Mueller B-50-B18, B-50-B24 Operating Instructions Manual

Operating
Instructions
CENTURY FIRE HYDRANT B-50-B18 HYDRANT B-50-B24 HYDRANT
Barrie, ON, L4N 8Z9
www.muellercanada.com
! CAUTION !
1. Mueller Canada has made every effort to ensure that this manual is accurate and correct, and cannot be held liable for its misuse. Part numbers shown are current at time of printing and may be subject to change due to changes in design or material.
3. Mueller Canada will assume no responsibility or liability for any malfunction or damage caused by, or resulting from, the use of parts not manufactured by Mueller Canada. Use of such parts will void any and all warranties as well as third party approvals and endorsements.
Copyright © 2014 Mueller Co., LLC. All Rights Reserved. The trademarks, logos and service marks displayed in this document are the property of
Mueller Co., LLC, its affiliates or other third parties. These products are intended for use in potable water applications. Please contact your Mueller Sales or
Form MC005-rev04/15 Printed in U.S.A.
Customer Service Representative concerning any other application(s).
INDEX
CENTURY FIRE HYDRANT,
B-50-B18 HYDRANT,
B-50-B24 HYDRANT
Page
Installation, Operation, Inspection
and Maintenance .............................................3-4
Internal Parts Removal and
Hydrant Valve Rubber Replacement.....................5
Hydrostatic Test, 100mm Storz Adapter and
Storz Nozzle Installation .......................................6
Notes....................................................................7
2
www.muellercanada.com
CENTURY, B-50-B18 AND B-50-B24 FIRE HYDRANTS
Installation, Operation, Inspection and Maintenance
INSTALLATION
OTE: The following information is supplemental
N to the AWWA M-17 manual.
When hydrants are received, they should be handled carefully to avoid damage to the flanges or operating mechanism. Hydrant valve should be kept closed and nozzle caps should be in place to prevent entry of foreign matter prior to installation. Hydrants to be stored should be protected from the elements if possible.
Hydrant should be located to give minimum hazard to or from traffic. Place hydrant back from the curb line to prevent damage to or from overhanging vehicles. On main thoroughfares place hydrants far enough from intersections to avoid damage from accidents. Place hydrants so they are readily visible and accessible.
It is recommended practice to install an auxiliary or secondary gate valve in the lateral between the hydrant and the main to permit inspection and repair of hydrant without shutting down mains.
Before installation of hydrant, clean piping, hydrant base, and drain ring of hydrant of any foreign material.
It is recommended that a firm footing be used in setting the hydrant such as stone slabs on undisturbed soil. The hydrant should also be anchored to oppose the force due to pressure tending to force the hydrant off the end of the lateral. Several methods such as strapping, blocking or restraining type of joint may be used.
Nozzle caps should be sufficiently tight to prevent removal by hand.
OPERATION
Hydrants are designed to be opened and closed without the use of "cheaters". Excessive leverage may damage the hydrant, therefore:
• Check directio n of opening as marked on the hydrant cover.
• To open, remove a cap and turn the operating nut unt il the v alv e h its t he sto p in the o pen ing direction. Do not force the hydrant in the
open i ng d irect i on b eyond full open as indicated by sudden resistance to turning. If
water does not flow when the hydrant is open, it is probably due to a closed valve up stream from the hydrant.
• To close, slowly turn the operating nut until the valve closes off the flow. It is not necessary to
close this style of hydrant with great force.
Once the flow has stopped, loosen the operating nut in the opening direction to take the strain off the operating parts of the hydrant and to make it easier to open the hydrant when needed again.
Fire hydrants are not a throttling device and
therefore should be operated in the fully-open or fully-closed position.
If a draining type of hydrant is to be installed, provision should be made to carry off drainage. An acceptable method is to excavate around the hydrant to allow placement of approximately ½ cubic yard of crushed stone to level about five inches above the drain ring. The stone should be covered with roofing or tar paper before backfilling to prevent plugging of the drainage pit.
Both drainage stone and earth fill above the stone should be tamped to give firm support to the hydrant barrel.
When first installed, the hydrant should be operated from the fully-closed to fully-open position and back to make sure no obstructions are present.
After the hydrant is installed and the line has been hydrostatically tested, the hydrant should be flushed. Proper drainage can be verified by placing palm of hand over nozzle after hydrant has been closed. Drainage rate should be sufficiently rapid to create a suction.
INSPECTION
To assure proper operation of the hydrant, regular inspections should be carried out. All hydrants should be inspected twice yearly, in the spring and fall. When hydrants have been used during freezing weather, they should be inspected after each use.
Inspection should cover the following items:
External Condition – Note condition of operating nuts, caps, flanges, chains and paint.
Valve Leakage – Use aquaphone to verify that there is no leakage past hydrant valve.
Barrel or Drain Leakage – Remove a cap and open hydrant so barrel fills with water. Replace cap. Open hydrant fully with nozzle caps in place. Note, if there is leaka ge at the no zzles, ca p gaskets or barr el gaskets. Use aqua phone to check leakage through drains.