Munchkin T50M, 140M, 199M, T80M, 80M Maintance Manual

Page 1
HEAT TRANSFER PRODUCTS, INC.
120 BRALEY RD., E. FREETOWN, MA 02717
Installing, Operating & Maintaining
MUNCHKIN HIGH EFFICIENCY HEATER
with the “925” Controller
Do not store or use gasoline or other flammable vapors and
liquids in the vicinity of this or any other appliance.
WHAT TO DO IF YOU SMELL GAS
• Do not touch any electrical switch: do not use any phone in your building.
• Immediately call your gas supplier from a neighbor's phone. Follow the gas supplier's instructions.
• If you cannot reach your gas supplier, call the fire department. Installation and service must be performed by a qualified installer, service agency or the gas supplier.
WARNING
If the information in this manual is not followed exactly, a fire or explosion may result causing property damage, personal injury or loss of life.
WARNING
This manual must only be used by a qualified heating installer / service technician. Failure to comply could result in severe personal injury, death or substantial property damage. It is also important to keep these Instructions with the appliance.
MH27745
CONTROLS
Page 2
USING THIS MANUAL
2
DANGER
Indicates a condition or hazard which will
cause severe personal injury, death
or major property damage.
SPECIAL ATTENTION BOXES
Throughout this manual you will see these special attention boxes similar to this one, which are intended to supplement the instructions and make special notice of potential hazards. These categories mean, in the judgement of Heat Transfer Products, Inc.:
WARNING
Indicates a condition or hazard which may
cause severe personal injury,
death or major property damage.
WARNINGS
THIS UNIT IS FOR CATEGORY IV VENTING - 2 PIPE ONLY. THIS IS A SEALED COMBUSTION APPLIANCE.
THIS HEATER INSTALLATION MUST CONFORM TO THE LATEST EDITION OF THE “NATIONAL FUEL GAS CODE” ANSI Z223.1 NEPA 54 AND OR CAN/CGA B149 INSTALLATION CODES. STATE AND LOCAL CODES MIGHT ALSO APPLY TO INSTALLATION.
WHERE REQUIRED BY THE AUTHORITY HAVING JURISDICTION, THE INSTALLATION MUST CONFORM TO THE STANDARDS FOR CONTROLS AND SAFETY DEVICES FOR AUTOMATICALLY FIRED HEATERS, ANSI/ASME HEATER AND PRESSURE VESSEL CODE, Section IV, ALONG WITH CSD1.
THE HEATER, GAS PIPING, WATER PIPING, VENTING AND ELECTRICAL MUST BE INSTALLED BY TRAINED & QUALIFIED PERSONNEL FAMILIAR WITH INSTALLATION PRACTICES, LOCAL CODE, LICENSING REQUIREMENTS.
IF THE INFORMATION IN THESE INSTRUCTIONS ARE NOT FOLLOWED EXACTLY, A FIRE OR EXPLOSION MAY RESULT; CAUSING PROPERTY DAMAGE, PERSONAL INJURY, OR DEATH.
DO NOT STORE OR USE GASOLINE OR OTHER FLAMMABLE VAPORS AND LIQUIDS IN THE VICINITY OF THIS OR ANY OTHER APPLIANCE;
THE USE OF A LOW WATER CUT-OFF DEVICE MAY BE REQUIRED BY STATE OR LOCAL CODES IF THE MUNCHKIN IS INSTALLED ABOVE RADIATION LEVELS.
CAUTION
Indicates a condition or hazard which will or can cause minor personal injury or property damage.
USING THIS MANUAL
Page 3
TABLE OF CONTENTS
3
TABLE OF CONTENTS
PART 1 . . . . . . . . . . . . . . . . . . . . .4 thru 7
GENERAL INFORMATION
A How It Operates . . . . . . . . . . . . . . . . .4
B Munchkin Ratings and Dimensions . . .4
C Pre-installation Requirements . . . . . . .7
D Pressure Relief Valve . . . . . . . . . . . . . .7
PART 2 . . . . . . . . . . . . . . . . . . . . .8 thru 9
ELECTRICAL
A Electrical Connection . . . . . . . . . . . . . .8
PART 3 . . . . . . . . . . . . . . . . . . .10 thru 12
GAS CONNECTION
A Gas Connection . . . . . . . . . . . . . . . . .10
B Gas Piping . . . . . . . . . . . . . . . . . . . . .10
C Gas Table . . . . . . . . . . . . . . . . . . . . . .10
PART 4 . . . . . . . . . . . . . . . . . . .13 thru 21
VENTING
A Approved Venting Materials . . . . . . .13
B Venting the Munchkin in
2” or 3” Plastic Pipe . . . . . . . . . . . . .14
C Longer Vent Runs . . . . . . . . . . . . . . .16
D Heater Removal from a
Common Vent System . . . . . . . . . . .17
E Condensate Requirements . . . . . . . .21
PART 5 . . . . . . . . . . . . . . . . . . .22 thru 34
PIPING
A Hydronic piping with
Circulators or Zone Valves . . . . . . . .22
B Circulator Sizing . . . . . . . . . . . . . . . .23
C Fill and Purge Heating System . . . . .24
D Piping Illustrations . . . . . . . . . . . . . . .25
PART 6 . . . . . . . . . . . . . . . . . . .35 thru 37
START UP PROCEDURES
A Items to be checked before
lighting the Munchkin . . . . . . . . . . . .35
B Lighting Instructions . . . . . . . . . . . . .35
C Operating Instructions . . . . . . . . . . . .36
D Adjusting the Temperature
on the Munchkin Display . . . . . . . . . .36
E Status Menu . . . . . . . . . . . . . . . . . . .37
F To Turn Off Gas to Appliance . . . . . .37
PART 7 . . . . . . . . . . . . . . . . . . .38 thru 41
SERVICING
A Sequence of operation . . . . . . . . . . .38
B Munchkin Temporary
Fault Condition . . . . . . . . . . . . . . . . .38
C Munchkin Fault Requiring
Manual Reset . . . . . . . . . . . . . . . . . .39
PART 8 . . . . . . . . . . . . . . . . . . .42 thru 46
MAINTENANCE
A Maintenance Procedures . . . . . . . . . .42
B Before Each Heating Season . . . . . . .42
C Condensate Cleaning Instructions . . .42 D Combustion Chamber
Coil Cleaning Instructions . . . . . . . . .43
E Munchkin Controller . . . . . . . . . . . . .44
F Components Diagrams . . . . . . . .45–46
Page 4
GENERAL INFORMATION
4
B. MUNCHKIN RATINGS AND DIMENSIONS
PERFORMANCE RATINGS
CONNECTION SIZES
PART 1. GENERAL INFORMATION
A. HOW IT OPERATES
When the room thermostat calls for heat, the Munchkin control board will start the circulator and start to monitor the return temperature of the system before the heater will begin to heat the water. Once the controller has sensed a drop in the return water temperature below the temperature set point minus the differential set point, the heater will start to heat the water. This eliminates the Munchkin starting every time the thermostat calls for heat. This feature keeps the system from short cycling.
Once the system has sensed the temperature difference, the Munchkin will activate the blower motor for 5 seconds to pre-purge the system before starting the Munchkin
. The Munchkin controller will now start to modulate the pre-mix burner based on analyzing the return temperature, supply water temperature and the set point temperature. By compiling this information, the controller utilizes an algorithm to fully adjust the firing rate while maintaining the desired output temperature. The pre-mix burner fan has a direct drive current low-voltage motor with a pulse relay counting. This system allows precise control over the fan speed and combustion air volumes. Coupled with the Honeywell gas valve and the Venturi system which are set to provide a one-to-one ratio of precisely measured volumes of fuel to air, an accurate and instant burner output is achieved. This keeps the Munchkin running at the
highest efficiency.
When the thermostat is satisfied, the Munchkin will then go through a 4 second post-purge cycle before shutting off. Every Munchkin heater is equipped with a display which will read the outlet temperature of the heater and then will illuminate a green light showing flame on. If a problem occurs, the front indicator light will turn red and the display will read a fault code; see Part 7, Section B/C, pages 38 and 39.
ledoMnoitaludoMtupnIgnitaeHEODEUFAthgieWgnippihSRBI
M05T000,05ot000,81000,64ot000,61%29.sbl85000,04 M08T000,08ot000,91000,47ot000,71%29.sbl85000,46
M08000,08ot000,72000,47ot000,52%29.sbl57000,46
M041000,041ot000,64000,921ot000,34%29.sbl101000,211 M991000,991ot000,66000,381ot000,16%29.sbl111000,951
ledoM
M05TTPN"4/1"4/3"2 M08TTPN"4/1"4/3"2
M08TPN"4/1"4/3"3
M041TPN"4/1"4/3"3 M991TPN"4/1"4/3"3
nruteR/ylppuS
noitcennoCeziSnoitcennoCsaG.aiDtneV
Page 5
GENERAL INFORMATION
5
Figure 1-1
(NOTE: The Munchkin is rated at zero clearance to combustibles.)
Figure 1-3
T50M/T80M
80M/140M/199M T50M/T80M
DIMENSIONS
RECOMMENDED SERVICE CLEARANCES
Figure 1-2
Page 6
GENERAL INFORMATION
6
DIMENSIONS
80M
140M/199M
Figure 1-4
Figure 1-5
Page 7
7
GENERAL INFORMATION
C. PRE-INSTALLATION REQUIREMENTS
The Munchkin is designed for installation on non-rated flooring, in alcoves, basements, utility rooms, and closet but never a bedroom closet. Choose a location for your Munchkin, centralized to the piping system, along with consideration for Electrical (Part 2, Page 8), Gas Connection (Part 3, Page 10) and Venting (Part 4, Page 13).
