Submit comments about this document at: http://www.sun.com/hwdocs/feedback
Page 2
Copyright 2006Sun Microsystems,Inc., 4150 NetworkCircle, SantaClara, California95054, U.S.A. Allrights reserved.
Sun Microsystems,Inc. hasintellectual propertyrights relating to technology thatis described in this document.In particular, andwithout
limitation, theseintellectual propertyrights may includeone ormore ofthe U.S. patentslisted athttp://www.sun.com/patentsand one or
more additionalpatents orpending patent applicationsin theU.S. and in other countries.
This documentand the product to whichit pertainsare distributedunder licenses restricting theiruse, copying, distribution, and
decompilation. Nopart of the product orof thisdocument may be reproduced in any formby anymeans without priorwritten authorizationof
Sun andits licensors, if any.
Third-party software, includingfont technology, is copyrighted andlicensed fromSun suppliers.
Parts ofthe productmay be derivedfrom BerkeleyBSD systems,licensed from the University ofCalifornia. UNIXis a registered trademarkin
the U.S.and in other countries, exclusivelylicensed throughX/Open Company, Ltd.
Sun, Sun Microsystems,the Sunlogo, Sun Fire, Java,OpenBoot, docs.sun.com, and Solaris are trademarksor registeredtrademarks of Sun
Microsystems, Inc.in theU.S. and inother countries.
All SPARCtrademarks areused under licenseand aretrademarks or registered trademarksof SPARC International,Inc. inthe U.S. andin other
countries. Productsbearing SPARCtrademarks are based upon anarchitecture developedby SunMicrosystems, Inc.
The OPENLOOK and Sun™ Graphical UserInterface wasdeveloped by SunMicrosystems, Inc.for its users and licensees. Sun acknowledges
the pioneeringefforts ofXerox inresearching anddeveloping the conceptof visualor graphical user interfaces forthe computer industry.Sun
holds anon-exclusive license from Xeroxto the Xerox GraphicalUser Interface, which license alsocovers Sun’s licensees who implementOPEN
LOOK GUIsand otherwise comply with Sun’swritten licenseagreements.
U.S. GovernmentRights—Commercial use.Government users are subjectto the Sun Microsystems, Inc.standard licenseagreement and
applicable provisionsof theFAR and its supplements.
DOCUMENTATION IS PROVIDED "AS IS" AND ALL EXPRESS OR IMPLIED CONDITIONS, REPRESENTATIONS AND WARRANTIES,
INCLUDING ANYIMPLIED WARRANTY OFMERCHANTABILITY, FITNESSFOR A PARTICULARPURPOSE OR NON-INFRINGEMENT,
ARE DISCLAIMED, EXCEPT TO THE EXTENT THAT SUCH DISCLAIMERS ARE HELD TO BE LEGALLY INVALID.
Copyright 2006Sun Microsystems,Inc., 4150 NetworkCircle, SantaClara, Californie95054, Etats-Unis. Tousdroits réservés.
Sun Microsystems,Inc. ales droitsde propriété intellectuels relatants àla technologiequi est décrit dans cedocument. En particulier, etsans la
limitation, cesdroits depropriété intellectuelspeuvent inclure un ou plusdes brevetsaméricains énumérés à http://www.sun.com/patents et
un oules brevetsplus supplémentairesou les applicationsde breveten attente dans les Etats-Uniset dansles autres pays.
Ce produitou documentest protégépar un copyrightet distribuéavec des licencesqui enrestreignent l’utilisation,la copie, la distribution, etla
décompilation. Aucunepartie de ce produit oudocument nepeut êtrereproduite sousaucune forme, par quelque moyenque ce soit, sans
l’autorisation préalableet écrite de Sun etde sesbailleurs de licence,s’il yen a.
Le logicieldétenu par des tiers, etqui comprendla technologie relative aux policesde caractères,est protégépar un copyright et licenciépar des
fournisseurs deSun.
Des partiesde ce produit pourrontêtre dérivées des systèmes BerkeleyBSD licenciés par l’Université deCalifornie. UNIXest une marque
déposée auxEtats-Unis et dans d’autres payset licenciéeexclusivement par X/Open Company, Ltd.
Sun, SunMicrosystems, lelogo Sun, SunFire, Java,OpenBoot, docs.sun.com,et Solaris sontdes marquesde fabriqueou des marques déposées
de SunMicrosystems, Inc.aux Etats-Unis etdans d’autrespays.
