ALL CABINETS MUST BE MOUNTED TO STUDS ON A SECURE WALL, AS PER THESE INSTRUCTIONS. FAILURE TO DO SO MAY RESULT IN SERIOUS INJURY AND VOIDS PRODUCT WARRANTY AND MANUFACTURER’S LIABILITY.
52” WORKTOP
WALL CABINET
LOCKER CABINET
1 DRAWER, 2 DOOR BASE CABINET
WARNING: DO NOT OVERLOAD CABINETS! CABINETS ARE DESIGNED TO
CARRY THE FOLLOWING
MAXIMUM WEIGHT CAPACITIES:
Cabinet Shelf Weight
Capacity (lbs)
Locker 50 300
Wall 40 100
2 Door Base 50 200
3 Drawer Base 40 200
1 Drawer, 2 Door Base 40 200
Overall Weight
Capacity
26” WORKTOP
2 DOOR BASE CABINET
WARNING: EXCESSIVE WEIGHT HAZARD
Use two or more people to move, assemble or install cabinet or locker.
Failure to do so can result in back or other injury.
DO NOT LEAVE CHILDREN UNATTENDED NEAR CABINETS. WHEN FULLY LOADED, CABINETS ARE HEAVY AND THERE IS A RISK OF CABINETS OR ITEMS TIPPING IF IMPROPERLY OPENED.
NEED MORE INFORMATION? TRY, 1 877 306 8930 FOR ANSWERS TO COMMONLY ASKED QUESTIONS.
STEEL WELDED BOLD AND DIAMOND PLATE SERIES
INSTALL INSTRUCTIONS
READ THE COMPLETE INSTRUCTIONS BEFORE UNPACKING CABINETS
TOOLS AND PARTS REQUIRED:
Gather the required tools and parts before starting installation.
TOOLS NEEDED:
Adjustable wrench or pliers
12” Magnetic Level
#2 Philips Bit
Cordless Power Drill with 7/16th socket attachment
Tape Measure
Stud Finder
Pencil
Hammer Drill with Masonry Bit (optional)
PARTS AND HARDWARE SUPPLIED WITH CABINETS:
Parts Base Locker Wall
“Base cabinets” include 2 Door Base, 3 Drawer Base and 2 Door Base with Drawer
Height-Adjustable Steel Leveling Legs 4 4 0
5/8” L x ¼” W Zinc Plated Bolt ( Philips Head) 16 16 0
Hex-Head Nut 16 16 0
Foot Plate Washers 16 16 0
#8 x 5/8” Wood Screw, Round Head with
Washer, Deep Thread with Speedpoint
Drawer Keys 1 1 1
Full Width Adjustable Shelves 1 3 1
2.5” L X ¼” W Cabinet Mounting Lag Bolts
(7/16th HEX HEAD)
Large Fender Washers 2 4 4
4 0 0
2 4 4
UNPACKING OF THE CABINETS:
Begin by placing the cabinet on a sound level surface.
Remove all cardboard and foam packaging material.
Remove clear plastic bag.
Dispose / recycle all packaging materials.
Remove and verify all the contents in the box. See “Parts and
Hardware Supplied List”
REMOVE THE LOCKER DOORS FIRST
Note: Applicable when base and wall cabinet are packed inside the locker cabinet To remove the base and wall cabinet from the inside of the locker, the locker doors must rst be unhinged and removed. To do this, pull down on the tab at the inside top of the locker door. Once the tab is pulled down, the L-shaped door hinge can be slid down and the door can be removed from the locker. BE CAREFUL NOT TO LET THE DOOR FALL
FORWARD, as this m
both doors. The base cabinet and wall cabinet can now be removed from the locker.
To re-install the doors, repeat the process in the opposite order. First t the door’s bottom hinge into the hole in the bottom of the locker frame. Re-insert the upper door hinge, and then align the hinge with the hole in the top of the locker frame. When these are aligned, you can push the tab back upwards and the hinge will be secured in place.