45° Left/Right UTP TG Modular Jacks & Wire Caps
STANDARD
CJ%%88TG**
SPRING SHUTTERED
CJH%%88TG**
KEYED
CJK%%88TG**
CORROSION RESISTANT
CJE%%88TG**
Compatible Jack Modules
45° ANGLED JACK
CJLR%%88TG**,
CJLR%%88TG-24
(CAT 6 & 6A ONLY)
IMPORTANT!: Determine the desired direction of cable before wiring the cap. The cap, in relation
to the jack, must be kept consistent throughout the entire termination.
Understanding the Label
Left Orientation
Right Orientation
Follow solid line
instructions for
Left Orientation.
(Pages 2-3)
Follow dotted line
instructions for
Right Orientation.
(Pages 4-5)
Category 6A
(CJLRCAPBU-^)
Category 6
(CJLRCAPIW-^)
Category 5e
(CJLRCAPRD-^)
Jack
45° Left/Right
Wire Cap
Part Numbers: CJLRCAPBU-^, CJLRCAPIW-^, CJLRCAPRD-^, CJLR%%88TG**,
CJLR%%88TG**-24
© Panduit Corp. 2018
INSTALLATION INSTRUCTIONS
PN609E
% % D e n o t e s C a t e g o r y . * * D e n o t e s c o l o r .
^ Denotes package quantity (X=10, C=100)
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 1 of 6

© Panduit Corp. 2018
6
Be sure cable is fully
inserted into wire cap
Cable End 1 Shown
Bend wires to
ease inserting
them into the
cap.
1.75”
(44.5mm)
0.75”
(19.1mm)
1.75”
(44.5mm)
0.75”
(19.1mm)
1
IMPORTANT!:
Be sure that
strain relief is fully
retracted before
inserting cable.
INSTALLATION INSTRUCTIONS
Left Orientation
PN609E
Do not pre-arrange
conductors.
3
4
5
Cable End 1 Shown
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 2 of 6
(OR)

© Panduit Corp. 2018
9
Important!
Maintain orientation of
cap in relation to jack
from previous steps.
1.
1. 2.
7
T568B Wiring
(OR)
T568A Wiring
(OR)
1.
1.
2.
2.
Termination side
Label side
Termination side
Label side
T568A not shown on wire map label
INSTALLATION INSTRUCTIONS
Left Orientation
PN609E
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 3 of 6

© Panduit Corp. 2018
6
Be sure cable is fully
inserted into wire cap
Cable End 1 Shown
1.75”
(44.5mm)
0.75”
(19.1mm)
1.75”
(44.5mm)
0.75”
(19.1mm)
INSTALLATION INSTRUCTIONS
Right Orientation
PN609E
IMPORTANT!:
Be sure that
strain relief is fully
retracted before
inserting cable.
Do not pre-arrange
conductors
3
Bend wires to
ease inserting
them into the
cap.
.
45
(OR)
Cable End 1 Shown
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 4 of 6

© Panduit Corp. 2018
9
Important!
Maintain orientation of
cap in relation to jack
from previous steps.
7
T568B Wiring
(OR)
T568A Wiring
Termination side Label side
1.
1. 2.
1.
1. 2.
2.
(OR)
Termination side
Label side
T568A not shown on wire map label
INSTALLATION INSTRUCTIONS
Right Orientation
PN609E
10
11
For Technical Support: www.panduit.com/resources/install_maintain.asp
Page 5 of 6

© Panduit Corp. 2018
INSTALLATION INSTRUCTIONS
REMOVAL STEPS
Notes:
1. For specified performance, follow TIA/EIA 568-C installation guidelines.
2. Jack Modules can terminate 22-26 AWG solid data cable with 0.062" (1.57mm) maximum insulated conductor outside diameter.
3. Jack Modules may be re-terminated at least 20 times.
4. For technical and performance information, consult Panduit Technical Support.
As with all Wiring Accessories, the following statements apply:
1. Never install communications wiring during a lightning storm.
2. Never install communications wiring in wet locations unless the jack is specifically designed for use in wet locations.
3. Never touch uninsulated communications wiring or terminals unless the communication line has been disconnected at the network interface.
4. Use caution when installing or modifying communication wiring.
PN609E
For Instructions in Local Languages
and Technical Support:
www.panduit.com/resources/install_maintain.asp
www.panduit.com
Page 6 of 6
E-mail:
techsupport@panduit.com
Phone:
866-405-6654