If the Munchkin is set up for liquefied petroleum (LP) gas, some geographic areas follow the Uniform Mechanical Code, section 304.6, “Liquefied petroleum gas burning appliances shall not be installed in a pit, basement or similar location where heavier-than-air gas might collect. Appliances so fueled, shall not be installed in a below grade under-floor space or basement unless such location is provided with an approved means for removal of unburned gas.”
WARNING
The Munchkin is certified as an indoor appliance. Do not install the Munchkin outdoors or locate where it will be exposed to freezing temperature. This includes all related piping and components. If the Munchkin is subjected to flood water or submersed in water, the Munchkin must be replaced.
NOTICE
Service clearance of the Munchkin: See Section 1, Figures 1-1 and 1-2.
NOTICE
Condensation removal: This is a condensing high efficiency appliance, therefore
condensation removal must be addressed to avoid damage to surrounding area or appliance. See Part (4) Section E for Condensate Requirements (pg. 21).
WARNING
D. PRESSURE RELIEF VALVE
A pressure relief valve is installed into the front right side manifold. We recommend a WATTS ¾" M 335 MI valve or equivalent and meets the requirements of ANSI/ASME Heater and Pressure Vessel Code, Section IV or CSA B51; Heater, Pressure Vessel and Piping Code as applicable for heating heaters. A ¾" pipe must be directed to a floor drain or suitable location within 6" of a drain or floor. Protect from freezing, do not plug or cap pressure relief valve. Serious explosion causing property damage and or loss of life could result. Under no circumstances should the relief valve be eliminated, capped or plugged.
Page 8
8
ELECTRICAL
PART 2. ELECTRICAL
A. ELECTRICAL CONNECTION
The electrical connection for the Munchkin is on the left hand side of the unit. There is a ½” knockout location for an electrical connection for both the incoming power and the central heating circulator connection. All electrical wiring must be performed by a qualified licensed electrician in accordance with National Electrical Code ANSI/NEPA to and/or the Canadian Electrical Code, Part 1 CSA C22.1, or to the applicable codes and standards. For your convenience, we have labeled all the wires that need to be connected to operate the Munchkin.
The electrical requirements are for standard 120 volts, 60 Hz 15 Amp service. This unit is wired with #18 awg and fused for no more than 15 Amps.
There are two ground points in the electrical compartment that must be connected to the building ground system. Connect the building ground to the green ground screw and the green ground wire inside electrical box provided.
The Incoming Power Supply is connected to the Black (Hot) and the White (Neutral).The Munchkin Control board is polarity sensitive. If the polarity is reversed, the Munchkin control will not sense a flame and lock out the system. The Orange and Brown wire are provided to the supply of 120 volts to the Central Heating Circulator. Connect the Orange (Hot) and the Brown (Neutral) directly to the Central Heating Circulator.
Connect the gray wires to your heating thermostat (TT) connection. Your thermostat heat anticipator setting is .056 amp.
CAUTION
Electrical wiring on the Incoming Power and Central Heating Circulator shall be connected directly to the intended connection source and not be connected together inside the electric box provided. An Electrical Short will result and the Control board will have to be replaced! If Electrical Requirements of the Central Heating Circulator exceeds 4 amps (or 3 amps on HA models only) please follow the wiring diagrams on Page 9, Figures 2-1, 2-2 and 2-3.
DANGER
IT IS EXTREMELY IMPORTANT THAT THIS UNIT BE PROPERLY GROUNDED!
DANGER
IT IS VERY IMPORTANT THAT THE BUILDING GROUND IS INSPECTED BY A QUALIFIED ELECTRICIAN PRIOR TO MAKING THIS CONNECTION!
DANGER
The Orange wire for the Central Heating Circulator is Switched Hot and must have a wire nut if not connected to the Central Heating Circulator. Failure to follow this instruction will result in a short, and the Control Board will have to be replaced.
Page 9
9
ELECTRICAL
It is important that the electrical power is not turned on at this time. Double check all connections and then turn the power on. The display that is provided with the Munchkin should now be reading the outlet temperature. Note: see Part 6/Startup Procedure section in the manual to change the temperature setting or run the heater.
NOTICE
Do not power zone valves directly from the heater transformer. Doing so will greatly reduce the life of the transformer. Use a separate transformer sized to handle the total electric load of all zone valves.
Figure 2-1: Connection Wiring Directly to Central Heating Circulator
Figure 2-2: Connection Wiring without Wiring Central Heating Circulator
Note to Electrical Contractor: The orange wire is 120 Volt/4 Amp maximum for central
heating circulator only. Loads greater than 4 amps or 3 amps for HA models only will blow the fuse on the board. The brown wire is the neu­tral wire for the central heating pump only.
Figure 2-3: For circulator amp loads greater than 4 amps (3 amps for “HA” models) use the wiring diagram shown at left. The brown and orange wires will not be used in this application.
5
T
1
2
3
6
4
T
1K1 1K2
BOILER
"TT"
GRAY
ZONE
CIRCULATOR
120 VOLT
L1 HOT (BLACK)
GRAY
BOILER
"TT"
THERMOSTAT
ZONE
R845A
SWITCHING
RELAY ZONE
1K1
L2 NEUTRAL
(WHITE)
DIAGRAM "A"
WIRING DIAGRAM CONNECTING TO CIRCULATOR
GREEN (GROUND)
WHITE (NEUTRAL)
BLACK
NORMALLY OPEN
THERMOSTAT
CONNECTION
GRAY
T
GRAY
T
BROWN (NEUTRAL)
ORANGE (HOT)
GREEN (GROUND)
(NEUTRAL)
ELECTRICAL
SWITCH JUNCTION BOX
120V 60 HZ
WHITE
(GROUND)
GREEN
BLACK (HOT)
DIAGRAM "B"
WIRING DIAGRAM WITHOUT CONNECTION TO CIRCULATOR
IMPORTANT NOTE:
N
BE CERTAIN THAT THE ORANGE WIRE IS SECURELY CAPED.
GREEN
ORANGE
NORMALLY OPEN
THERMOSTAT
CONNECTION
GRAY
T
GRAY
T
BROW
ORANGE (HOT)
BROWN (NEUTRAL)
SWITCH JUNCTION BOX
120V 60 HZ
FAILURE TO DO SO COULD RESULT IN INJURY OR FIRE AND COULD DAMAGE THE CONTROL.
WHITE
(NEUTRAL)
GREEN (GROUND)
GREEN
(GROUND)
ELECTRICAL
BLACK (HOT)
GROUND
BUS
Page 10
10
GAS CONNECTION
PART 3. GAS CONNECTION
A. GAS CONNECTION
The gas supply shall have a maximum inlet pressure of less than 14" water column (350 mm), ½ pound pressure (3.4 kPa), and a minimum of 7" water column. The entire piping system, gas meter and regulator must be sized properly to prevent pressure drop greater than 0.5" as stated in the National Fuel Gas Code. This information is listed on the rating plate. It is very
important that you are connected to the type of gas as noted on the rating plate. "LP" for liquefied petroleum, propane gas or, "Nat" natural or
city gas. All gas connections must be approved by the local gas supplier, or utility in addition to the governing authority, prior to turning the gas supply on. The nipple provided is ½" and it is mandatory that a ¾" to ½" reducing coupling (provided) is used, threaded into the branch of a ¾" tee, and a drip leg fabricated, as per the National Fuel Gas code. You must ensure that the entire gas line to the connection at the Munchkin is no smaller than ¾". Once all the inspections have been performed, the piping must be leak tested. If the leak test requirement is a higher test pressure than the maximum inlet pressure, you must isolate the Munchkin from the gas line. In order to do this, you must shut the gas off using factory and field-installed gas cocks (following the lighting instructions in Part 6 Section B.) This will prevent high pressure. Failure to do so may damage the gas valve. In the event the gas valve is exposed to a pressure greater than ½ PSI, 14" water column, the gas valve must be replaced. Never
use an open flame (match, lighter, etc.) to check gas connections.
B. GAS PIPING
1. Run the gas supply line in accordance with all applicable codes.
2. Locate and install manual shutoff valves in accordance with state and local requirements.
C. GAS TABLE
Refer to Table (1) to size the supply piping to minimize pressure drop between meter or regulator and unit.
Maximum Capacity of Pipe in Cubic Feet of Gas per Hour for Gas Pressures of 0.5 psi or Less and a Pressure Drop of 0.3 Inch water Column
(TABLE 1) (Based on a 0.60 Specific Gravity Gas)
Nominal Iron Pipe Internal Length of Pipe (Feet) Size Diameter (inches) (inches) 10 20 30 40 50 60 70 80 90 100 125 150 175 200. 3/4 .824 278 190 152 130 115 105 96 90 84 79 72 64 59 55} BTU'S
1 1.049 520 350 285 245 215 195 180 170 160 150 130 120 110 100} PER 1 1/4 1.380 1,050 730 590 500 440 400 370 350 320 305 275 250 225 210} HOUR 1 1/2 1.610 1,600 1,100 890 760 670 610 560 530 490 460 410 380 350 320} X 1,000
WARNING
Failure to follow all precautions could result in fire, explosion or death!
Page 11
11
GAS CONNECTION
It is recommended that a soapy solution be used to detect leaks. Bubbles will appear on the pipe to indicate a leak is present. The gas piping must be sized for the proper flow and length of pipe, to avoid pressure drop. Both the gas meter and the gas regulator must be properly sized for the total gas load. If you experience a pressure drop greater than 1" WC, the meter, regulator or gas line is undersized or in need of service. You can attach a manometer to the incoming gas drip leg, by removing the cap and installing the manometer. The gas pressure must remain between 7" and 14" during stand-by (static) mode and while in operating (dynamic) mode. If an in-line regulator is used, it must be a minimum
of 10 feet from the Munchkin. It is very important that the gas line is properly purged by the gas supplier or utility. Failure to properly purge the lines or improper line sizing, will result in ignition failure. This problem is especially noticeable in NEW LP installations and also in empty tank situations.
