The “D” series valves are identified by the raised letter “D” cast into the bonnet as shown above.
These guidelines apply only to the valves so marked.
CAUTION: Only qualified personnel should undertake the procedures outlined in this document.
NIBCO INC., its agents, representatives and employees assumes no liability for the use of these
procedures. These procedures are offered as suggestions only.
The NIBCO F-869-B automatic steam stop check valve is the preferred type of valve used on
discharge nozzles of steam boilers in multiple boiler installations. The ANSI/ASME Power Piping
Code B31.1 makes reference to this in Section 122.1.7A.
Periodically it may become necessary to perform maintenance on these valves to keep them
performing at their best. Depending on the water used, conditioners used in the water, as well
as other characteristics of the piping system, accumulation of scale and other foreign materials
may interfere with good operation of the valve.
After some years of operation, it would be wise to disassemble the valve and inspect for buildup
of scale, damage to seating surfaces or any other cause that may interfere with good operation.
This can be done during normal shutdown and is not a complicated or expensive job if done
properly. Normally, insulation will not have to be removed. Insulation is usually limited to the
body portion of the valve. The body should not have to be removed from the system in the
majority of cases. In an effort to improve maintenance efficiency, some large multiple boiler
installations with four or more boilers keep a spare valve on hand and change one valve every
year. This gives the maintenance staff the opportunity to renew one valve each year at their
convenience. The following will be a step-by-step guide for this purpose. Also included will be
guidelines for renewing the seat and disc surfaces.
CAUTION: A valve shop can do this type of work if they are competent. You may want to check
with others in your locale to find out if there is a competent valve shop in your area; but in no
case undertake this work yourself or assign this work to others if you have any doubts
concerning safety and/or possible damage to the valve or the piping system.
1. Shut down, isolate and drain the portion of the system where the valve is located. Let the
system cool off before starting any work on the valve.
2. Mark the body and the bonnet of the valve with chalk or an ink marker in three or four
places at the bonnet-body joint to serve as aligning marks during reassembly. Open the
valve main operating stem all the way with the handwheel.
3. Remove the valve bonnet-body bolts.
4. Remove the bonnet assembly from body. This must be done very carefully to avoid
damaging the main operating stem or the dashpot adjustment stem. The dashpot
adjustment stem sticks down into the dashpot without much clearance. Jerking or quick
release of the bonnet may result in damage. It may be necessary to loosen the gasket
between the bonnet and the dashpot in the body with a putty knife or some similar tool
before lifting off the bonnet. Be careful to lift the bonnet straight up until the dashpot
adjusting stem clears the dashpot. Take care when setting the bonnet down not to
damage or bend the dashpot adjusting valve stem.
Mark the position of the dashpot adjustment assembly on the bonnet if you remove it
from the bonnet. You may want to mark the open and closed position of the dashpot
adjustment valve permanently by using a small punch mark on the top of the bonnet.
The full operation of this adjustment is only of a turn, 90°, from full open to full close.
5. Remove and discard the gasket between the bonnet and the top lid of the dashpot
cylinder. It is not worth the gamble to use an old gasket over again when you consider
the valve my leak at the joint afterwards.
6. Mark the dashpot cylinder and body with an ink marker or chalk for alignment when
reassembling. The dashpot cylinder may be stuck to the body. Carefully pry the lip of the
dashpot cylinder to loosen. Remove the dashpot cylinder. Remove the piston-disc
assembly. Lift straight up so as not to bend the disc pilot on the bottom of the disc.
7. Remove and discard the gasket between the body of the valve and underside of the lip
on the dashpot cylinder. Carefully clean gasket surfaces.
8. Inspect the valve carefully for evidence of wear, buildup of scale, other foreign matter
and any other problem which may cause the valve to operate erratically or incorrectly. It
will not be necessary to disassemble the piston-disc, disc seat and pilot to thoroughly
examine all components. It will be necessary to examine the piston rings for wear or
damage. If they are worn or damaged, they must be replaced. They are not repairable.