Toutes lesmarques SPARC sont utilisées souslicence et sont des marques defabrique ou desmarques déposéesde SPARC International, Inc.
aux Etats-Uniset dans d’autres pays. Lesproduits portantles marquesSPARCsont baséssur une architecture développéepar Sun
Microsystems, Inc.
L’interfaced’utilisation graphiqueOPEN LOOK etSun™ aété développée parSun Microsystems,Inc. pourses utilisateurs etlicenciés. Sun
reconnaît lesefforts depionniers deXerox pour la rechercheet le développementdu conceptdes interfaces d’utilisationvisuelle ougraphique
pour l’industriede l’informatique. Sun détient unelicense nonexclusive de Xerox surl’interface d’utilisation graphiqueXerox, cettelicence
couvrant égalementles licenciées de Sun quimettent enplace l’interface d’utilisation graphiqueOPEN LOOK etqui enoutre seconforment
aux licencesécrites de Sun.
LA DOCUMENTATION EST FOURNIE "EN L’ÉTAT" ET TOUTES AUTRES CONDITIONS, DECLARATIONS ET GARANTIES EXPRESSES
OU TACITES SONT FORMELLEMENT EXCLUES,DANS LAMESURE AUTORISEEPARLA LOI APPLICABLE,Y COMPRISNOTAMMENT
TOUTE GARANTIE IMPLICITE RELATIVE A LA QUALITE MARCHANDE, A L’APTITUDE A UNE UTILISATION PARTICULIERE OU A
L’ABSENCE DE CONTREFAÇON.
Please
Recycle
Page 3
Contents
Prefaceix
1.Parts Removal and Installation1–1
1.1Replaceable Components1–2
1.2Controlling Server Power1–2
1.2.1Powering On the Server1–2
1.2.2Powering Off the Server1–3
1.3Avoiding Electrostatic Discharge1–3
1.3.1Avoiding Electrostatic Discharge While Working on the Back of the
Server1–4
1.3.2Avoiding Electrostatic Discharge While Working on the Front of the
Server1–5
1.4Opening the Server1–5
1.4.1Removing the Front Section of the Cover Assembly1–6
1.4.2Installing the Front Section of the Cover Assembly1–7
1.4.3Opening the Back Section of the Cover Assembly1–7
1.4.4Closing the Back Section of the Cover Assembly1–8
1.4.5Removing the Whole Cover Assembly1–9
1.5Location of Components1–10
1.6Front Bezel Assembly1–10
1.6.1Removing the Bezel Assembly1–11
iii
Page 4
1.6.2Installing the Bezel Assembly1–11
1.7Hard Drives1–11
1.7.1Removing a Hard Drive1–11
1.7.2Installing a Hard Drive1–12
1.8System Configuration Card Reader1–13
1.8.1Removing the System Configuration Card Reader1–13
1.8.2Installing the System Configuration Card Reader1–14
1.9Power Supply Unit1–15
1.9.1Removing the PSU1–15
1.9.2Installing a PSU1–15
1.10Memory1–16
1.10.1Memory Configuration Rules1–16
1.10.2Installing Memory1–16
1.10.3Removing Memory1–17
1.11Fans1–18
1.11.1Removing a Fan1–18
1.11.2Replacing a Fan1–19
1.12CPU, Heat Sink, and System Board Assembly1–20
1.12.1Removing the System Board1–20
1.12.2Installing a System Board1–22
1.13Lower Interface Board Assembly1–23
1.13.1Removing a Lower Interface Board Assembly1–23
1.13.2Installing a Lower Interface Board Assembly1–24
1.14PCI Cards1–25
1.14.1Adding a PCI Card1–25
1.14.1.1Replacing a PCI card1–27
1.15Sun Cryptographic Accelerator1–27
1.15.1Removing the Sun Cryptographic Accelerator1–28
ivSun Fire V125 Server Service Manual • September 2006
Page 5
1.15.2Installing the Sun Cryptographic Accelerator1–28
1.16Battery1–29
1.16.1Replacing the RTC Battery1–29
Contentsv
Page 6
viSun Fire V125 Server Service Manual • September 2006
Page 7
Figures
FIGURE 1-1Grounding Point in Back of the Server 1–4
FIGURE 1-2Location of Screws on the Front Section of the Cover 1–6
FIGURE 1-3Removing the Front Section of the Cover 1–7
FIGURE 1-4Location of Captive Screw and Side Catches on Back Section of the Cover 1–8
FIGURE 1-5Removing the U-Channel 1–9
FIGURE 1-6Location of Major Components 1–10
FIGURE 1-7Removing a Hard Drive 1–12
FIGURE 1-8Location of Connectors on the System Configuration Card Reader 1–13
FIGURE 1-9Removing the System Configuration Card Reader 1–14
FIGURE 1-10Installing Memory 1–17
FIGURE 1-11Disconnecting Fans’ Power Cables 1–18
FIGURE 1-12Removing Fans 1–19
FIGURE 1-13Accessing the System Board for Removal 1–21
FIGURE 1-14Removing the System Board From the Chassis 1–22
FIGURE 1-15Lower Interface Board Standoff and Screw Locations 1–24
FIGURE 1-16Location of PCI Lockdown Screw 1–26
FIGURE 1-17Removing a PCI Card 1–27
FIGURE 1-18Removing the Cryptographic Accelerator 1–28
vii
Page 8
viiiSun Fire V125 Server Service Manual • September 2006
Page 9
Preface
The Sun Fire V125 Server Service Manual provides detailed instructions about service
procedures for the Sun Fire™ V125 server and should be used by qualified service
personnel only.
