Marley M1712, M1713, M1712.5 User Manual

user manual
Geareducer® model M1712 – M1712.5 – M1713
INSTALLATION - OPERATION - MAINTENANCE
Z1051231 ISSUED 04/2017
READ AND UNDERSTAND THIS MANUAL PRIOR TO OPERATING OR SERVICING THIS PRODUCT.
fan hub installation
RETENTION
RETENTION BOLT
The following instructions detail the process for installing a fan on a Marley Geareducer with a straight fan shaft using a split taper bushing or a tapered fan shaft utilizing a bolted fan hub retention plate.
1. Remove the retention plate and hardware from the top of the Geareducer shaft. Thoroughly clean the fan shaft, fan shaft key, and the fan hub center bore to remove any debris and/or protective coatings. After cleaning, apply a coat of anti-seize compound to the top 7" (180mm) of the fan shaft.
2. Prior to hub installation, fully seat the key in the fan shaft keyway. The key is a tight fit across the width and must never be altered.
3. Raise the fan hub above the fan shaft for installation. Slowly lower the hub onto the shaft with the keyways properly aligned. Make certain the key does not slide down during installation. Stake the key in the keyway with a center punch if necessary.
The fan shaft key should be approximately centered in the
engaged portion of the hub when engaged on the shaft. Verify the center hub is fully seated by visual inspection.
4. Figure 1 illustrates proper retention plate and hardware instal­lation. The retention plate is designed to allow clearance for the fan shaft key, and when properly installed will not extend over or interfere with the key in any way. Torque the retention bolts to 70 ft·lbƒ (95 N·m).
PLATE
Figure 1 Retention Plate Assembly
operation and service
Corrosion and Dry Start-Up Protection
Marley Geareducers utilize iron and steel materials, which if not maintained correctly, may degrade. While some external corro­sion is acceptable, an internal lubrication film must be main­tained at all times to protect the working components against corrosion and potential startup damage. The following informa­tion describes methods of operation and preventive measures to ensure suitability for long-term operation.
Status Definitions
Pre-Commission
Duration* = Up to 4 months after receipt.
* export shipment status duration is reduced by 1 month
This is the as-shipped condition, which contains a factory rust-
proofing coating on the interior of the unit as well as a grease coating on the exposed shaft surfaces.
If the cooling tower is not ready for operation at the time of
status expiration, steps must be taken to place the Geareducer into Long-Term Storage or Downtime status.
Operational
This stage is initiated upon the first motor driven sequence. The
Geareducer is now considered as being placed into regular service and operation.
Idle
Duration = 2 to 4 weeks.
This stage is a suspension in operational status and lasts up
to two 2 weeks. The duration may be doubled by completing a Run Cycle.
It is not recommended to extend the idle status more than once
in any given sequence.
A common application is during a temporary outage
Seasonal Shutdown
Duration = Up to 4 months after operational is suspended.
This stage may be considered an extended idle condition.
Requires additional preventive maintenance.
Long-Term Storage or Downtime
Duration = Indefinite.
Requires long-term preventive measures.
Run Cycle
Defined as full speed operation for a minimum of 30 minutes.
This recoats all internal components and surfaces with lubri­cant and also helps to expel some moisture that may have accumulated from daily ambient condition cycling.
As shipped, a Marley Geareducer is protected internally against corrosion with machine enamel on un-machined parts and with rust-proofing oil and grease on machined surfaces. These coatings normally protect the Geareducer against corrosion for the duration of the Pre-Commission phase. Adding normal lubricant to the unit will dissolve the rust-proofing oil in the Geareducer sump. Provided it is added via the filler-neck or pumped in through the drain connection, this lubricant will not reduce the overall level of protection however, if the unit is operated for any amount of time, the Pre-Commission period is depleted and the unit is now considered to be in Operational status.
Check the Geareducer exterior yearly. Touch up with paint as required. Exposed pipe threads are coated to prevent corrosion. Touch up coating as required.
Initial Operation
Priming
Due to lack of control over facility operational readiness, site ambient conditions or storage practices, etc., it is recommended to supplement lubricant prior to initial operation. The same fill lubri­cant should be poured or pumped into the port above the interstage shaft. Remove pipe plug in center of Interstage Bearing Cap to expose port. Refer to Figure 3. If additional oil is being used, an amount of 1 to 1.5 quarts should be used. If the lubricant is being pumped from the sump bulk volume, at least 1 quart should be transferred. In either case, this priming step should be performed within 5 days of initial operation. If a delay occurs and the 5 day duration is exceeded, repeat the process. In either case, this priming step should be performed while rotating the gear train by hand and within 5 days of initial operation.
Warning – Operating the Geareducer at an oil level other than between the Add and Full levels may damage the unit and possibly mating equipment. This could also escalate to a safety concern for nearby personnel.
The Geareducer must be filled with oil to the Full oil level mark on the Geareducer case before it is placed in operation. If the unit is being taken out of Long-Term Storage or Downtime, the oil should be drained down to the Full operating level. If drain-down occurs within 5 days of the initial startup, the above priming se­quence may be skipped. See Service and Lubrication section for oil filling instructions.
Geareducers supplied with new cooling towers include oil for the initial filling and in some cases, will also ship with an additional amount required to place the unit into Long-Term Storage or Downtime status. Normally, oil is not furnished with Geareducers supplied as a spare or on replacement orders. Before operating the mechanical equipment, check to be sure the oil level is at the Full mark at the Geareducer and that the external gauge placard Full mark corresponds with the Full level in the Geareducer. Check oil lines to be sure there are no leaks.
Loading...
+ 5 hidden pages