Page 2
© PCE Instruments
Contents
1 Safety notes ........................................................................................... 1
2 Specifications ........................................................................................ 2
3 Delivery scope ....................................................................................... 2
4 Device description ................................................................................ 3
4.1 Display description ........................................................................................................... 5
4.2 Connections ..................................................................................................................... 6
5 Switch the meter on and off ................................................................. 6
6 Set zero point ........................................................................................ 7
7 Wiring diagram ...................................................................................... 8
8 Make a measurement ............................................................................ 8
8.1 Settings ............................................................................................................................ 9
8.2 Automatic total measurement ..........................................................................................10
8.3 Manual total measurement ..............................................................................................10
8.4 Single-point measurement ...............................................................................................11
9 Data recording ..................................................................................... 11
10 Clear memory ...................................................................................... 11
11 Replace battery ................................................................................... 12
12 Replace fuse ........................................................................................ 12
13 Software ............................................................................................... 13
13.1 Display measured values ................................................................................................14
13.2 Settings ...........................................................................................................................14
13.3 General view of all measurements ..................................................................................15
14 Contact ................................................................................................. 16
15 Disposal ............................................................................................... 16
Page 3
© PCE Instruments
1
1 Safety notes
Please read this manual carefully and completely before you use the device for the first time. The device may only be used by qualified personnel and repaired by PCE Instruments personnel. Damage or injuries caused by non-observance of the manual are excluded from our liability and not covered by our warranty.
The device must only be used as described in this instruction manual. If used otherwise, this can cause dangerous situations for the user and damage to the meter.
The instrument may only be used if the environmental conditions (temperature, relative
humidity, …) are within the ranges stated in the technical specifications. Do not expose
the device to extreme temperatures, direct sunlight, extreme humidity or moisture.
Do not expose the device to shocks or strong vibrations.
The case should only be opened by qualified PCE Instruments personnel.
Never use the instrument when your hands are wet.
You must not make any technical changes to the device.
The appliance should only be cleaned with a damp cloth. Use only pH-neutral cleaner,
no abrasives or solvents.
The device must only be used with accessories from PCE Instruments or equivalent.
Before each use, inspect the case for visible damage. If any damage is visible, do not
use the device.
Do not use the instrument in explosive atmospheres.
The measurement range as stated in the specifications must not be exceeded under
any circumstances.
Ensure that the fans are not covered and can cool completely.
Non-observance of the safety notes can cause damage to the device and injuries to
the user.
We do not assume liability for printing errors or any other mistakes in this manual. We expressly point to our general guarantee terms which can be found in our general terms of
business.
Page 4
© PCE Instruments
2
2 Specifications
DC voltage
Measurement range
Resolution
Accuracy
0 ... 10 V
0.001 V
±1 % ±(1 % of Vopen ±0.1 V)
10 ... 60 V
0.1 V
±1 % ±(1 % of Vopen ±0.1 V)
Vopen: open voltage measurement on a solar module
Direct current
Measurement range
Resolution
Accuracy
0.01 ... 10 A
1 mA
±1 % ±(1 % of Ishort ±9 mA)
10 ... 12 A
10 mA
±1 % ±(1 % of Ishort ±0.09 A)
Ishort: short-circuit current of a solar cell
Further specifications
Adjustable photovoltaic surface
0.001 ... 9999 m² Adjustable light intensity
10 ... 1000 W/m²
Display
4.8" LC display
Fuse
F250 V, 12 A
Data memory
100 measurements
Storage rate
0 ... 99 minutes
Battery life
approx. 400 linear measurements from 60 ... 0 V and 0 ... 12 A
Power supply battery
11.1 V, 3400 mAh lithium battery
Power supply mains adaptor
primary: 100 ... 240 V AC 50/60 Hz secondary: 15 V DC / 3A
Degree of pollution
2
Temperature coefficient
0.1 % of the measurement range / °C at temperatures <18 °C / 64 °F and >28 °C / 82 °F
Operating conditions
5 ... 50 °C, <85 % RH, non-condensing
Storage conditions
-20 ... 60 °C / -4 ... 140 °F, <75 % RH, non-condensing
Dimensions
257 x 155 x 57 mm / 10.1 x 6.1 x 2.2 in
Weight
1160 g / 2.6 lbs
3 Delivery scope
1 x solar measuring device PCE-PVA 100 1 x optical USB cable 1 x battery 1 x software CD 1 x pair of Kelvin clamps 1 x pair of safety test leads (100 mm) 1 x mains adaptor 1 x user manual
Page 5
© PCE Instruments
3
4 Device description
Page 6
© PCE Instruments
4
No.