Before You Read This Document
This book does not cover server installation. For detailed information on this topic,
refer to the Sun Fire V125 Server Installation Guide. Before following any procedures
described in this book, ensure that you have read the Sun Fire V125 Server Safety andCompliance Manual.
Using UNIX Commands
This document does not contain information on basic UNIX®commands and
procedures such as shutting down the system, booting the system, and configuring
devices.
Refer to one or more of the following documents for this information:
■ Solaris 10 Sun Hardware Platform Guide
■ Solaris™ Operating System documentation, which is at:
http://docs.sun.com
■ Other software documentation that you received with your system
ix
Page 10
Shell Prompts
ShellPrompt
C shellmachine-name%
C shell superusermachine-name#
Bourne shell and Korn shell$
Bourne shell and Korn shell superuser#
Typographic Conventions
*
Typeface
AaBbCc123The names of commands, files,
AaBbCc123
AaBbCc123Book titles, new words or terms,
* The settings on your browser might differ from these settings.
MeaningExamples
Edit your.login file.
and directories; on-screen
computer output
What you type, when contrasted
with on-screen computer output
words to be emphasized.
Replace command-line variables
with real names or values.
Use ls -a to list all files.
% You have mail.
% su
Password:
Read Chapter 6 in the User’s Guide.
These are called class options.
Yo u must be superuser to do this.
To delete a file, type rm filename.
x Sun Fire V125 Server Service Manual • September 2006
Getting StartedSun Fire V125 Server Getting Started
Guide
AdministrationSun Fire V125 Server Administration
Guide
InstallationSun Fire V125 Server Installation Guide819-7422PDF and
Latest informationSun Fire V125 Server Product Notes819-7424PDF and
Compliance and safetySun Fire V125 Server Safety and
Compliance Manual
OpenBoot™ PROMOpenBoot PROM Enchancements for
Diagnostic Operation
Lights-Out ManagementSun Advanced Lights Out Manager
(ALOM) 1.6 Administration Guide
819-7423PDF,
HTML, and
hard copy
819-7420PDF and
HTML
HTML
HTML
817-7425PDF and
HTML
817-6957Hard copyAssociates
819-2445PDF and
HTML
Online and
accessories
kit (English
only)
Online
Online
Online
Online
kit
Online
Documentation, Support, and Training
Sun FunctionURL
Documentation
Support
Training
http://www.sun.com/documentation/
http://www.sun.com/support/
http://www.sun.com/training/
Prefacexi
Page 12
Third-Party Web Sites
Sun™ is not responsible for the availability of third-party web sites mentioned in
this document. Sun does not endorse and is not responsible or liable for any content,
advertising, products, or other materials that are available on or through such sites
or resources. Sun will not be responsible or liable for any actual or alleged damage
or loss caused by or in connection with the use of or reliance on any such content,
goods, or services that are available on or through such sites or resources.
