McQuay HSS Installation Manual

Page 1
Installation & Maintenance Data IM 283-8
Group: Fan Coil Part Number: 106332300 Date: August 2000
Additional Installation Instruction for
Type HSS HiLine SeasonMaker Twin Units
Refer to Installation and Maintenance Bulletins 254 and 255 for additional information.
Twin opposite hand units share a common riser system; i.e., supply, return, and drain riser. This is commonly called a “master/slave” arrangement. The master unit is shipped with the risers attached. These special risers have stub-outs which must be field connected to the slave units. In addition to the instructions in bulletins IM 254 (KZZ units) or IM 255 (HSS units), the following procedures must be followed for all twin unit installations.
1. The slave unit has no risers and no stub-outs. Knock­out holes are provided for internal piping connections.
2. HSS-S10 and -S12 units will not match up with the smaller units sizes S03, S04, S06 and S08 due to differences in riser stub-out locations.
3. Master units are offered in two-pipe or four-pipe systems with either right-hand or left-hand. Slave units are offered to accomodate internal connections to any of these riser systems or locations.
4. The riser location (right or left) is determined by facing the return air grille panel. The risers are located on either the right or left of the unit. This defines the riser location. See Figure 1.
5. The riser block-off plates are located in the base of the slave unit. Block-offs must be installed on slave before putting unit into position. See Figure 8.
6. Install the master unit per IM 254 or IM 255.
7. Recommended wall opening sizes for the slave unit stub-outs are shown in Figure 6.
8. The openings must provide enough space to allow
easy installation of the unit. During installation, the unit is tilted at an angle to set into place. Unless the opening in the wall is large enough, there will be interference and the unit cannot be set into position.
9. Openings must be large enough to accommodate riser stubs with foam insulation. An allowance must be made for insulation thickness, fitting connections, and hand valves on the stub-outs.
10. The opening in the wall must provide space for vertical movement of riser stubs as a result of riser expansion and contraction.
5
11. The slave unit piping terminates with
8" sweat connec­tion. The piping is also supported inside the cabinet to prevent any damage to them during shipment. This
support bracket must be removed to allow expan­sion or contraction in the piping after unit is installed.
12. On the slave units, the ball valves will not be attached to the unit. The ball valves (quantity 2 on two-pipe, 4 on four-pipe), if ordered from McQuay, will be shipped in a separate box. The ball valves are not factory mounted to the slave unit piping because there would be insufficient room between ball valve and cabinet to make field connections to the unit. The correct installation proce­dure as outlined in subsequent paragraphs is to first mount the ball valves to the riser stub-outs and then set the slave unit in place with the ball valves protruding through the slave unit riser knockouts. The connections can then be made between ball valves and unit piping within the HiLine slave unit.
Figure 1. HiLine Twin Unit Arrangements
Right-Hand
Master
Left-Hand
Slave
Left-Hand
Master
Wall
Right-Hand
Slave
Note: Arrows refer to return air panel position
©2000 McQuay Incorporated
Page 2
Figure 2. Return Air Grille and Plaster Frame HSS/KZZ Sizes S03 Thru S08
Figure 3. Riser Location Plan View
Page 2 / IM 283
Page 3
Figure 4. Return Air Grille and Plaster Frame HSS/KZZ Sizes S10 & S12
Figure 5. Riser & Discharge Locations (Plan View)
IM 283 / Page 3
Page 4
Figure 6. HSS HiLine Twin Unit (sizes S03, S04, S05, S06, S08)
Recommended Wall Openings for Riser Stub-outs
Note: Wall openings are shown as seen looking at riser side of master unit.
Master unit riser stub-outs should be centered vertically in wall opening.