Key
Description
1 No function
2 No function
3 Set zero point for voltage and current 4 Audible alarm for insufficient power
5 Change graphical view P-V P-I P-V-I (both graphics)
6 One-point test based on the settings and voltage measurement
7 Manual scan based on the settings
8 Automatic scan
9 LC display
10 Open and close settings
11 Graphics: Move cursor to the left Menu: Reduce value
12 Menu: Parameter upwards
13 Menu: Parameters downwards
14 Graphics: Move cursor to the right Menu: Increase value
15 No function
16 No function
17 Press briefly: Start and stop data logging Long press: Delete data memory
18 Show and hide grid
19 Change graphical view I-V V-I
20 Switch on and off
Page 7
© PCE Instruments
5
4.1 Display description
No.
Description
1
Connection for the optical USB cable
2
Tripod
3
Battery
4
Screw for the battery holder
5
Mains adaptor connection
Page 8
© PCE Instruments
6
4.2 Connections
No.
Description
1
Voltage input
2
Power input
3
Voltage output
4
Current output
5 Switch the meter on and off
To switch the meter on or off, briefly press the key once. If the meter overheats, it should remain active until it has cooled down.
Page 9
© PCE Instruments
7
6 Set zero point
The zero point of the test leads should be reset before a measurement. To do this, short-circuit
all measuring connections and press the key. ZERO CAL ..." appears on the display. As soon as the message disappears, a normal measurement can be started.
Page 10
© PCE Instruments
8
7 Wiring diagram
The meter is connected according to the following connection diagram:
8 Make a measurement
During the measurement, make sure that the fans are not covered to ensure sufficient cooling capacity. If the meter overheats, this is indicated by "Overheated:cooling". As long as this message is displayed, no measurement can be carried out. If the instrument is switched off during the cooling phase, you must wait at least three more minutes until cooling is complete. It is therefore advisable to allow the meter to cool down first before switching it off.
The mains adaptor must not be connected to the meter during a measurement.
Page 11
© PCE Instruments
9
8.1 Settings
To make settings, briefly press the key once to open the settings. Use the arrow keys to select the desired parameter and you can edit it directly. The value is adopted directly. Press the
key again to return to measurement mode.
Menu
Description
Time Delay before scan
Waiting time between individual measurements
Sampling Time of Datalogging
Storage rate in minutes
Current Range of Scan begin
Initial current value for "Scan" mode Note: If this value is higher than Ishort, no measurement is possible.
Current Range of Scan end
Final current value for "Scan" mode
Area of Solar Cell of Panel
Surface area of the solar cells
Irradiance
Light intensity in W/m²
Single test point
Setting the measuring point of the single-point measurement
Alarm of Low Power
Setting the alarm limit value when the power falls below the limit. Maximum value: 500 W
Year/Month/Date/Hour/Minute/Second
Setting the date and time. Minutes and seconds cannot be set
Page 12
© PCE Instruments
10
8.2 Automatic total measurement
This measurement gives you a rough overview of the solar cell. To carry out an automatic measurement, press the key. Connect the test lead before the
measurement.
8.3 Manual total measurement
After the automatic measurement, you can enter the start and end values of the current measurement in the settings and start a measurement. Once the settings have been made, the
measurement can be started using the key. Note: If the short-circuit current exceeds the set measurement range, a measurement is not possible.
Page 13
© PCE Instruments
11
8.4 Single-point measurement
The single-point measurement is useful when the values for a specific current value need to be determined. This has the advantage that the measurement can be carried out quickly. The measuring point is selected in the settings. Once the measuring point has been set, the
measurement can be carried out using the key. The measurement result is shown at the bottom right of the display.
TestP TestV TestA
9 Data recording
To start data recording, briefly press the key once. The meter now automatically carries out the automatic measurement at the set measurement interval. To cancel data logging, press the key again.
10 Clear memory
To clear the entire memory, first switch off the meter. Then press and hold the key and then press the key to switch on the meter. You will hear a long beep. Now release all
keys. The memory is deleted and you can resume operation.
Page 14
© PCE Instruments
12
11 Replace battery
To replace the battery, disconnect the meter from all test leads and switch it off. You can then loosen the battery using the battery compartment screw. Once you have loosened the screw, you can remove the battery with its housing and replace it by a new one. Pay attention to the connector plug. Once you have replaced the battery and refitted it securely, you can use the meter again.
12 Replace fuse
To replace the fuse, the test leads must first be disconnected from the meter. The meter must then be switched off and the battery removed. The housing must now be opened to access the fuse. There are two screws to loosen at the top on the back and two screws in the battery compartment. The housing can then be lifted. Pay attention to the battery cable when opening. The fuse is located above the sensor system. Replace the fuse with a 15A / 250V fuse. Then re­assembe the meter. It can then be used again.
