Application is quite easy, the panels are mounted on a
rail system and can be changed with another Mikodam
panel when desired.
Mikodam
panel
Wall
silicone seal
Z-shaped
U-shaped profile
profile
EPDM seal
screw anchor
plastic seal
The panels comes with Z shaped hanging profiles on it.
During the installation, U shaped hanging profiles are
mounted to the wall and the wall panels are assembled
to these. The hardware details to be used are shown in
the pictures below.
Hardware set for U shaped profiles to be mounted to
the wall are included in the package.
Hardware set for U shaped profiles are
included in the package.
2
INSTALLATION GUIDE
Mikodam panel
h:2400 mm
(7'-10 1/2")
PANEL INSTALLATION - Wall & Ceiling
Wall
U-shaped
profile
silicone seal
screw
plastic seal
EPDM seal
screw anchor
We use 2 seal elements in or der to separat e metal
installation elements from scre ws. To pr ev ent any
direct connection between the wall and the wall
panels. This is acoustically required for vibration
control from noises coming from the inside or
the outside.
Z shaped hanging profiles are fix ed on the panels comes a t a standar d height so that if y ou change the panel with
another Mikodam panel you will not have to change the position of the U-shaped profile on the wall.
GETABISA
FILAHAZA
KARA
SA PA
TOBAVEROKOSA
(old)
3
INSTALLATION GUIDE
Mikodam
panel
Wall
Mikodam
panel
Ceiling
Mikodam
panel
Ceiling
Mikodam
panel
Ceiling
Mikodam
panel
Wall
Mikodam
panel
Wall
PANEL INSTALLATION - Wall & Ceiling
Wall
1004
Mikodam panel
h:2400 mm
(7'-10 1/2")
[3'-3 1/2"]
Mikodam panel
h:2400 mm
(7'-10 1/2")
Wall
1004
[3'-3 1/2"]
Baseboard
h:100 mm (4")
or as required
The drawing above shows the standard heights of the U-shaped profiles.
1003
[3'-3 1/2"]
300
[11 3/4"]
(dimensions given are based on the hole centers)
1003
[3'-3 1/2"]
200
[7 3/4"]
The same railing system can be applied both on walls and on ceilings .
4
INSTALLATION GUIDE
steel profile for fixation
(if needed)
PANEL INSTALLATION - Wall & Ceiling
steel profile for fixation
A
wooden lath
for fixation
(if needed)
2400
[7'-10 1/2"]
1004
[3'-3 1/2"]
B
steel profile
for fixation
(if needed)
A
wooden lath
for fixation
(if needed)
1004
[3'-3 1/2"]
B
steel profile
for fixation
(if needed)
1003
[3'-3 1/2"]
1003
[3'-3 1/2"]
100
300
[11 3/4"]
200
[7 3/4"]
[4"]
It may be necessary to fix the panels to the wall in order to prevent the panels from dislodging in extreme cases
such as earthquakes. We suggest two methods for this. The first is to fix the panel in place by placing a wooden lath
between the panel and the ceiling, thus clamping the panel. The sec ond method is to fix the panel to the wall with the
help of a metal profile previously mounted on the back of the panel. If the second method is chosen, acoustic seals
included in the assembly kit should be used. The second method can also be applied to the last row of the panels
installed on ceilings in order to fix them in place.
5
INSTALLATION GUIDE
PANEL INSTALLATION - Wall
GETA FRONT ELEVATIONRIGHT ELEVATIONLEFT ELEVATION
6
INSTALLATION GUIDE
PANEL INSTALLATION - Wall
Our railing system can be applied both on wooden studs
& metal profiles/studs. It can also be applied when there is
no drywall on the surface an d only studs & rockwool are
available.
wooden lath for fixation
(if needed)
wooden lath for fixation
(if needed)
Mikodam
Hanging System
Mikodam
Hanging System
drywall
baseboardbaseboard
rockwool
steel profile
7
INSTALLATION GUIDE
PANEL INSTALLATION - Wall - 60 X 120 cm Panels
60x120 cm panels come with preinserted nuts at the corners on the back
of the panel, ready to fix the Z-shaped
profiles. Z-shaped profiles, allen bolt,
allen key, and lamellos for 60x120 cm
panels comes separately as a package.
pre-inserted nuts
8
INSTALLATION GUIDE
PANEL INSTALLATION - Wall - 60 X 120 cm Panels
Using these pre-inserted nuts, Z-shaped profiles can be fixed according to the direction of the panel to be hung.
9
INSTALLATION GUIDE
PANEL INSTALLATION - Wall - 60 X 120 cm Panels
The locations of the Z-shaped profiles are the same for all 60 x 120 panels so that if you change the panel with
another 60 x 120 cm Mikodam panel you will not have to change the position of the U-shaped profile on the wall.
You can also change the direction of the panels without changiing the position of the U-shaped profiles.
[4"]
100
100
TORA
1200
[3'-11 1/4"]
[4"]
1200
[3'-11 1/4"]
1200
1200
[3'-11 1/4"]
[3'-11 1/4"]
1200
1200
[3'-11 1/4"]
[3'-11 1/4"]
LEDAPIRA VATADETA
1200
1200
600,3
[1'-11 3/4"]
[3'-11 1/4"]
600,3
[1'-11 3/4"]
600,3
[1'-11 3/4"]
[3'-11 1/4"]
600,3
[1'-11 3/4"]
TORA
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
LEDAPIRAVATADETA
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
[1'-11 1/2"]
600
400
[1'-11 1/2"]
[1'-3 3/4"]
81,5
[3 1/4"]
While hanging the panels, both lower and upper z pr ofiles should be used for the panel at the bott om. For the panels
above it only the z profiles on the top are used.
