GP6 PLUS Standard Density Tower Kit
Part Number: GPKT724Y
© Panduit Corp. 2014
INSTALLATION INSTRUCTIONS
CABLE REQUIREMENT: Terminates most 22-26 AWG solid or stranded
IWC wire with a 0.050" (1.27mm) max. o.d., either PVC or Plenum rated.
1. Mount tower to wall using #12 wood screws (not provided) or
equivalent. Some applications will require different mounting
hardware. Ensure that the bottom of the tower is at least 8" from
the floor to provide space for horizontal cable manager trough.
PN259D
2. Route cable bundle into tower and fan out individual cables
into their appropriate positions through the cutouts provided
along the tower leaving 12" to 18" of slack. Each cutout
accommodates up to 6, 4 pair cables. Use cable ties to secure
bundle to raised tabs on back of tower.
3. Position base over slots in tower and secure with two #12
sheet metal screws (supplied). Place conductors into index
strip and install connecting blocks as per instruction sheet
PN153* (provided).
SCREW HERE
4. Install jumper troughs between bases with two #12 sheet
metal screws (supplied).
SCREW HERE
* Denotes instruction sheet revision letter.
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 2 of 3

© Panduit Corp. 2014
INSTALLATION INSTRUCTIONS
CABLE REQUIREMENT: Terminates most 22-26 AWG solid or stranded
IWC wire with a 0.050" (1.27mm) max. o.d., either PVC or Plenum rated.
5. To help contain cross-connections, install vertical cable managers (P110VCM300) adjacent to towers using #12 wood screws
(not provided) or equivalent.
Attach horizontal cable manager trough to towers and vertical cable managers using #12 sheet metal screws and #12 external tooth
lock washers (provided). Fasten securely to assure grounding. Attach ground lug (P/N:LAM2A2/0-14-6) with 1/4" x 3/4" machine screw,
nut, and 1/4" external tooth lock washer (provided), to the bottom of the horizontal cable manager trough.
PN259D
Component Quantity per Tower System
Base
Part Number
GPB24
GPKT724Y 3
Trough
P110JT
3
Connecting Blocks
GPCB4
72
Label Holders
P110LH
6
INSTALLATION TIPS:
1. GP6 PLUS product terminates most 22-26 AWG solid or stranded IWC wire with a 0.050” (1.27mm) max. o.d., either PVC or Plenum rated.
2. Never install wire into a slot previously used for a larger gauge.
3. Be careful to strip back cable jacket only as required for termination.
4. Use care to maintain pair twists up to the termination strip.
5. When stripping cable jacket, be careful not to cut the insulation on the individual wires.
6. Avoid sharp bends when routing cable.
As with all Wiring Accessories, the following statements apply:
1. Never install communications wiring during a lightning storm.
2. Never install communications wiring in wet locations unless the product is specifically designed for use in wet locations.
3. Never touch uninsulated communications wiring or terminals unless the communication line has been disconnected at the network interface.
4. Use caution when installing or modifying communication wiring.
For Instructions in Local Languages
and Technical Support:
www.panduit.com/resources/install_maintain.asp
www.panduit.com
Page 3 of 3
E-mail:
techsupport@panduit.com
Phone:
866-405-6654
Labels
DSLGP
6