![](/html/99/99c4/99c4e0a07aa17d73bc88a40c2ea16a20a958a04e6c451f047cdaceb0d4075f7c/bg1.png)
Matthews Fan Company
MP/BP Installation Instructions
Page 1
2/14/2019
MICHELLE PAREDE – BRUNA PAREDE
READ AND SAVE THESE SAFETY AND INSTALLATION INSTRUCTIONS.
Consult a licensed electrician if unsure of any point below mentioned.
DANGER/WARNING/AVERTISSEMENT/CAUTION/PRUDENCE
1 WARNING: TO REDUCE THE RISKS OF FIRE, ELECTRIC SHOCK OR INJURY TO PERSONS, OBSERVE
THE FOLLOWING:
A. Use this unit only in the manner intended by the manufacturer. If you have any questions, contact the
Manufacturer.
B. Before servicing or cleaning unit, switch power off at service panel and lock the service disconnecting
means to prevent power from being switched on accidentally. When the service disconnecting means cannot be
locked, securely fasten a prominent warning device, such as a tag, to the service panel.
C. Installation work and electrical wiring must be done by qualified persons in accordance with all applicable
codes and standards including fire-related construction.
D. When cutting or drilling into wall or ceiling, do not damage electrical wiring and other hidden utilities.
AVERTISSEMENT: POUR RÉDUIRE LES RISQUES D'INCENDIE, D'ÉLECTROCUTION OU DE BLESSURES,
OBSERVEZ CE QUI SUIT:
A. Utilisez cet appareil uniquement de la manière prévue par le fabricant. Si vous avez des questions, contactez le
fabricant.
B. Avant de procéder à l'entretien ou au nettoyage de l'unité, éteignez le panneau de service et verrouillez le
sectionneur de service.
des moyens pour empêcher l'alimentation d'être activée accidentellement. Lorsque les moyens de déconnexion du
service ne peuvent pas être verrouillés, fixez fermement un dispositif d'avertissement proéminent, tel qu'une
étiquette, sur le panneau de service.
C. Les travaux d'installation et le câblage électrique doivent être effectués par des personnes qualifiées
conformément à tous les
codes et normes, y compris la construction liée au feu.
D. Lors de la coupe ou du perçage dans le mur ou le plafond, ne pas endommager le câblage électrique et autres
services publics cachés
2 High voltage and moving parts around motors and motor driven equipment can cause serious or fatal
injuries. Always disconnect power source at main switch before wiring, servicing or cleaning unit. Do not rely on
fan control device to prevent unexpected start-up or electrical shock. In addition, power supply must have fuses or
circuit breakers for short circuit protection.
3 All electrical wiring must be performed by qualified persons in accordance and conform withal applicable
national and local electrical codes such as: NEC, OSHA, etc.
4 Fan should be secure in its electrical grounding to avoid possible electrical shock.
5 Fan should not be used in any wet or hazardous location defined by article 500 of the NEC. In addition, its
ambient temperature should not exceed 104 degrees Fahrenheit.
6 Power supply should conform to voltage rating of 115V.
7 Before applying power, visually re-inspect the installation. Make sure that all guards and protective devices are
securely in place and all visible screws and bolts are tightened. All set-screws must be retightened before
installation.
8 WARNING: to reduce the risk of fire, electrical shock or personal injury, the fan in this box may be either directly
supported from a structural framing member of a building and/or may be mounted to an outlet box marked
“Acceptable for fan support of 15.9 kg (35 lbs) or less”. Do not mount fan to sheet rock or drywall type materials and
use only the screws provided with the outlet box
AVERTISSEMENT: pour réduire les risques d'incendie, d'électrocution ou de blessure, le ventilateur de cette boîte
peut être directement
supporté par un élément d'ossature structural d'un bâtiment et / ou peut être monté sur une boîte de sortie marquée
"Acceptable pour supporter un ventilateur de 15,9 kg (35 lb) ou moins". Ne montez pas le ventilateur sur des
matériaux de type tôle ou placoplâtre et N'utilisez que les vis fournies avec la boîte de sortie.
.9 CAUTION: to reduce the risk of injury to persons, install fan so that bottom edges of fan blades are to be:
In Canada, to satisfy CSA requirements: at least 8.3 Ft/2.5 M above the floor and all objects in room. In the US, to
satisfy UL requirements: at least 7.0 Ft above the floor and all objects in room.
ATTENTION: Installer de sorte que les pieces inferieures soient a au moins 2.5 metres au-dessus du plancher ou
du sol.
![](/html/99/99c4/99c4e0a07aa17d73bc88a40c2ea16a20a958a04e6c451f047cdaceb0d4075f7c/bg2.png)
Matthews Fan Company
MP/BP Installation Instructions
Page 2
10 To reduce the risk of personal injury, do not bend blades or any other part of fan when cleaning. Do not insert
foreign objects in between rotating fan blades or in space surrounding entire rotating fan unit. Fan must be turned
off at power at supply source before installation, cleaning or servicing.
11 After making the wire connections in junction box, the wires should be spread apart with the grounded conductor
and the fan-grounding conductor on one side of the junction box and the ungrounded conductor on the other side of
the outlet box. Be sure that all wiring connections are properly insulated from each other and any surrounding metal
parts. For safety and best operating results, we recommend that you have a qualified electrician assemble and
install your fan.
12 To reduce the risk of personal injury, install the supplementary mounting means and use only the hardware
provided with the fan.
READ AND SAVE THESE INSTALLATION INSTRUCTIONS
CONTENTS OF BOX / See Diagram I
---One wall fan assembly. Total fan assembled weight is approximately 8.0 Lbs.
---One canopy (C2) to cover junction box.
---One support pole (D), one mounting plate (H) and one side mount wall junction box.
---One 1/8th set screw wrench to tighten 1/8th set screws in fan head (B2) and canopy (C2).
---
One proprietary 3 speed wall control.
INSTALLATION DIRECTIONS / See Diagram I
Read these instructions prior to installation.
NOTE: Before installing fan turn off power at service panel and check all visible
screws and bolts for tightness
1. Attach side mount junction box securely to building structure. Use provided hardware.
NOTE: Tighten screws well. Junction box is suitable for support of Michelle Pared wall
mounted fan.
2. Fully retract the set screws in wall canopy (C2) and carefully push canopy (C2) up the goose
neck/support pole (D) to reveal mounting plate (H). Slide canopy (C2) over the protective
sleeve. Wires (M) are already strung through support pole (D).
3. Pull wires (M) taut through back of mounting plate (H).
4. NOTE: Connect fan and power source wires at junction box according to national and
local electrical codes such as: NEC, OSHA etc. Re-read recommendations under heading
of "Danger/Warning/Avertissement/Caution/Attention." Note: Green wire is always
grounding wire and should be attached to the junction box for safe operation. If you are
not sure if the outlet box is grounded, contact a licensed electrician for advice. Note:
Do not turn power back on at service panel until step #6 below has been completed.
5. Attach mounting plate (H) to side mount wall junction box using hardware provided. The two
longest screws provided should be use to attach the fan/mounting plate (H) to side mount wall
junction box. Tighten screws well.
6. Push canopy (C2) down support pole (D) until the canopy lays flat against the wall - covering
junction box and mounting plate (H). Tighten set screws (Q) in canopy (C2) well so that it is
secure in its new, permanent position.
Do not use power tools of any sort in the assembly and mounting of this product.