This can also occur when a utility company shuts off service to an area to provide maintenance to their lines. This gas valve must not be replaced with a conventional gas valve under any circumstances. As an additional safety feature, this gas valve has a flanged connection to the Venturi and blower.
MUNCHKIN GAS VALVE
Fig. 3-1
DO NOT REMOVE THIS SCREW
OR ATTEMPT TO MAKE
ANY ADJUSTMENT TO THIS SCREW.
OUTLET PRESSURE TAP
INLET PRESSURE TAP
THROTTLE ADJUSTMENT SCREW.
NOTE: IF FOR ANY REASON THE SCREW IS ADJUSTED, A "COMBUSTION ANALYZER" MUST BE USED TO ENSURE SAFE AND PROPER OPERATION. TURNING THE SCREW CLOCKWISE DECREASES YOUR GAS FLOW WHICH WILL LOWER THE CO/CO2 % LEVELS. TURNING THE SCREW COUNTER-CLOCKWISE INCREASES YOUR GAS FLOW WHICH WILL RAISE THE CO/CO2 % LEVELS.
OUT
MIN
24 VOLT DC ELECTRICAL CONNECTION
V1
V2
1/2" NPT
GAS INLET
AIR INLET, KEEP FREE OF DEBRIS
Page 12
12
GENERAL INFORMATION
WARNING
Failure to follow all precautions could result in fire, explosion or death!
Fig. 3-3
Fig. 3-2
T50M/T80M GAS VALVE
COMBUSTION SETTINGS
HIGH FIRING RATES and LOW FIRING RATES ON ALL MODELS
Natural Gas Propane LP
high
Carbon CO ppm
Monoxide
Carbon CO
Dioxide
2%
low high
0-20 ppm
8-1/2 % - 9-1/2 %
80 ppm - 135 ppm
8-1/2 %- 9-1/2 %
low
0-20 ppm 80 -150 ppm
9-1/2 %- 10-1/2 % 9-1/2 %- 10-1/2 %
Page 13
13
VENTING
PART 4. VENTING
A. APPROVED VENTING MATERIALS
Exhaust V
ent and Extensions
in Plastic 2", 3" and 4" Pipe Schedule 40 or 80.
1. Non Foam Core PVC Pipe
2. Non Foam Core CPVC Pipe
3. Non Foam Core ABS Pipe
Vent Piping must conform to following
1. PVC Non Foam Core Pipe (Polyvinyl Chloride) to ASTM D-1784 Class 12454-B, Formerly desig­nated Type 1, Grade 1.
2. CPVC (Chlorinated Polyvinyl Chloride) Class 23447-B, Formerly designated Type IV, Grade 1 con­forming to ASTM D-1784.
3. ABS (Acrylonitrile-Butadiene-Styrene) Class 3-2-2-2-2 conforming to ASTM D3965.
The Munchkin is a direct vent appliance. The Munchkin is listed as a Category IV Condensing Appliance. (The Munchkin Venting is rated at Zero Clearance to combustibles.)
Note: For Concrete construction or to meet certain fire codes, exhaust and inlet piping at the wall penetration to the Munchkin must be CPVC Schedule 40 or 80 to meet local fire codes. The balance from the penetrated wall to the outside, may be PVC Schedule 40 or 80.
Inlet Air V
ent
Use the same material as used for exhaust in either 2", 3" or 4" Plastic Pipe. Cellular Foam Core Pipe may be used for the inlet only, NEVER ON EXHAUST PIPING!
DANGER
It is extremely important to follow these venting instructions carefully. Failure to do so can cause severe personal injury, death or substantial property damage.
DANGER
Foam Core Pipe is not to be used in connecting the exhaust pipe.
WARNING
This vent system will operate with a positive pressure in the vent pipe. Do not connect vent connectors serving appliances by natural draft into any portion of mechanical draft systems operating under positive pressure.
Page 14
14
VENTING
B. VENTING THE MUNCHKIN
The inlet pipe on the back of the cabinet should be 3" PVC schedule 40. It is very important that you plan the location properly to eliminate long pipe runs and excessive fittings. Inlet pipe size must not be reduced. Do not combine the inlet air with any other inlet pipe including an inlet to an additional similar appliance. The joints must be properly cleaned, primed and cemented. The piping must also be properly supported as per Local and National Standard Plumbing Codes. It is important that the piping must be clean and free from burrs, debris, ragged ends and particles of PVC.
Exhaust piping should be sloped back to the connection on the Munchkin, at least ¼" per foot to remove additional condensate that forms within the pipe. The total combined length of pipe (intake piping plus exhaust piping added together) including elbow allowances intake and exhaust (each elbow = 5' of pipe) should not exceed 85'. The combined vent length should not be less than a com­bined length of 6' plus two 90 degree elbows. Choose your vent termination locations carefully. You must also make certain that exhaust gas does not re-circulate back into the intake pipe. You must place them in an open area and follow the following guidelines.
1) Never vent into a walkway, patio area, alley or otherwise public area less than 7' from the ground. (See the following detail references Fig. A.10.8 in the National Fuel Gas Code 2002 “Exit Terminals of Mechanical Draft and Direct-Venting Systems”.)
2) Never vent over or under a window or over a doorway where the exhaust plume or conden­sation liquid will cause obtrusive or dangerous conditions. (Or refer to National Fuel Gas Code, CAN B149)
3) Never install a heat saver or similar product to capture waste heat from exhaust.
4) Always have a vent location at least 1' above maximum snow level.
5) Always have vent 1' above ground level, away from shrubs and bushes.
6) Follow local gas codes in your region or refer to National Fuel Gas Code, Can B149.
7) Always have at least 3' from an inside corner of outside walls.
8) Maintain at least 4' clearance to electric, gas meters, windows, exhaust fans, chimneys, inlets or mechanical vents.
9) Very Important! The inlet air connection must be connected to outside air and should be located no closer than 8" to the exhaust and no further than 36".
10) Always place screens in all openings in intake and exhaust to prevent foreign matter from entering the Munchkin.
11) The vent intake and exhaust must be properly cleaned and glued for a pressure tight joint. Several methods for venting the Munchkin can be found in Figures 4-1 thru 4-6, this section pages 18 and 20. Use these layouts as guidelines: certain site conditions such as multiple
DANGER
It is extremely important to follow these venting instructions exactly. Failure to do so can cause severe personal injury, death or substantial property damage.
NOTICE
The following are code restrictions for the location of the flue gas vent terminal. Compliance to these requirements doesn’t insure a satisfactory installation; good common sense must also be applied. It is important to make sure that exhaust gases are not recirculated into the inlet air of the Munchkin.
Page 15
15
roof lines/pitches may require venting modifications (consult factory). The air inlet must be a minimum of 1' vertically above the maximum snow level. It is very important that there are no other vents, chimneys or air inlets in any direction for at least 4'.
All venting must be properly supported. The Munchkin is not intended to support any venting whatsoever. All piping, glue, solvents, cleaners, fittings and components, must conform to ASTM
(American Society for Testing and Materials), and ANSI (American National Standards Institute). It is recommended that you use one of the optional vent kits specifically designed for Munchkin installa­tions, available from Heat Transfer Products, Inc. (KGAVT0601CVT [3 in.], KGAVT0501CVT [2 in.] or V1000). NOTE: When using the KGAVT601CVT KIT, REMOVE THE 2 SCREENS FROM THE PROVID­ED INLET TEE AND INSTALL THEM IN THE INLET SOCKET AND OUTLET SOCKET (Y TEE CON­NECTION) OF THE KIT PRIOR TO INSTALLING THE SCHEDULE 40 PIPE AND GLUING.
*Note: The V1000 when used for the T50 or T80 will require a transition piece from 2" to 3".
VENTING
CAUTION
Flue Gas will condense as it exits the vent termination. This condensate can freeze on exterior building surfaces which may cause discoloration of these surfaces. Consideration should be given to the plume of condensation that exits the exhaust which may affect the cosmetic appearance of the building.
echanical
M
ent
raft v
d
al
in
rm
te (see 10.8.1)*
raft
ical d
echan
M
al
in
12 in.m
vent term (see 10.8.2)*
inimum
Less
than 10 ft.
3 ft.minimum
Forced air inlet
rade
G
C
12 in.minimum
Direct vent terminal clearance Minimum clearance, C
Input (Btu/hr) 10,000 or less 10,001 to 50,000
Over 50,000 (see 10.8.3)*
For SI units: 1 ft = 0.305 m; 1 in. = 25.4 mm; 1 Btu/hr = 0.293 W
Clearance (in.)