Sun Welcomes Your Comments
Sun is interested in improving its documentation and welcomes your comments and
suggestions. You can submit your comments by going to:
http://www.sun.com/hwdocs/feedback
Please include the title and part number of your document with your feedback:
Sun Fire V125 Server Service Manual, part number 819-7421-10
xii Sun Fire V125 Server Service Manual • September 2006
Page 13
CHAPTER
1
Parts Removal and Installation
This chapter contains procedures for replacing the internal hardware components
for the Sun Fire V125 server. The procedures in this section are for qualified service
engineers only.
Caution – Read Section 1.8, “System Configuration Card Reader” on page 1-13, and
wear a properly grounded antistatic strap, before you carry out any of the
procedures in this document.
The chapter contains the following sections:
■ Section 1.1, “Replaceable Components” on page 1-2
■ Section 1.2, “Controlling Server Power” on page 1-2
■ Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3
■ Section 1.4, “Opening the Server” on page 1-5
■ Section 1.5, “Location of Components” on page 1-10
■ Section 1.6, “Front Bezel Assembly” on page 1-10
■ Section 1.7, “Hard Drives” on page 1-11
■ Section 1.8, “System Configuration Card Reader” on page 1-13
■ Section 1.9, “Power Supply Unit” on page 1-15
■ Section 1.10, “Memory” on page 1-16
■ Section 1.11, “Fans” on page 1-18
■ Section 1.12, “CPU, Heat Sink, and System Board Assembly” on page 1-20
■ Section 1.13, “Lower Interface Board Assembly” on page 1-23
■ Section 1.14, “PCI Cards” on page 1-25
■ Section 1.15, “Sun Cryptographic Accelerator” on page 1-27
■ Section 1.16, “Battery” on page 1-29
1-1
Page 14
1.1Replaceable Components
Replaceable components in the front of the server are:
■ Bezel assembly
■ Hard drive
■ System configuration card reader
■ Lower interface board
The remaining replaceable components are in the back of the server.
Caution – Printed circuit boards and hard drives contain electronic components
that are extremely sensitive to static electricity. Ordinary amounts of static from your
clothes or the work environment can destroy components. Do not touch the
components or any metal parts without taking proper antistatic precautions.
Before you carry out the procedures covered in this document, the server must be
powered down. To do this you must remove the power cable. Follow the
instructions in Section 1.2.2, “Powering Off the Server” on page 1-3.
1.2Controlling Server Power
The On/Standby button does not power off the server, but it toggles the server
between On and Standby mode.
1.2.1Powering On the Server
Caution – Never move the system when the system power is on. Movement can
cause catastrophic drive failure. Always power off the system before moving it.
1. Connect the server to an AC power source.
Once connected, the server automatically goes into Standby power mode.
2. Turn on power to any peripherals and external storage devices you have connected
to the server.
Read the documentation supplied with the device for specific instructions.
1-2Sun Fire V125 Server Service Manual • September 2006
Page 15
3. Open the bezel.
4. Press the On/Standby switch.
5. Close the bezel.
1.2.2Powering Off the Server
1. Notify users that the system will be powered down.
2. Back up system files and data.
3. Press and release the On/Standby switch behind the bezel.
The system begins an orderly software system shutdown.
Note – Pressing and releasing the On/Standby switch initiates an orderly software
shutdown. Pressing and holding the switch for four seconds causes an immediate
hardware shutdown. Whenever possible, initiate an orderly shutdown. Forcing an
immediate hardware shutdown can corrupt the hard drive and cause loss of data.
4. Wait for the front panel green indicator to go out.
Caution – As long as the power cord is connected, potentially hazardous energy is
present inside the server.
5. Disconnect the power cable.
This is the only way to remove power from the server. Electrical power is present
when the server is in Standby mode.
1.3Avoiding Electrostatic Discharge
Whenever you work with the server’s internal components, follow this procedure to
prevent damage caused by static electricity.
You need the following items:
■ Antistatic wrist or foot strap
■ Antistatic mat
Chapter 1 Parts Removal and Installation1-3
Page 16
1.3.1Avoiding Electrostatic Discharge While Working
on the Back of the Server
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Open the back section of the cover.
See Section 1.4, “Opening the Server” on page 1-5.
3. Attach one end of the antistatic strap to the grounding stud located on the
partition inside the server, and the other end to your wrist.
FIGURE 1-1 Grounding Point in Back of the Server
1-4Sun Fire V125 Server Service Manual • September 2006
Page 17
1.3.2Avoiding Electrostatic Discharge While Working
on the Front of the Server
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Perform either Step a or Steps b and c.
a. Attach one end of the antistatic strap to a grounding point on the rack and the
other to your wrist.
b. Remove the server from the rack.
c. Place the server on an antistatic mat or other suitable antistatic surface.
