Multi-Fittings One Piece Expansion Joints Installation Manual

One Piece
Expansion Joints
The perfect expansion fitting for short runs of PVC
1
/2" - 2"
Molded one piece construction
One Kraloy One Piece Expansion Joint (OPEJ) controls 1
1
/4" of thermal expansion or contraction on a 30 foot conduit run (or less) regardless of the temeprature at the time of installation.
Dimension Part Product Std. Wgt/Pkg
(in) Number Code Pkg. (lbs)
1
/2 OPEJ05 078240 80 6
3
/4 OPEJ07 078209 50 5
1 OPEJ10 078208 40 5.5
11/
4 OPEJ12 078204 25 5
1
1
/
2 OPEJ15 078045 15 4
2 OPEJ20 078388 10 4
E 59258
Kraloy Customer Service Center
Toll Free: 1-800-265-1815 Direct: 519-681-2140 Fax: 519-681-2156 www.kraloyfittings.com
Dimension A 2 3 Overall
(in) Dia. Length Length Length
1
/2 1.102 0.660 2.465 3.25
3
/4 1.314 0.729 2.646 3.50
1 1.610 0.885 2.725 3.75
1
1
/4 1.987 0.950 2.895 4.00
1
1
/2 2.208 1.075 3.030 4.25
2 2.701 1.140 3.206 4.50
AB
Installation
The 2002 NEC Code (352.44) specifies:
Expansion fittings for Rigid Nonmetallic Conduit shall be provided to compensate for thermal expansion and contraction where the length change is expected to be ¼” or greater in a straight line between securely mounted items such as boxes, cabinets, elbows or other conduit terminations.
Graph 1 illustrates when expansion fittings are required based on the length of the conduit run and the expected temperature change.
As a general rule 100 feet of PVC conduit will undergo a change in length of 4” for every 100°F temperature change.
On a 30 foot run of PVC conduit or less a single One Piece Expansion Joint fitting will control 11/4" of expansion or contraction regardless of the ambient temperature at time of installation. For long conduit runs the use of Kraloy EJ series expansion joints is recommended.
Installing the One Piece Expansion Joint (OPEJ):
1. Solvent cement the PVC conduit into the conduit hub of the OPEJ and firmly secure the PVC conduit on the solvent cement side of the OPEJ using Kraloy pipe straps.
2. Set the expansion fitting by marking a line 11/2" from the end of the conduit to be inserted and insert the conduit into the OPEJ to this mark.
3. Secure and support the conduit raceway using Kraloy pipe straps.
Note: Expansion fittings are not required when the conduit is embedded in concrete or direct earth buried.
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
110
115
120
Expected Temperature Change (∆) ˚F
Length of Conduit Run (FT)
The shaded area represents where an expansion fitting is required based on the length of the run and the expected temperture changes.
i.e. 40' conduit run & temperature ∆ 40˚F exp. fitting is required i.e. 30' conduit run & temperature 20˚F exp. fitting not required.
X
X
Line indicates the point at which 1/4" of expansion or contraction will occur.
Graph 1
© 2002 Kraloy PIELRPKR020305
OAL
23