on the gagecock ball check by closing both the upper and lower gagecock stems completely. Drain contents from and relieve pressure on liquid gage to an appropriate safe container/area. Note: some loss of process fluid to the drain line is expected with this test procedure.
WARNING
Use only qualified, experienced personnel who are familiar with gagecock equipment and thoroughly understand the implications of the tables and all the instructions. DO NOT proceed with any maintenance unless the gagecock assembly has been relieved of all pressure or vacuum, has been allowed to reach ambient temperature and has been drained or purged of all fluids. Failure to do so can cause serious personal injury and property damage.
With the drain line in place, open the BOTTOM gagecock as rapidly as possible. Listen for 'click' sound, which will indicate that the ball has seated. If possible, observe the quantity of flow from the drain line. Flow should either stop completely or be no greater than single drips (no solid stream). Close lower gagecock. Repeat above procedure for UPPER gagecock. There must be a pressure differential of at least 5 psig (35 kPa) for the above procedure to work properly. If the above procedure is not successful, the only alternative is to isolate the gage and gagecock assembly from the vessel or to shut the process down completely. Disassemble the gagecock as outlined in Section 8.1 using the exploded parts drawing in Section 11 as a reference. Visibly inspect ball check and ball seats in the gagecock body. Remove any foreign matter and/or replace with new ball checks if inspection indicates this is required. If the ball seat is damaged, consider replacing the gagecock or the seat. Reassemble gagecocks as outlined in Section 8.2.
7.3 Troubleshooting Stem packing leakage can often be stopped
by tightening the stem packing nut. If leakage persists, the stem packing should be replaced by following steps 1) through 5) of the Disassembly and 1) through 7) of the Reassembly instructions.
Internal seat leakage is an indication of a worn or damaged stem or seat. To replace the stem follow steps 1) through 5) of the Disassembly and 1) through 7) of the Reassembly instructions. To replace the seat , follow steps
1) through 3) of the Disassembly and 3) through
7) of the Reassembly instructions. Remove the seat by inserting a ¼" (6 mm) square driver in the seat and turning it counterclockwise. Install the new seat by turning it clockwise using the square driver, making sure that the ball check, if used, is replaced in the body. Tighten the seat in place.
Leakage around union connections can often be stopped by tightening union coupling nut or remaking the connection using PTFE tape, or equivalent, on all male pipe threads as shown in Figure 1.
Internal or external corrosion could be an indication of a misapplication. An investigation should be carried out immediately to determine the cause of the problem. It is the user's responsibility to choose a material of construction compatible with both the contained fluid and the surrounding atmosphere.
5
Page 6
InstallatIon, operatIon and maIntenance InstructIons
8 REMOVAL - DISASSEMBLY - REASSEMBLY
WARNING
Use only qualified, experienced personnel who are familiar with illuminators and thoroughly understand the implications of the tables and all the instructions. DO NOT proceed with any maintenance unless the gage assembly has been relieved of all pressure or vacuum, has been allowed to reach ambient temperature, has been drained or purged of all fluids and the electrical power has been turned off. Failure to do so can cause death, serious personal injury or property damage.
8.1 Disassembly
Refer to the exploded parts drawing in Section11 for additional reference during disassembly and reassembly of the gagecocks.
1. Remove lever screw (100) and lever (261) from stem.
2. Loosen and remove stem packing nut (26) and stem packing gland (19).
3. Loosen and remove bonnet coupling nut (21) and bonnet (20).
4. Remove stem (17) from bonnet (20) by turning clockwise through the bonnet.
5. Remove stem packing (25) from bonnet (20).
6. To replace seat (16), follow instructions as described in maintenance procedures, Section 7.3.
8.2 Reassembly
Refer to the exploded parts drawing in Section11 for additional reference during disassembly and reassembly of the gagecocks.
1. Prepare for installation of new packing by cleaning all packing chambers and glands of upper and lower gagecocks.
2. Replace stem (17) in bonnet (20) by turning in a counter clockwise direction.
3. Replace bonnet (20) and bonnet coupling nut(21) and tighten securely in place.
4. Install new stem packing (25) and stem packing gland (19).
5. Assemble stem packing nut (26) and tighten in place.
6. Assemble lever (261) and lever screw (100) on stem and tighten securely in place.
7. Close both gagecocks by turning lever clockwise until stem seats.
A Material Safety Data Sheet (MSDS) may be required before disposal services accept certain components. Metal, glass and polymers should be recycled whenever possible. Refer to order and applicable technical data sheets for materials of construction.
10 TELEPHONE ASSISTANCE
If you are having difficulty with your Penberthy Series 600 gagecocks, contact your local Penberthy distributor.You may also contact the factory direct at (956) 430-2500 and ask for an applications engineer. So that we may assist you more effectively, please have as much of the following information available as possible when you call:  Model #  Name of the company from whom you
purchased the Penberthy Series 600
gagecocks  Invoice # and date  Process conditions (pressure, flow rates,
tankshape, etc)  A brief description of the problem  Trouble shooting procedures that failed
If attempts to solve your problem fail, you may request to return your gagecock to the factory for intensive testing. You must obtain a Return Authorization (R.A.) number from Emerson before returning anything. Failure to do so will result in the unit being returned to you without being tested, freight collect. To obtain an R.A. number, the following information (in addition to that above) is needed:  Reason for return  Person to contact at your company  'Ship-to' address
There is a minimum charge for evaluation of non-warranty units. You will be contacted before any repairs are initiated should the cost exceed the minimum charge. If you return a unit under warranty, but it is not defective, the minimum charge will apply.
NOTE
Carbonite is manufactured by John Crane, Inc.
Refer to Section 6 for operation of the gagecock when returned to service.
9 DISPOSAL AT END OF USEFUL LIFE
Penberthy Series 600 gagecocks are used in a variety of fluid applications. By following the appropriate federal and industry regulations, the user must determine the extent of preparation and treatment the Series 600 gagecocks must incur before their disposal.
6
Page 7
InstallatIon, operatIon and maIntenance InstructIons
11 EXPLODED PARTS DIAGRAM
FIGURE 2
PARTS LIST
Item Description
11 Body 12 Tailpipe, vessel 13 Nut, vessel coupling 14 Retainer, ball check 15 Ball 16 Seat 17 Stem 19 Gland, stem packing 20 Bonnet 21 Nut, bonnet 25 Packing, stem 26 Nut, stem packing 39 O-ring 100 Screw, lever 163 Nameplate 261 Lever
RECOMMENDED SPARE PARTS
Item Description Min. qty.
19 Gland, stem packing 1 25 Packing, stem 4
Neither Emerson, Emerson Automation Solutions, nor any of their affiliated entities assumes responsibility for the selection, use or maintenance of any product. Responsibility for proper selection, use, and maintenance of any product remains solely with the purchaser and end user.
Penberthy is a mark owned by one of the companies in the Emerson Automation Solutions business unit of Emerson Electric Co. Emerson Automation Solutions, Emerson and the Emerson logo are trademarks and service marks of Emerson Electric Co. All other marks are the property of their respective owners.
The contents of this publication are presented for informational purposes only, and while every effort has been made to ensure their accuracy, they are not to be construed as warranties or guarantees, express or implied, regarding the products or services described herein or their use or applicability. All sales are governed by our terms and conditions, which are available upon request. We reserve the right to modify or improve the designs or specifications of such products at any time without notice.
Emerson.com/FinalControl