Be very careful not to score or mark any of the components while examining them. This
is an unhandy procedure so extra care must be taken. It is easy to break or bend the
disc pilot on the bottom of the disc if proper care is not taken. The piston rod cannot be
removed from the disc or the piston, as it is all one piece.
9. Clean all components as necessary, except the seating surface on the disc and in the
body seat. Use light emery cloth of fine sand paper so no large scratches are made on
the operating surfaces or sealing surfaces. Check the disc pilot hole in the bottom of the
body seat cage.
10. Replace any damaged and non-repairable components. It is always better to change a
questionable component then to use it.
11. If the disc and seat are leaking and need to be renewed, cut strips of 120 grit emery
paper about 1-1/2” long and 3/8” or 1/2” wide. Using double-backed adhesive tape, stick
strips on the seat ring seating surface. The strips should be evenly spaced around the
seat. Place the disc in the body and rotate the disc back and forth with very light
pressure. The further around you can rotate, the better the surface you will get. Finish up
with full rotation. Examine surface periodically, and the new surface will be seen
developing. When complete, the new surface on the disc should be all the way across
equal to the width of the seat ring seating surface.
12. Repeat this previous step on the seat ring by placing the strips of emery and doublebacked tape on the disc.
13. Clean thoroughly then rotate the disc once or twice lightly in the seat. A shiny line should
appear all the way around on the disc and the seat ring. Repeat the above steps until
this shiny line can be clearly seen. This line must be unbroken if a good seal is to be
achieved. A break in the line is a place the valve will leak. Repeat as needed.
14. Before reassembly make sure all the components are thoroughly clean, particularly
gasket surfaces. Check carefully inside the valve body (still mounted on the boiler). It is
very important that all foreign particles and residue be removed from the valve. A light
lubricant such as kerosene or fuel oil may be used very sparingly for parts difficult to
reassemble. A drop or two is plenty.
15. Two new identical gaskets are required – one on top of and one under the lip of the
dashpot. The top one will seal against the bonnet and the bottom one will seal against
the body of the valve. Carefully replace the cylinder in the valve body with one gasket
under the lip. Carefully reinstall the disc-piston assembly into the valve making sure the
disc pilot pin is through the pilot pin hole in the seat ring cage. Use aligning markings put
on earlier. Make sure the piston-disc can slide up and down freely before going any
further. This can be done by grasping the piston and pulling up and down. Use two vise
grips on the flange and dashpot cylinder to keep the dashpot from moving. Don’t forget
to use a tongue depressor or the like under the vise grips to keep from damaging the
flange and dashpot lip.
16. Carefully place the bonnet and one gasket on top of the valve body making sure the
stem of the dashpot adjustment can move freely. Align with markings put on earlier.
Make sure the valve stem is well open (by turning the handwheel counterclockwise) so
the stem is not pressing on the piston. Damage can be caused when the bonnet-body
bolts are being tightened if this is not done.
17. Make sure that the body and bonnet bolts are thoroughly cleaned and lubricated before
fastening down the bonnet. Check each threaded hole carefully. Install all bolts finger
tight then torque to the figure indicated in foot pounds on the attached sheet and use the
tightening sequence indicated.
18. Operate the stem up and down by turning the handwheel counterclockwise then
clockwise to make sure nothing is preventing the piston from rising.
19. When the boiler is brought back up and steam is flowing through the valve, it is a good
idea to check for complete operation of the automatic feature. This would require closing
off then reopening. The valve should then open automatically. With pressure in the
header, if the boiler is shut down, the valve should close automatically. (The handwheel
should be in the wide open position to operate in the full check position).
CAUTION: When doing these final checks, your specific system may require additional
operation for safe performance and to prevent damage to boiler or piping components.