6 9
12
inim
4 ft.m
12 in.minimum
um
4 ft.
minimum
EXIT TERMINALS OF MECHANICAL DRAFT
AND DIRECT-VENT VENTING SYSTEM
* REFERENCE: THE NATIONAL FUEL GAS CODE
2002 EDITION
Page 16
16
VENTING
Friction Loss Equivalent in Piping and Fittings
Fittings or Piping Equivalent Feet
90 degree elbow = 5 45 degree elbow = 3 Coupling = 0 air inlet tee = 0 Plastic Pipe = 1 concentric vent kit = 3 V1000 vent kit = 0
Example: Installation requires the following material for both inlet and exhaust piping for the Munchkin
Required: 4 Pcs. (2" or 3") 90 degree elbow (4 x 5 = 20 Equivalent Feet) = 20 Equivalent Feet
Required: 20' of (2" or 3") Plastic PVC Pipe (20 x 1 = 20 Equivalent Feet) = 20 Equivalent Feet
Total Friction Loss in Equivalent Feet (20 + 20 = 40 Equivalent Feet) = 40 Equivalent Feet
C. LONGER VENT RUNS
The connection of the air inlet and exhaust vent at the heater must remain at the standard vent size from the unit (2" for the T50/T80) (3" for the 80M/140M/199M). If a transition is required, it must occur at a minimum of 5 feet from the unit for both intake and exhaust and no greater than 15 feet. Then transition to the next size pipe. See the friction loss equivalent table to apply longer vent runs. The overall extended combined length of pipe on the inlet and exhaust must not exceed 125 equivalent feet total.
Example: Installation requires the following material for both the inlet and exhaust piping when extending the vent run for the Munchkin.
3" Vented Appliance
2 Pcs. – 3" 90 degree elbow (2 x 5 = 10 Equivalent Feet) = 10 Equivalent Feet 20' of 3" Plastic PVC Pipe (20 x 1 = 20 Equivalent Feet) = 20 Equivalent Feet
Total of 3" Equivalent Piping with Fittings = 30 Equivalent Feet
Transitioning to 4" Venting
6 Pcs. – 4" 90 degree elbows (6 x 3 = 18 Equivalent Feet) = 18 Equivalent Feet 4 Pcs. – 4" 45 degree elbows (4 x 1 = 4 Equivalent Feet) = 4 Equivalent Feet 40' of 4" Plastic PVC Pipe (40 x 1 = 40 Equivalent Feet) = 40 Equivalent Feet
Total of 4" Equivalent Piping with Fittings = 62 Equivalent Feet
Total Friction Loss in Equivalent Feet for both 3" and 4"
(30 + 62 = 92 Equivalent Feet) = 92 Equivalent Feet
NOTICE
Do not exceed the 85 foot maximum requirement (intake plus exhaust piping added together) including fitting allowance.
WARNING
Transitioning from 2" to 3" or 3" to 4" should be done in the Vertical position to avoid condensation blockage. If done in the horizontal position check to make sure condensation blockage will not occur.
Page 17
17
D. HEATER REMOVAL FROM A COMMON VENT SYSTEM
At the time of removal of an existing heater, the following steps shall be followed with each appli­ance remaining connected to the common venting system placed in operation, while the other appli­ances remaining connected to common venting system are not operating.
1. Seal any unused openings in the common venting system.
2. Visually inspect the venting system for proper size and horizontal pitch to determine if there is blockage, leakage, corrosion or other deficiencies that could cause an unsafe condition.
3. If practical, close all building doors, windows and all doors between the space in which the appliance remains connected to the common venting system located and other spaces in the building. Turn on clothes dryers and any appliances not connected to the common venting system. Turn on any exhaust fans, such as range hoods and bathroom exhausts, at maximum speed. Do not operate a summer exhaust fan. Close all fireplace dampers.
4. Place in operation the appliance being inspected. Follow the lighting instructions. Adjust the thermostat so the appliance will operate continuously.
5. Test for spillage at the draft hood relief opening after 5 minutes of main burner operation. Use the flame of a match or candle or smoke from a cigarette.
6. After it has been determined that each appliance remaining connected to common venting system properly vents when tested as outlined, return doors, windows, exhaust fans, fire­place dampers and any other gas burning appliance to their previous condition of use.
7. Any improper operation of the common venting system should be corrected so the installa­tion conforms with the National Fuel Gas Code, ANSI Z223.1. When resizing any portion of the common venting system, the common venting system should be resized to approach the minimum size as determined using the appropriate tables in Appendix G in the National Fuel Gas Code , ANSI Z 223.1
DANGER
The Munchkin is not intended to be common vented with any other
existing appliance!
Page 18
18
VENTING
**IMPORTANT NOTE: All vent pipes must be glued, properly supported and the exhaust must be pitched a minimum of a ¼" per foot back to the heater (to allow drainage of condensate).
Figure 4-1
**IMPORTANT NOTE: All vent pipes must be glued, prop­erly supported and the exhaust must be pitched a mini­mum of a ¼" per foot back to the heater (to allow drainage of condensate).
Figure 4-2
DIAGRAMS FOR SIDEWALL VENTING
Page 19
VENTING
19
**IMPORTANT NOTE: All vent pipes must be glued, properly supported and the exhaust must be pitched a minimum of a ¼" per foot back to the heater (to allow drainage of condensate).
Figure 4-3
**IMPORTANT NOTE: All vent pipes must be glued, properly supported and the exhaust must be pitched a minimum of a ¼" per foot back to the heater (to allow drainage of condensate).
Figure 4-4
Page 20
VENTING
20
**IMPORTANT NOTE: All vent pipes must be glued, properly supported, and the exhaust must be pitched a minimum of a ¼" per foot back to the heater (to allow drainage of condensate).
Figure 4-5
**IMPORTANT NOTE: All vent pipes must be glued, properly supported, and the exhaust must be pitched a minimum of a ¼" per foot back to the heater (to allow drainage of condensate).
Figure 4-6
DIAGRAMS FOR VERTICAL VENTING
Page 21
21
VENTING
E. CONDENSATE REQUIREMENTS
This is a condensing high efficiency appliance, therefore this unit has a condensate removal system. Condensate is nothing more than water vapor, derived from the combustion products, similar to an automobile when it is initially started. This condensate does have a low PH and should be treated with a condensate filter. This filter contains either lime crystals or marble crystals, which will neutralize the condensate. The outlet of the filter is sized for 5/8" ID (Inside diameter) plastic tubing. It is very important that the condensate line is sloped away from and down to a suitable inside drain, if the condensate outlet on the Munchkin is lower than the drain, you must use a condensate removal pump. A condensate filter and a condensate pump kit are available from Heat Transfer Products, Inc. It is also very important that the condensate line is not exposed to freezing temperatures, or any other type of blockage. Plastic tubing should be the only material used for the condensate line. Steel, brass, copper or others will be subject to corrosion and deterioration. A second vent may be necessary to prevent condensate line vacuum lock if a long horizontal run is used. Also, an increase to 1" tubing may be necessary.
Page 22
22
PIPING
PART 5. PIPING
A. HYDRONIC PIPING WITH CIRCULATORS OR ZONE VALVES
The Munchkin is designed to function in a closed loop 15 PSI System. To assure you that you have adequate pressure in the system, we have installed in the outlet manifold, a pressure switch that will not let the Munchkin operate without a minimum of 10 PSI water pressure. This assures you that if the system does have leak, the Munchkin will lock out (PRO on the display) before it damages the Stainless Steel Heat Exchanger. We have also included a Temperature and Pressure gauge which should be located on the Munchkin outlet to monitor the system pressure and outlet temperature from the Munchkin. It is important to note that the Munchkin has a minimal amount of pressure drop and must be figured in when sizing the circulators. Each Munchkin installation must have an Air Elimination device which will remove air from the system. Install the Munchkin so the gas ignition system components are protected from water (dripping, spraying, etc.) during appliance operation for basic service of circulator replacement, valves and other. Observe minimum 1” clearance around all un­insulated hot water pipes when openings around pipes are not protected by non-combustible materials. On a Munchkin installed above radiation level, some states and local codes require a low water cut off device at the time of installation. If the Munchkin supplies hot water to heating coils in air handler units, flow control valves or other devices must be installed to prevent gravity circulation of heater water in the coils during the cooling cycle. Chilled Water Medium must be piped in parallel with the heater. Freeze Protection for new or existing systems must use glycol that is specially formulated for this purpose. It includes inhibitors, which prevent the glycol from attacking the metallic system components. Make certain that the system fluid is checked for the correct glycol concentration and inhibitor level. The system should be tested at least once a year and as recommend by the producer of the glycol solution. Allowance should be made for the expansion of the glycol solution in the system piping. Example 50% by volume solution expands 4.8% in volume for the temperature increase from 32 F to 180 F, while water expands 3% with the same temperature rise.
Basic steps are listed below, with Illustration, which will guide you through the installation of the Munchkin.
1. Connect the system return marked “Heater In”, make sure to install with pipe sealant com­pound. Threaded connections are 1 ¼” NPT Brass nipples located on the left hand side of unit.
2. Connect the system supply marked “Heater Out”, make sure to install with pipe sealant com­pound. Threaded connections are 1 ¼” NPT Brass nipples located on the left hand side of the unit.
3. Install Purge and Balance Valve or shut off valve and drain on system return to purge air out of each zone.
4. Install a Back Flow preventor on the Cold Feed Make-Up Water line.
5. Install a Pressure Reducing Valve on the Cold Feed Make-Up Water line, (15 PSI nominal on the system return). Check Temperature and Pressure Gauge which should read minimum pressure of 12 PSI.
6. Install a circulator on system supply. Make sure the circulator is properly sized for the system and friction loss.
7. Install an Expansion Tank on the system supply. Consult the tank manufacturer’s instruction for specific information relating to tank installation. Size the expansion tank for the required system volume and capacity.
CAUTION
The Munchkin should not be operated as a potable Hot Water Heater. It should not be used as a direct Hot Water Heating Device.
Page 23
23
PIPING
8. Install an Air Elimination Device on the system supply.
9. Install a drain valve at the lowest point of the system. Note: The Munchkin can not be drained completely of water without purging the unit with an air pressure 15 PSI.