Two-Pipe System Four-Pipe System
Left-Hand
Unit
Outline
5" (127mm) 5" (127mm)
3" (76mm)
14"
(356mm)
3" (76
mm)
1"
(25mm)
1" (25mm)
3" (76mm)
Wall Opening for Supply and Return Stubs
Wall Opening
for Drain Stub
1" (25mm)
14"
(356mm)
20"
(508mm)
14"
(356mm)
Wall Opening for Supply and Return Stubs
41"
(1041mm)
Wall Opening
for Drain Stub
5" (127mm)
1" (25mm)
5" (127mm) 5" (127mm)
Right-Hand Unit Outline
3" (76
mm)
5" (127mm) 5" (127mm)
(356mm)
1"
(25mm)
14"
20"
(508mm)
5" (127mm)
1" (25mm)
Page 4 / IM 283
5"
(127mm)
5" (127mm)
Wall Opening for Supply and Return Stubs
Wall Opening for Drain Stub
1" (25mm)
(356mm)
20"
(508mm)
14"
5"
(127mm)
5" (127mm)
Wall Opening for Supply and Return Stubs
Wall Opening for Drain Stub
1" (25mm)
(356mm)
20"
(508mm)
41"
(1041mm)
14"
Page 5
Figure 7. HSS HiLine Twin Unit Field Piping
Figure 8. HSS HiLine Twin Unit Riser Block-offs
Master Unit
Floor
Risers
Partition
Slave Unit
Riser Stub-out
Field Supplied Tubing
Master
Unit
Block-off for
Master Unit
Riser Block-offs for Slave Unit
Drain Riser
13. The length of tubing between the
5
8" O.D. slave unit stub-out and the hand valve for the slave unit is to be provided by the contractor (see Figure 7). The length will be determined by the dimension between the walls.
After the master unit is set in place, the field supplied tubing should be sweated to the riser stub-outs and ball valves sweated to the field supplied tubing. Hand valves should be closed and risers pressurized to locate any leaks. Leaks should be repaired before slave units are installed and access is restricted.
1
14. Stub-outs from the supply and return risers are 43 (1105mm) on center from the bottom of the unit. They are to be made of
5
8" copper tubing on unit sizes S03
2"
through S08. The standard stub-out length is 23⁄4" (70mm) beyond the outside diameter of the riser.
1
15. The drain stub-out is either
2" PVC or 5⁄8" O.D. copper,
depending on which was ordered for the job.
16. Slave unit stub-outs should be well insulated by the contractor to prevent condensation problems.
17. Remove the appropriate riser and drain knockouts in the lower cabinet of the slave unit.
18. Slit the fiberglass insulation so that the riser ball valves can be pushed through and into the slave unit.
19. Install the slave unit riser block-off plates as shown in Figure 8.
20. Position the slave unit to the hand valves. The horizontal stub-outs should be centered in the opening in the cabinet.
21. Solder connections if sweat valves have been supplied.
22. Attach plastic drain hose to the drain line. Be sure hose clamp is properly installed and that there are no kinks in the hose.
23. With unit in final location, check level to insure proper condensate drainage and operation.
24. Use IM 254 or IM 255 to complete the installation of the slave unit.
25. Figure 9 shows a typical example of a master/slave arrangement for a two-pipe system. For four-pipe mas­ter/slave riser location, refer to Certified Drawing #405017Y.
IM 283 / Page 5
Page 6
Figure 9. Typical 2-Pipe Master/Slave Arrangement
1
7
8"
(181mm)
7" (178mm)
Left-Hand Master UnitRight-Hand Slave Unit
Supply &
Return Risers
Knockouts Provided
for Internal Piping
Connections 3" x 3"
(76mm x 76mm)
43
(1105mm)
57⁄8" (149mm)
Supply &
Return
Stub-outs
1
4" (83mm)
3
1
2"
Drain Riser
*Drain Stub-out
4" Dia.
(102mm)
4"
(102mm)
20"
(508mm)
*Stub-outs are of 1⁄2" PVC plastic or 5⁄8" O.D. copper for drain risers and
5
8" copper for supply and return riser.
Installation and maintenance are to be performed only by qualified personnel who are familiar with and in compliance with state, local and national codes and regulations, and experienced with this type of equipment.
Caution: Sharp edges and coil surfaces are a potential injury hazards. Avoid contact with them.
Page 6 / IM 283
Page 7
Notes
IM 283 / Page 7
Page 8
AAF-McQuay Incorporated 4900 Technology Park Boulevard, Auburn, NY 13021-9030 USA (315) 253-2771
Printed on recycled paper containing at least 10% post-consumer recycled material.
IM 283 (Rev. 8/00)
Loading...