Suitable antistatic surfaces include:
■ Sun electrostatic discharge (ESD) mat, Sun part number 250-1088 (available
through your Sun sales representatives)
■ The bag or shipping container used to package Sun replacement parts
■ Disposable ESD mat, shipped with replacement parts or options
1.4Opening the Server
The cover of the server is split into two sections, front and back.
■ The back section hinges to provide access.
■ The front section detaches to provide access.
■ The whole cover assembly detaches to provide access to both front and back
sections of the server. This is necessary to replace some components.
Caution – Disconnect the power cord before carrying out this procedure. As long as
the power cord is connected, potentially hazardous energy is present inside the
server.
Caution – After servicing, install and fasten the cover before plugging in the power
cords or turning power on.
Chapter 1 Parts Removal and Installation1-5
Page 18
1.4.1Removing the Front Section of the Cover
Assembly
1. Open the bezel.
2. Undo the screws that fasten the front section of the cover to the chassis
(
FIGURE 1-2).
FIGURE 1-2 Location of Screws on the Front Section of the Cover
3. Slide the front section of the cover towards the front of the server.
Use the indentations in the cover to provide grip if necessary.
4. Lift off the front section of the cover (
1-6Sun Fire V125 Server Service Manual • September 2006
FIGURE 1-3).
Page 19
FIGURE 1-3 Removing the Front Section of the Cover
1.4.2Installing the Front Section of the Cover Assembly
1. Align the clips on the bottom of the cover with the corresponding slots in the
server chassis.
2. Press the cover down into the slots.
3. Slide the cover towards the back of the server.
4. Replace the screws that fasten the cover to the server.
1.4.3Opening the Back Section of the Cover Assembly
1. Locate the latches at the back of the server and release them (FIGURE 1-4).
2. Undo the captive Phillips screw in the catch on top of the server (
Chapter 1 Parts Removal and Installation1-7
FIGURE 1-4).
Page 20
FIGURE 1-4 Location of Captive Screw and Side Catches on Back Section of the Cover
3. Pull the lever to release the catch and lift the cover up, pulling from the center
and one corner of the cover.
The cover hinges forward to lay flush against the front section of the server.
1.4.4Closing the Back Section of the Cover Assembly
1. Rotate the cover back to its closed position.
Ensure that the catch clips the cover into its closed position.
2. Tighten the captive screw in the catch on the cover.
3. Secure the cover using the clips on the outside of the server.
1-8Sun Fire V125 Server Service Manual • September 2006
Page 21
1.4.5Removing the Whole Cover Assembly
1. Remove the front section of the cover assembly.
See Section 1.4.1, “Removing the Front Section of the Cover Assembly” on page 1-6.
2. Open the back section of the cover assembly.
See Section 1.4.3, “Opening the Back Section of the Cover Assembly” on page 1-7.
3. Remove the back section of the cover assembly.
4. Unclip the U-channel that runs across the server and remove it (
You must remove this bar to reach the cables that connect the front of the server to
the rear.
FIGURE 1-5).
FIGURE 1-5 Removing the U-Channel
Chapter 1 Parts Removal and Installation1-9
Page 22
1.5Location of Components
The internal components of the server are located in FIGURE 1-6.
The front bezel assembly includes the bezel, the front server status indicators, and
hinges. The front bezel is replaced as a single unit.
1-10Sun Fire V125 Server Service Manual • September 2006
Page 23
1.6.1Removing the Bezel Assembly
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See the instructions in Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Hold the bezel firmly at both ends and rotate it down to its open position.
Grip the bezel at the points marked by the green triangles at each end to open it. Do
not attempt to open the bezel using a single gripping point or by holding the middle
of the bezel, as damage may occur.
4. Disconnect the cable connecting the bezel assembly to the server.
5. Unscrew the bezel hinges and remove them from the server.
1.6.2Installing the Bezel Assembly
1. Locate the new bezel and hinges onto the server, and screw the bezel hinges to the
server.
2. Reconnect the bezel cable.
1.7Hard Drives
For information on removing a hard drive while the operating server is running, see
the Sun Fire V125 Server Administration Guide.