10. The Safety Relief Valve is installed at the factory located on the right hand side of Munchkin. Pipe the discharge of safety relief valve to prevent injury in the event of pressure relief. Pipe the discharge to a drain. Provide piping that is the same size as the safety relief valve outlet. Never block the outlet of safety relief valve.
11. In compliance with ASME CSD-1, a low water cut-off device should be properly connected in the field, both electrically and mechanically.
See the piping illustrations included in this section, pages 25–34, Figs. 5-3 to 5-11 for suggested guidelines in piping the Munchkin heater with either zone valves or circulator pumps. *Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes.
B. CIRCULATOR SIZING
The Munchkin Heat Exchanger does have pressure drop which must be considered in your system design. Refer to the graph below for pressure drop through the Munchkin Heat Exchanger.
Figure 5-1
20 19 18 17 16 15 14 13 12 11 10
9 8 7 6 5
Friction in Feet of Head
4 3 2 1 0
123456789101112131415161718192021
Flow in Gallons per Minute
MUNCHKIN 50M MUNCHKIN 80M MUNCHKIN 140M MUNCHKIN 199M
* THE RECOMMENDED CIRCULATORS ARE BASED ON 1 GPM PER 10,000 BTU/HR W/20
BOILER TACO P/N GRUNDFOS P/N
50M/80M 007 * 15-42 F SPD-2
140M 0010 * 26-64 F 199M 0011 * 26-96 F
Page 24
24
PIPING
C. FILL AND PURGE HEATING SYSTEM
Attach the hose to balance and purge hose connector or drain valve and run hose to near­est drain
Close the other side of the balance and purge valve or the shut off valve after the drain.
Open first zone balance and purge or drain valve to let water flow out the hose. If zone valves are used, open the valves one at a time manually. (Note: please check valve manu­facturer’s instruction prior to opening valves manually, so as not to damage the valve.)
Manually operate fill valve regulator. When water runs out of the hose, while it’s connect­ed to the balance and purge valve or drain you will see a steady stream or water (with no bubbles). Close balance and purge valve or drain to stop the water from flowing. Disconnect the hose and connect it to next zone to be purged.
Repeat this procedure for additional zones (one at time).
Upon completion, make sure that the fill valve is in automatic position and each zone balance and purge or shut off is in an open position and zone valves are positioned for automatic operation.
1. Glycol in hydronic applications which is specially formulated for this purpose includes inhibitors which prevent the glycol from attacking metallic system components. Make certain that the system fluid is checked for the correct glycol concentration and inhibitor level.
2. The glycol solution should be tested at least once a year and as recommended by the glycol manufacturer.
3. Anti-freeze solutions expand more than water. For example a 50% by volume solution expands 4.8% in volume for a temperature increase from 32° F to 180° F, while water expands 3% with the same temperature rise. Allowances must be made for this expansion in the sys­tem design.
4. A 30% mixture of glycol will result in a BTU output loss of 15% with a 5% increase in head against system circulator.
5. A 50% mixture of glycol will result in a BTU output loss of 30% with a 50% increase in head against system circulator.
CAUTION
For installation that incorporates standing Iron Radiation and systems with manual vents at the high points. Follow above section and starting with the nearest manual air vent, open vent until water flows out, then close vent. Repeat procedure, working your way toward furthest air vent. It may be necessary to install a basket strainer in an older system where larger amounts of sediment may be present. Annual cleaning of the strainer may be necessary.
WARNING
Use only inhibited propylene glycol solutions which are specially formulated for hydronic systems. Ethylene glycol is toxic and can attack gaskets and seals used in hydronic systems.
Page 25
25
PIPING
D. PIPING ILLUSTRATIONS
Fig. 5-2
Piping Symbol Legend
circulator (w/ isolation flanges)
circulator w/ integral flow check
gate valve
globe valve
ball valve
swing-check valve
flow-check valve spring-loaded check valve
hose bib / boiler drain
TRV (straight)
pressure reducing valve
diff. pressure bypass
3-way thermostatic
Munchkin heater
pressure gauge
4-way motorized mixing valve
3-way motorized mixing valve
pressure relief valve P&T relief valve
backflow preventer
TRV angle
circuit setter
manual 3-way valve
zone valve
air separator
diaphragm-type expansion tank
float -type air vent
union temperature / pressure
T/P
radiant manifold
gauge
heat exchanger
Super Stor
indirect DHW tank
Page 26
26
PIPING
Fig. 5-3
Standard Munchkin heater Traditional piping (zoning with valves)
Space heating mode
zone valves
make-up water
P1
purging
valves
V1
OFF
Drawing 1A
flow
bypass
valve
anti-scald
mixing valve
T/P
Munchkin heater
NOTES:
1. This drawing is meant to show system piping concept only. Installer is responsible for all equipment & detailing required by local codes.
2. Adjust flow bypass valve for the following minimum boiler flow rates in any operating mode: Munchkin model T50M: 3 gpm Munchkin model T80M: 3 gpm Munchkin model 80M: 3 gpm Munchkin model 140M: 5 gpm Munchkin model 199M: 7 gpm
3. The minimum pipe size for connecting a Super Stor water heater is 1 inch. The minimum pipe size for connecting a Munchkin heater is 1.25 inches.
4.
5. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.
6. The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119 Install a minimum of 12 diameters of straight pipe upstream of all circulators.
7.
8. A purging valve may be used in lieu of the ball valve / hose bib combination shown.
Super Stor
indirect DHW tank
F.
˚
Page 27
27
PIPING
Fig. 5-4
Standard Munchkin heater Traditional piping (zoning with valves)
Domestic water heating mode
zone valves
make-up water
P1
purging
valves
OFF
V1
OFF
OFF
anti-scald
mixing valve
Drawing 1B
OFF
flow
bypass
valve
T/P
NOTES:
1. This drawing is meant to show system piping concept only. Installer is responsible for all equipment & detailing required by local codes.
2. Adjust flow bypass valve for the following minimum boiler flow rates in any operating mode: Munchkin model T50M: 3 gpm Munchkin model T80M: 3 gpm
Munchkin model 80M: 3 gpm Munchkin model 140M: 5 gpm Munchkin model 199M: 7 gpm
3. The minimum pipe size for connecting a Super Stor water heater is 1 inch.
4. The minimum pipe size for connecting a Munchkin heater is 1.25 inches. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.
5.
6. The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119 Install a minimum of 12 diameters of straight pipe upstream of all circulators.
7.
8. A purging valve may be used in lieu of the ball valve / hose bib combination shown.
Munchkin heater
Super Stor
indirect DHW tank
F.
˚
Page 28
28
PIPING
Fig. 5-5
Standard Munchkin heater Traditional piping (zoning with circulators)
Space heating Mode
space heating zone circuit
make-up water
closely
spaced
tees
Drawing 1C
zone circulators
zone
purging
valves
P1
T/P
Munchkin heater
NOTES:
This drawing is meant to show system piping concept only.
1. Installer is responsible for all equipment & detailing required by local codes.
2. All closely spaced tees shall be within 4 pipe diameter center to center spacing. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and
3. downstream of all closely spaced tees. The ninimum pipe size for connecting a Super Stor water heater is 1 inch.
4.
5. The minimum pipe size for connecting a Munchkin heater shall be 1.25 inches. All pumps are shown with isolation flanges. The alternative is standard flanges
6. with full port ball valves for isolation. The anti-scald mixing valve shown on the domestic water heater is optional.
7.
8. Install a minimum of 12 diameters of straight pipe upstream of all circulators. A purging valve may be used in lieu of the ball valve / hose bib combination shown.
9.
P2
indirect DHW tank
Super Stor
Page 29
29
PIPING
Fig. 5-6
Standard Munchkin heater Preferred piping (zoning with circulators)
Domestic water heating Mode
space heating zone circuit
make-up water
closely
spaced
tees
purging
valves
P1
P2
Drawing 1D
zone circulators
anti-scald
mixing valve
T/P
NOTES:
This drawing is meant to show system piping concept only.
1. Installer is responsible for all equipment & detailing required by local codes.
All closely spaced tees shall be within 4 pipe diameter center to center spacing.
2.
3. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream of all closely spaced tees.
4. The minimum pipe size for connecting a Super Stor water heater is 1 inch. The minimum pipe size for connecting a Munchkin heater shall be 1.25 inches.
5.
6. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.
7.
8. Install a minimum of 12 diameters of straight pipe upstream of all circulators.
9.
The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119
A purging valve may be used in lieu of the ball valve / hose bib combination shown.
Munchkin heater
Super Stor
indirect DHW tank
F.
˚
Page 30
30
PIPING
Fig. 5-7
Standard Munchkin heater Preferred piping (zoning with valves)
Space heating mode
zone valves
make-up water
P2
closely
spaced
tees
purging
valves
V1
Drawing 2A
differential pressure bypass valve
anti-scald
mixing valve
P1
T/P
Munchkin heater
Super Stor
indirect DHW tank
NOTES:
1. This drawing is meant to show system piping concept only. Installer is responsible for all equipment & detailing required by local codes.
2. Adjust differential pressure bypass valve to eliminate any flow velocity noise when zone with highest pressure drop operates by itself.
3. The minimum pipe size for connecting a Super Stor water heater is 1 inch. The minimum pipe size for connecting a Munchkin heater is 1.25 inches.
4.
5. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves. The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119
6.
7. Install a minimum of 12 diameters of straight pipe upstream of all circulators.
8. A purging valve may be used in lieu of the ball valve / hose bib combination shown. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream
9. of all closely spaced tees.
F.