Lamello biscuits are used to join and level the panels to each other.
10
INSTALLATION GUIDE
PANEL INSTALLATION - Wall
Lamello biscuits are used to join and level the panels to each other.
11
INSTALLATION GUIDE
PANEL INSTALLATION - Wall - 60 X 120 cm Panels
12
INSTALLATION GUIDE
PANEL INSTALLATION - Wall - 60 X 120 cm Panels
13
INSTALLATION GUIDE
135
[5 3/8"]
18[3/4"]
600
[23 5/8"]
18[3/4"]
PANEL ENDING - 60 X 120 cm Panels
1200
[47 1/4"]
65
[2 1/2"]
18
[3/4"]
600
[23 5/8"]
135
[5 3/8"]
18
[3/4"]
End panels can be easily attached to the panels using lamellos.
18
[3/4"]
18
[3/4"]
14
INSTALLATION GUIDE
RAILING SYSTEM
15
INSTALLATION GUIDE
PANEL INSTALLATION - Wall
The photos below show an installation process on the wall.
16
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
The photos below show an installation process on the ceiling.
17
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
Given below is the method of installation
of our panels hanging on the ceiling
by using wire ropes. This method is
preferred when the panels need to be
hung at a distance from the ceiling
instead of being directly mounted to the
ceiling. (The examples in the following
pages are given using Geta & Tora panels;
the same system can also be applied to
other Mikodam Panels.)
*Similar system is used Haydar Aliyev Auditorium project
18
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
Tora panels
pre-inserted nuts
60x120 cm panels come
with pre-inserted nuts at
the corners on the back of
the panel, ready to fix the
eyebolts.
eyebolts
19
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
Geta panels
pre-inserted nuts
For panels which do not have pre-inserted
nuts, in order to fix the eyebolts, preinserted nuts should be inserted to the
corners on the back of the panel first.
eyebolts
20
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
eyebolt
shackle
turnbuckle
wire rope
shackle
shackle
eyebolt
zip tie
21
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
We use lamello biscuits to join and level the panels to each other.
22
INSTALLATION GUIDE
PANEL INSTALLATION ORDER - Ceiling
The panels must be installed on ceilings following a certain
order. The installation should start at the corner and follow the
consecutive sequence in both directions as shown below, making
sure the shorter edges join each other and the longer edges join
each other as well.
1
2
1
1
2
2
23
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
1
2
3
After hanging the first panel, the corner of the panel should be stabiliz ed by hanging fr om three points on the c eiling.
The other corners should be fixed by using temporary turnbuckles until the other panels are hung.
4
24
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
5
The second panel should be attached to the first panel on its shorter edge by using lamellos and zip ties.
Free corners should be suspended from the ceiling by using temporary turnbuckles.
6
After the second panel is fixed in place temporarily, a wire rope should be inserted through the eyebolts
at the outer corner of both panels. To tie the inner corners, the second row should be installed first.
25
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
7
8
The same steps should be applied until the installation of the last panel in the row. Then the height of the panels at
both ends of the first row must be adjusted. After that the panels in the middle should be adjusted too, so that the
height is the same for all the panels in the row.
The two corners in the starting r ow mus t be connected fr om 3 points on the ceiling so that the direction of the panels
are fixed.
In order to provide stabilization, the panels should be hung not only from perpendicular points but also from cross
points, on corners and every 5 to 6 panels in a row.
26
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
9
10
11
Then the first panel of the next r ow is installed, again first by using zip ties and hanging free corners fr om the c eiling
by using temporary turnbuckles. Then a wire rope should be inserted through the eyebolts at the outer corners of
the panels.
27
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
12
13
14
To pull the panels towards each other, the wire ropes must be inserted through the eyebolts at the corners of all
adjacent panels.
28
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
15
16
17
29
INSTALLATION GUIDE
PANEL INSTALLATION STAGES- Ceiling
18
The panels should be hung not only from perpendicular points but also from cr oss points. In order to pr ovide stabilization,
it is necessary to hang them from 3 points on corners and every 5 to 6 panels in a row.
30
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
31
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling Flaps
If there is a need to reach behind the panels, some of the panels may be movable. In this situation, for
movable panels, wire rope or lamellos should not be used. Moveable panels should be placed with the help
of wooden wedges which can be removed when desired thus allowing to access behind the panels.
32
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
for concrete ceilings
for ceilings with
wooden structure
for ceilings with
metal structure
33
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
34
INSTALLATION GUIDE
PANEL INSTALLATION - Ceiling
35
INSTALLATION GUIDE
PACKAGING DETAILS
Packaging details: First of all, we cover the product with interlining to prevent it from being scrat ched. We wrap the
4 edges and corners of the product with blue PE, as shown in the pictures and we cover the surface of the product
with 10-12 mm PE. Finally, we wrap it with bubble paper and shrink packaging.
36
INSTALLATION GUIDE
PACKAGING DETAILS
Packaging details for 60x120 panels: The package contains 2 panels. All sides of the products are covered with
honeycomb cardboard to prevent it from damages and being scratched. The products are wrapped with shrink
packaging after being put in boxes specially prepared for the panels.
37
INSTALLATION GUIDE
INSTRUCTIONS FOR CARRYING THE PANELS
To prevent cracks on the corners, never put
Mikodam Panels with their corners on the
floor. The panels should always be placed
in an upright position with the entire edge
standing on the floor.
For proper handling, Mikodam Panels should be
carried with the long edge parallel and vertical to
the ground, by 2 persons.
38
INSTALLATION GUIDE
INSTRUCTIONS FOR STORAGE
Never put Mikodam Panels on top of each other.
The pictures above show proper vertical storage of our panels in our warehouse.
39
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.