1.7.1Removing a Hard Drive
1. Ensure that you are properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
2. Open the front bezel.
3. Check that the blue indicator indicator is lit on the hard drive.
The blue indicator comes on when the hard drive is ready to remove.
Chapter 1 Parts Removal and Installation1-11
Page 24
4. Slide the catch at the front of the hard drive to the right (FIGURE 1-7).
The handle on the front of the hard drive releases.
5. Pull the handle and remove the hard drive from the server by sliding the drive out
from its bay.
Slide catch
to release
handle
Pull handle to
remove hard drive
FIGURE 1-7 Removing a Hard Drive
Note – Note that in the preceding graphic, the standard configuration includes only
the leftmost HDD; the second HDD is optional.
1.7.2Installing a Hard Drive
1. Slide the catch on the front of the hard drive to the right.
This releases the hard drive. The lever must be open before you insert the hard drive
into the server. If the lever is closed, the hard drive will not correctly engage.
2. Slide the hard drive into its bay at the front of the server.
Push the drive in firmly until the metal lever starts to close. The hard drive has
engaged with its connector in the server.
3. Push the metal lever until the hard drive clicks into place.
4. Close the bezel.
1-12Sun Fire V125 Server Service Manual • September 2006
Page 25
1.8System Configuration Card Reader
For more information on the function of the system configuration card, see the SunFire V125 Server Administration Guide.
1.8.1Removing the System Configuration Card Reader
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Remove the front section of the cover assembly.
See Section 1.4, “Opening the Server” on page 1-5.
4. Remove the system configuration card.
Place the system configuration card aside (
5. Disconnect the cable leading to the lower interface board from the configuration
card reader (
FIGURE 1-8).
FIGURE 1-9).
Lower interface board
connector
FIGURE 1-8 Location of Connectors on the System Configuration Card Reader
Chapter 1 Parts Removal and Installation1-13
Page 26
6. Unclip the system configuration card reader (FIGURE 1-9).
Hold the reader board firmly and unclip one corner at a time by pulling up. Take care
not to damage the On/Standby switch when you remove the assembly.
FIGURE 1-9 Removing the System Configuration Card Reader
1.8.2Installing the System Configuration Card Reader
1. Position the new configuration card reader board by lining up the fixing holes
with the clips in the top of the DVD drive enclosure.
2. Press the new reader board firmly onto the clips to secure it in place.
3. Reconnect the system configuration card reader power cable.
4. Install the system configuration card.
1-14Sun Fire V125 Server Service Manual • September 2006
Page 27
1.9Power Supply Unit
1.9.1Removing the PSU
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Remove the cover assembly.
See Section 1.4, “Opening the Server” on page 1-5.
4. Disconnect the cables leading to the system board and interface board.
To access the cable connector to the interface board, open the front cover assembly.
5. Undo the two screws on the back panel of the server.
6. Move the PSU towards the front of the server to release it from the locating tab on
the base of the server.
7. Lift the PSU out of the chassis.
1.9.2Installing a PSU
1. Position the new PSU over the location tab and slide it towards the back of the
server.
2. Install and tighten the two screws on the back panel of the server.
3. Connect the power supply wiring harness to the connectors on the system board
and interface board.
4. Install the cover assembly.
Chapter 1 Parts Removal and Installation1-15
Page 28
1.10Memory
There are four memory module sockets per processor on the system board. Memory
is supplied by Sun in pairs. Use the DIMM pair as supplied and do not mix DIMMs.
For a list of the available memory options, see the Sun Fire V125 ServerAdministration Guide.
1.10.1Memory Configuration Rules
Memory is shipped in matched pairs for use on the Sun Fire V125 server.
When you install memory into a Sun Fire V125 server, follow the se guidelines:
■ A minimum of two matched DIMMs are required for the server. The matched
DIMMs must be the same size, manufacturer, and part number.
■ DIMMs must be installed in identical pairs. Both size and manufacturer must be
the same per pair, but you can mix manufacturers and size between pairs.
Note – A DIMM pair that has identical attributes, but different vendors will not be
rejecte. However, such a DIMM pair will cause OpenBoot
warning message to the console and will disable autoboot.
1.10.2Installing Memory
1. Power down the server and disconnect the power cable.
See Section 1.2, “Controlling Server Power” on page 1-2
2. Open the back cover.
See Section 1.4.3, “Opening the Back Section of the Cover Assembly” on page 1-7.