These steps are suggestions to check out the valve only – the operator must keep in mind
the characteristics of his own system and check out the valves using the steps based on
these characteristics.
NIBCO® Cast Iron, Alloy Iron and Ductile Iron Valves
The following procedure outlines the methods to be used in the assembly of and field installation
of the body to bonnet bolts and nuts in order to assure the proper clamping stresses. The
correct sequence and torque for tightening the body to bonnet bolts and nuts is also identified.
These instructions apply for ASTM A307 Grade B high tensile strength bolting material used on
NIBCO cast iron, alloy iron, and ductile iron valve body and bonnet flange joints.
1. Visually inspect all threads and remove all foreign matter such as rust, dirt, corrosion
and any lubricant.
2. Clean the body gasket and bonnet gasket seating area thoroughly.
The gasket seating area must be clean prior to assembly as the area becomes
inaccessible after assembly. The area is to be cleaned with a suitable solvent or
cleanser that can remove all dirt, grime and gasket particles.
3. The threads of the bolts and the surfaces under the bolt heads and nuts are to be coated
with an anti-seize compound such as Felpro, type C5A Hi-Temp Anti-seize compound or
equal. The threads of the nuts should also be lubricated. Clean off excess lubricant with
solvent as noted in Item 2.
4. Clean off the gasket. Make sure that no foreign particles are stuck to it that might cause
a leak. Make sure the gasket is the correct size. It should fit inside the bonnet-body bolt
holes.
5. Place the bonnet in position; insert the bolts and hand tighten the nuts against the body.
A minimum of 2-1/2 threads should extend beyond each nut.
6. After the nuts are hand tight, follow the tightening sequence shown in the table. The
sequence shown is an illustrated method only, and the actual sequence is dependent
upon the total number of bolts.
7. The use of an air impact device which does not have a direct torque control is prohibited
for the torquing of body to bonnet bolts. The use of a hand torque wrench, electronic
torquing system, or power wrench with direct torque control is recommended. If such
equipment is not available, the following standard wrenches may be used:
Before tightening, make sure all surfaces that the fastener will contact are clean and dry.
The torque tightening table listed below applies to clean, undamaged, well lubricated threaded
fasteners. When tightening, use the sequence chart below. Tighten in two steps.
When tightening, use the sequence chart below. Tighten in two steps.
1. Tighten fastener using about 1/2 the final torque figure.
2. Final tighten using the full torque figure. ASTM A307 steel only.
Stop-check valves are as essential to the safe operation of a multi-boiler plant as any other
safety device that is attached to a boiler, and have four very important functions in the steam
piping systems.
1. To act as an automatic non-return valve by preventing the back flow of steam from the
header to the boiler in the event of failure in the boiler.
2. To assist in cutting a boiler out of the steam system when it has ceased to fire. In this case
the disc automatically closes and prevents the pressure in the header from entering the
boiler.
3. To assist in bringing a boiler into service after a shutdown. This operation requires
considerable care when performed manually, but is accomplished automatically by a stopcheck valve without pressure fluctuations or disturbance of the water level.
4. To act as a “safety first” valve by preventing back flow of the steam from the header into a
boiler that has been shut down for inspection should the valve be opened accidentally.
There are three basic questions regarding the NIBCO stop-check valve:
1. What is a stop-check valve?
2. Where is it used?
3. How does it work?
Question #1 – What is a stop-check valve?
The purpose of a stop-check valve is predominantly in the steam line at the boiler steam
riser. It allows steam to pass through it from the boiler to the main steam header, but in
case the boiler steam delivery is interrupted, the stop-check will automatically prevent
steam from flowing back into the boiler. The stop-check valve is a back flow preventer.
Its function is the same as the swing or lift check valve in that it allows flow in one
direction but not in the opposite direction.
A stop-check valve can also function as a stop and throttling valve the same way as a
globe pattern valve is used.
Question #2 – Where is a stop-check valve used?