˚
Page 31
31
PIPING
Fig. 5-8
Standard Munchkin heater Preferred piping (zoning with valves)
Domestic water heating mode
zone valves
make-up water
P2
closely
spaced
tees
purging
valves
OFF
V1
OFF
OFF
anti-scald
mixing valve
Drawing 2B
OFF
differential pressure bypass valve
P1
T/P
Munchkin heater
Super Stor
indirect DHW tank
NOTES:
1. This drawing is meant to show system piping concept only. Installer is responsible for all equipment & detailing required by local codes.
2. Adjust differential pressure bypass valve to eliminate any flow velocity noise when zone with highest pressure drop operates by itself.
3. The minimum pipe size for connecting a Super Stor water heater is 1 inch. The minimum pipe size for connecting a Munchkin heater is 1.25 inches.
4.
5. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.
6.
7. Install a minimum of 12 diameters of straight pipe upstream of all circulators.
8.
9.
The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119
A purging valve may be used in lieu of the ball valve / hose bib combination shown. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream of all closely spaced tees.
F.
˚
Page 32
32
PIPING
Fig. 5-9
Standard Munchkin heater Preferred piping (zoning with circulators)
Space heating mode
space heating zone circuit
make-up water
closely
spaced
tees
purging
valves
P2
Drawing 2C
zone circulators
anti-scald
mixing valve
P1
T/P
Munchkin heater
Super Stor
indirect DHW tank
NOTES:
This drawing is meant to show system piping concept only.
1. Installer is responsible for all equipment & detailing required by local codes.
All closely spaced tees shall be within 4 pipe diameter center to center spacing.
2.
3. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream of all closely spaced tees.
4. The minimum pipe size for connecting a Super Stor water heater is 1 inch. The minimum pipe size for connecting a Munchkin heater shall be 1.25 inches.
5.
6. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.
7. The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119 Install a minimum of 12 diameters of straight pipe upstream of all circulators.
8.
9. A purging valve may be used in lieu of the ball valve / hose bib combination shown.
F.
˚
Page 33
33
PIPING
Fig. 5-10
Standard Munchkin heater Preferred piping (zoning with circulators)
Domestic water heating mode
space heating zone circuit
make-up water
closely
closely
spaced
spaced
tees
tees
purging
valves
P2
Drawing 2D
zone circulators
anti-scald
mixing valve
P1
T/P
Munchkin heater
Super Stor
indirect DHW tank
NOTES:
This drawing is meant to show system piping concept only.
1. Installer is responsible for all equipment & detailing required by local codes. All closely spaced tees shall be within 4 pipe diameter center to center spacing.
2.
3. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream of all closely spaced tees.
4. The minimum pipe size for connecting a Super Stor water heater is 1 inch. The minimum pipe size for connecting a Munchkin heater shall be 1.25 inches.
5.
6. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves. The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119
7.
8. Install a minimum of 12 diameters of straight pipe upstream of all circulators. A purging valve may be used in lieu of the ball valve / hose bib combination shown.
9.
F.
˚
Page 34
34
PIPING
Fig. 5-11
Standard Munchkin heater Preferred piping (multiple heaters / zoning with circulators)
Space heating mode
space heating zone circuit
make-up water
closely spaced
tees
purging
valves
Drawing 2E
zone circulators
anti-scald
mixing valve
P2
PB1
T/P
Munchkin heater
PB2
T/P
Munchkin heater
Super Stor
indirect DHW tank
NOTES:
This drawing is meant to show system piping concept only.
1. Installer is responsible for all equipment & detailing required by local codes.
2. All closely spaced tees shall be within 4 pipe diameter center to center spacing. A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream
3. of all closely spaced tees. The minimum pipe size for connecting a Super Stor water heater is 1 inch.
4.
5. The minimum pipe size for connecting a Munchkin heater shall be 1.25 inches. All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.
6.
7. The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119 Install a minimum of 12 diameters of straight pipe upstream of all circulators.
8.
9. A purging valve may be used in lieu of the ball valve / hose bib combination shown.
F.
˚
Page 35
35
START-UP PROCEDURES
PART 6. START-UP PROCEDURES
A. ITEMS TO BE CHECKED BEFORE LIGHTING THE MUNCHKIN
It is recommended that you read the General Information Section (Part 1) to get a better under­standing how the Munchkin operates before you start the unit.
1. Make sure that you follow the Lighting instruction before running the Munchkin.
2. Make sure the unit has a minimum water supply pressure of 10 PSI or a fault code of PrO will appear in the display. While this Fault code is on the display the unit will not operate unit until the water pressure is brought above 10 PSI. This Fault code is caused by the Water pressure switch being open for more than 5 seconds which is an indication your system pressure is below 10 PSI. Increase the water pressure in the system until the pressure gauge reads 10psi. This code will disappear once the Water Pressure switch is closed, which will allow you to start the Munchkin.
3. Check to see if all the electrical connections are on securely. Also, make sure the clear plas­tic hose is connected to the outlet of the combustion blower outlet and connected back to the Air Switch.
4. Make sure that the Gas is turned on inside the cabinet and outside of the Munchkin.
5. Double check the temperature setting (Note: The Munchkin is factory set at 180 degrees)
6. Make sure the unit is properly grounded and the electrical wiring meets the requirements of the electrical section (Part 2, Page 8).
7. Turn on the power to the Munchkin. The Temperature of the Munchkin Outlet will appear in the display provided. If a fault code appears, correct the fault before operating. Make sure that the room thermostat is connected and turn the room thermostat up above room temperature to start the combustion blower fan to run the Munchkin. The Munchkin will now run its pre­purge cycle, then begin running, which will be indicated by the Green light illuminating under “Flame On” in your display.
B. LIGHTING INSTRUCTIONS
FOR YOUR OWN SAFETY READ BEFORE OPERATING
1. This appliance does not have pilot. It is equipped with an ignition device which automatical­ly lights the burner. Do not try to light the burner by hand.
2. BEFORE OPERATING smell all around the appliance area for gas. Be sure to smell next to the floor because some gas is heavier than air and will settle on the floor.
WHAT TO DO IF YOU SMELL GAS
Do not try to light any appliance.
Do not touch any electric switch; do not use any phone in your building.
Immediately call your gas supplier from a neighbor's phone. Follow the gas suppliers'
instructions.
If you cannot reach your gas supplier, call the fire department.
3. Turn on gas shutoff valve (located inside of the Heater) so that the handle is aligned with the gas pipe. If the handle will not turn by hand, don't try to repair it, call a qualified service tech­nician. Force or attempted repair may result in a fire or explosion.
WARNING
If you do not follow these instructions exactly, a fire or explosion may
result, causing property damage, personal injury or loss of life.
Page 36
36
START-UP PROCEDURES
4. Do not use this appliance if any part has been under water. Immediately call a qualified serv­ice technician to inspect the appliance and to replace any part of the control system and any gas control which has been under water.
5. The Munchkin Heater shall be installed so the gas ignition system components are protected from water (dripping, spraying, rain, etc.) during appliance operation and service (circulator replacement, condensate trap, control replacement, etc.)
C. OPERATING INSTRUCTIONS
1. STOP! Read the safety information in Part 6, Page 35.
2. Set the thermostat to the lowest setting.
3. Turn off all electric power to the appliance.
4. This appliance is equipped with an ignition device which automatically lights the burner. Do not try to light the burner by hand.
5. Remove front cover.
6. Turn gas shutoff valve clockwise to “off ”. The handle will be vertical, do not force it.
7. Wait five (5) minutes to clear out any gas. If you then smell gas, STOP! Follow Part 6, Section B/Lighting Instructions in the safety information. If you don't smell gas, go to the next step.
8. Turn the gas shutoff valve counter clockwise to “on”. The handle will be horizontal.
9. Replace the Front Cover.
10. Turn on all electric power to appliance.
11. Set the thermostat to the desired setting.
12. If the appliance will not operate, follow the instructions “To Turn Off Gas To Appliance” Section E pg. 33 and call your service technician or gas supplier.
D. ADJUSTING THE TEMPERATURE ON THE MUNCHKIN DISPLAY:
1. Before you can change the temperature from the factory setting of 180 degrees. You must make sure that none of the thermostats are calling for heat. The Munchkin controller will not memorize a program setting while in a heating cycle. To adjust the temperature to the Munchkin simply press in the S3/Program key for three seconds until you see a flashing (C) then an alternate value of (180)
. This number is the factory set point of the unit, which is 180 degrees. To change the temperature, simply push either the S1/– or S2/+ on the display. The S1/– button will decrease the tempera- ture while the S2/+ will increase the temperature of the Munchkin. The temperature of the Munchkin can be set as low as 50 Degrees and as high 203 Degrees. These ranges are your maxi­mum and minimum ranges of the Munchkin. In addition to changing the temperature you are also allowed to change three more settings in this model (1. Munchkin differential – 2. Indirect setting (Vision System Only) – 3. Celsius to Farenheit measurement. Simply press in the S3/Program key to get to next value, the Munchkin differential setting will appear in the display ch and alternating value of 30. This allows the installer to adjust the activation of the burner based on the differential temperature setting of the Munchkin. The burner will not start until the outlet water temperature reaches a temperature that is equal to the temperature setting for the Munchkin, minus the differ­ential EX: The Munchkin is set to heat at 180° F degrees and the differential is set at 20° F. The burn­er will not start until the outlet temperature of the system falls below 159° F degrees (180° – 20° F = 160° F). To adjust, press either S1/– (Decrease Value) or S2/+ (Increase Value) Ranges 5° F to 30° F. Press the S3/Program key again and you will see the Indirect Setting de and an alternative value of 119 (Vision Systems Only) To adjust, press either S1/– (Decrease Value) or S2/+ (Increase Value).
The final adjustment in this mode is the Farenheit to Celcius measurement. Press the S3/Program key again and you will see t and alternating value of F
. To change value press the S1/– or S2/+ to
choose the correct measurement.