3. Locate the correct DIMM socket.
4. Ensure that the retaining clips are open (
5. Press the memory module in the DIMM socket.
6. Press down until the clips snap into place.
FIGURE 1-10).
™
PROM to issue a
1-16Sun Fire V125 Server Service Manual • September 2006
Page 29
FIGURE 1-10 Installing Memory
Note – Note that the second DIMM pair shown in the preceding figure is optional.
The standard configuration includes only the DIMM pair that is closest to the CPU.
1.10.3Removing Memory
1. Power down the server and disconnect the power cable.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Open the back cover.
See Section 1.4.3, “Opening the Back Section of the Cover Assembly” on page 1-7.
3. Locate the correct DIMM socket.
4. Open the latches at the sides of the socket.
5. Remove the module from the DIMM socket.
6. Close the rear cover.
Chapter 1 Parts Removal and Installation1-17
Page 30
1.11Fans
The Sun Fire V125 server has four 40 mm fans mounted side by side. Three of these
cool the system board, while the fourth cools the PCI card area. All of these fans
plug into the system board individually. The fans can be removed from the server
without the use of tools.
1.11.1Removing a Fan
1. Open the back section of the cover.
See Section 1.4, “Opening the Server” on page 1-5.
2. Disconnect the fans’ power cables from the system board (
FIGURE 1-11).
FIGURE 1-11 Disconnecting Fans’ Power Cables
1-18Sun Fire V125 Server Service Manual • September 2006
Page 31
3. Push back the fan retaining tab.
4. Lift the fan out of the chassis (
Pull on the tab on top of the fan assembly.
FIGURE 1-12).
FIGURE 1-12 Removing Fans
1.11.2Replacing a Fan
1. Insert the replacement fan.
2. Connect the fan’s power cable to the system board.
3. Install the back section of the cover.
Chapter 1 Parts Removal and Installation1-19
Page 32
1.12CPU, Heat Sink, and System Board
Assembly
The CPU, heatsink, and system board are replaced as a single assembly.
Tip – To perform the steps in this section, you need a 5 mm wrench to remove and
install the SCSI pillars and the DB-9 jackposts.
1.12.1Removing the System Board
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Open the back section of the cover.
See Section 1.4, “Opening the Server” on page 1-5.
4. Disconnect the power supply wiring harness from the system board.
5. Disconnect the interface board SCSI and IDE cables from the system board.
6. If any PCI cards are fitted, remove them.
See Section 1.14.1, “Adding a PCI Card” on page 1-25.
7. Remove the PCI slider assembly.
8. Remove the server fan assembly.
9. Unscrew and remove the DB-9 and SCSI jackposts on the server’s back panel.
1-20Sun Fire V125 Server Service Manual • September 2006
Page 33
PCI card (optional)
U-channel
PCI slider assembly
Fan assembly
Lower interface
board
Hard disk
drives (rightmostHDD,
optional)
System board
DIMM pair (farthest
pair from CPU,
optional)
Power supply unit
System configuration card reader
DVD (optional)
FIGURE 1-13 Accessing the System Board for Removal
10. Unscrew the system board.
The system board is secured to the chassis by ten screws.
11. Slide the system board toward the front of the chassis so that the SCSI, Ethernet,
and serial connectors come free from the chassis.
12. Lift the system board out of the chassis.
Chapter 1 Parts Removal and Installation1-21
Page 34
FIGURE 1-14 Removing the System Board From the Chassis
1.12.2Installing a System Board
1. Insert the new system board and locate it so that the SCSI, Ethernet, and serial
connectors are firmly positioned in their slots at the back of the chassis.
2. Insert all system board screws loosely.
Do not put any screws in the holes for the PCI card slide retainer. These holes are
identified by a circle printed around their circumference.
1-22Sun Fire V125 Server Service Manual • September 2006
Page 35
3. Install the PCI slider assembly.
The arrow embossed on the slider should point to the rear of the server.
4. Install any PCI cards you removed.
5. Reconnect all system board cables and wiring harnesses.
6. Install the server’s cover and tighten the screws.
1.13Lower Interface Board Assembly
The interface board assemblies handle the connections between the system board
and the components in the front section of the server. The assemblies are positioned
in the front section of the server, behind the hard drives and system configuration
card reader assembly.
1.13.1Removing a Lower Interface Board Assembly
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Remove all hard drives.
4. Remove DVD drive, if one is fitted in the system.
5. Remove the cover assembly.
See Section 1.4, “Opening the Server” on page 1-5.
