• This Conversion kit shall be installed by a qualied service agency in accordance with the manufacturer’s
instructions and all applicable code and requirements of the authority having jurisdiction.
• If the information in these instructions is not followed exactly, a re, explosion or production of carbon
monoxide may result causing property damage, personal injury or loss of life.
• The qualied service agency is responsible for the proper installation of this kit.
• The installation is not proper and complete until the operation of the converted appliance is checked as
specied in the manufacturer’s instructions supplied with the kit.
Caution!
The gas supply must be shut off prior to
disconnecting the electrical power before
proceeding with the conversion.
Before You Start
This conversion shall be installed by a qualied
service agency.
Any damaged valve components should not be
installed. If a valve or regulator has been dropped
or appears to have been modied, the valve or
regulator should not be installed.
KIT CONTENTS
Gas Valve Regulator
with Rubber Gasket ....................................One (1)
Pilot Orice ...................................................One (1)
Gas Type Label ............................................One (1)
Burner Orice .............................................. One (1)
Accessing Gas Control Valve
NOTE: The valve compartment must be accessed
through the rebox of the appliance.
1. Turn off gas supply at external shutoff and allow
the unit to cool (required).
2. Disconnect power at GFCI circuit breaker
(required).
3. Remove logs or glass and vacuum media from
unit.
4. Remove six (6) screws securing cover assembly
from appliance, set aside. See Figure 1.
5. With the cover assembly removed, the tamperproof torx screws can be accessed to remove
the regulator. See Figure 1.
Installation and service of this appliance should be performed by
qualied personnel. Hearth & Home Technologies recommends
HHT Factory Trained or NFI certied professionals.
Hearth & Home Technologies • Gas Conversion Instructions for Courtyard • 4608-904 Rev. B • 11/18
Figure 1.
1
Page 2
Converting Gas Control Valve
1. Locate the gas valve. Using a #20 tamper-proof Torx
screwdriver, remove the regulator and rubber gasket
on face of valve. See Figure 2. Discard both the
regulator and rubber gasket.
2. Install the new regulator along with the new rubber
gasket included in the conversion kit. See Figure 2.
WARNING
Fire Risk
Explosion Risk
Gas Leak Risk
• Rubber gasket must be seated properly on valve face.
• Do not install a valve or regulator that has been dropped.
3. Place the gas type label on the appliance adjacent to
rating plate. Ensure the gas type label is appropriate
for the type of gas to which you are converting the
appliance.
Converting Main Burner & Pilot Orice
NOTE: Remove burner assembly from the rebox to
complete main burner and pilot orice conversion.
1. With the cover assembly removed locate the single
(1) screw securing the burner tube in place on the
left side and remove. Figure XX
2. Lift the burner tube up from the left end allowing the
air-shutter to pivot at the bulkhead. Lift until the tube
clears all the tube support brackets and pull straight
out.
Burner
Air
Shutter
1/16”
Open
Fully
Open
Gas Type
Burner
Orice
Pilot
Orice
NG#270.023
Propane#450.014
Table 1.
Note: The qualied service agency installing this conversion
must enter the day, month, and year, and sign the propane
conversion plate added to this appliance.
Valve
Rubber
Gasket
Regulator
#20 Torx Screws
Figure 2. Valve Regulator Conversion
Valve
Figure 3.
3. Replace the orice located on the end of the bulkhead with the supplied #45 orice.
4. Open the air-shutter, located at the end of the burner
tube, to fully open by loosening the screw holding
the shutter housing in place. Rotate to fully open and
retighten. See the air-shutter settings listed according to the table 1 below.
5. Set the burner tube aside and continue on with the
conversion process by locating the pilot assembly.
6. Remove (2) screws securing pilot to the burner assembly.
7. Carefully pull pilot assembly through the opening of
the burner assembly until the ttings behind the base
place are easily accessible.
8. Grasp pilot rmly and loosen the pilot tube tting.
Remove the existing pilot orice and replace it with
the pilot orice included in the kit. Ensure the pilot
orice is appropriate for the type of gas to which you
Control
Module
Pilot
Junction
Box
Bulkhead
Injector
Burner
Tube
WARNING
Shock or burn risk.
• Disconnect green wire from gas valve.
Failure to disconnect green wire could result in
severe burns.
Hearth & Home Technologies • Gas Conversion Instructions for Courtyard • 4608-904 Rev. B • 11/182
Page 3
are converting the appliance. See Figure 4.
9. Secure pilot assembly to burner assembly with (2)
screws.
10. Holding the left end of the burner tube up at an angle
with the air shutter at the lowest point. Slip the air
shutter over the orice and rotate the tube down over
the support brackets until coming to rest on the burner attachment bracket.
11. Reinstall the single screw on the left end of the burner
tube.
12. Disconnect green wire attached to the gas valve.
13. Turn on gas supply and electrical power to the appliance.
14. Turn appliance “On” and use a commercially available, non-corrosive leak check solution to test for
leaks around the pilot tting. See Figure 4.
15. Extinguish the pilot ame by turning the appliance
“Off”.
16. Reconnect green wire to the valve.
17. Turn the appliance “On” and use a commercially
available, non-corrosive leak check solution to test for
leaks around the newly installed gas valve regulator.
18. Turn the appliance “Off” to extinguish pilot and main
burner ames.
19. Be sure to rinse off all leak check solution following
testing and prior to placing the appliance into operation.
20. Reinstall the cover assembly, secure using (6) screws.
21. Verify that the conversion plate has been signed and
dated. Afx the conversion plate adjacent to the rating
label.
22. Install media per the instructions included with the
media kit or in the appliance installation manual.
Note: Appearance of
pilot may vary.
PILOT
HOOD
ORIFICE
SPUD
(Used in assembly
with 2-sided hood).
PILOT TUBE
ASSEMBLY
Figure 4. Pilot Burner Conversion
PILOT RETAINING SCREWS (2)
PILOT HOOD
CHECK FOR LEAKS
WARNING
Delayed Ignition Risk
• Place media according to instructions.
• Do NOT place media in area in front of pilot.
• Do NOT place media in a position that they may
fall into area in front of pilot.
• Do NOT use any media other than the media
supplied with this replace.
Fireplace will not function properly.
Delayed ignition may occur.
Hearth & Home Technologies • Gas Conversion Instructions for Courtyard • 4608-904 Rev. B • 11/18
3
Page 4
Propane Gas Appliance Specications
MAXIMUM MINIMUM
• Inlet Gas Pressure: .....................................13.0 in. w.c. .........11.0 in. w.c.
• Manifold Gas Pressure: ...............................10.5 in. w.c. .........10.0 in. w.c.
• Input Rate BTUH: 0-2000 Ft. MAX. ..............See below
Minimum rate with variable regulator on control valve.
NOTE: Input rate should be reduced by 4% for each 1000 feet above a 2000 foot elevation in the U.S.A. or
10% for elevations between 2000 and 4000 feet in Canada.
Models
LPK-ODCOUG#45 (1)Fully Open53,000
Burner
Orice
Burner
AirShutter
BTU Max
Hearth & Home Technologies • Gas Conversion Instructions for Courtyard • 4608-904 Rev. B • 11/184
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.