Page 37
37
E. STATUS MENU
Installers are also able to check the current status of the Munchkin parameters by pressing S4/RESET key for 3 seconds. Once activated, the display will show d1 alternating value of the actual outlet tem­perature. Actual values are displayed for each function. To view the next value simply press the S/4 key to go to the next displayed value. Listed below are the values which can be displayed. These val­ues cannot be changed. To exit this menu, simply press S3/Program key to resume normal operation.
Function Value
d1/ Actual Temperature from outlet sensor d2/ Actual Temperature from inlet sensor d3/ If using a standard mechanical control, the control will display 1 for closed 0 for open
If the sensor is connected to the SuperStor Indirect Fired Water Heater it will measure
the actual temperature. (Vision only.) d4/ Not used d5/ Actual Temperature from the outdoor sensor. (Vision only.) d6/ Actual Fan speed multiplied by 10 (Example: If fan speed displayed is
410 RPM x 10 = 4100 actual fan speed)
d7/ Actual Ionization current read from Flame Rectification probe d8/ Actual Status of the Central Heating Circulator Off = 0 , On = 1 . (Vision only.) d9/ Actual Status of the Indirect Fired Circulator Off = 0 , On = 1 . (Vision only.) d10/ Actual Status bus communication co = connected, no = not connected
F. TO TURN OFF GAS TO APPLIANCE
1. Set the thermostat to lowest setting.
2. Turn off all electric power to the appliance if service is to be performed.
3. Remove the front cover.
4. Turn gas shutoff valve clockwise to "off". Handle will be vertical. Do not force.
5. Install front cover.
START-UP PROCEDURES
DANGER
Water temperature over 125 degrees F. can cause severe burns instantly, or death from scalds. Children, disabled, and elderly are at highest risk of being scalded. See instruction manual before setting temperature at water heater. Feel water before bathing or showering! Temperature limiting valves are available.
Fig. 6-1
GAS VALVE SHUT OFF
80M / 140M / 199M
T50 / T80
GAS VALVE SHUT OFF
Page 38
38
PART 7. SERVICING
A. SEQUENCE OF OPERATION
1. When power is first applied to the control, the control display will read the outlet tempera­ture. The control will initially run through a self-diagnostic routine and then go into its oper­ating mode. If there is no call for heat, the System will go into an idle state.
2. If the thermostat is calling for heat, the control will apply power to the circulator pump. If the control determines the water temperature is below the programmed set point value minus the switching differential, the control will initiate a heating cycle.
3. The control then performs selected system diagnostic checks. If all checks are successfully passed, a pre-purge cycle is initiated (the blower will be on maximum speed).
4. When the pre-purge period is complete, power is applied to the spark ignitor for approxi­mately 6 seconds. Approximately 2 seconds later, we verify flame. If a flame is not verified during the trial-for-ignition, the gas valve is immediately closed and the control will return to step. After three trials, if a flame is not verified, the control will go into a lockout mode. If a flame is confirmed, the control enters the heating mode. The fire rate will be based on the proprietary algorithm.
5. When water temperature reaches the temperature set point value plus 10 degrees F (or if the thermostat call-for-heat is satisfied), the gas valve is closed and the control enters a post­purge state (the blower will be on maximum speed). NOTE: If the thermostat is still calling
for heat, the circulator pump will continue to run until the thermostat call for heat is satis­fied.
6. When the post-purge is complete, the control enters an idle state while continuing to moni­tor temperature and the state of other system devices. If a call-for-heat is received, the con­trol will automatically return to step 2 in sequence and repeat the entire operating cycle.
During the idle state and heat state, if the control detects an improper operating state from external devices, such as the high-limit switch, the red light on the control will illuminate an error code will appear in the display.
B. MUNCHKIN TEMPORARY FAULT CONDITION
A Temporary Fault Condition may occur in the installation of the Munchkin. This condition may lead to a lock out condition of the controller, which will need to be manually reset through the S4/Reset button. These temporary codes will help the installer correct the problem before going into a lock out condition, which will require a manual reset. Example: A temporary fault-code of E15 indicates that the Air Pressure Switch is open when the fan is in the pre-purge function, when it should be closed. This could occur if the clear hose, which is connected to the outlet of the fan is disconnect­ed. This can be corrected by re-connecting the hose. Listed below are the Temporary Fault Codes.
E00 This code will appear if there is an overshoot of the high limit. The Temporary Fault Code will
be displayed only 50 seconds.
E13 This code will appear if the expected fan speed is lower then 70%. This will show on the dis-
play 10 seconds after the fan has started. The Temporary Fault code will only be displayed an additional 50 seconds before going into lock out mode (F13).
Remedy – Check wiring to assure that the Fan is connected correctly.
E14 This code will appear if the expected fan speed is higher then 130%. This will show on the
display 10 seconds after fan is started. The Temporary Fault Code will only be displayed an additional 50 seconds before going into lock mode (F14).
Remedy – Check wiring to assure that the Fan is connected correctly.
E15 This code will appear if the Air Pressure Switch is open when the fan is switched on in the
SERVICING
Page 39
39
SERVICING
pre-purge or post purge cycle. This code will only appear 10 seconds after the fan starts. The Temporary fault will only be displayed an additional 50 seconds before going into lock mode (F15).
Remedy – Check the hose connection from switch to fan. Check to see if the inlet is blocked. Check the air pressure switch contact. Adjust the switch, turn center screw counter clockwise in ¼ turn increments until the switch clicks into closed position. Also check to see if the fan is functional.
E16 This code will appear if the Air Pressure Switch is closed when the fan is switched on in the
pre-purge or post purge state. This code will only appear 10 seconds after the fan has start­ed. The Temporary fault will only be displayed an additional 50 seconds before going into lock mode (F16).
Remedy – Check the Air pressure switch for a possible adjustment. Adjust switch, turn center screw clockwise in ¼ turn increments until the switch clicks into open position.
PR0 This code will appear if the Water Pressure Switch is open for more than 5 seconds. The unit
will not be allowed to operate while this code is on the display.
Remedy – Check the water pressure in the system. Make sure the pressure is at least 10 PSI. Check all electrical connections to the switch. If the switch still does not close, try adjusting the switch with a screw driver and turn screw in center of the switch counter­clockwise to close switch. If the switch still does not close with a minimum supply pressure of 10 PSI, then replace the switch.
C. MUNCHKIN FAULT REQUIRING MANUAL RESET
When a fault condition occurs or is sensed on the Munchkin controller or in the appliance, the con­troller goes into a lockout state. When in LOCKOUT state, the red led light will illuminate and a fault code will be presented in the display. To reset the lockout condition, simply push the S4/Reset to bring the control out of its lockout state. If the problem is not corrected, the Munchkin will repeat the fault until the condition is corrected. Once corrected, the display will resume its supply temperature setting. Listed below are the Fault Codes and the remedies to correct the fault.
F00 Safety Limit ECO – This code appears if the Safety Limit ECO opens. The ECO will normally
open if it senses a temperature greater than 225 degrees.
Remedy – Let the unit cool down and push the reset button (S4). Determine if there is water flow through the heater. Manually reset the unit by pushing the S4/reset button. If the lockout continues, replace the switch to correct the problem.
F01 Safety Limit Flue – This code appears if the Safety Limit Flue senses a temperature higher
than 210 degrees.
Remedy – Push the red button down on the Flue sensor, then push the reset button on the display. If you experience another F01 lock out code, replace the flue sensor, then try again. Check to see that condensation line is not frozen. Manually reset by pushing the S4/reset button. If this problem persists, call factory for further assistance.
F02 Interrupted or Shorted Supply Thermister – This code appears if the Supply thermister
located on the Munchkin Outlet manifold has been interrupted or shorted.
Remedy – Check the wiring connection and connectors on the thermister. If the unit locks out again, replace the Supply Thermister. Manually reset the unit by pushing the S4/reset button
F03 Interrupted or Shorted Return Thermister – This code appears if the Return thermister
located on the Munchkin Outlet manifold has been Interrupted or shorted.
Remedy – Check the wiring connection and connectors on the thermister. If the connection is okay, hit reset S4/Reset . If the unit locks out again, replace the Return Thermister.
F05 Supply Temperature is to High – This code appears if the Supply temperature sensor
goes above 230 degrees.
Remedy – Let the Munchkin cool down, then manually push the reset button and see if the
Page 40
40
temperature increases to above 230 degrees. Determine if you have water flow or if the thermostat is continuously energized and correct the problem. Manually reset by pushing the S4/reset button.
F06 Return temperature is too High – This code comes if the return water temperature goes
above 230 degrees,
Remedy – Let the Munchkin cool down then manually push the reset button and see if the temperature on the return increases to above 230 degrees. Check piping and determine the source of over heating and correct the problem. Manually reset by pushing the S4/reset button.
F09 This code will occur if the Munchkin control does not detect a flame. The Munchkin
will make three attempts for ignition before the control will go into a lockout condition. The Munchkin control will try to re-ignite after one hour and continue to try to ignite every hour.
Remedy – Check the Flame Rod, Spark electrode or Hot Surface Igniter to see if they are in good condition. If the flame rod or spark electrode has corrosion, then clean it and re­ignite. Also, check spark gap of ¼” on the spark electrode. If the Hot Surface igniter has any visible cracks, then replace it with a new Hot Surface Igniter. Check any flue blockage and condensate blocks. Also, check the Gas supply (Check Part 3, Table 1 [pg. 9] for pipe sizes and gas pressure settings) and correct problem if it is out of specification. Manually reset by pushing the S4/reset button.