6. Disconnect the system board cable.
7. Disconnect the PSU cable.
8. Disconnect the system configuration card reader cable.
9. Unscrew the eight screws that secure the LIB to the server’s chassis as shown in
the following figure.
Chapter 1 Parts Removal and Installation1-23
Page 36
FIGURE 1-15 Lower Interface Board Standoff and Screw Locations
10. Lift the LIB assembly part of the way out of the server chassis.
11. Disconnect the cable from the bezel assembly.
12. Remove the LIB from the server.
1.13.2Installing a Lower Interface Board Assembly
1. Locate the new LIB assembly using the screw holes at each corner as guides.
The LIB printed circuit board (PCB) pushes onto (blind-mates) its connectors.
2. Screw the LIB into place.
3. Attach the bezel PCB, PSU, and system board cables.
4. Install the cover assembly.
1-24Sun Fire V125 Server Service Manual • September 2006
Page 37
1.14PCI Cards
The PCI slot on the Sun Fire V125 server operates at 3.3 Vdc and supports one 64-bit
PCI card running at 33 MHz or 66 MHz.
1.14.1Adding a PCI Card
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Open the back section of the server.
See Section 1.4, “Opening the Server” on page 1-5.
4. Unscrew the PCI lockdown screw on the back of the server.
Chapter 1 Parts Removal and Installation1-25
Page 38
FIGURE 1-16 Location of PCI Lockdown Screw
5. Remove the PCI lockdown bracket on the inside of the server.
6. Slide the PCI card support clear of the PCI card.
7. Disconnect and remove the PCI card.
1-26Sun Fire V125 Server Service Manual • September 2006
Page 39
FIGURE 1-17 Removing a PCI Card
1.14.1.1Replacing a PCI card
1. Locate the PCI card in the appropriate slot and press it firmly into the connector.
2. Locate the PCI card support so that it supports the back of the card.
3. Attach the PCI lockdown bracket and tighten the PCI lockdown screw.
1.15Sun Cryptographic Accelerator
The hardware cryptographic accelerator clips onto the server’s system board. For
more information, see the Sun Crypto Accelerator 1000 Installation and User’s Guide.
Chapter 1 Parts Removal and Installation1-27
Page 40
1.15.1Removing the Sun Cryptographic Accelerator
1. Locate the clip that secures the cryptographic accelerator onto the system board.
2. Squeeze the clip to compress it.
3. Lift the cryptographic accelerator away from the chassis (
FIGURE 1-18 Removing the Cryptographic Accelerator
FIGURE 1-18).
1.15.2Installing the Sun Cryptographic Accelerator
1. Press the standoff into the motherboard.
2. Place the cryptographic accelerator onto the standoff and connector on the
motherboard.
3. Press the accelerator into place.
1-28Sun Fire V125 Server Service Manual • September 2006
Page 41
1.16Battery
The battery powers the server’s internal real time clock (RTC).
Tip – When replacing the battery, only use an identical replacement part.
1.16.1Replacing the RTC Battery
1. Power off the server.
See Section 1.2, “Controlling Server Power” on page 1-2.
2. Ensure that the server is properly grounded.
See Section 1.3, “Avoiding Electrostatic Discharge” on page 1-3.
3. Open the back section of the cover.
See Section 1.4, “Opening the Server” on page 1-5.
4. Unclip the battery from its housing on the system board.
Push the retaining clip to one side to release the battery.
5. Locate the new battery in the housing and press down to secure it in place.
Chapter 1 Parts Removal and Installation1-29
Page 42
1-30Sun Fire V125 Server Service Manual • September 2006
Page 43
Index
B
battery, replacing, 1-29
bezel assembly
installing, 1-11
overview, 1-10
removing, 1-11
C
cautions
connected power cord, 1-5
moving the system, 1-2
static electricity, 1-2
cover assembly (back)
closing, 1-8
opening, 1-7
cover assembly (front)
installing, 1-7
opening, 1-5
removing, 1-6
CPU and system board assembly, 1-20
cryptographic accelerator
bezel assembly, 1-11
cryptographic accelerator, 1-28
hard drive, 1-12
lower interface board, 1-24
memory, 1-16
new system board, 1-22
power supply unit, 1-15
system configuration card reader, 1-14
Index-1
Page 44
L
LIBs, See lower interface board
location of components, 1-10
lower interface board