The stop-check valve is designed to be used between the boiler steam exit and the
steam header in a multiple boiler plant to serve as a backflow preventer and stop valve.
Generally, there are two valves between the boiler and the header. One valve is a stopcheck valve and the other valve is a stop valve, either gate, angle or globe type. The two
valves are used to make maintenance more convenient and in most cases, are required
by code for the inspectors safety while inspecting the boiler (See sketch).
Question #3 – How does a stop-check valve work?
As stated in the answer to question #1, the stop-check valve in principle works like a lift
check valve but with two very important additional features:
1. A method is provided to control the rate of ascent and descent of the disc.
2. A means is provided to close the disc positively so that the fluids may not flow in
either direction regardless of the pressure differential.
Various manufacturers provide different methods of controlling dashpot movement. Basically,
the two methods are by spring tension or dashpot arrangement.
Lunkenheimer is the only manufacturer that produces a valve with an external spring tension
adjustment to control the disc movement. Other manufacturers, including NIBCO, use the less
complicated dashpot arrangement. NIBCO is the only manufacturer who supplies a valve with
an external control of the dashpot. All other popular manufacturer’s valves must be
disassembled so that the piston rings may be added or removed to respectively slow down or
speed up automatic disc movement.
Generally, all manufacturers provide a globe valve stem arrangement to positively close the
disc. This stem merely pushes down on the disc through the linkage on the Lunkenheimer
valve, or the dashpot piston on other valves (See sketch).
The purpose of the dashpot is to control the rate of ascent and descent of the disc so that the
disc does not slam and chatter in the line. Since valves are connected to a network of pipes in
the system, this would mean that the noise of a slamming and chattering disc could be
transmitted through the piping system. This noise is distracting in office buildings, hospitals, etc,
where concentration is essential. Moreover, the slam and chatter is extremely harmful to the
disc. It should also be noted that slamming and chattering of the disc causes pulsations within
the steam line which makes it very difficult for automatic steam regulator and other steam
equipment to function properly. Therefore, the disc must be controlled by some means of
dampening which, in most cases, is the dashpot.
The disc has a tendency to slam and chatter at various times. Usually the slam and chatter will
be obvious when the boiler is coming up to operating pressure. At this time, the steam is tending
to lift the disc and as it does the pressure in the boiler drops allowing the disc to fall and make
noise. Sometimes this is in the form of a slam, or it can be in the form of a chatter if it occurs
many times a minute. The disc can also make noise at periods when the boiler is at peak
delivery. Here the disc can rise rapidly banging up against the stem end or the dashpot housing
to cause noise.
We cannot stop the disc from coming into contact with the seat or stem, but we can and do
control the rate of impact to prevent loud noises in the piping system.
Finally, we come to the questions – How is this done? How does the dashpot work? How is the
adjustment made?
The dashpot is the same in principle as a shock absorber on an automobile. It does not prevent,
but rather controls the rate of movement. The dashpot must have fluid to displace. In the case of
the stop-check, this fluid is the fluid within the piping system, namely steam. All dashpots are
very similar to an air cylinder.
If one tries to push the disc-piston down in the cylinder, air will come out of the bottom of the
cylinder into Port A. Pushing the disc-piston up in the cylinder will cause air to be pushed
through Port A. Now if a throttle (dampener) valve is put on Port A and throttled very closely, the
same amount of force applied to push down the disc-piston will allow a much reduced rate of air
movement. This creates a partial vacuum in the cylinder. This reduces the rate of descent much
as ketsup is held in the bottom by a partial vacuum. So, when the disc bottoms out there will
only be a small click heard instead of a loud bang. The rate of travel will be controlled by the
dampener control valve being opened or closed.
We have now developed the principle on which the NIBCO stop-check valve was designed, only
now we add the principle of gravity and keep the air cylinder in the vertical position and add a
disc to have the following diagram.