F10 This code appears if the flame is going out while the burner is on and this hap-
pens more then 4 times in one heat demand.
Remedy – Check to see if the green light on your display is out while the unit is running. If the green light on the display either does not come on or goes out while running, read the flame rod with a voltage meter to read the flame current. If it’s less than 1 micro-amp, change or clean the flame rod. Also, check the Gas pressure while the unit is running to determine if pressure is adequate. See Part 3, Gas Connection. If the gas pressure is too low, correct the problem. Manually reset by pushing the S4/reset button.
F11 The flame detector circuit is seeing a flame signal while no flame is present.
Remedy – Check the wiring to the Gas Valve. Check the flame rod and make sure it’s clean, then manually reset S4/Reset button. If a lockout occurs, replace the board.
F13 Combustion fan running too slow. The speed detected of the hall pulse signal is less than
70% of the desired fan speed for longer then 1 minute.
Remedy – Check the Fan wiring. Manually reset by pushing the S4/reset button.
F14 The speed detected of the hall pulse is more then 130% of the desired fan speed
for longer then 1 minute when the fan should be on. If the fan should be off and the
speed detected of the hall pulse output is more then 1500rpm and longer then 1 minute, this code will appear.
Remedy – Check Fan Wiring. Manually reset by pushing the S4/reset button.
F15 Air Pressure Switch is stuck open. When in the pre-purge cycle, if the Air Switch does-
n’t close during the pre-purge high-speed mode after 1 minute, this code will appear.
Remedy – Check the hose connection from the switch to the fan. Check to see if the inlet is blocked. Check the air pressure switch contact. Adjust the switch, turn the center screw counter clockwise in ¼ turn increments until switch clicks into closed position. Also check to see if the fan is functional. Manually reset by pushing the S4/reset button.
F16 Air Pressure Switch is stuck closed. If the Air Switch does not open while in the pre-
purge cycle, the unit will lockout after 1 minute.
Remedy – Check the Air pressure switch for possible adjustment. Adjust the switch, turn center screw clockwise in ¼ turn increments until switch clicks into open position if necessary. Manually reset by pushing the S4/reset .
SERVICING
Page 41
41
F18 Gas Valve not correctly connected/internal fault. Just before ignition, a test is per-
formed on the gas connection. If there is a failure in the gas valve connection and or the valve is not connected, this fault code will appear.
Remedy – Check the connection to gas valve. Check the wiring to the board. If the problem persists, change gas valve cable. Manually reset by pushing the S4/reset .
F30 Watchdog. Call Factory for further assistance.
Remedy – Call Factory for further assistance
F31 Parameter Memory. External Parameter memory corrupted
Remedy – Call Factory for further assistance
F32 Parameter memory write error. External Parameter memory fault
Remedy – Call Factory for further assistance
F33 Programming Error. Programming with PC not successful
Remedy – Call Factory for further assistance
SERVICING
RESISTANCE TABLES
Boiler & Indirect Temperature (˚F) Resistance (ohms)
32 32550 41 25340 50 19870 59 15700 68 12490 77 10000 86 8059
95 6535 104 5330 113 4372 122 3605 131 2989 140 2490 149 2084 158 1753 167 1481 176 1256 185 1070 194 915 203 786 212 667
Page 42
42
MAINTENANCE
PART 8. MAINTENANCE
A. MAINTENANCE PROCEDURES
Periodic maintenance should be performed once a year by a qualified service technician to assure that all the equipment is in safe efficient operation. The owner can make necessary arrangements with a qualified heating contractor for periodic maintenance of the heater. Installer must also inform the owner that the lack of proper care and maintenance of the heater may result in a hazardous con­dition. The installer should discuss the contents of the User's Information Manual with the owner.
B. BEFORE EACH HEATING SEASON:
A trained and qualified service technician should perform the inspections listed below at least once a year.
Heater – check the heater for dust or foreign materials, which may have been drawn in from the air intake of the heater. Simply blow out or wipe down with a dry rag.
Vent Termination – check to remove any obstructions, such as leaves, bushes, or other sources which may interfere with the units ability to draw fresh air on the air intake or exhaust flue gas from the exhaust outlet.
Vent Piping – make sure that all vent piping is in good condition. Check Joints for possible leaks.
Condensate – check the Condensate trap by simply starting the unit and observing the flow of Condensate which should not be restricted in any fashion. (See instructions below.)
Heat Exchanger – in the unlikely event the heater flue passage is becoming blocked, service must be performed only by an authorized Heat Transfer Products Representative or Certified Installing Contractor. (See coil cleaning instructions pg. 43 Section D)
Burner – check burner for deterioration. If deterioration is observed, replace burner.
System Water / Pressure – check pressure regulator and system pressure. Check system for air which will create noise. Open air vents or purge system to bleed air then close once air is fully purged from the system.
Water Piping – check for and repair any leaks.
Gas Piping – check for and repair any leaks.
C. CONDENSATE CLEANING INSTRUCTIONS
1. Turn down the thermostat so the Munchkin will not cycle and then follow the steps below. a. Close gas valve b. Disconnect the poly hose from the combustion blower motor c. Disconnect the condensate hose from the outside connection (not from the Munchkin) so
flow can be observed. d. Block the air flow in the exhaust by temporarily plugging the exhaust from the outside vent. e. Disconnect the white, red, blue, and black connection from the Molex on the combustion
blower. (Refer to Control Wiring Layout pg. 44 fig. 8-1.) This will cause the fan to run at 100%,
which will then blow out any sediment that has accumulated in the condensate line. (This
process should only take a few minutes.) f. The unit should now be ready to re-start.
2. Before re
-starting the Munchkin follow the steps below:
a. Reconnect the Molex connection and un-block the vent (IMPORTANT: MAKE SURE
EXHAUST VENT IS NO LONGER BLOCKED!)
b. Open the gas valve and turn up the thermostats c. Observe the boiler function to make sure you see a condensate flow. d. If you do not observe a condensate flow, repeat the above procedure.
3. If the problem is not corrected at this point, it is possible you have a material deposit problem, in which case, a qualified plumber will need to be contacted to follow the Coil Cleaning Instructions (Section D) included in this section to dissolve deposit and clean condensate line.
Page 43
43
MAINTENANCE
D. COMBUSTION CHAMBER COIL CLEANING INSTRUCTIONS*
*Before beginning this procedure, you must have on hand the following items:
– a nylon, stainless or brass brush (not steel) – “Marsolve” (recommended for best results) (available on line www.marsolve.com) or “CLR”
(available at most hardware stores)
1. Shut down the Munchkin by using the following steps: a. Close the gas valve, shut down the unit and wait for the unit to be cool to the touch b. Disconnect the condensate hose from the outside connection, (not from the Munchkin side),
so the flow can be observed. c. Remove the (4) screws on the aluminum ½” NPT connector on the gas valve. d. Disconnect the poly hose connected to the combustion blower motor. (This does not apply
to T50/T80.) e. Remove the (6) 10MM nuts from the burner plate assembly to access the coils. f. Pull the entire burner plate assembly towards you, while removing or pushing aside any
wiring to allow the removal of the assembly.
2. Using a spray bottle filled with the recommeded product “MARSOLVE” or “CLR”, spray liberally on the coils, making sure the solution penetrates and funnels down through the condensate hose. If the con­densate hose is blocked, let the chemical penetrate for at least 15 minutes or until it drains.
3. Use the nylon, stainless or brass brush (do not use steel) and scrub coils to remove any buildup, then vacuum the debris from the coils.
4. Spray the coils with clear water, making sure to confine the spray to the area being cleaned (Try to avoid getting the back cermic wall of the unit wet). Flush the combustion chamber with fresh water. At this point, the Munchkin should be ready to power back up.
Before powering up the Munchkin follow the steps below
a. Re-install the burner assembly b. Replace the (6) 10MM nuts to the burner plate c. Re-connect the wiring d. Re-connect the poly hose to the combustion blower motor. (Does not apply to the T50 or
T80.)
e. Replace the (4) screws on the aluminum ½” NPT connector on the gas valve. Turn the gas
back on. (IMPORTANT: CHECK FOR GAS LEAKS)
f. Re-set thermostats (IMPORTANT: MAKE SURE EXHAUST VENT IS NO LONGER BLOCKED!) g. Turn the Munchkin back on** and observe condensate flow. h. Re-connect the condensate hose to the outside connection.
**NOTE: When firing up the boiler for the first few times you may experience some flut­tering of the gas burner that may result in a flame lockout. This is normal and will require you to re-cycle the unit until this clears up. This is caused by water still present in the combustion chamber.
DANGER
IT IS EXTREMELY IMPORTANT TO MAKE SURE THE EXHAUST VENT IS NO LONGER BLOCKED. FAILURE TO DO SO MAY RESULT IN PERSONAL INJURY OR DEATH.
DANGER
IT IS EXTREMELY IMPORTANT THAT YOU CHECK FOR LEAKS WHEN RECONNECTING THE GAS VALVE AND MAKING SURE THE EXHAUST VAN IS NO LONGER BLOCKED. FAILURE TO DO SO MAY RESULT IN SEVERE PERSONAL INJURY OR DEATH.
Page 44
MAINTENANCE
44
CONTROL WIRING LAYOUT
Fig. 8-1
*
There is a spare 6.3 amp “slow blow” fuse included on the control cover. HTP p/n 7250-378 or you may purchase it from Radio Shack p/n: 270-1068
Caution: Do not replace with any amperage other than 6.3A
E. MUNCHKIN CONTROLLER
Page 45
MAINTENANCE
45
Page 46
MAINTENANCE
46
Page 47
NOTES
47
Page 48
48
LP-61 REV. 9/01/03