Determine Location of Switch Ducting and Switch Support Bracket
NOTES: Front to back span of equipment rails may need to be adjusted to accomodate your switch. Front to rear rail spacing
requirements range from 24.0" TO 30.5". Equipment installed directly below CDE3 may impede routing of switch power cord if installed
prior to CDE3.
Switch Ducting and Switch Support Bracket components of CDE3 require (4) rack spaces for installation. Switch Ducting and Switch Support Bracket are to be installed at the same vertical rack position. CDE3 components are to be installed prior to switch installation and are
designed to support the switch. (CDE3 ducting system
cradle or extension brackets are not compatible with CDE3.)
ONLY requires use of primary Cisco rack mount brackets. Cisco supplied switch
REAR OF
CABINET
3 RU Switch
(reference; port side of
switch faces Hot Aisle)
FRONT OF
CABINET
Intended Mounting Location
(4 rack spaces)
Perforated Door of Switch Ducting
(faces Cold Aisle)
Intended
Mounting
Location
(4 rack spaces)
Switch Support Bracket
Switch Ducting
Install Cage Nuts
Insert (3) cage nuts per Front and Rear equipment rail at CDE3 component mounting locations (12 total cage nuts are to be installed). (1)
grounding cage nut (green)
view below depicts cage nut locations for front and rear equipment rails on Left Hand Side of Cabinet
FRONT OF
CABINET
must be installed in (1) Front and (1) Rear equipment rail opposite each other on Left or Right Hand side. The
Grounding Cage Nut
(green)
REAR OF
CABINET
Intended
Mounting
Location
(4 rack spaces)
For Technical Support: www.panduit.com/resources/install_maintain.asp
Position Switch Ducting so that the perforated door of ducting faces the cold aisle and the mounting holes of Switch Ducting align with cage
nuts in equipment rails (installed on page 2). Secure Switch Ducting to equipment rails using (5) #12-24 Phillips screw, (5) #12 External
Tooth Washers and (1) hex head grounding screw (green; use 5/16” socket wrench) on front rail. Ensure that hex head grounding screws
fasten into grounding cage nuts.
Position Switch Support Bracket so that the mounting holes of Switch Support Bracket align with cage nuts in equipment rails (installed on
page 2). Secure Switch Support Bracket to Rear equipment rails using (5) #12-24 Phillips screw, (5) #12 External Tooth Washers. (1) hex
head grounding screw (green; use 5/16” socket wrench) on rear rail. Ensure that hex head grounding screws fasten into grounding cage
nuts
.
Grounding Cage Nut
(green)
Switch Support
Bracket
(1) #12-24 Hex Head
Grounding Screws
(use 5/16” socket wrench)
FRONT OF
CABINET
Cage Nuts
(installed)
For Technical Support: www.panduit.com/resources/install_maintain.asp
NOTE: Dashed outline of 3 RU Switch is shown for power cord routing reference only.
DO NOT INSTALL SWITCH AT THIS TIME.
Prior to switch installation, route power cord through Switch Ducting and Switch Support Bracket as shown. Slit grommet(s) along guide
lines as needed to allow for power cord pass-through. Use bridge features on Switch Support Bracket as tie-down point(s) to secure
switch power cord to Switch Support Bracket with cable tie.
Cabinet and equipment rails are not shown to add clarity to view.
FRONT OF CABINET
Bridge Feature
(use as tie-down
point for cable tie)
Switch
Support
Bracket
Switch Power Cord
Switch Ducting
Switch Power Cord
(to rear-mounted power
outlet unit)
Slit Grommet(s) along guide lines as needed
to allow for power cord pass-through
Install Switch
NOTE: Cabinet and equipment rails are not shown to add clarity to view.
Slide the 3 RU Switch onto positioning flanges of Switch Support Bracket. Carefully insert inlet side of switch into rear opening of Switch
Ducting. Position holes of 3 RU Switch rack mount brackets over threaded studs of Switch Support Bracket. Secure switch to Switch
Support Bracket with (6) #10-32 acorn nuts (use 3/8” socket wrench), (6) #10 External Tooth Washers
FRONT OF CABINET
Rear Opening of
Switch Ducting
Positioning
Flange
3 RU Switch
(reference; port side of
switch faces Hot Aisle)
Positioning
Flange
REAR OF
CABINET
For Technical Support: www.panduit.com/resources/install_maintain.asp
Position Switch Supports Bracket with middle support bracket removed. Align the mounting holes of Switch Support Bracket with cage nuts
in equipment rails (installed on page 2). Secure Switch Support Brackets to Rear equipment rails using (5) #12-24 Phillips screw, (5) #12
External Tooth Washers. (1) hex head grounding screw (green; use 5/16” socket wrench) on rear rail. Ensure that hex head grounding
screws fasten into grounding cage nuts
REAR OF
CABINET
. Install Middle Support Bracket using (4) #12-24 Phillips screw, (4) #12 External Tooth Washers.
Install Chassis Side Bracket on 3900 Series Switch by Aligning the holes in the Chassis Side Bracket. Carefully Insert Inlet side of Switch
Inside front opening of Switch Ducting.
Standard Chassis Mounting Brackets
Removed
Switch Ducting
FRONT OF
CABINET
Chassis Side Brackets
Cisco Nexus 3900 Series Switch
(reference)
FRONT OF
CABINET
For Technical Support: www.panduit.com/resources/install_maintain.asp
NOTE: Top cover of Switch Ducting removed for clarity
Center Slots in Chassis Side Brackets with holes located on both sides of the Switch Ducting. Secure Chassis Side Brackets to switch
ducting using (4) #12-24 Phillips screw, (4) #12 External Tooth Washer.
Cisco Nexus 3900 Series Switch
(reference)
Switch Ducting
FRONT OF
CABINET
Perforated Door of Switch Ducting
(faces Cold Aisle)
For Instructions in Local Languages
and Technical Support:
www.panduit.com/resources/install_maintain.asp
(2) Chassis Side
Bracket
(4) #12-24 Phillips Screw
(4) #12 External Tooth Washer
www.panduit.com
E-mail:
techsupport@panduit.com
Phone:
866-405-6654
Page 6 of 6
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.