Now note that Port B is merely a drilled hole at the bottom of the dashpot, which allows the
steam to enter and exit freely. Also, it serves to drain any resultant condensation. Port A, you
will note, has a control valve which can be throttled to allow steam to enter the chamber above
the piston, either rapidly for quick descent or slowly for a slow descent. This is a function of the
dashpot arrangement. It should be pointed out that the stop-check valve must always be in an
upright position with the handwheel on top of the valve. If this is not done there is no way that
the valve will work in its proper capacity.
Adjusting the F-869-B NIBCO Automatic Stop-Check Valve
The external control valve near the packing gland requires only a quarter turn to allow the disc
to descend or rise slowly or rapidly when the F-869-B valve is functioning as an automatic stop
and check valve (See sketch).
If slam or chatter exists in the line, the small control valve should be moved through 90° until the
noise no longer exists. At this point, the small packing nut on the control valve should be
tightened to assure the control valve does not move from its setting.
If a noise problem is still present and the steam delivery from the boiler is at a minimal operating
range, the delivery may have fallen below the range the valve was designed for. This may be
corrected by partially closing or “throttling” the valve by closing the handwheel. It is important to
remember the valve must be opened again when the boiler demand is increased. If the steam
delivery is changed to any great degree, the adjustment procedure may have to be repeated.
NOTE: 2-1/2” and 3” F-869-B stop-check valves do not have external disc control valves. The
disc control setting is made at the factory and permanently fixed.
Sizing the NIBCO F-869-B Automatic Stop-Check Valve
It has been said that the automatic stop-check valve is the most sophisticated valve in the
NIBCO line. One reason for this statement is the procedure required to select the proper size
stop-check valve for a given installation.
The obvious way to determine valve size is to match the pipe diameter. For the stop-check
valve this is not correct. In many boiler installations a valve smaller than pipe size could and
should be selected. There are cases where a 3” stop-check valve should be used on a 8”
header.
Size specification of the stop-check valve used on the boiler system is usually done by the
architect or engineer, but it should be possible for the NIBCO salesman or technical services to
assist the wholesaler or contractor in selecting the right valve if there is some doubt.
In order to size a stop-check valve, the technical information needed is saturated steam
pressure, maximum and minimum required steam volume flow in pounds per hour. This
information is then applied to the flow rates on the chart attached to determine proper valve
size.
Boiler “turn down ratio” must also be considered. If the turn down ratio is 4:1, this means the
boiler maximum output can be reduced to 25%.
Another technical question that comes up regarding our automatic stop-check valve is what
pressure is required to open the disc on various sizes?
The line pressure required to open the valve is a function of the disc and dashpot piston weight
and the size of the port diameter. For instance, on a 6” valve the weight of the piston is 7
pounds and the disc weighs 12-1/2 pounds for a combined weight of 19-1/2 pounds. The
diameter of the opening is 6” or an area of 28.2 inches squared. Therefore, the minimum
pressure required to open the valve, disregarding friction which is minimal, would be:
19.5 pounds for weight of piston = .7 PSI
28.2 inches squared
Due to the design of the valves, all sizes open with a .7 PSI differential across the seat,
providing the valve is properly installed (handwheel is in the open position), the valve has not
been damaged (for instance, the pilot on the disc has not been bent) and no foreign particles
from the line have cause the working parts to become inoperative.
In the event that a boiler does shut down, the stop-check valve must prevent backflow into the
boiler. The weight of the disc-piston, through the force of gravity, promotes rapid sealing so
steam and condensation cannot backflow into the boiler even at low pressures. The weight of
the disc and piston is very helpful, especially in low pressure systems. In the NIBCO stop-check
valves, you will note that the disc is mounted to permit the disc to settle into the seat area for
positive sealing in case there is any misalignment due to assembly or uneven heat expansion.
This feature also permits field repair of the valve seat without fear of improper assembly by field
mechanics.