Page 15
© PCE Instruments
13
13 Software
To transfer the measured values from the meter to the PC, first install the software and the corresponding driver. You can download these here if necessary:
https://www.pce-instruments.com/deutsch/download-win_4.htm
To ensure proper use of the software, we recommend that you always install and start the software with administrator rights.
After installation, you can connect the USB cable to the PC and the meter and read out the measured values.
Symbol
Function
Connect to the meter
Reset view
Call up saved measurement
Save the raw data
Save measured values as csv or tab file
Print current view
Set the date and time in the meter
Mirror the current image from the meter on the PC (no live view)
Transfer saved measurement data to the PC
Delete memory
Perform automatic measurement
Perform automatic measurement with quantity
Perform manual measurement
Page 16
© PCE Instruments
14
13.1 Display measured values
All measurements can be viewed individually in the "Information" window. The characteristic curve is displayed in the first area. From there, each individual measuring point can be approached using the mouse. The respective measured values are displayed in the third area. The axes can be adjusted if required. The measured values are displayed in the second area. In the fourth area, you can switch between the individual measurements.
13.2 Settings
Measurement settings can be made in the "Parameter" field. Load" transfers the current settings from the measuring device to the software. A specific value is transferred with "Apply". "Apply All" transfers all settings.
Page 17
© PCE Instruments
15
13.3 General view of all measurements
All measurements are summarised in the "Overall" field. All measured values are displayed graphically in the first area. All measured values for the selected measurement are displayed in the second area.
Page 18
© PCE Instruments
16
14 Contact
If you have any questions, suggestions or technical problems, please do not hesitate to contact us. You will find the relevant contact information at the end of this user manual.
15 Disposal
For the disposal of batteries in the EU, the 2006/66/EC directive of the European Parliament applies. Due to the contained pollutants, batteries must not be disposed of as household waste. They must be given to collection points designed for that purpose.
In order to comply with the EU directive 2012/19/EU we take our devices back. We either re-use them or give them to a recycling company which disposes of the devices in line with law.
For countries outside the EU, batteries and devices should be disposed of in accordance with your local waste regulations.
If you have any questions, please contact PCE Instruments.
Page 19
© PCE Instruments
17
PCE Instruments contact information
Germany France Spain
PCE Deutschland GmbH PCE Instruments France EURL PCE Ibérica S.L. Im Langel 26 23, rue de Strasbourg Calle Mula, 8 D-59872 Meschede 67250 Soultz-Sous-Forets 02500 Tobarra (Albacete) Deutschland France España Tel.: +49 (0) 2903 976 99 0 Téléphone: +33 (0) 972 3537 17 Tel. : +34 967 543 548 Fax: +49 (0) 2903 976 99 29 Numéro de fax: +33 (0) 972 3537 18 Fax: +34 967 543 542 info@pce-instruments.com info@pce-france.fr info@pce-iberica.es www.pce-instruments.com/deutsch www.pce-instruments.com/french www.pce-instruments.com/espanol
United Kingdom Italy Turkey
PCE Instruments UK Ltd PCE Italia s.r.l. PCE Teknik Cihazları Ltd.Şti. Trafford House Via Pesciatina 878 / B-Interno 6 Halkalı Merkez Mah. Chester Rd, Old Trafford 55010 Loc. Gragnano Pehlivan Sok. No.6/C Manchester M32 0RS Capannori (Lucca) 34303 Küçükçekmece - İstanbul United Kingdom Italia Türkiye Tel: +44 (0) 161 464902 0 Telefono: +39 0583 975 114 Tel: 0212 471 11 47 Fax: +44 (0) 161 464902 9 Fax: +39 0583 974 824 Faks: 0212 705 53 93 info@pce-instruments.co.uk info@pce-italia.it info@pce-cihazlari.com.tr www.pce-instruments.com/english www.pce-instruments.com/italiano www.pce-instruments.com/turkish
The Netherlands United States of America Denmark
PCE Brookhuis B.V. PCE Americas Inc. PCE Instruments Denmark ApS Institutenweg 15 1201 Jupiter Park Drive, Suite 8 Birk Centerpark 40 7521 PH Enschede Jupiter / Palm Beach 7400 Herning Nederland 33458 FL Denmark Telefoon: +31 (0)53 737 01 92 USA Tel.: +45 70 30 53 08 info@pcebenelux.nl Tel: +1 (561) 320-9162 kontakt@pce-instruments.com www.pce-instruments.com/dutch Fax: +1 (561) 320-9176 www.pce-instruments.com/dansk info@pce-americas.com www.pce-instruments.com/us
Loading...