INSTALLATION INSTRUCTIONS
Pull back braid as shown. Remove foil and any cable
Splice
Seal options
Select appropriate seal according to the cable diameter.
Lock nut
Seal
IndustrialNet M12 D-Code
Field Terminable Plug
Part Number: ISPS5E44MFA
Splice element
Connector housing
Remove cable jacket.
1 2 3 4
WH/O WH/G O G
Braid
Slide screw cap and seal onto the cable. The seal
should be flush with the end of the cable jacket.
For Technical Support: www.panduit.com/resources/install_maintain.asp
element
fillers. Untwist wires back as far as seal and straighten.
Insert wires into the splice element according to the
wiring chart.
Page 1 of 2

© Panduit Corp. 2014
INSTALLATION INSTRUCTIONS
Push splice element onto braid and seal. Trim off excess
Align connector housing properly and push onto the
While holding the connecting housing end firmly, twist
braid material and cut conductors flush with the splice
element.
ATTENTION: Ensure no braid material is caught
between the key of the seal and slot of splicing element.
housing
splice element.
Lock nut
only the lock nut until fully tightened. Use of 13mm and
17mm open end wrenches may be used to fully seat the
o-ring gasket.
1. For reconnection, cut off the used cable end and repeat steps 2-7.
2. The seal must be replac ed when wor n.
3. Connector may be re-terminated 10 times with the same or larger cable conductor diameter.
For Instructions in Local Languages