Panduit PXPCB4 Installation Manual

Page 1
Panduit Cross Connect System
PXMT50
PXDR
PXLK-VI
PXPCB4
PXPCB5
Tools Needed:
CWST
CJAST
Punchdown Tool PDT110 with Cross Connect Blade 10665000 (not supplied by Panduit)
PDT110
Fig. 1
Fig. 2
TOP
#8-3/4" wood screws
Part Numbers: PXMT300, PXMT50, PXPCB4, PXPCB5, PXDR, PXLK-VI
© Panduit Corp. 2013
INSTALLATION INSTRUCTIONS
This product is to be installed in a secured location per TIA standards.
Cross Connect Layouts
PN498B
Draw Position Lines on Wall or Mounting Surface
Draw lines as shown in Fig. 1 to guide placement of the first base. Use a level and measure the shown distances.
Mounting the First Base
Align the base with the position lines and fasten the base to the wall using #8-3/4" wood screws.
When using a false wall, cut out holes before installing the bases.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 1 of 8
Page 2
© Panduit Corp. 2013
Fig. 3
Base 1
Rings
Base 2
Fig. 5
Ta k- Ty Hook & Loop Cable Tie
Fig. 4
INSTALLATION INSTRUCTIONS
Attachment of Addition Bases
Engage the second base into the first base using two rings. Secure the second base using #8-32" wood screws.
Horizontal and vertical rings should be used to position additional bases.
Additional bases and rings should be installed as needed per typical industry practices.
Secure rings with wood screws where needed.
PN498B
4-Pair Cable Installation
(See page 6 for 25-Pair Cable Installation)
Routing the Cables
Start by routing the cable bundle for the lower base.
Attach the bundle to the center cable mount on the right side of the upper base using a Tak-Ty Hook & Loop Cable Tie.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 2 of 8
Page 3
© Panduit Corp. 2013
Fig. 6
Tak-Ty Hook & Loop Cable Tie
Fig. 7
Color code
Pair 1
Pair 24
Blank pair
WH/ BU WH/ OR BU OR
WH/GRGR WH/BRBR
Color code
Fig. 8
INSTALLATION INSTRUCTIONS
Route the upper base cable bundle next.
Using a Tak-Ty Hook & Loop Cable Tie, secure both upper and lower cable bundles at the top cable mount location as shown.
PN498B
Connector Block Termination
Snap connector block into the second position from the top of the upper base. Orient the connector by aligning the color code shown below.
Spread out each cable to the correct connector location. While keeping the cable tight to the connector locations, mark each cable. This will be the mark to strip the cable jacket to in the next step.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 3 of 8
Page 4
© Panduit Corp. 2013
Fig. 9
Fig. 10
Cutting blade
edge
Fig. 11
Fig. 12
WH/ BU WH/ OR BU OR
WH/GRGR WH/BRBR
Color code
INSTALLATION INSTRUCTIONS
Using the CJAST tool, strip each cable to the marks you made in the previous step.
Using the CWST tool, trim off the excess strength member and rip cord.
PN498B
CJAST
CWST
Position conductors over the pair splitter into the connector slots with matching color code.
Punchdown each conductor using punchdown tool.
Properly orient the tool blade so the cutting edge is on the bottom as shown.
PDT110
Cross Connect Blade 10665000
(not supplied by Panduit)
Remove connector block, rotate, and place into the top position of the base.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 4 of 8
Page 5
© Panduit Corp. 2013
Fig. 14
Fig. 13
INSTALLATION INSTRUCTIONS
Place the next connector block into the third position down from the top and terminate as previously described.
After terminated, rotate the connector block up into the second position from the top.
Repeat this process for remaining connector blocks and cables.
Labeling and Cross Connect Wiring
Mark identification labels.
Apply label to the front face of the label holder.
Install label holders onto the base. Label holders snap into position between upper and lower connector blocks as shown.
PN498B
Label Holder
Label
Install cross connect wires according to the engineering work plan.
Route wires through the horizontal rings to the second location leaving 3" of slack. Wire ends should always face towards the label.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 5 of 8
Page 6
© Panduit Corp. 2013
Fig. 17
Ta k- Ty Hook & Loop Cable Tie
Fig. 16
Tak-Ty Hook & Loop Cable Tie
Slack
Fig. 15
INSTALLATION INSTRUCTIONS
25-Pair Cable Installation
(See page 2 for 4-Pair Cable Installation)
NOTE: The following procedure is a quick and simple method for installing high performance data cable. Traditional installation methods are also acceptable; however, the following steps must be utilized.
1. Place a cable tie through the slot on the connector block.
2. Leave approx 7" of wire slack from the end of the cable sheath to the cable tie.
3. Lay the bundle along the top of the connector block as shown and lightly fasten the cable tie. Leave approx 50% space.
4. After termination, dress the wire bundle in the space between the connectors and into the back of the base as needed.
Routing the Cables
Start by routing the cable bundle for the lower base.
Attach the bundle to the center cable mount on the right side of the upper base using a Tak-Ty Hook & Loop Cable Tie.
PN498B
Route the upper base cable bundle next.
Using a Tak-Ty Hook & Loop Cable Tie, secure both upper and lower cable bundles at the top cable mount location as shown.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 6 of 8
Page 7
© Panduit Corp. 2013
Fig. 20
Fig. 18
Pair 1
Pair 25
Left side
Fig. 19
Fig. 21
Cutting blade
edge
INSTALLATION INSTRUCTIONS
Locate the appropriate cable from the center of the base.
Trim off a small portion of the jacket to expose the rip cord. Pull the rip cord until the slit is level with the first position of the upper base as shown.
Remove excess jacket and rip cord.
Install connector block into the second position from the top of the upper base.
PN498B
Insert wires per engineering work plan.
Punchdown each conductor using punchdown tool. Properly orient the tool blade so the cutting edge is on the bottom as shown.
PDT110
Cross Connect Blade 10665000
(not supplied by Panduit)
Remove connector block, rotate, and place into the first position of the base.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 7 of 8
Page 8
© Panduit Corp. 2013
Fig. 22
Fig. 24
Fig. 23
INSTALLATION INSTRUCTIONS
Lower the trim line to the second position from the top of the base and strip the cable.
Place next connector block in the third position down from the top of the base and terminate as previously described.
After terminated, rotate the connector block up into the second position.
Repeat steps for remaining connectors and cables.
PN498B
Labeling and Cross Connect Wiring
Mark identification labels.
Apply label to the front face of the label holder.
Install label holders onto the base. Label holders snap into position between upper and lower connector blocks as shown.
Label Holder
Label
Install cross connect wires according to the engineering work plan.
Route wires through the horizontal rings to the second location leaving 3" of slack. Wire ends should always face towards the label.
For Instructions in Local Languages
and Technical Support:
www.panduit.com/resources/install_maintain.asp