5
REDUCER
SIZE
MOTOR
FRAME
MOTOR
COUPLING
REDUCER
COUPLING
REDUCER
SIZE
MOTOR
FRAME
MOTOR
COUPLING
REDUCER
COUPLING
C150 56 .090 / (3/32) .00 (EVEN) C200 56 .090 / (3/32) .00 (EVEN)
C150 140 .030 / (1/32) .00 (EVEN) C200 140 .030 / (1/32) .00 (EVEN)
C150 180 N.A. N.A. C200 180 .171 / (11/64) .188 / (3/16)
C150 IEC71 .090 / (3/32) .00 (EVEN) C200 IEC71 .090 / (3/32) .00 (EVEN)
C150 IEC80 .156 / (5/32) .00 (EVEN) C200 IEC80 .156 / (5/32) .00 (EVEN)
C150 IEC90 .141 / (9/64) .00 (EVEN) C200 IEC90 .141 / (9/64) .00 (EVEN)
C262 56 .090 / (3/32) .00 (EVEN) C350 56 .070 / (5/64) .00 (EVEN)
C262 140 .030/ (1/32) .00 (EVEN) C350 140 .125 / (1/8) .00 (EVEN)
C262 180 .090 / (3/32) .00 (EVEN) C350 180 .156 / (5/32) .00 (EVEN)
C262 210 N.A. N.A. C350 210 .090 / (3/32) .00 (EVEN)
C262 IEC71 .141 / (9/64) .250 / (1/4) C350 IEC71 .141 / (9/64) .250 / (1/4)
C262 IEC80 .141 / (9/64) .250 / (1/4) C350 IEC80 .141 / (9/64) .250 / (1/4)
C262 IEC90 .109 / (7/64) .250 / (1/4) C350 IEC90 .109 / (7/64) .250 / (1/4)
C262 IEC100/112 .188 / (3/16) .015 /(1/64) C350 IEC100/112 .188 / (3/16) .015 /(1/64)
C262 IEC132 .047 / (3/64) .00 (EVEN) C350 IEC132 .047 / (3/64) .00 (EVEN)
N.A. (NOT APPLICABLE)
NOTE: IEC Motors are B5 flanges.
6. The position of the wormgear must be adjusted so
the worm contacts the center of the wormgear teeth.
Failure to make this adjustment may cause reduced
efficiency and life as well as overheating and tooth
breakage.
7. Apply Prussian Blue lightly but evenly to both sides
of five adjacent teeth on the bronze wormgear.
8. Install the intermediate shaft assembly into the
gearcase so that the intermediate shaft pinion will be
on the same side as the output gear when the reducer
is reassembled. Install the open bearing housing and
secure with two bolts at diagonal corners. The hollow
dowel pins must be in place.
9. Rotate the input shaft so the “blued” wormgear teeth
are rotated through the gear mesh. Then rotate in the
opposite direction. Marks of contact will be made by
the worm in the bluing on the wormgear teeth.
10. Remove the open bearing housing and
intermediate shaft assembly. Examine the contact
pattern on the wormgear teeth. The ideal pattern is
centered in the wormgear teeth.
11. If the pattern is not centered, the intermediate shaft
must be moved in the direction where the contact
shows the heaviest. Remove a thin shim from the
bearing cup on the side that the contact is heaviest and
install it under the cup on the opposite side. Shims may
be moved from one side to the other but the total
number of shims must not be changed, as this controls
the endplay of the bearings.
COUPLING LOCATION
The motor and reducer coupling halves must be
properly located before assembly to prevent bearing
and coupling failure. Refer to the following chart and
reference diagram for proper locations.
MOTOR INSTALLATION
The MASTER ComboGear uses a standard NEMA Cface motor with a 3-piece flexible coupling. IEC motor
adapters and couplings are available.
12. Repeat the above steps, cleaning, rebluing and
inspecting each time, until the contact pattern is
centered on the wormgear.
13. Install the intermediate and output shaft
assemblies. Apply sealant to the gearcase machined
sealing surfaces. Install the open bearing housing and
tighten all bolts. Be sure all parts rotate freely.
14. Lubricate the shaft seal surface and seal bore
liberally with SHC 634. Install a new seal, taking care
not to cut or roll the lip or dislodge the seal garter
spring. Seat the seal flush with the outside of the
bearing housing. The use of a driver is recommended.
15. Fill unit with proper amount of lubricant. See
charts. Use sealant on plug threads. Test unit.